Attachment 4 - Specifications Red Rock Lookout Renovation.pdf

PDF 2 MB Posted

Attached to
GAOA Red Rock Lookout Renovation, Plumas National Forest
Solicitation number
127EAW26Q0028
Issued by

About this file

This is a specification document for the PNF Red Rock Lookout (LO) Renovation project, containing detailed technical requirements across multiple construction divisions dated April 17, 2026.

The project encompasses comprehensive renovation work including demolition, lead-based paint encapsulation, synthetic roof tile installation, hollow metal and wood door installation with hardware, painting and coating systems, residential casework (kitchen cabinets and countertops), plumbing piping (domestic water and propane gas), and photovoltaic solar collectors. Key administrative requirements include submission of a schedule of values within 14 calendar days of award, progress payment applications using AIA Forms G702/G703, requests for information (RFIs) with 14-calendar-day government response times, and submittal procedures requiring one electronic PDF copy with 15-day review periods for standard submittals (plus an additional 7 days for sequential reviews). Lead-based paint work requires extensive pre-work notifications, Cal/OSHA certifications, worker protection measures including blood lead level monitoring, and comprehensive clearance testing before reoccupancy. The roofing system specifies Brava synthetic shake tiles with a 50-year manufacturer warranty and Class A fire rating capability. Painting specifications mandate Sherwin-Williams products or approved equivalents with strict VOC compliance and multiple coat applications. The photovoltaic system requires a ground-mounted off-grid installation with battery storage and monitoring capabilities, including minimum five-year warranties on combiner boxes, inverters, and charge controllers, with two extra solar panels to be provided before project completion. All installations must comply with current industry standards (ASTM, ANSI, NFPA, UL, IEC standards as applicable) and local codes.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PNF - Red Rock LO Renovation TABLE OF CONTENTS 04-17-2026

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

012900 PAYMENT PROCEDURES

013000 ADMINISTRATIVE REQUIREMENTS

DIVISION 02 - EXISTING CONDITIONS

024100 DEMOLITION

028319 LEAD BASED PAINT ENCAPSULATION

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

073100 SYNTHETIC ROOF TILES

DIVISION 08 - OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES

081416 FLUSH WOOD DOORS

087100 DOOR HARDWARE

DIVISION 09 - FINISHES

099000 PAINTING AND COATING - COMMERCIAL FACILITY GUIDE

SPECIFICATION - SHERWIN-WILLIAMS

DIVISION 12 - FURNISHINGS

123530 RESIDENTIAL CASEWORK

DIVISION 22 - PLUMBING

221005 PLUMBING PIPING

DIVISION 26 - ELECTRICAL

263100 PHOTOVOLTAIC COLLECTORS

PNF - Red Rock LO Renovation 012900 - 1 Payment Procedures

SECTION 012900

PAYMENT PROCEDURES

SECTION 012900 - PAYMENT PROCEDURES

PART 1 GENERAL

2.01 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

2.02 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of construction schedule.

1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule.

2. Submit the schedule of values to Government within 14 calendar days of receiving award.

3. An acceptable schedule of values shall be agreed upon by the contractor and the

Government before the first progress payment is processed.

B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Arrange schedule of values consistent with format of AIA Document G703.

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.

3. Closeout Costs. Include separate line items under Contractor and principal subcontracts for Project closeout requirements.

4. Schedule of Values Revisions: Revise the schedule of values when Change Orders or

Construction Change Directives result in a change in the Contract Sum. Include at least one separate line item for each Change Order and Construction Change Directive.

2.03 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by the Government.

B. Payment Application Times: Progress payments are accepted. The period of construction work covered by each Application for Payment shall be listed on the invoice. Coordinate with Government to determine frequency of payments.

1. Submit draft copy of Application for Payment to Government for review before uploading into the Government Invoice Payment processing platform.

C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as a reference form for Applications for Payment.

D. Transmittal: Submit one signed electronic copy of each Application for Payment to the

Government via email.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

2. Include the following with the application: Construction progress schedule & partial release of liens from major subcontractors and vendors.

E. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

4. Products list (preliminary if not final).

5. Schedule of unit prices.

6. Submittal schedule (preliminary if not final).

7. List of Contractor's staff assignments.

PNF - Red Rock LO Renovation 012900 - 2 Payment Procedures

8. List of Contractor's principal consultants.

9. Report of preconstruction conference.

10. Certificates of insurance and insurance policies.

11. Performance and payment bonds.

F. Application for Payment at Substantial Completion: After Government issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificate(s) of Substantial Completion issued previously for

Government occupancy of designated portions of the Work.

G. Final Payment Application: After completing Project closeout requirements, submit final

Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. Reference AIA Document G706, G706A, G707.

5. Evidence that claims have been settled.

6. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Government took possession of and assumed responsibility for corresponding elements of the Work.

7. Final liquidated damages settlement statement.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

END OF SECTION

PNF - Red Rock LO Renovation 013000 - 3 Administrative Requirements

SECTION 013000

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Preconstruction meeting.

B. Construction progress schedule.

C. Submittals for review, information, and project closeout.

D. Requests for Information (RFI) procedures.

E. Submittal procedures.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRECONSTRUCTION MEETING

A. Schedule meeting after Notice of Award.

B. Owner will schedule a meeting after Notice of Award.

C. Attendance Required:

1. Government.

2. Contractor.

D. Agenda:

1. Execution of Owner-Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.

4. Designation of personnel representing the parties to Contract.

5. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

6. Scheduling.

3.02 CONSTRUCTION PROGRESS SCHEDULE

A. If preliminary schedule requires revision after review, submit revised schedule within 5 days.

B. Submit updated schedule with each Application for Payment.

3.03 REQUESTS FOR INFORMATION (RFI)

A. Definition: A request seeking one of the following:

B. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of

Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.

