Summary: Attachment 3 - Delivery Schedule

This document is a delivery schedule for a weapon system development contract encompassing three primary components: weapons, ammunition, and fire control systems. The schedule outlines contractor deliverables organized into four phases: program start-up activities, design finalization activities, prototype test deliveries, and prototype test post-activities, with specific submission deadlines relative to key program milestones.

Program start-up activities require the contractor to conduct a scheduled program start-up meeting with read-ahead materials submitted five business days prior, along with quarterly technical and production metrics submissions. Design finalization deliverables include a marking plan due 60 days after award, pre-ship meetings for both prototype test (PT) and Technology in Context (TiC) hardware, and ammunition lot data packages due six weeks prior to shipment. Prototype test deliveries include 16 weapons, specified quantities of family ammunition variants (17,600 tactical rounds, 2,200 close-quarters battle, 2,700 canister, and 2,900 counter-small unmanned aircraft rounds), 28 fire control units, magazines, high-pressure test ammunition, technical manuals, system safety documentation, environmental assessments, and hazard classification reports—all due 30 days prior to PT. Post-PT activities require technical data packages, computer software deliverables if applicable, interface control documentation, and manufacturing maturity plans due 60 to 90 days after PT completion. Additional deliverables include quarterly integrated master schedule updates, integrated logistics support documentation, counterintelligence and operations security briefings as necessary, hazardous waste reports due 180 days after award with yearly updates, and accident/incident reports within 24 hours of occurrence. The government prototype test is scheduled to commence 15 months after contract award.

View the file

Other files

File Type Posted
W15QKN-26-R-1BH5 PPON PGS QandAs - 2026MAY29.docx DOCX document
W15QKN-26-R-1BH5 PPON PGS QandAs - 2026MAY27.docx DOCX document
PGE PPON Updated 20MAY2026.docx DOCX document
W15QKN-26-R-1BH5 PPON PGS QandAs - 2026MAY19.docx DOCX document
W15QKN-26-R-1BH5 PPON PGS QandAs - 2026MAY18.docx DOCX document
Attachment 15 - PGS Model OTA DRAFT Updated 2026MAY07.docx DOCX document
W15QKN-26-R-1BH5 PPON PGS QandAs - 2026MAY11.docx DOCX document
PGS PPON Updated 28APR2026.docx DOCX document
W15QKN-26-R-1BH5 PPON PGS QandAs - 2026APR30.pdf PDF
Attachment 16 - Fire Control Sample SLA.docx DOCX document
Attachment 17 - Ammunition Sample SLA.docx DOCX document
Attachment 18 - Weapons Sample SLA.docx DOCX document
Attachment 4 - Pricing Updated 14APR2026.xlsx XLSX spreadsheet
Attachment 15 - PGS Model OTA DRAFT Updated 14APR2026.docx DOCX document
PGS PPON Updated14APR2026.docx DOCX document
Attachment 3 - Delivery Schedule Updated 14APR2026.pdf PDF
Attachment 9 - Protoype Testing Outline Updated 14APR2026.pdf PDF
W15QKN-26-R-1BH5 PPON PGS QandAs - 2026APR17.docx DOCX document
W15QKN-26-R-1BH5 PPON PGS Questions and Answers - 2026APR13.pdf PDF
Attachment 21- Accounting System Questionnaire.pdf PDF
AMSTA-AR 1350 - Data Request Questionnaire.pdf PDF
DD Form 2345 - Militarily Critical Technical Data Agreement.pdf PDF
Non-Disclosure Non-Use Agreement.docx DOCX document
Attachment 19 - Business Status Certification.pdf PDF
Attachment 11 - Security Information Requirements.pdf PDF
Attachment 9 - Prototype Test Outline.pdf PDF
Attachment 7 - User Acceptance.pdf PDF
Attachment 18 - Weapons Sample SLA.pdf PDF
Attachment 15 - PGS Model OTA DRAFT 23JAN2026.docx DOCX document
Attachment 10 - Available Maintenance Tools.pdf PDF
PGS PPON Final 01APR2026.pdf PDF
Attachment 17 - Ammunition - Sample SLA.pdf PDF
Attachment 16 - Fire Control - Sample SLA.pdf PDF
Attachment 8_Weapons_Ammo_FC TDP Worksheet.pdf PDF
Attachment 14- Ammo Packaging Drawings.pdf PDF
Attachment 12 - Mount Drawings.pdf PDF
Attachment 5_ICD TDP Worksheet.pdf PDF
Attachment 6 -Operational Effectiveness.pdf PDF
Attachment 4 - Pricing .xlsx XLSX spreadsheet
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3 - Delivery Schedule

Weapon Ammunition Fire Control

2.3.2.2.3 Program Start up Meeting Contractor Scheduled

2.3.2.2.3 Program Start up Meeting Read Aheads Read ahead 5 business days prior to meeting

2.3.2.2.3 Technical and Production Metrics

Read ahead 5 business days prior to meeting and Quarterly

2.3.12 Marking Plan 60 days after award

2.3.2.2.4 PT Pre-Ship Meeting Contractor Scheduled prior to PT hardware shipment

2.3.2.2.4 PT Pre-Ship Read Aheads Read ahead 5 business days prior to meeting

2.3.2.2.4 PT Ammo LOT Data 1 6 Weeks prior to PT Ammo Shipment

2.3.2.2.5 TiC Task Pre-Ship Meeting Contractor Scheduled prior to TiC hardware shipment

2.3.2.2.5 TiC Task Read Aheads Read ahead 5 business days prior to meeting

2.3.2.2.4 TiC Ammo LOT Data 1 6 Weeks prior to TiC Ammo Shipment

2.2.1.2.1 Weapons 16 30 days prior to PT

2.2.1.3.1

Family of Ammunition (As proposed per Attachment 1)

NOTE: If a capability is not proposed, that round type is not required for delivery.

