This document includes an attachment to a solicitation for maintenance and repair services for tactical infrastructure assets in the Tucson Sector for U.S. Customs and Border Protection. The solicitation seeks contractor services to perform maintenance, repair and improvement work for roads and bridges, fencing and gates including concertina wire, vegetation control, debris removal, border lighting and electrical systems, drainage and grate systems, and tunnel remediation. Offerors are instructed to fill out an attached site visit form if attending the site visit, with emails due to the contracting officer no later than February 25, 2021. The work will be performed for CBP's tactical infrastructure assets within the Tucson Sector in Arizona, as set forth in the attached statement of work.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| 70B01C21R00000008 ATTACHMENT 2 - LINE ITEM SUMMARY |
| Instructions to Offeror: |
| The Offeror shall complete the sheets for the Base Period, Option Period 1, Option Period 2, Option Period 3, and Option Period 4 by filling the cells highlighted in YELLOW. In addition, the offeror shall propose its coefficient for the unscheduled maintenance work by completing Cell B6 in the Summary sheet. After entering the proposed prices and the coefficient, the amounts will transfer automatically to the summary sheet to give the total evaluated price. |
Summary
| Requirement | Base Period: | ||||||||
| 07/01/21 - 06/30/2022 | Option Yr 1 | ||||||||
| 07/01/22 - 06/30/23 | Option Yr 2 | ||||||||
| 07/01/23 - 06/30/24 | Option Yr 3 | ||||||||
| 07/01/24 - 06/30/25 | Option Yr 4 | ||||||||
| 07/01/25 - 06/30/26 | Total | Extension Period 07/01/26 - 12/31/26 | Total with 6 month extension | ||||||
| Scheduled Maintenance (FFP-TCA) | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0 | $0.00 | $0.00 | |
| Unscheduled Maintenance (TCA) | $8,992,354.80 | $9,262,125.44 | $9,539,989.21 | $9,826,188.88 | $10,120,974.55 | $47,741,633 | $5,299,524.23 | $53,041,157.11 | |
| Total Price: | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! | ERROR:#REF! |
Coefficient %
Base Period
| BASE PERIOD: TCA SCHEDULED MAINT [FFP] | Description of Service | Qty of Asset | Count of Events | Duration | PRICE | Labor | Equipment | Material | Other | Comments/assumptions | |
| TON Vamori Wash - Normandy Vehicle Barrier | Routine: Remove barriers premonsoon / replace post monsoon | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for removing and one event for re-installing. Install T-posts and barbed wire | |
| TON Culvert inspections pre monsoon | Routine: Inspect culverts for sedimentation and debris accumulation and proper drainage | 37 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| DGL Flood swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 105 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NCO Flood Lift and Swing Gate | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 161 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NGL Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 182 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| AJO Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 63 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| DGL Lighting inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 380 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NCO Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 550 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NGL Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 132 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| DGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 54 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NCO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 29 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| SON Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 19 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 55 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| TUS Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 47 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| AJO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 49 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Smugglers Basin Cleanout | Routine: Remove debris/trash and sedimentation | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
OPT Period 1
| Option 1: TCA SCHEDULED MAINT [FFP] | Description of Service | Qty of Asset | Count of Events | Duration | PRICE | Labor | Equipment | Material | Other | Comments/assumptions | |
| TON Vamori Wash - Normandy Vehicle Barrier | Routine: Remove barriers premonsoon / replace post monsoon | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for removing and one event for re-installing. Install T-posts and barbed wire | |
| TON Culvert inspections pre monsoon | Routine: Inspect culverts for sedimentation and debris accumulation and proper drainage | 37 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| DGL Flood swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 105 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NCO Flood Lift and Swing Gate | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 161 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NGL Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 182 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| AJO Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 63 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| DGL Lighting inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 380 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NCO Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 550 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NGL Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 132 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| DGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 54 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NCO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 29 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| SON Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 19 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 55 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| TUS Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 47 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| AJO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 49 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Smugglers Basin Cleanout | Routine: Remove debris/trash and sedimentation | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
OPT Period 2
| Option 2: TCA SCHEDULED MAINT [FFP] | Description of Service | Qty of Asset | Count of Events | Duration | PRICE | Labor | Equipment | Material | Other | Comments/assumptions | |
| TON Vamori Wash - Normandy Vehicle Barrier | Routine: Remove barriers premonsoon / replace post monsoon | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for removing and one event for re-installing. Install T-posts and barbed wire | |
| TON Culvert inspections pre monsoon | Routine: Inspect culverts for sedimentation and debris accumulation and proper drainage | 37 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| DGL Flood swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 105 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NCO Flood Lift and Swing Gate | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 161 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NGL Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 182 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| AJO Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 63 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| DGL Lighting inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 380 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NCO Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 550 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NGL Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 132 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| DGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 54 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NCO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 29 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| SON Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 19 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 55 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| TUS Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 47 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| AJO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 49 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Smugglers Basin Cleanout | Routine: Remove debris/trash and sedimentation | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
OPT Period 3
| Option 3: TCA SCHEDULED MAINT [FFP] | Description of Service | Qty of Asset | Count of Events | Duration | PRICE | Labor | Equipment | Material | Other | Comments/assumptions | |
| TON Vamori Wash - Normandy Vehicle Barrier | Routine: Remove barriers premonsoon / replace post monsoon | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for removing and one event for re-installing. Install T-posts and barbed wire | |
| TON Culvert inspections pre monsoon | Routine: Inspect culverts for sedimentation and debris accumulation and proper drainage | 37 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| DGL Flood swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 105 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NCO Flood Lift and Swing Gate | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 161 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NGL Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 182 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| AJO Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 63 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| DGL Lighting inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 380 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NCO Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 550 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NGL Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 132 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| DGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 54 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NCO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 29 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| SON Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 19 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 55 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| TUS Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 47 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| AJO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 49 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Smugglers Basin Cleanout | Routine: Remove debris/trash and sedimentation | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
OPT Period 4
| OPTION 4: TCA SCHEDULED MAINT [FFP] | Description of Service | Qty of Asset | Count of Events | Duration | PRICE | Labor | Equipment | Material | Other | Comments/assumptions | |
| TON Vamori Wash - Normandy Vehicle Barrier | Routine: Remove barriers premonsoon / replace post monsoon | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for removing and one event for re-installing. Install T-posts and barbed wire | |
| TON Culvert inspections pre monsoon | Routine: Inspect culverts for sedimentation and debris accumulation and proper drainage | 37 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| DGL Flood swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 105 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NCO Flood Lift and Swing Gate | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 161 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| NGL Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 182 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| AJO Flood Lift and Swing Gates | Routine: Open premonsoon/Close postmonsoon/ Includes lubing and inspection for proper operation and installing barbed fencing across opening | 63 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | one event for opening and one event for closing | |
| DGL Lighting inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 380 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NCO Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 550 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| NGL Lighting Inspections | Routine: Inspect, clean, replace failed components as needed, ie ballasts, lamps, photocells | 132 fixtures | 4 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | Assume 10% quarterly failure rate on lamps, 5% failure rate on ballasts and 5% failure rate on photo cells | |
| DGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 54 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NCO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 29 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| SON Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 19 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| NGL Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 55 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| TUS Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 47 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| AJO Culvert/Cattleguard/Grates | Routine: Inspect for sedimentation and debris accumulation and proper drainage | 49 | 1 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Smugglers Basin Cleanout | Routine: Remove debris/trash and sedimentation | 1 | 2 | 0 | $0 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |