This document is a federal contract opportunity announcement for the construction of a new F-35 simulator facility and base supply complex. The Alabama National Guard intends to award a firm fixed-price contract between $10-25 million to construct a 19,000 square foot simulator facility and 39,000 square foot supply complex in accordance with specifications and drawings dated March 2021. The North American Industry Classification System code is 236220 for nonresidential commercial and health care structure construction. The small business size standard is $39.5 million and this award is reserved for small businesses. A pre-bid conference will be held on October 26th at 2pm at a specified location for briefing and questions, with site visits following. Interested vendors must submit an entry authorization list by October 21st to the listed points of contact. Vendors are encouraged to review all attachments before the pre-bid conference.
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
187th Fighter Wing, Dannelly Field, AL ANG, Montgomery, AL
F-35: Simulator Facility (FAKZ189019)
New Base Supply Complex (FAKZ999088)
Consolidated General Requirements Specifications for the
Date: 31 March 2021 Revised:
Job No: FAKZ189019 (SS&l#18049) /FAKZ999088(SSL#18042) Set No:
Submittal: B-3
PROPERTY OF THE UNITED STATES GOVERNMENT
COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE DRAWINGS, PLANS,
OR SPECIFICATIONS TO UNAUTHORIZED USERS IS PROHIBITED
Do not remove this notice
Properly destroy documents when no longer needed
ARCHITECTURE & INTERIOR DESIGN
1115 South Court Street | Montgomery, AL 36104
Tel. 334. 263. 5162 | WWW.SSLARCH.COM
Consolidated Specifications for: Type B-3 (100%) Submittal F-35 Simulator Facility (FAKZ18019 / SSL#18049) and 31 March 2021 New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
TABLE OF CONTENTS 1
TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING
REQUIREMENTS
00 0100 PROJECT CONSOLIDATION & SEQUENCING
- CONSOLIDATION SCOPE DIAGRAM
DIVISION 01 - GENERAL REQUIREMENTS
01 0450 CUTTING AND PATCHING 5
01 0500 FIELD ENGINEERING 3
01 2000 PRICE AND PAYMENT PROCEDURES 3
01 2300 ALTERNATE BID ITEMS 9
01 3000 ADMINISTRATIVE REQUIREMENTS 8
01 3001 SUBMITTALS
- AF FORM 66
01 3225 PROJECT SUSTAINABILITY SUMMARY 3
01 3329 SUSTAINABLE DESIGN REPORTING
- FAKZ189019 SUSTAINABILITY SCORESHEET
- FAKZ999088 SUSTAINABILITY SCORESHEET
01 3553 SECURITY PROCEDURES 2
01 4000 QUALITY REQUIREMENTS 7
01 4100 REGULATORY REQUIREMENTS 3
01 4217 DEFINITIONS AND STANDARDS 3
01 5000 TEMPORARY FACILITIES AND CONTROLS 3
01 5100 TEMPORARY UTILITIES 3
01 5213 FIELD OFFICES AND SHEDS 2
01 5460 SAFETY AND HEALTH 5
01 5500 VEHICULAR ACCESS AND PARKING 3
01 5719 TEMPORARY ENVIRONMENTAL CONTROLS 9
01 6000 PRODUCT REQUIREMENTS 10
01 6116 VOLATILE ORGANIC COMPOUND (VOC) CONTENT
RESTRICTIONS
01 7000 EXECUTION AND CLOSEOUT REQUIREMENTS 11
01 7419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 9
01 7800 CLOSEOUT SUBMITTALS 7
01 7900 DEMONSTRATION AND TRAINING 5
01 9113 GENERAL COMMISSIONING REQUIREMENTS 15
DIVISION 02 THROUGH 33 – REFER TO FAKZ189019 & FAKZ999088 TECHNICAL SPECIFICATIONS
APPENDIX A – TECHNICAL SPECIFICATIONS FOR CONSTRUCTION AND MANAGEMENT OF
SENSITIVE COMPARTMENTED INFORMATION FACILITIES (ICD TECH SPEC FOR IC/ICS705)
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
PROJECT CONSOLIDATION AND SEQUENCING 000100 - 1
SECTION 000100 - PROJECT CONSOLIDATION AND SEQUENCING
PART 1 GENERAL
1.01 SECTION INCLUDES:
A. Project Consolidation and Government Intent
B. Overall Contract Duration and Sequencing
C. Overall Supervision Minimum Standards
D. Field Offices
1.02 PROJECT CONSOLIDATION AND GOVERNMENT INTENT
A. It is the intent of the Government to award construction of FAKZ189019 – F-35 Simulator Facility and FAKZ999088 – Base Supply Complex within one firm fixed price contract in accordance with the solicitation requirements provided by the Government to prospective Contractors.
B. A brief project scope includes:
1. FAKZ189019 – Construct 19,000 square foot F-35 Flight Simulator Facility.
Refer to FAKZ189019 specification section 00 0102 “Project Information and Summary” for more detailed description of work associated with
FAKZ189019.
2. FAKZ999088 – Construct 39,000 square foot Base Supply Complex. Refer to FAKZ999088/FAKZ182356 specification section 00 0102 “Project Information and Summary” for more detailed description of work associated with FAKZ999088.
3. See attached Consolidation Scope Diagram for a graphical delineation of the two project scopes.
C. The complete scope of the consolidated award is as outlined in the Government’s solicitation and is inclusive of the following drawings/specifications:
1. FAKZ189019 – F-35 Simulator Facility
a. Revised 100% (Type B3) Drawings dated 31 March 2021.
b. Revised 100% (Type B3) Specifications, Volume 1, dated 31 March 2021.
c. Revised 100% (Type B3) Specifications, Volume 2, dated 31 March 2021.
2. FAKZ999088 – Base Supply Complex
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
PROJECT CONSOLIDATION AND SEQUENCING 000100 - 2
a. 100% (Type B3) Drawings dated 31 March 2021.
b. 100% (Type B3) Specifications, Volume 1, dated 31 March 2021.
c. 100% (Type B3) Specifications, Volume 2, dated 31 March 2021.
1.03 OVERALL CONTRACT DURATION AND SEQUENCING
A. The Period of Performance for the consolidated award of FAKZ189019 and FAKZ999088 is 500 calendar days from the date established by the Contracting Officer in the Notice to Proceed.
B. The work will be completed in a single phase. Work sequence and scheduling shall be the Contractor’s sole responsibility. The project sequence and schedule for the consolidated award shall be as required to achieve beneficial occupancy of all facilities included within the listed period of performance.
1.04 OVERALL SUPERVISION MINIMUM STANDARDS
A. Construction scheduling, sequencing, and supervision is the sole responsibility of the Contractor. The Contractor shall provide on-site, and off-site, staff as required to successfully complete the combined award within the listed Period of Performance. The following are minimum requirements/expectations of the Government for job supervision.
B. Construction Superintendents:
1. The Contractor shall assign the consolidated award a minimum of two on-site superintendents.
2. One superintendent shall be assigned to FAKZ189019.
3. The second superintendent shall be assigned to FAKZ999088.
4. The Contractor may assign additional on-site superintendents as deemed necessary for successful completion of the Work. A minimum of two qualified superintendents are required.
5. All on-site superintendents shall meet the qualification standards outlined in section 01 3000 – Administrative Requirements.
6. The project superintendent for each facility must be on site at all times that any work is being performed by the General Contractor's personnel or any personnel from a subcontractor. The Contractor's Quality Control Manager may temporarily fulfill the project superintendent requirement as outlined below.
C. Quality Control (QC) Manager:
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
PROJECT CONSOLIDATION AND SEQUENCING 000100 - 3
1. The Contractor shall employ a full-time, on-site, staff member to serve as the overall quality control manager for the consolidated award.
2. The QC Manager must meet the following requirements:
a. The QC Manager must have documented experience serving in a quality control role for a minimum of 10 years. Alternatively, the QC Manager may have 5 years of experience serving in a quality control role if the QC Manager has a 4-year degree in Building Science from an accredited university.
b. The QC Manager must have served as the QC Manager on projects of similar size and complexity. An individual will experience on projects of similar size and complexity is defined as an individual meeting two of the following criteria.
1) Served as construction superintendent or quality control manager for one project exceeding $15,000,000 in construction cost.
2) Served as construction superintendent or quality control manager for one project that contained a Secure Access Program Facility (SAPF) in excess of 2,000 square feet.
3) Served as construction superintendent or quality control manager for at least three projects exceeding $5,000,000 in construction cost.
3. The QC Manager may serve as an alternate superintendent for up to 5 consecutive calendars days upon either a planned or unexpected absence of one of the primary superintendents. The QC Manager may not serve as the alternate superintendent for more than one facility at a time. If the primary superintendent absence overlaps or exceeds 5 consecutive calendar days, the Contractor shall assign a fourth qualified individual to assume the role of the absent primary superintendent.
D. Site Safety Manager:
1. In addition to the require superintendents and Site QC Manager, the General Contractor shall provide one or more Site Safety Manager(s).
2. The role of site safety manager can be filled by the QC Manager or the project Superintendent.
a. If the project Superintendents are intended to fill the role of Site Safety Manager, both required Superintendents must meet the required OSHA credential below and shall serve as the Site Safety Manager for the respective project scope.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
PROJECT CONSOLIDATION AND SEQUENCING 000100 - 4
b. Alternatively, the QC Manager may serve as an overall Site Safety Manager for both facilities.
3. The individual fulfilling the Site Safety Manager Responsibility must have completed required OSHA training and be a holder, in good standing, of a current OSHA 30-Hour Card.
E. Project Manager:
1. The Contractor shall employ at least one full-time, off-site project manager assigned to the consolidated award.
2. The contractor’s project manager must be an employee of the General Contractor. Third-party project management will not be acceptable for the consolidated award.
3. Refer to section 01 3000 Administrative Requirements for additional project manager requirements.
FIELD OFFICES
A. The Contractor shall furnish one, or more, field offices for the duration of the period of performance.
B. The field office shall be large enough to accommodate, at a minimum, the following:
1. Dedicated private office space for the construction superintendent of
FAKZ189019
2. Dedicated private office space for the construction superintendent of
FAKZ999088
3. Dedicated private office space for the on-site quality control and safety manager
4. Dedicated private office space for one full-time, on-site representative of the Architect.
5. Meeting space to accommodate at least eight persons.
C. The Contractor may, at their discretion, provide one large field office to accommodate the above requirements, or provide two smaller field offices. If two separate field offices are provided, they should be co-located on the project site with easy accessibility to both facilities included with the consolidated award.
D. The Contractor shall furnish the field office with the minimum following furniture/equipment:
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
PROJECT CONSOLIDATION AND SEQUENCING 000100 - 5
1. Two plan tables
2. Filing cabinets for project documents including specifications, addenda, RFI, change orders, submittals, and record documents.
3. One filing cabinet for each of the full time, on-site, representatives of both the Contractor and Architect.
4. One office desk and chair for each of the full time, on-site, representatives of both the Contractor and Architect.
5. Conference table and chairs for at least eight.
6. Six adjustable band protective helmets and reflective safety vests for visitors.
7. Restroom facility.
8. All required utilities including high speed internet for use by both the Contractor’s full time, on site representatives as well as the Architect’s full-time, on-site representative.
9. Personal computer/laptop and laser jet printer for each of the Contractor’s full time, on-site representatives. The Architect will provide a computer/laptop and printer for the Architect’s full-time, on-site representative.
E. The Contractor will be responsible for all required utilities associated with the field office/shed including those utilities utilized by the Architect’s full-time on-site representative for the duration of the consolidated award.
F. Refer to specification section 01 5213 “Field Offices and Sheds” for additional applicable requirements.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
END OF SECTION
This page intentionally left blank
DW
R
EF
BASE SUPPLY COMPLEXFAKZ999088
F35 FLIGHT SIMULATORFAKZ189019
SQUADRON OPERATIONS
BUILDING
GYM BUILDING
PERIMETER ROAD
PE
R
IM
ET
ER
R O
A D
FUEL CELL
BUILDING
COMMUNICATIONS BUILDING 1109 DENOTES SCOPE OF WORK
INCLUDED IN FAKZ189019
DENOTES SCOPE OF WORK
INCLUDED IN FAKZ999088
R
IC
H A R D
S O
N R
O A D
FAKZ 999088 / FAKZ 189019
CONOSLIDATION SCOPE DIAGRAM
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
CUTTING AND PATCHING 010450 - 1
SECTION 010450 - CUTTING AND PATCHING
1. GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including Requirements of the Government's Solicitation and other Division-1 Specification Sections, apply to this Section.
1.02 SUMMARY
A. This Section specifies administrative and procedural requirements for cutting and patching.
B. Refer to other Sections for specific requirements and limitations applicable to cutting and patching individual parts of the Work.
1. Requirements of this Section apply to mechanical and electrical installations.
Refer to Divisions 21, 22, 23, 26 & 27 Sections for other requirements and limitations applicable to cutting and patching mechanical and electrical installations.
1.03 SUBMITTALS
A. Cutting and Patching Proposal: Where approval of procedures and/or phasing for cutting and patching is required before proceeding, submit a proposal describing procedures well in advance of the time cutting and patching will be performed and request approval to proceed. Include the following information, as applicable, in the proposal:
B. Describe the extent of cutting and patching required and how it is to be performed;
indicate why it cannot be avoided.
C. Describe anticipated results in terms of changes to existing construction; include changes to structural elements and operating components as well as changes in the building's appearance and other significant visual elements.
D. List products to be used and firms or entities that will perform Work.
E. Indicate dates when cutting and patching is to be performed.
F. List utilities that will be disturbed or affected, including those that will be relocated and those that will be temporarily out-of-service. Indicate how long service will be disrupted.
G. Where cutting and patching involves addition of reinforcement to structural elements, submit details and engineering calculations to show how reinforcement is
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
CUTTING AND PATCHING 010450 - 2
integrated with the original structure.
H. Approval by the Contracting Officer to proceed with cutting and patching does not waive the Contracting Officer's right to later require complete removal and replacement of a part of the Work found to be unsatisfactory.
1.04 QUALITY ASSURANCE
A. Requirements for Structural Work: Do not cut and patch structural elements in a manner that would reduce their load-carrying capacity or load-deflection ratio.
B. Obtain approval of the cutting and patching proposal before cutting and patching the following structural elements:
1. Foundation construction.
2. Bearing and retaining walls.
3. Structural concrete.
4. Structural steel.
5. Lintels.
6. Timber and primary wood framing.
7. Structural decking.
8. Stair systems.
9. Miscellaneous structural metals.
10. Exterior curtain wall construction.
11. Equipment supports.
12. Piping, ductwork, vessels and equipment.
13. Structural systems of special construction in Division-13.
C. Operational and Safety Limitations: Do not cut and patch operating elements or safety related components in a manner that would result in reducing their capacity to perform as intended, or result in increased maintenance, or decreased operational life or safety.
1. Obtain approval of the cutting and patching proposal before cutting and patching the following operating elements or safety related systems:
a. Primary operational systems and equipment.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
CUTTING AND PATCHING 010450 - 3
b. Membranes and flashings.
c. Fire protection systems.
d. Communication systems.
e. Electrical wiring systems.
PART 2 PRODUCTS
2.01 MATERIALS
A. Use materials that are identical to existing materials. If identical materials are not available or cannot be used where exposed surfaces are involved, use materials that match existing adjacent surfaces to the fullest extent possible with regard to visual effect. Use materials whose installed performance will equal or surpass that of existing materials.
PART 3 EXECUTION
3.01 INSPECTION
A. Before cutting existing surfaces, examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed. Take corrective action before proceeding, if unsafe or unsatisfactory conditions are encountered.
1. Before proceeding, meet at the site with parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.
3.02 PREPARATION
A. Temporary Support: Provide temporary support of Work to be cut.
B. Protection: Protect existing construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of the Project that might be exposed during cutting and patching operations.
C. Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.
D. Take all precautions necessary to avoid cutting existing pipe, conduit or ductwork serving the building, but scheduled to be removed or relocated until provisions have been made to bypass them.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
CUTTING AND PATCHING 010450 - 4
3.03 PERFORMANCE
A. General: Employ skilled workmen to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time and complete without delay.
1. Cut existing construction to provide for installation of other components or performance of other construction activities and the subsequent fitting and patching required to restore surfaces to their original condition.
B. Cutting: Cut existing construction using methods least likely to damage elements to be retained or adjoining construction. Where possible review proposed procedures with the original installer; comply with the original installer's recommendations.
1. In general, where cutting is required use hand or small power tools designed for sawing or grinding, not hammering and chopping. Cut holes and slots neatly to size required with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
2. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces.
3. Cut through concrete and masonry using a cutting machine such as a carborundum saw or diamond core drill.
4. Comply with requirements of applicable Sections of Division-2 where cutting and patching requires excavating and backfilling.
5. By-pass utility services such as pipe or conduit, before cutting, where services are shown or required to be removed, relocated or abandoned. Cut-off pipe or conduit in walls or partitions to be removed. Cap, valve or plug and seal the remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after by-passing and cutting.
C. Patching: Patch with durable seams that are as invisible as possible. Comply with specified tolerances.
1. Where feasible, inspect and test patched areas to demonstrate integrity of the installation.
2. Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.
3. Where removal of walls or partitions extends one finished area into another, patch and repair floor and wall surfaces in the new space to provide an even surface of uniform color and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary to achieve uniform color
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
CUTTING AND PATCHING 010450 - 5
and appearance.
a. Where patching occurs in a smooth painted surface, extend final paint coat over entire unbroken containing the patch, after the patched area has received primer and second coat.
4. Patch, repair or rehang existing ceilings as necessary to provide an even plane surface of uniform appearance.
3.04 CLEANING
A. Thoroughly clean areas and spaces where cutting and patching is performed or used as access. Remove completely paint, mortar, oils, putty and items of similar nature.
Thoroughly clean piping, conduit and similar features before painting or other finishing is applied. Restore damaged pipe covering to its original condition.
END OF SECTION 01045
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
FIELD ENGINEERING 010500 - 1
SECTION 010500 - FIELD ENGINEERING
1. GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including Requirements of the Government's Solicitation and other Division-1 Specification Sections, apply to this Section.
1.02 SUMMARY
A. General: This Section specifies administrative and procedural requirements for field engineering services, including, but not necessarily limited to, the following:
1. Land Survey Work.
1.03 SUBMITTALS
A. Certificates: Submit a certificate signed by the Land Surveyor or Professional Engineer certifying that the location and elevation of improvements comply with the Contract Documents.
B. Project Record Documents: Submit a record of Work performed and record survey data as required under provisions of Sections "Submittals" and "Project Closeout".
1.04 QUALITY ASSURANCE
A. Surveyor: Engage a Registered Land Surveyor registered in the State where the project is located, to perform land surveying services required.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.01 EXAMINATION
A. The Government will identify existing control points and property line corner stakes.
B. Verify layout information shown on the Drawings, in relation to the property survey and existing benchmarks before proceeding to layout the Work. Locate and protect existing benchmarks and control points. Preserve permanent reference points during construction.
1. Do not change or relocate benchmarks or control points without prior written approval. Promptly report lost or destroyed reference points, or requirements to relocate reference points because of necessary changes in grades or
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
FIELD ENGINEERING 010500 - 2
locations.
2. Promptly replace lost or destroyed project control points. Base replacements on the original survey control points.
C. Establish and maintain a minimum of one permanent benchmark on the site, referenced to data established by survey control points.
1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents.
D. Existing utilities and equipment: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities and other construction.
1. Prior to construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer and water service piping.
2. The Government requires a dig permit to be submitted for and approved prior to drilling or digging that might impact underground utilities. Coordinate with Contracting Officer Representative in advance of activities requiring an approved dig permit. Submit permit application to Base Civil Engineering a minimum of one week prior to scheduled start of activities requiring a dig permit.
3.02 PERFORMANCE
A. Working from lines and levels established by the property survey, establish benchmarks and markers to set lines and levels at each story of construction and elsewhere as needed to properly locate each element of the Project. Calculate and measure required dimensions within indicated or recognized tolerances. Do not scale Drawings to determine dimensions.
