TI Maintenance Work Plan Development Process Flowchart_3-19-21.pdf
PDF 180 KB Posted
- Solicitation number
- 70B01C21R00000008
About this file
This document outlines the maintenance work plan development process for tactical infrastructure assets within the Tucson Sector in Arizona. The process involves nine steps over 90 days, beginning with the contracting officer's representative and area coordinator gathering requirements and planning a site visit. They then send the requirements to the contractor and develop work descriptions. The contractor develops a cost estimate and enters the work plan into the Work Management System. The contracting officer's representative reviews and finalizes the work plan, gaining approval from department directors before activating it in the system.
The related federal contract opportunity is solicitation number 70B01C21R00000008 to provide maintenance, repair and improvement services for tactical infrastructure assets in the Tucson Sector categories of roads and bridges, fencing and gates, vegetation control, debris removal, border lighting and electrical systems, drainage and grates, and tunnel remediation. Services will be required within the specified timeframe and location according to the attached statement of work.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TI Maintenance Work Plan Development Process
Step 3: CTR Finalizes CWP Day 61 - 62: CTR finalizes CWP (hardcopy)
• Submits to COR for review and approval
Step 1: COR/ACOR Gathers Work Plan Requirements
Day 1 - 45: 90 Day CWP Requirements Identified by CTR, BP, and COR
• CTR sends requirements to COR
• BP sends requirements to TI
Coordinator Day 45: All requirements are due
• Prior to next work plan
Day 46: COR and TI Coordinator:
• Review identified requirements , WMS and backlog
• Plan site visit to discuss identified requirements with respective BP stations and CTR
Day 47 - 53: COR Conducts site visit/tailgate meeting with contractor and develops brief work descriptions, Work Order or SOW (as required)
Step 5: CTR Develops Cost Estimate and Enters CWP in WMS Day 68 - 76:
• CTR develops cost estimates for Work
Orders/CWP, submits to COR review/ acceptance (outside of WMS)
• CTR submits CWP to COR/ACOR via WMS
Cost Estimate
Approved?
Yes
No
GO TO
Work Plan Execution
Process
Step 2: COR/ACOR Sends WP Requirements to CTR
Day 54 - 58:
• COR directs CTR to develop CWP
(hard copy) Using Work Orders
• CTR submits CWP to COR for review
Day 58 - 60: COR makes edits to proposed CWP (hardcopy) and submits back to CTR
CWP
Step 6: COR/ACOR Reviews CWP Day 77 - 81:
• Validates all CWP activities
• Reviews cost
• Revises Work Orders/CWP (as necessary)
• Prioritizes work activities
60 days 7 days 23 days
Step 7: COR/ACOR Finalizes CWP in WMS Day 82 - 89:
• COR submits CWP to Director in WMS
• Director validates CWP, adds funds, and submits to OBP
• OBP validates prioritized requirements and submits to BC
• Director marks CWP “Reviewed” and submits to COR Day 90: COR activates CWP in WMS
Step 4: COR/ACOR Meets w/CTR and Routes Final CWP to ENG/ENV/RE
Day 63 - 67:
• COR/ACOR holds discussions to:
- Outline requirements and expectations
- Ensure mutual understanding
• COR submits final CWP (hard copy) to ENG/ENV/RE for review
Slide Number 1