1. Prepare a separate RFI for each specific item.

2. Prepare in a format and with content acceptable to Owner.

3. Combine RFI and its attachments into a single electronic file. PDF format is preferred.

C. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.

1. Official Project name and number, and any additional required identifiers established in

Contract Documents.

2. Discrete and consecutive RFI number, and descriptive subject/title.

3. Issue date, and requested reply date.

4. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).

PNF - Red Rock LO Renovation 013000 - 4 Administrative Requirements

5. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example;

routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.

D. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.

E. Review Time: Government will respond and return RFIs to Contractor within 14 calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 12:00 noon will be considered as having been received on the following regular working day.

F. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to COR.

3.04 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

B. Submit to Government for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.

C. Samples will be reviewed for aesthetic, color, or finish selection.

3.05 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Test reports.

3. Manufacturer's instructions.

4. Other types indicated.

3.06 NUMBER OF COPIES OF SUBMITTALS

A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.

3.07 SUBMITTAL PROCEDURES

A. General Requirements:

1. Use a single transmittal for related items.

2. Submit separate packages of submittals for review and submittals for information, when included in the same specification section.

3. Transmit using any one of the following forms.

a. Use Form AIA G810.

b. Use Form CSI/CSC Form 12.1A.

c. Use Contractor's form, subject to prior approval by Government.

4. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.

5. Schedule submittals to expedite the Project, and coordinate submission of related items.

a. For each submittal for review, allow 15 days excluding delivery time to and from the

Contractor.

b. For sequential reviews involving Architect's consultants, Owner, or another affected party, allow an additional 7 days.

PNF - Red Rock LO Renovation 013000 - 5 Administrative Requirements

3.08 SUBMITTAL REVIEW

A. Submittals for Review: Government will review each submittal, and approve, or take other appropriate action.

B. Submittals for Information: Government will not acknowledge receipt, and take no other action.

C. Government's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.

1. Notations may be made directly on submitted items and/or listed on appended Submittal

Review cover sheet.

PNF - Red Rock LO Renovation 024100 - 6 Demolition

SECTION 024100

DEMOLITION

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Building demolition excluding removal of hazardous materials and toxic substances.

B. Selective demolition of building elements for alteration purposes.

C. Abandonment and removal of existing utilities and utility structures.

1.02 RELATED REQUIREMENTS

A. Section 02 83 19 - Lead-Based Paint Encapsulation:

1.03 REFERENCE STANDARDS

A. 29 CFR 1926 - Safety and Health Regulations for Construction; Current Edition.

B. NFPA 241 - Standard for Safeguarding Construction, Alteration, and Demolition Operations;

2022, with Errata (2021).

1.04 SUBMITTALS

A. See Section 013000 - Administrative Requirements for submittal procedures.

B. Site Plan: Indicate:

1. Vegetation to be protected.

C. Demolition Plan: Submit demolition plan as required by OSHA and local AHJs.

1. Indicate extent of demolition, removal sequencing, bracing and shoring, and location and construction of barricades and fences.

2. Summary of safety procedures.

3. Demolition firm qualifications.

PART 2 EXECUTION

2.01 DEMOLITION

A. Remove items as shown on Government provided drawing set. .

B. Remove other items indicated, for salvage, relocation, and recycling.

2.02 GENERAL PROCEDURES AND PROJECT CONDITIONS

A. Do not begin removal until receipt of notification to proceed from Owner.

B. Protect existing structures and other elements to remain in place and not removed.

C. Minimize production of dust due to demolition operations. Do not use water if that will result in ice, flooding, sedimentation of public waterways or storm sewers, or other pollution.

2.03 EXISTING UTILITIES

A. Protect existing utilities to remain from damage.

B. Remove exposed piping, valves, meters, equipment, supports, and foundations of disconnected and abandoned utilities.

2.04 SELECTIVE DEMOLITION FOR ALTERATIONS

A. Existing construction and utilities indicated on drawings are based on casual field observation only.

1. Verify construction and utility arrangements are as indicated.

2. Report discrepancies to Architect before disturbing existing installation.

3. Beginning of demolition work constitutes acceptance of existing conditions that would be apparent upon examination prior to starting demolition.

B. Remove existing work as indicated and required to accomplish new work.

1. Remove items indicated on drawings.

PNF - Red Rock LO Renovation 024100 - 7 Demolition

C. Protect existing work to remain.

1. Prevent movement of structure. Provide shoring and bracing as required.

2. Perform cutting to accomplish removal work neatly and as specified for cutting new work.

3. Repair adjacent construction and finishes damaged during removal work.

4. Patch to match new work.

2.05 DEBRIS AND WASTE REMOVAL

A. Remove debris, junk, and trash from site.

B. Leave site in clean condition, ready for subsequent work.

C. Clean up spillage and wind-blown debris from public and private lands.

PNF - Red Rock LO Renovation 028319 - 8 Lead Based Paint Encapsulation

SECTION 028319

LEAD BASED PAINT ENCAPSULATION

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Removal and legal disposal of lead-based paint (LBP).

B. Encapsulation of lead-based paint

1.02 REFERENCE STANDARDS

A. Federal, State and local laws and latest guidelines and regulations published by Housing and

Urban Development (HUD), Environmental Protection Agency (EPA) and Occupational Safety and Health Agency (OSHA) including but not limited to:

1. 29 CFR 1910.1025 Lead Standard for General Industry

2. 29 CFR 1926.62 Construction Industry Lead Standard

3. 40 CFR Part 745 Requirements for Lead-Based Paint Activities in Target Housing and

Child-Occupied Facilities

4. HUD Guidelines for the Evaluation and Control of Lead-Based Paint Hazards in Housing

5. Uniform Building Code, Latest Edition

6. Title 8 Section 1532.1 Cal/OSHA Construction Safety Orders, Lead

7. Title 17, California Code Of Regulations, Division 1, Chapter 8

1.03 SUBMITTALS

A. See section 013000 – Administrative Requirements for submittal procedures.

B. Training Certificates – Required for all workers performing lead related construction activities.

Shall include documentation on a lead training course approved by the California California Department of Health Services (DHS), Lead Accreditation and Certification Unit. Workers shall have current state lead certification and at least one on-site supervisor shall have current certification as Supervisor/Monitor. Certificate must be valid for the duration of work being performed.

C. Proof of insurance for lead paint abatement work to a minimum of $500,000.00 single limit for bodily injury and property damage limits of $1,000,000.00 per occurrence.

D. Abatement Plan: Submit abatement plan to Government for review. Shall include at a minimum:

1. Material and equipment to be used.

2. Procedures for work area isolation. Including but not limited to as applicable:

a. Area containment

3. Methods and equipment for providing negative air pressure

4. Negative air pressure monitoring

E. Airlock/clean room entrance/exit F. Procedures for worker decontamination system, including OSHA compliant decontamination enclosures.

G. Procedures and protocols for lead based paint removal and subsequent encapsulation.

H. Waste handling protocols for loading, hauling and disposal of lead-based paint/lead-based paint containing materials. Including the name of the waste transporter and the waste disposal means and destination location.

I. Written Hazard Communication Plan and SDS for products brought on-site by the Contractor.

J. Written Respiratory Protection Plan K. Project Work Schedule L. Health and Safety Plan M. Current lead-based paint abatement certification and licensing for all personnel performing work under this contract.

PNF - Red Rock LO Renovation 028319 - 9 Lead Based Paint Encapsulation

N. Final Abatement Report: Submit after work has been completed for record. Shall include:

O. Detailed description and documentation of the site-specific operations performed. Including, but not limited to lead based paint identification, sampling and analytical data, and lead-based quantities removed and disposed.

P. Lead-based paint abatement Contractor Daily Logs.

Q. OSHA Monitoring results; and applicable project -specific data.

R. Before and after site photos S. Final disposition of the lead-based paint waste including copies of all waste disposal forms

PART 2 EXECUTION

2.01 SITE ACCESS

A. A person may not enter or remain on site at any time during a lead demolition project unless that person is:

1. The Contractor engaged for the lead abatement project and his employees;

2. State, County or local enforcement official or his designee;

3. A Federal, State or local official, or his designee, engaged in research on buildings with lead paint.

2.02 ACTIVITES PRIOR TO WORK

A. Lead-Based Paint Removal Work Shall Not Commence Until:

1. Arrangements have been made for disposal of waste at an EPA a State approved landfill and the Forest Service has provided an EPA ID Number.

2. Arrangements have been made for containing and/or disposal of wastewater resulting from showering and other abatement activities.

3. Containment, decontamination enclosure system, and waste load-out area are appropriately constructed.

4. All tools, equipment, PPE, and material waste receptacles are on-site.

5. Suitable barricades and warning signs are established to restrict access to the work area to abatement associated personnel only.

6. All other preparatory steps have been taken and applicable notices posted, and permits are obtained.

7. A visitor and employee log-in log-out system is in place at the job site. All persons entering the site will be required to sign in and sign out.

8. All notifications for lead related work have been completed in accordance with Federal, State, and local requirements.

2.03 CONTROL OF EMISSIONS AND DUST

A. The ground and any plants or shrubs in the area in which demolition is occuring shall be covered with plastic and weighted at all edges so as to prevent blowing. The covering shall be placed in a manner that traps debris and water. The covering shall be properly disposed of and not re-used.

1. Exterior work shall not be conducted when winds are in excess of 20 mph.

B. Caution Signs

1. At each separate work area, the Contractor performing demolition shall display a caution sign wherever the treatment process is reasonably expected to break or disturb any lead-containing substances.

2. At least 3 days before demolition of structures, the Contractor shall post signs immediately outside all entrances and exits to the work area.

3. The Contractors shall keep the signs posted until all work has been copleted and any remaining LBP is encapsulated.

4. The Contractor shall insure that the sign meets the following description:

5. The sign is at least 20" by 14" and states the date and place of the lead abatement project;

PNF - Red Rock LO Renovation 028319 - 10 Lead Based Paint Encapsulation

6. The sign includes the phrase, "Caution Lead Hazard, Keep Out" in bold lettering at least 2 inches high.

C. Warning Signs

1. Warning signs in the work area shall confrom to 29 CFR 1926.62 (M) and Title 8 Code of

California Regulation Section 1532.1 subsection (m).