1. Advise entities engaged in construction activities, of marked lines and levels provided for their use.
2. As construction proceeds, check every major element for line, level and plumb.
B. Surveyor's Log: Maintain a surveyor's log of control and other survey Work. Make this log available for reference.
1. Record deviations from required lines and levels, and advise the Contracting Officer when deviations that exceed indicated or recognized tolerances are detected. On Project Record Drawings, record deviations that are accepted and not corrected.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
FIELD ENGINEERING 010500 - 3
C. Site Improvements: Locate and lay out site improvements, including pavements, stakes for grading, fill and topsoil placement, utility slopes and invert elevations by instrumentation and similar appropriate means.
D. Building Lines and Levels: Locate and lay out batter boards for structures, building foundations, column grids and locations, floor levels and control lines and levels required for mechanical and electrical Work.
E. Existing Utilities: Verify locations of all utilities prior to commencing. Furnish information necessary to adjust, move or relocate existing structures, utility poles, lines, services or other appurtenances located in, or affected by construction.
Coordinate with local authorities having jurisdiction with construction.
END OF SECTION 01050
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
PRICE AND PAYMENT PROCEDURES 012000 - 1
SECTION 012000 - PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Procedures for preparation and submittal of applications for progress payments.
B. Documentation of changes in Contract Price and Contract Time.
C. Procedures for preparation and submittal of application for final payment.
1.02 RELATED REQUIREMENTS
1.03 SCHEDULE OF VALUES
A. Form to be used: Government's Approved Form.
B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to the Government for approval.
C. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification section. Identify site mobilization, bonds and insurance, and material versus labor costs .
1. Provide seperate line items for material and labor for each item of work.
2. Provide separate line items for each direct general contractor's cost for general conditions including:
a. Bonds
b. Insurance
c. Superintendent
d. Quality Control Representative
e. On Site Office Cost including rent (if applicable), utilities and supplies.
3. Break larger items of work down into line items not exceeding $50,000 in value unless specifically approved by the Government.
4. Provide separate schedule of values for ech facility included witin the consolidated award.
D. Revise schedule to list approved Change Orders, with each Application For Payment.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
PRICE AND PAYMENT PROCEDURES 012000 - 2
1. Change Orders should be listed as separate line items included at the end of the schedule of values.
2. When a Change Order includes mutiple items of work, each item of work shall be listed as a separate line item with the approximate percentage complete for each scope of work listed.
E. Submit schedule of values within the timeframe outlined in the General Conditions of the Contract for Construction.
1.04 APPLICATIONS FOR PROGRESS PAYMENTS
A. Comply with all requirements of the General Conditions of the Contract for Construction. Additional requirements/explanations are listed below.
B. Use Government's Approved Form .
C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to the Government for approval.
D. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored products.
1. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.
E. Include the following with the application:
1. Transmittal letter as specified for submittals in Section 013000.
2. Construction progress schedule, revised and current as specified in Section 013000.
3. Current construction photographs specified in Section 013000.
1.05 STORED MATERIALS:
A. Off-site stored materials must be authorized for consideration in the awarded contract and be approved by the Contracting Officer if the Contactor anticipates requesting payment for off-site stored materials prior to the materials being delivered to the project site and and/or placed into operation/construction.
B. The following will be required prior to approval of payment for off-site stored materials:
1. Bill of lading for materials.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
PRICE AND PAYMENT PROCEDURES 012000 - 3
2. Documentation that the materials have been titled to the Contractor and will be used exclusively in the performance of the Contract.
3. Evidence of insurance for the facility storing the materials reflecting 100% total replacement value coverage.
4. Photographs of the materials being stored.
C. The Contracting Officer must verify and approve of off-site stored materials prior to approval of payment. Approval of off-site storage (item A above) will not guarantee approval of payment for off-site stored materials. Payment of off-site stored materials will be at the discretion of the Contracting Officer pending verification of the materials being stored and review of required documentation (item B above) offered by the Contractor with the application for payment.
1.06 MODIFICATION PROCEDURES
A. Comply with all requirements of the General Conditions of the Contractor for Construction.
B. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.
1.07 APPLICATION FOR FINAL PAYMENT
A. Comply with all requirements of the General Conditions of the Contractor for Construction.
B. Application for Final Payment will not be considered until the following have been accomplished:
1. All closeout procedures specified in Section 017000.
2. All stipulated requirements stated in the General Conditions of the Contract for Construction. .
PART 2 PRODUCTS - NOT USED
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ALTERNATE BID ITEMS 012300 - 1
SECTION 012300 - ALTERNATE BID ITEMS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Description of Alternate Bid Items .
B. Procedures for pricing Alternate Bid Items .
1.02 ACCEPTANCE OF Alternate Bid Items
A. Alternate Bid Items quoted on Bid Forms will be reviewed and accepted or rejected at the Government's option in accordance with the requirements of the Contract Documents. Accepted Alternate Bid Items will be identified in the Construction Contract.
B. Coordinate related work and modify surrounding work to integrate the Work of each Alternate Bid Items .
1.03 SUMMARY
A. Definition: An Alternate Bid Items is an amount proposed by Bidders and stated on the Bid Form for certain construction activities defined in the Bidding Requirements that may be added to the Base Bid amount if the the Government decides to accept a corresponding change in either the amount of construction to be completed, or in the products, materials, equipment, systems or installation methods described in Contract Documents. The Base Bid is all items shown on the the Contract Documents except items to be added back by below schedule of Alternate Bid Items.