17,600 (TP)

2,200 (CQB)

2,700 (CD)

2,900 (C-sUAS)

30 days prior to PT

2.2.1.4 Fire Control 28 30 days prior to PT

2.2.1.2.2 Magazine 6 months prior to PT

2.2.1.3.2 DDI, HPT, Primed Cases, Arena Ammunition

16 (HPT)

800 (DDI)

15 (Primed) 20 (Arena)

300 (Special Fuze)

30 days prior to PT

2.2.1.3.2 High Pressure Establishment Test raw data and calculations 1 report 30 days prior to PT

2.2.1.4 Fire Control System/Subsystem Specification 1 30 days prior to PT

2.2.1.4.1 Fire Control Prototype Hardware Kit 28 30 days prior to PT

2.2.5 Company System Test Support Package 1 1 30 days prior to PT and TiC Task

2.2.6 Non Metalic Coupons 22 if necessary 22 if necessary 22 if necessary 30 days prior to PT

2.2.8.1 EPVAT/Mann Barrels 30 days prior to PT

2.2.8.1 Mann Barrels drawings 30 days prior to PT

2.3.3 Reliability Growth Plan 1 1 1 30 days prior to PT

2.3.4.1 System Safety Program 30 days prior to PT

2.3.4.2 System Safety Hazard Analysis Report 30 days prior to PT

2.3.4.3 Safety Assessment Report 30 days prior to PT

2.3.7.2 Explosive Ordnance Disposal Procedure 30 days prior to PT

2.3.10.1 Life Cycle Environmental Assessment 30 days prior to PT

2.3.10.3 Pollution Prevention Program/Plan 30 days prior to PT

2.3.10.4 Hazardous Materials Management Program/Plan 30 days prior to PT

2.3.10.5 Hazardous Materials Management Plan Report 30 days prior to PT

2.3.11.1 Technical Manuals (-10 and -20&P) 30 days prior to PT

2.3.11.2 Training Materials As necessary

2.3.11.2 Instructor and Key Personnel Training As necessary

15 months after award

2.2.7 Bulk Energetic Materials 30 days prior to PT

2.3.5 Ammunition Hazard Classification 2 months prior to any delivery to support USG tests

2.3.5.1 Interim Hazard Classification 3 months prior to start of any USG tests

2.3.12.2 Ammunition Packaging and Marking 3 months prior to start of any USG tests

2.3.1.1.1 Technical Data Package (TDP): Weapon, Fire Control, Ammunition 1 1 1 60 days after PT end

2.3.1.1.2 Computer Software Data Delivery (if applicable) 60 days after PT end

2.3.1.1.3 Fire Control Interace Control Documentation 1 60 days after PT end

2.3.1.1.4 Ammunition Programmer Interace Control Documentation 1 60 days after PT end

2.3.7.3 Cartridge EOD Models and Desk Models 1 60 days after PT end

2.3.15 Manufacturing Maturity Plan 1 1 1 90 days after PT end

Attachment 11 Counterintelligence Awareness and Reporting As necessary Attachment 11 Antiterrorism As necessary Attachment 11 Information Security As necessary Attachment 11 Operations Security As necessary

2.2.2.1.3 TiC Ammunition - Data Cards Before delivery of ammunition

2.3.2.4 Integrated Master Schedule (IMS) Quarterly (or when required)

2.3.2.5.1 Copyright and Technical Data Rights As necessary

2.3.2.5.2 Copyright and Computer Software Data Rights As necessary

2.3.6 AFSRB Briefings Quarterly

2.3.4.4 Accident/Incident Report Within 24 hrs of incident

2.3.8.1 Radioactive Material Justification As necessary

2.3.8.2 Radioactive Wipe Test Report As necessary

2.3.9.3 System Level Company Test Documentation

Plan: 5 days prior to test / Report: 30 days after test completion

2.3.10.6 Hazardous Materiels As Necessary

2.3.10.7 Hazardous Waste Report 180 days after award

2.3.10.7 Updated Hazardous Waste Report Yearly

2.3.14 Cartridge Marking Drawing/Information and Ammunition Data Cards 6 Weeks prior to PT

Other Data Deliverables

1 for each round and/or Lot

1 combined or 1 for each (per Lot)

1 combined or 1 for each 1 combined or 1 for each 1 combined or 1 for each 1 combined or 1 for each 1 combined or 1 for each

1 combined or 1 for each

Statement of Work Reference

Quantities

1 combined or 1 for each

1 combined or 1 for each

Prototype Test Deliveries

3 Magazines

1 combined or 1 for each

1 combined or 1 for each 1 combined or 1 for each 1 combined or 1 for each

Government Prototype Test Start

Date Program Start-up Activities

Design Finalization Activities 50 lbs Propellant if necessary

1 as necessary

1 as necessary

1 combined or 1 for each

Prototype Test Post Activities