2.04 ABATEMENT METHODS

A. The following methods shall not be used to remove paint that is, or may be, lead-based paint:

1. open flame burning or torching,

2. machine sanding or grinding without a high-efficiency particulate air (HEPA) local exhaust control,

3. abrasive blasting or sandblasting without HEPA local exhaust control,

4. heat guns operating above 1100 degrees Fahrenheit or charring the paint,

5. dry sanding or dry scraping, except dry scraping in conjunction with heat guns or within

1.0 feet of electrical outlets, or when treating defective paint spots totaling no more than 2

sq. ft. (0.2 sq. m.) in any one interior room or space or totaling no more than 20 sq. ft. (2.0

sq. m.) on exterior surfaces, B. paint stripping in a poorly ventilated space using a volatile stripper that is a hazardous substance in accordance with regulations of the Consumer Product Safety Commission at 16 CFR 1500.3, and/or a hazardous chemical in accordance with the Occupational Safety and Health Administration regulations at 29 CFR 1910.1200 or 1926.59, as applicable to the work.

2.05 CLEAN UP PROCEDURES

A. The work site shall be cleaned at end of each day's abatement activities. A separate, secured area within the project site shall be designated for storage of debris until it can be properly disposed of. Disposable supplies shall be replaced regularly and disposed of properly. Durable equipment, such as power and hand tools, generators, and vehicles shall be cleaned monthly or prior to removal from the site. All equipment shall be cleaned by HEPA vacuuming and high-phosphate washing.

B. Clean-Up Methods and Equipment

1. Large debris from demolition (i.e. doors, windows, baseboards) shall be wrapped in plastic sheets at lest 6 mil thick, sealed with heavy duct tape, and stored in the designated area.

This debris will be removed according to specifications outlined in Section 2.04 contract specifications.

2. Small debris will be picked up, collected, and placed into a single plastic bag, at least 6 mil thick, or double bags of 4 mil thick plastic. The bags shall not be overloaded, shall be securely tied, and shall be stored in the designated area until disposal.

3. Plastic sheeting shall be sprayed, picked up, and HEPA vacuumed prior to removal. The plastic sheeting shall be carefully folded from the corners and ends toward the middle and placed into a double 4 mil or single 6 mil plastic bag and sealed. Bags shall be stored in the designated area and disposed according to contract specifications.

4. The Contractor shall removal all plastic sheeting for preclearance cleanup. Visible debris in the soil shall be removed.

5. The Contractor shall await analysis results of baseline and post-hazard control soil samples. If post-hazard control soil levels are greater than or equal to 1000 ug/g, baseline soil samples will be analyzed to determine the additional work that will be needed. If paint chips originating from the work are identified in the soil, they shall be removed with a HEPA vacuum.

6. The Contractor shall begin final cleanup no less than 24 hours (unless notified otherwise) after final clearance and all materials, equipment, debris, and plastic sheeting have been removed. All disposable supplies used during cleanup shall be disposed of according to Section 2.04 of these specifications.

PNF - Red Rock LO Renovation 028319 - 11 Lead Based Paint Encapsulation

2.06 POST ABATEMENT CLEAN UP AND INTERIOR CLEARANCE

A. Final clean-up prior to re-occupancy shall include wet wiping using a TSP solution and HEPA vacuuming all suspect dust and debris for final visual inspection and wipe dust sampling. All cleaning will be performed by the abatement contractor.

B. Visual inspections and clearance sampling (wipe sampling) will be performed by an independent third party to ensure that abatement areas are safe for re-occupancy. If the most stringent of EPA, or HUD or State of California clearance standards are not met, the Contractor must return to the project site and perform additional cleaning. This process will be repeated until the applicable clearance standards are achieved.

C. If clearance samples fail the Contractor is responsible for all subsequent consulting and testing costs until the clearance is achieved. The Contractor shall remedy the situation that caused the failure, i.e., filter outside dirty air, re-clean inside surfaces or other, and then the containment area shall be retested. Once the work areas have achieved clearance, the Contractor shall remove containment barriers.

2.07 POST ABATEMENT CLEAN UP AND EXTERIOR CLEARANCE

A. Exterior clearance shall include a visual examination of the ground, vegetation, and horizontal building surfaces near the exterior work surfaces to confirm that paint chips and other paint-related debris have been removed. Outdoor, hard surfaced living areas within the clearance area shall be visually examined to ensure these areas are free of visible dust and debris. The Contractor is responsible for exterior post abatement cleaning.

B. Visual examinations will be performed by an independent third party to ensure abatement areas are safe for occupancy.

C. If exterior cleanup is necessary, the Contractor is responsible for cleaning up the exterior areas.

Clearance has not been achieved until such cleanup has been satisfactorily completed.

2.08 WASTE DISPOSAL

A. This section covers the disposal of waste generated during the demolition of structures containing lead-based paint.

B. The Contractor shall remove and dispose of in a legal manner all hazardous and nonhazardous waste generated. Waste (both hazardous and nonhazardous) shall be properly labeled, stored and secured while on site. Waste shall be removed from the project site for proper disposal within one week of project completion. At no time will waste be allowed to accumulate on-site for a period of more than 90 days.

C. The Contractor shall contact the regional EPA, State, and local authorities to determine current lead-based paint debris disposal requirements. The requirements of the Resource Conservation and Recovery Act (RCRA) shall be complied with as well as applicable state solid waste plan requirements. During demolition, the Contractor shall not leave debris in the yard or nearby property, incinerate debris, dump waste by a road or in an unauthorized dumpster, or introduce lead-contaminated water into storm drains or sanitary sewers.

D. Testing on lead-based paint abatement waste materials by use of the TCLP method will be completed by the Contractor and results supplied to the U.S. Forest Service.

E. Forest Service will obtain and provide an EPA number to use for disposal of all hazardous material produced as part of project scope.