B. Coordination: Coordinate related Work and modify or adjust adjacent Work as necessary to ensure that Work affected by each accepted Alternate Bid Item is complete and fully integrated into the project.
C. Schedule: A "Schedule of Alternate Bid Items" is included at the end of this Section. Specification Sections referenced in the Schedule contain requirements for materials and methods necessary to achieve the Work described under each Alternate Bid Item.
D. Include as part of each Alternate Bid Item, miscellaneous devices, accessory objects and similar items incidental to or required for a complete installation whether or not mentioned as part of the Alternate Bid Item.
1.04 SCHEDULE OF Alternate Bid Items
A. Alternate Bid Item No. 1 (Additive): Spray Foam Insulation (FAKZ189019)
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ALTERNATE BID ITEMS 012300 - 2
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the F-35 Simulator Facility (FAKZ189019):
a. Provide and install spray foam insulation at all SAPF and SAPCA perimeter walls.
b. Install spray foam for the full width of metal stud cavity and in accordance with specification section 07 2119 - Spray Foam Insulation.
c. If this Alternate Bid Item is not awarded, the base bid shall consist of installation of rockwool insulation at all SAPF and SAPCA (refer to FAKZ189019 drawing sheets A2.1, A2.2, and A2.8 for locations of SAPF and SAPCA walls) perimeter interior wall assemblies. Spray foam insulation shall be provided at all exterior SAPF/SAPCA perimeter wall applications.
B. Alternate Bid Item No. 2 (Additive): Interior Upgrades (FAKZ189019):
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the F-35 Simulator Facility (FAKZ189019):
a. This Alternate Bid Item shall include all plant, labor, and material for the following finish upgrades in rooms 105, 108, 110, 111, and 114
1) In room 105, the Alternate Bid Item shall include all required plant, labor, and materials to install wall tile type 4 (including required cementituous concrete backer board and all tile accessories) behind water fountains as indicated on drawing sheet A7.1. If this Alternate Bid Item is not awarded, the base bid shall consist of painted sheetrock in areas indicated to receive wall tile type 4.
2) In room 108, the Alternate Bid Item shall include all required plant, labor, and materials to install Wall Tile Type 2 behind architectural casework as indicated on sheet A7.1. This Alternate Bid Item shall also include all plant labor and materials to install acoustical felt baffles and thin veneer masonry cladding in room 108. If this Alternate Bid Item is not awarded, the base bid wall finish shall consist of painted sheetrock walls. If this Alternate Bid Item is not awarded the base bid ceiling finish will consist of exposing the aluminum composite ceiling assembly and installation of the pendent mounted light fixtures without the installation of the acoustical baffles.
3) In room 110 the Alternate Bid Item shall include all plant, labor, and materials required for installation of thin veneer masonry cladding in
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ALTERNATE BID ITEMS 012300 - 3
this space. This Alternate Bid Item shall also include all accessory materials (including cementituous backer board) necessary for thin veneer masonry installation. If the Alternate Bid Item is not awarded, the base bid shall consist of installation of painted sheetrock in this areas.
4) In room 111, the Alternate Bid Item shall include all required plant, labor, and materials to install wall tile type 2 (including required cementituous concrete backer board and all tile accessories) behind architectural casework as indicated on drawing sheet A7.1. If this Alternate Bid Item is not awarded, the base bid shall consist of painted sheetrock in areas indicated to receive wall tile type 2.
5) In room 114, the Alternate Bid Item shall include all required plant, labor, and materials to install wall tile type 2 (including required cementituous concrete backer board and all tile accessories) behind water fountains and architectural casework as indicated on drawing sheet A7.2. If this Alternate Bid Item is not awarded, the base bid shall consist of painted sheetrock in areas indicated to receive wall tile type 2.
C. Alternate Bid Item No. 3 (Additive): Interior Upgrades (FAKZ999088)
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the Base Supply Facility (FAKZ999088):
a. Solid Surface Countertops: Provide solid surface countertops at all locations shown to receive plastic laminate. Provide integral solid surface, ADA compliant sink basins at all restroom lavatories per specification section 12 3600.
b. Anti-fatique Mats: Provide and install anti-fatique mats as specified in section 09 6500 and at locations shown on drawings.
c. Wood Base: Provide 1x6 solid wood, white oak, wall base and 1/2" x 3/4" floor molding (transparent finish) in Circulation 102 and Day Room 202 in lieu of rubber base as specified in section 06 2000.
d. Accent Wall Tile at Water Cooler: Provide and install WT2 on walls behind and adjacent to electric water cooler in room 114. See A6.2 and A3.1 for additional location and configuration of wall tile.
e. Additional Wall Tile in Restroom 117: Provide and install WT1 on walls as indicated on A6.1 and A3.1.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ALTERNATE BID ITEMS 012300 - 4
f. Additional Wall Tile in Restroom 115: Provide and install WT1 on walls as indicated on A6.1 and A3.1.
g. Wood wall, plywood, associated fasteners and additional framing as required in rooms 113, 118, and 125. In lieu of gypsum wallboard on metal stud framing, provide and install 3/4" X 4" poplar boards and plywood on metal stud framing. Refer to A7.1 and A3.1 for extents and exact location of wood wall.