F. The Contractor shall place lead-based paint chips, debris and lead dust in double (4-mil) or single (6-mil) polyethylene bags that are air-tight and puncture-resistant. Pieces of wood or other types of substrates that do not fit into plastic bags will be wrapped and labeled "DANGER, LEAD DUST".

G. The Contractor will place all disposable cleaning materials, such as sponges, mop heads, filters, disposable clothing, and brooms in double (4-mil) or single (6-mil) plastic bags and seal.

H. The Contractor shall clean surfaces and equipment and bag large debris. The Contractor shall then remove plastic sheeting and tape from covered surfaces. Prior to removig the plastic

PNF - Red Rock LO Renovation 028319 - 12 Lead Based Paint Encapsulation sheeting, the Contractor shall lightly mist the sheeting in order to keep dust down and fold inward to form tight small bundles to bag for disposal. The Contractor shall place all plastic sheeting in double (4-mil) or single (6-mil) thick plastic bags and seal.

I. The contractor shall bag and seal vacuum bags and filters in double (4-mil) or single (6-mil) thick plastic bags.

J. The Contractor shall place all contaminated clothing or clothng covers used during demolition and cleanup in plastic bags for disposal.

K. The Contractor shall contain and properly dispose of all liquid waste, including lead-dust contaminated wash water.

L. The Contractor shall HEPA vacuum the exterior of all liquid waste containers prior to removing the waste containers from the work area and shall wet wipe the containers to ensure that there is no residual contamination. Containers should then be moved out of the work area into the designated storage area. The Contractor shall carefully place the containers into the truck or dumpster used for disposal.

M. The Contractor shall ensure that all waste is transported in covered vehicles to a landfill, or lined landfill.

N. If the Contractor subcontracts the removing of the lead-based paint waste, he shall insure that the company removing the waste material adequately covers all loads so as to assure that no dust or debris is released.

O. The Forest Service shall supply the contractor with an EPA ID Number.

P. If the Contractor is not a licensed hazardous waste transporter, a contract shall be entered into with a transporter licensed to haul hazardous waste.

2.09 NOTIFICATION

A. Contractor is responsible for providing written notification to Cal/OSHA twenty four (24) hours before conducting lead-related construction work involving trigger tasks identifiied in Title 8 Section 1532. Copies of the notification indicating the date and time submitted shll be provided to the Forest Service Contracting Officer

2.10 WORKER PROTECTION

2.11 WORKERS PERFORMING LEAD RELATED CONSTRUCTION ACTIVITIES MUST HAVE

CURRENT STATE OF CALIFORNIA CERTIFICATION TO PERFORM SUCH WORK.

A. All workers must have baseline and post demolition blood lead level screenings determined by the whole blood lead method. The blood tests will also be required at the end of each 30 day period, if the employee is working on the job. This test must be performed before workers enter a lead contaminated work areas. A worker will be removed from the job if his blood lead level is 50 ug/dl or greater. The Contractor shall be responsible for medical surveillance and record keeping.

B. The Contractor will provide all workers, foremen, and superintendents with properly fitted half-faced respirators approved by NIOSH and OSHA. When respirators and disposable filters are employed, sufficient replacement filters will be provided by the Contractor for the workers..All workers inside the work area will wear the proper respirator for the lead dust level generated.

C. All workers performing lead-based paint abatement shall have properly fitted half-face respirators approved by NIOSH and OSHA and meet all minimum respiratory protection requirements as regulated by OSHA when performing tasks that are above the permissible exposure level. Workers will wear full body disposable suite with hoods and booties and appropriate goggles with a side shield. Disposal suits shall be used once, then properly discarded.

PNF - Red Rock LO Renovation 028319 - 13 Lead Based Paint Encapsulation

D. The abatement Contractor shall follow and enforce good personal hygiene practices during abatement activities. Upon leaving the work area, each worker will remove and dispose of work suit, wash and dry face and hands and vacuum clothes.

PNF - Red Rock LO Renovation 073100 - 14 Synthetic Roof Tiles

SECTION 073100

SYNTHETIC ROOF TILES

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Synthetic roof tiles of the following types:

1. Shake tiles. (Cedar Shake)

B. Accessories.

1.02 RELATED REQUIREMENTS

A. Section 06 10 00 - Rough Carpentry.

B. Section 07 60 00 - Flashing and Sheet Metal.

1.03 REFERENCE STANDARDS

A. ASTM International (ASTM):

1. ASTM D226 - Standard Specification for Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing.

2. ASTM D3161 - Standard Test Method for Wind-Resistance of Asphalt Shingles (Fan- Induced Method).

3. ASTM E108 (UL 790) - Standard Test Methods for Fire Tests of Roof Coverings.

4. ASTM D1970 - Standard Specification for Self-Adhering Polymer Modified Bituminous

Sheet Materials Used as Steep Roofing Underlayment for Ice Dam Protection.

B. International Code Council (ICC): ES Acceptance Criteria AC07 Section 4.9.

C. Underwriters Laboratories (UL):

1. UL 790 - (Exterior Exposure), Standard Test Methods for Fire Tests of Roof Coverings.

2. UL 997 - Wind Resistance of Prepared Roof Covering Materials.

3. UL 2218 - Impact Resistance of Prepared Roof Covering Materials.

D. Manufacturer's recommendations and specifications.

1.04 SUBMITTALS

A. See Section 01 33 00 – Submittal Procedures, for submittal procedures.

B. Product Data:

1. Manufacturer's data sheets on each product to be used.

2. Preparation instructions and recommendations.

3. Storage and handling requirements and recommendations.

4. Typical installation methods.

C. Selection Samples: For each finish product specified, two sample roof tiles representing the manufacturer’s full range of available colors and patterns.