D. Alternate Bid Item No. 4 (Additive): Exterior Plaza Upgrades (FAKZ189019):
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the F-35 Simulator Facility (FAKZ189019):
a. Installation of architectural pavers and bench seating in exterior areas as indicated on the landscape drawings. If the Alternate Bid Item is not awarded, the base bid shall consist of textured concrete paving only (no pavers or benches will be installed) as indicated on the base bid landscape drawings.
b. Refer to drawing sheets L1.0, L1.1, L2.0, L2.1, C2.1, and C7.1 for application of architectural pavers/benches associated with this Alternate Bid Item.
E. Alternate Bid Item No. 5 (Additive): Exterior Plaza Upgrades (FAKZ999088):
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the Base Supply Facility (FAKZ999088):
a. Installation of architectural pavers and bench seating in exterior areas as indicated on the landscape drawings. If the Alternate Bid Item is not awarded, the base bid shall consist of textured concrete paving only (no pavers or benches will be installed) as indicated on the base bid landscape drawings.
F. Alternate Bid Item No. 6 (Additive): Tiered Auditorium Seating
(FAKZ189019):
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the F-35 Simulator Facility (FAKZ189019):
a. Provide and install tiered floor structure assembly, associated floor finishes and handrail assemblies at walls along aisles of tiered seating.
b. Provide and install Fixed Seating as shown on drawings and specified in Section 12 6100 - Fixed Audience Seating.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ALTERNATE BID ITEMS 012300 - 5
2. If this Alternate Bid Item is not awarded, the base bid shall include carpet tile and rubber base installed over a flat 18" raised floor system matching the floor system in the adjacent hallway and IOS areas.
G. Alternate Bid Item No. 7 (Additive): Increase extents of Access Flooring
(FAKZ189019)
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the F-35 Simulator Facility (FAKZ189019):
a. Provide and install additional raised access flooring in rooms 109, 113, 115, 116, 119, 120, & 121 - refer to sheet A9.2. Included in this Alternate Bid Item is all associated raised access flooring panels/pedestals, revised extents of depressed floor slabs, additional electrical bonding/grounding, and revised extents of foundation drainage systems required to install raised access flooring in these areas.
b. If this Alternate Bid Item is not awarded, the base bid shall consist of installation of the specified floor finish over a cast-in-place concrete floor slab in the listed rooms. Base bid shall include depression of the concrete slab, installation of foundation drainage systems, and installation of raised access flooring systems (inclusive of panels, pedestals, associated electrical bonding/grounding, and specified floor finish) for all areas scheduled to receive raised access flooring that are not included in this Alternate Bid Item . Refer to drawing sheet A9.2 for extents.
H. Alternate Bid Item No. 8 (Additive): Demolish Building 1202 & Associated Parking Lots (FAKZ999088)
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the Base Supply Facility (FAKZ999088):
a. Demolish, in its entirety, existing Building 1201 and all associated asphalt and portland cement pavings as indicated on drawing sheet C1.2.
Demolition shall include abatement of hazardous materials in accordance with specification sections 02 8213 and 02 8416. Demolition shall also include removal of all existing underground utilities as indicated on drawing sheet C1.2.
b. As part of this Alternate Bid Item, the Contractor shall install grass seed in accordance with section 32 9219 in all areas disturbed by the demolition.
c. If this Alternate Bid Item is not awarded, the existing Building 1202 and associated pavings and utilities will remain in their current condition, without change.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ALTERNATE BID ITEMS 012300 - 6
d. Coordination of Alternate Bid Items 8 & 9 with Hazmat Pharmacy &
DRMO:
1) As part of the base bid, the Contractor shall construct a temporary DRMO storage yard located to the East of Perimeter Road as indicated on the drawings. Contractor shall saw cut existing concrete curb, install gravel surface, and erect temporary fencing as indicated on the drawings. Upon completion of the permanent DRMO storage area (see below), the Contractor shall remove the fencing and gravel, restore/reestablish grass surfaces, and reinstall removed/damages sections of concrete curb/gutter as part of the base bid.
2) Additionally, as part of the base bid, the Contractor shall relocate the existing storage containers on the Base Supply project site and create a new Hazamat Pharmacy in the parking lot behind Building 1204 as indicated on the drawings. The base bid shall also include all electrical and plumbing shown on the drawing to support the temporary Hazmat Pharmacy. Additionally, upon completion of the Base Supply Project Construction, the Contractor shall relocate the storage containers again. One storage container will be relocated to the area indicated North of the new Base Supply. This storage container will be connected to the Base Supply complex electrical, fire protection, and fire alarm systems as indicated on the drawings. The other two storage containers will be relocated to the new DRMO area as indicated below:
(a) If Alternate Bid Item No. 8 is not awarded, the Contractor shall relocate the two storage containers from behind building 1202 to the existing paved area near Building 1202 as indicated on the drawings to create a new DRMO storage yard. As part of the base bid, the Contractor shall also erect the fencing around the DRMO storage area near Building 1202 as indicated on the drawings.