D. Verification Samples: For each finish product specified, two samples, representing actual product, color, and patterns.

E. Shop Drawings: Include details of materials, construction, and finish. Include relationship with adjacent construction.

1.05 QUALITY ASSURANCE

A. Manufacturer Qualifications: Company specializing in manufacturing products specified in this section with a minimum years documented experience.

B. Installer Qualifications: Company specializing in performing Work of this section with minimum two years documented experience with projects of similar scope and complexity.

C. Source Limitations: Provide each type of product from a single manufacturing source to ensure uniformity.

PNF - Red Rock LO Renovation 073100 - 15 Synthetic Roof Tiles

D. Mock-Up: Construct a mock-up with actual materials in sufficient time for Government’s review and to not delay construction progress. Locate mock-up as acceptable to Government and provide temporary foundations and support.

1. Intent of mock-up is to demonstrate quality of workmanship and visual appearance.

2. If mock-up is not acceptable, rebuild mock-up until satisfactory results are achieved.

3. Retain mock-up during construction as a standard for comparison with completed work.

4. Do not alter or remove mock-up until work is completed or removal is authorized.

1.06 PRE-INSTALLATION CONFERENCE

A. Convene a conference approximately two weeks before scheduled commencement of the

Work. Attendees shall include Government, Contractor and trades involved. Agenda shall include schedule, responsibilities, critical path items and approvals.

1.07 DELIVERY, STORAGE, AND HANDLING

A. Store and handle in strict compliance with manufacturer's written instructions and recommendations.

B. Protect from damage due to weather, excessive temperature, and construction operations.

C. Store and dispose of solvent-based materials, and materials used with solvent based materials, in accordance with requirements of local authorities having jurisdiction.

1.08 PROJECT CONDITIONS

A. Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer's recommended limits.

1.09 WARRANTY

A. Manufacturer's Warranty: Provide manufacturer's standard limited warranty:

1. Manufacturer's 50-year warranty for tiles against material defects that cause leaks under normal weather and use conditions.

PART 2 - PRODUCTS

2.01 MANUFACTURERS

A. Acceptable Manufacturer: Brava Roof Tile or approved equal.

2.02 PERFORMANCE REQUIREMENTS

A. Roof system to consist of manufactured synthetic tiles attached to structural substrate to form weather tight roof envelope with no measurable water penetration.

B. Tiles shall be manufactured with variations in color and size, textured faces and edges, and sufficient thickness to provide a realistic installed appearance.

C. Method of attachments shall be designed to adequately resist wind uplift for roof configuration and project location.

D. Fire resistance: When installed over one layer of 30 lbs. felt that meets ASTM D226 E. Type II standard or a listed synthetic underlayment: Class C tested in accordance with ASTM

E108/UL 790. See Code Evaluation Report for specific fire classified assemblies.

F. Fire resistance: When installed over one layer of GAF VersaShield Fire Resistant

Underlayment or approved equal. Class A tested in accordance with ASTM E108/UL 790. Meet product Code Evaluation Report for specific fire classified assemblies.

G. Wind Uplift Resistance: When installed over minimum 15/32-inch-thick plywood. Tested in accordance with method TAS 125.

H. Hail Impact Resistance: Class 4 to withstand two drops of 2 inches diameter, 1.2 lbs. (0.54 kg) steel ball dropped from 20 feet tested in accordance with UL 2218.

I. Freeze-thaw resistance: No crazing, cracking, delamination of coating, or other deleterious surface changes after one month exposure with temperature cycled from

PNF - Red Rock LO Renovation 073100 - 16 Synthetic Roof Tiles

J. -40 to in 22 hours tested in accordance with International Code Council (ICC)- ES Acceptance Criteria AC07 Section 4.9.

K. Accelerated weathering: Little change after 2,500 hours exposure to ultraviolet (UV) radiation, elevated temperature, moisture, and thermal shock.

2.03 SYNTHETIC SHAKE TILES

A. Basis of Design: Brava Roof Tile, Cedar Shake as manufactured by Brava Roof Tile.

B. Lightweight, synthetic shake shingles with the appearance, color, texture, and thickness of natural wood shakes C. Material: Engineered polymer formulated from post-industrial recycled plastic.

D. Installed weight: At 10-inch 10 inch exposure: 304 lbs. per 100 sq feet.

E. Profile: Rectangular shape with exposed to view upper surface and edges textured to

1. resemble natural wood shake. Underside formed with reinforcing ribs for added strength and stability.

F. Size:

1. Thickness: 3/8 to 1 inch (9.5 to 25 mm) at butt end.

2. Length: 22 inches.

3. Variable widths: 5, 7, and 12 inches.

G. Starter tile: 12 inches long by 12 inches wide.

H. Markings: Form tiles with markings on upper surface to indicate nailing locations and provide alignment guidelines for different exposure lengths.

I. Finish: Multi color comparable to natural wood shakes. Internal UV stabilizers to provide durable color stability.

1. Color: Canyon Gray.

2. Color: White (Premium color).

2.04 ACCESSORLES

A. Underlayment: Asphalt saturated and coated organic felt base sheet which meets or exceeds requirements of ASTM D226 Type II No. 30 non-perforated saturated asphalt felt or a listed synthetic underlayment which meets or exceeds requirements of ASTM D8257, in accordance with manufacturer's instructions.

1. Approved synthetic membranes include, but are not limited to:

a. Titanium UDL 50.

b. Low-E ThermaSheet

c. Eco Chief SOLARHIDE-SRW

d. GAF VersaShield Resistant Roof Deck Protection

B. Waterproof Sheet Membrane: Cold applied, self-adhering waterproof membrane composed of polyethylene film coated one side with rubberized asphalt adhesive which meets or exceeds requirements of ASTM D1970, in accordance with manufacturer's instructions.

1. Thickness: 40 mils 0.04 inch.

2. Low temperature flexibility: Unaffected at minus 32 degrees Fahrenheit.

3. Minimum tensile strength: 250 psi.

4. Minimum elongation: 250 percent.

5. Permeance: 0.05 perms maximum.

6. Approved membranes include, but are not limited to:

a. Titanium PSU 30.

C. Flashing: Fabricate from sheet to profiles and dimensions indicated on Drawings and approved shop drawings and in accordance with general requirements specified in Section 07 60 00 - Flashing and Sheet Metal- Flashing and Sheet Metal.

1. Material: 16-ounce copper.

2. Material: 26 gage 0.02 inch galvanized steel.

PNF - Red Rock LO Renovation 073100 - 17 Synthetic Roof Tiles

3. Base Flashings: To be used over or under the roof coverings and are turned up on the vertical surface.

a. Base flashings should extend under the uppermost row of tile the full depth of the tile or at least 4 inches over the tile immediately below the metal. The vertical leg of the metal should be turned up a minimum of 4 inches and extend 4 inches on the tile as it is laid.

4. Linear Components: Form in longest possible lengths with 8 feet as minimum.

5. Counter Flashings: Extend 4 inches minimum up vertical surfaces

6. and 4 inches minimum under shingles.

7. Eave Flashings: Form bottom edge outward 1/4-inch 0.24 inch and hem to form drip.

8. Valley Flashings: 24 inches minimum width and extending 10 inches minimum from valley center line.

D. Standard Fasteners: 3/8-inch 0.37 inch diameter, corrosion resistant flat head ring shank roofing nails 1-3/4 inches long.

1. Material: Copper.

2. Material: Stainless steel.

3. Material: Hot-dipped galvanized.

E. Standard Fasteners: No. 10 DSVT T25 screws 2 inches long.

1. Material: Copper.

2. Material: Stainless steel.

3. Material: Hot-dipped galvanized.

F. High wind fasteners (90,100, 130 mph): 1/8-inch 0.12 inch diameter, No. 8 x 2-inch (2.01 inch) screws.

1. Material: Copper.

2. Material: Stainless steel.

3. Material: Hot-dipped galvanized.

G. High wind fasteners (90,100, 130 mph): No. 10 x 2-1/2-inch 2.52 inch screws.

1. Epoxy, polymer or ceramic coated.

2. Material: Stainless steel.

3. Material: Hot-dipped galvanized.

H. Snow Guards

1. Alpine Fusion-Guard Hybrid Pad-Style Snow Guard.

2. Snow Gem Half Carat™ Metal Snow Guard with Plate

3. TRA Snow & Sun - Snow Bracket Brava - APEX

PART 3 - EXECUTION

3.01 EXAMINATION

A. Do not begin installation until substrates have been properly constructed and prepared.

B. If substrate preparation is the responsibility of another installer, notify Government in writing of unsatisfactory preparation before proceeding.

3.02 PREPARATION

A. Clean surfaces thoroughly prior to installation.

B. Prepare surfaces using the methods recommended by the manufacturer for achieving the best result for the substrate under the project conditions.

C. Coordinate installation with provision of gutters and downspouts as specified herein.

D. Verify roof is complete, rigid, braced, and deck members are securely fastened. Ensure proper ventilation has been provided for roof space. Do not proceed with roofing until deficiencies are addressed.

E. Verify roof deck is clean, dry, and ready to receive Brava synthetic Shake or approved equal.

PNF - Red Rock LO Renovation 073100 - 18 Synthetic Roof Tiles

3.03 INSTALLATION

A. Install products in accordance with manufacturer's instructions, approved submittals and in proper relationship with adjacent construction.

B. Underlayment Installation: Install self-adhered waterproof sheet membrane on the eaves.

Cover the waterproof sheet membrane and the remaining portions of the roof as scheduled with the approved underlayment. Then install waterproof sheet membrane in valleys, along walls and around projections terminating on top of underlayment. Install underlayment in accordance with underlayment and tile manufacturers' recommendations.

1. Stripping ply: Install full sheet of self-adhered waterproof sheet membrane in valleys, and minimum 18 inch width on gable ends, against walls, and around projections.

2. In areas where January average daily temperature is 25 degrees Fahrenheit (minus 4 degrees

a. C) or lower or where ice buildup is possible, install self-adhered waterproof sheet membrane from bottom edge extending two feet 24.02 inch above exterior wall line on eaves.

3. Install waterproof sheet membrane over entire roof area.

a. Apply waterproof sheet membrane at temperatures of 40 degrees Fahrenheit (4 degrees

1) C) or higher.

b. Adhere and attach as recommended by manufacturer of waterproof sheet membrane.

c. Start underlayment installation at lower edge of roof. Install perpendicular to roof slope with minimum 4-inch 4.02 inch side laps and minimum 6- inch (5.98 inch) end laps.

d. Extend underlayment minimum 4 inches up vertical wall intersections and at least 6 inches onto the roof.

e. Do not leave underlayment membrane exposed in excess of time limit required by manufacturer. Do not puncture or tear underlayment.

C. Flashing Installation:

1. Install overhanging drip edge on eaves and gable ends and metal flashings at valleys, ridges, hips, roof curbs, penetrations, and intersections with vertical surfaces in accordance with Section 07 60 00 - Flashing and Sheet Metal- Flashing and Sheet Metal.

2. Weather lap joints 2 inches minimum and seal with sealant as specified in Section 07 91 13 - Compression Seals- Joint Fillers.

3. Secure in place with clips, nails, and other fasteners.

3.04 TILE INSTALLATION- GENERAL

A. Install tiles in accordance with manufacturer's instructions and approved Shop Drawings.

B. Layout: Accurately layout tiles. Ensure that edges are parallel and perpendicular to roof eaves.

C. Confirm roof square before installation. Correct any out of square conditions and ensure that the eave line is straight.

D. Color: Verify that materials are the selected color. Some color variation is to be expected. If color variation exceeds original selection, immediately cease installation, and notify manufacturer.

E. Selection: Pull materials from multiple pallets to ensure proper color blending.

F. Roof Slope: Minimum roof slope recommended for the application of synthetic roof tile is

1. 4:12. When installed on a 3:12 slope, a self-adhered waterproof membrane should be used on the entire slope.

3.05 TILE INSTALLATION - SHAKE

A. Spacing: Provide a minimum 3/16-inch 0.19 inch gap between all tiles to allow for expansion and contraction. A 3/8-inch (9.5) spacing is recommended.

B. Exposure: Maximum 10 inches. Minimum 4 inches.

PNF - Red Rock LO Renovation 073100 - 19 Synthetic Roof Tiles

C. Fastening: Attach each tile to wood deck with 2 approved fasteners.

1. Place fasteners at locations indicated on tiles.

2. Use approved nails or screws for the tile type being installed.

3. Ensure full penetration but do not overdrive fasteners.

4. Ensure min. 3/4-inch 0.75 inch fastener penetration or completely through the deck.

5. Do not fasten at an angle.

6. Ensure that the fastener head is flush with shingle surface.

7. At valleys do not fasten tiles within 5 inches of valley center line.

D. Cutting: Layout work to avoid cutting shingles.

1. At gables and vertical intersections, vary combination of shingle width and spacing of shingles to avoid cutting.

2. If cutting is required, place shingle such that cut edge is not exposed. The use of solid field tiles is recommended be best aesthetics.

3. Use circular saw or straight edge and utility knife if cuts are necessary.

E. Sidelap: Stagger tiles joints in one course minimum 1-1/2 inches from joints in course below.

F. Eaves: Install row of starter tiles at eaves as base layer. Overhang starter tile at eave edge approximately 1/2 inch and 1 inch past rake edge, or as required to allow water to drain.

G. Ridges and Hips: After field shingle installation is complete, install an 8-inch-wide 7.99 inch strip of self-adhering membrane over the center of the hip and any unvented sections of ridge.

1. Install ridge or hip caps using the correct profile for correct fit (Low, Standard, Steep).

2. Install Hip/Ridge Caps with two fasteners at the formed fastener locators penetrating

a. ≥ 3/4 inches into the deck or completely through the deck.

3. Match Hip/Ridge exposure to Field Shake exposure ≤ 10 inches.

4. 3-inch 2.99 inch fasteners recommended for hip and ridge caps

H. Valleys: Install full 36-inch 35.98 inch sheet of self-adhered waterproof sheet membrane in valleys.

1. Open Valley: A minimum 4-inch 4.02 inch opening at the top of the valley is recommended using Solid Shakes with a “W” style flashing and 1-inch center crimp. If Solid Shakes are not used with 1 1/2-inch (1.5 inch) crimps, a “Double W” flashing may be used to cover exposed structural ribbing on cut Field Shakes.

2. Closed Valley: A “W” style flashing may be used with a 1 1/2-inch 1.5 inch center crimp.

Leave a minimum 3/16-inch (0.19 inch) gap between the shakes at the valley for thermal expansion.

3. At valleys do not fasten tiles within 5 inches of valley center line.

3.06 FIELD QUALITY CONTROL

A. Field Inspection: Coordinate field inspection in accordance with appropriate sections in

1. Division 01.

B. Inspect tiles as they are installed. Do not install cracked, broken, twisted, curled, or otherwise damaged tiles.

C. As work progresses, exercise care not to scratch or mark installed tiles. Tiles damaged during installation shall be immediately removed and discarded.

D. After approximately 200 sq feet of tiles have been installed, inspect roof from ground. Verify proper layout and appearance. Repeat inspection throughout installation.

E. Visually inspect complete installation to ensure that it is weather tight.

3.07 3CLEANING AND PROTECTION

A. Clean products in accordance with the manufacturer's recommendations.

B. Protect installed products until completion of project.

C. Color match accessories for aesthetic purposes if desired.

PNF - Red Rock LO Renovation 073100 - 20 Synthetic Roof Tiles

D. Touch-up, repair or replace damaged products before Substantial Completion.

PNF - Red Rock LO Renovation 081113 - 21 Hollow Metal Doors and Frames

SECTION 081113

HOLLOW METAL DOORS AND FRAMES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Non-fire-rated hollow metal doors and frames.

1.02 RELATED REQUIREMENTS

A. Section 087100 - Door Hardware.

1.03 REFERENCE STANDARDS

A. ANSI/SDI A250.3 - Test Procedure and Acceptance Criteria for Factory Applied Finish Coatings for Steel Doors and Frames; 2025.

B. ANSI/SDI A250.4 - Test Procedure and Acceptance Criteria for Physical Endurance for Steel Doors, Frames and Frame Anchors; 2024.

C.

This is the start of the file's text. The full file is on GovTribe.