(b) If Alternate Bid Item No. 8 is awarded but Alternate Bid Item No.
9 is not awarded, the Contractor shall leave the existing paved surfaces at the proposed DRMO area near Building 1202, saw cut the existing 0pavings adjacent to the DRMO area as requried to provide paving demolition shown on the drawings as part of Alterntate Bid Item No. 8, and erect fencing indicated on the drawings.
(c) If Alternate Bid Item No. 8 & No. 9 are awarded, the Contractor shall deomlish all the Building 1202 paving, install new asphalt/concrete paving indicated on the drawings, and erect
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ALTERNATE BID ITEMS 012300 - 7
fencing surrounding the larger DRMO area indicated as part of Alternate Bid Item No. 9.
(d) Upon completion of the DRMO area, regardless of which Alternate Bid Items are accepted, the Contractor shall remove the temoporary DRMO gravel area as described in paragraph H(1)d(1) above.
I. Alternate Bid Item No. 9 (Additive): New Parking Lot at Building 1202 Site
(FAKZ999088)
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the Base Supply Facility (FAKZ999088):
a. Provide grading, underground utilities, sub-surface preparation, asphalt paving, concrete paving, concrete curb and gutter, fencing, and other ancillary construction indicated to construct parking area and DRMO storage area at the site of Building 1202 as indicated on the drawings.
b. Refer to drawings sheets C2.2, C3.2, C4.2, and C5.2 for work required as part of this Alternate Bid Item.
c. This Alternate will not be awarded without award of Alternate Bid Item No. 8 above. If Alternate Bid Items 8 & 9 are not awarded, the base bid shall include Building 1202 and associated pavings/utilities remaining as indicated above. Base bid shall also include construction of DRMO yard on exisitng Building 1202 pavings and surrounding fencing as indicated on the drawings. See paragraph (H)1(d) above.
d. If this Alternate Bid Item is not awarded but Alternate Bid Item No. 8 is awarded, the Contractor will be required to erect the DRMO area on the existing Building 1202 paving, construct surrounding fencing, sawcut pavings adjacent to DRMO area to allow for demolition, demolish existing Buildign 1202 and associated pavings and utilities, and then seed distrubed areas of the site. Refer to paragraph (H)1(d) above for additional description.
J. Alternate Bid Item No. 10 (Additive): Operable Mesh Shades(FAKZ999088)
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the Base Supply Facility (FAKZ999088):
a. Provide and install operable mesh shades as specified in section 12 1115 - Operable Mesh Shades at all exterior curtain wall windows.
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ALTERNATE BID ITEMS 012300 - 8
b. If this Alternate Bid Item is not awarded, the base bid shall include no interior window shading devices.
K. Alternate Bid Item No. 11 (Additive): Sodding (FAKZ999088)
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the Base Supply Facility (FAKZ999088):
a. Provide and install sodding, in lieu of seeding, where sod is indicated on drawing sheet L1.0 as well as any other areas where existing lawns are disturbed by construction actvities.
b. Sodding shall be installed in accordance with specificaion section 32 9223 Sodding.
c. If this Alternate Bid Item is not awarded, the base bid shall include installation of grass seed in all areas disturbed by construction activities.
All seeding shall be installed in accordance with specification section 32 9219 - Seeding.
L. Alternate Bid Item No. 12 (Additive): Under Slab Vapor Barrier
(FAKZ999088)
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the Base Supply Facility (FAKZ999088):
a. Provide and install an integrally bonded underslab above grade vapor protection system as specified in Section 07 2650 -Integrally Bonded Underslab Vapor Protection Above and Below grade under all poured in place above grade concrete areas with non-depressed slabs above grade construction.
b. The base bid shall include installation of an underslab vapor barrier as specified in section 03 3000 - Cast-In-Place Concrete under all areas with non-depressed slab on grade construction. Below grade concrete slab vapor protection shall be per Section 07 2650.
M. Alternate Bid Item No. 13 (Additive): Under Slab Vapor Barrier
(FAKZ189019)
1. This Alternate Bid Item shall include all plant, labor, and material for the following scope of work at the F-35 Simulator Facility (FAKZ189019):
a. Provide and install an integrally bonded underslab above grade vapor protection system as specified in Section 07 2650 -Integrally Bonded Underslab Vapor Protection Above and Below grade under all poured in place above grade concrete areas with non-depressed slabs above grade
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ALTERNATE BID ITEMS 012300 - 9
construction.
b. The base bid shall include installation of an underslab vapor barrier as specified in section 03 3000 - Cast-In-Place Concrete under all areas with non-depressed slab on grade construction. Below grade concrete slab vapor protection shall be per Section 07 2650.
c. Refer to drawing sheets A5.2, A5.3, A5.4, A5.5, and A9.2 for location of vapor barrier.
PART 2 PRODUCTS - NOT USED
New Base Supply Complex (FAKZ999088 / SSL#18042) 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL
ADMINISTRATIVE REQUIREMENTS 013000 - 1
SECTION 013000 - ADMINISTRATIVE REQUIREMENTS
PART 1…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .