TI Maintenance Work Plan Development Process Flowchart_3-19-21.pdf

PDF 180 KB Posted

Attached to
CBP Tucson Sector Tactical Infrastructure Maintenance and Repair (CTIMR)
Solicitation number
70B01C21R00000008
Issued by

About this file

This document outlines the maintenance work plan development process for tactical infrastructure assets within the Tucson Sector in Arizona. The process involves nine steps over 90 days, beginning with the contracting officer's representative and area coordinator gathering requirements and planning a site visit. They then send the requirements to the contractor and develop work descriptions. The contractor develops a cost estimate and enters the work plan into the Work Management System. The contracting officer's representative reviews and finalizes the work plan, gaining approval from department directors before activating it in the system.

The related federal contract opportunity is solicitation number 70B01C21R00000008 to provide maintenance, repair and improvement services for tactical infrastructure assets in the Tucson Sector categories of roads and bridges, fencing and gates, vegetation control, debris removal, border lighting and electrical systems, drainage and grates, and tunnel remediation. Services will be required within the specified timeframe and location according to the attached statement of work.

View the file

Other files

File Type Posted
Amendment_07_-_70B01C21R00000008_-_SF_30.pdf PDF
Boat Ramp Design Standards.pdf PDF
EC1Y1 RFP TI V4_.pdf PDF
TI Design Standards_v1_Chapter 3_Sept 2012.pdf PDF
TI Design Standards_v1_Chapter 1_Sept 2012.pdf PDF
Submittal 01 - Engineering Letter Shop Drawings.pdf PDF
TI Standards v2_Wall-Fence-Gates Drawing Updates_080618 (003).pdf PDF
TI Design Standards_v1_Chapter 2_Sept 2012.pdf PDF
TI Design Standards_v1_Sept 2012 - Roads Section.pdf PDF
Amendment_06_-_70B01C21R00000008_-_SF_30.pdf PDF
Boat Ramp Detail.pdf PDF
Site Visit Questions Answers 3-22-21 Responses (002).pdf PDF
Amendment_05_-_70B01C21R00000008_-_SF_30.pdf PDF
Site Visit Questions Answers 3-22-21.pdf PDF
70B01C21R00000008 RFP 3-19-21.pdf PDF
ATTACHMENT 1 STATEMENT OF WORK CTIMR TUCSON 70B01C21R00000008 3-19-21 .pdf PDF
Site Visit Questions Answers 3-19-21 Responses (002).pdf PDF
TCA Attachment 2 Line Item Summary 3-19-21.xlsx XLSX spreadsheet
Amendment_04_-_70B01C21R00000008_-_SF_30.pdf PDF
Amendment_03_-_70B01C21R00000008_-_SF_30.pdf PDF
Attachment 2 Line Item Summary 70B01C21R00000008 3-3-2021.xlsx XLSX spreadsheet
Amendment_02_-_70B01C21R00000008_-_SF_30.pdf PDF
RFP 70B01C21R00000008 3-3-2021.pdf PDF
Amendment_01_-_70B01C21R00000008_-_SF_30.pdf PDF
CTIMR Contractor Site Visit.pdf PDF
SCA WAGES SANTA CRUZ.txt TXT text file
SCA WAGES COCHISE COUNTY.txt TXT text file
Attachment 7 Work Order Form 70B01C21R00000008 2-12-21.xlsx XLSX spreadsheet
Attachment 9 Preventive Maintenance Checklist 70B01C21R00000008 2-12-21.pdf PDF
Attachment 2 Line Item Summary 70B01C21R00000008 2-12-21_.xlsx XLSX spreadsheet
ATTACHMENT 5 PAST PERFORMANCE INFORMATION SURVEY 70B01C21R00000008 2-12-21 .docx DOCX document
Attachments 6 SCA WAGE DETERMINATIONS PIMA COUNTY.txt TXT text file
RFP 70B01C21R00000008 2-12-21.pdf PDF
Attachment 1 Statement of Work CTIMR Tucson 70B01C21R00000008 2-12-21.pdf PDF
DBA WAGES COCHISE COUNTY.pdf PDF
Attachment 3 _Unit_Pricing_Sheet 70B01C21R00000008 2-12-21_.xlsx XLSX spreadsheet
Site Visit Sign In.xlsx XLSX spreadsheet
Attachment 4 Notional Work Plan 70B01C21R00000008 2-12-21.xlsx XLSX spreadsheet
DBA WAGES SANTA CRUZ.pdf PDF
Attachment 8 Estimate Form 70B01C21R00000008 2-12-21.xlsx XLSX spreadsheet
DBA WAGES PIMA COUNTY.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TI Maintenance Work Plan Development Process

Step 3: CTR Finalizes CWP Day 61 - 62: CTR finalizes CWP (hardcopy)

• Submits to COR for review and approval

Step 1: COR/ACOR Gathers Work Plan Requirements

Day 1 - 45: 90 Day CWP Requirements Identified by CTR, BP, and COR

• CTR sends requirements to COR

• BP sends requirements to TI

Coordinator Day 45: All requirements are due

• Prior to next work plan

Day 46: COR and TI Coordinator:

• Review identified requirements , WMS and backlog

• Plan site visit to discuss identified requirements with respective BP stations and CTR

Day 47 - 53: COR Conducts site visit/tailgate meeting with contractor and develops brief work descriptions, Work Order or SOW (as required)

Step 5: CTR Develops Cost Estimate and Enters CWP in WMS Day 68 - 76:

• CTR develops cost estimates for Work

Orders/CWP, submits to COR review/ acceptance (outside of WMS)

• CTR submits CWP to COR/ACOR via WMS

Cost Estimate

Approved?

Yes

No

GO TO

Work Plan Execution

Process

Step 2: COR/ACOR Sends WP Requirements to CTR

Day 54 - 58:

• COR directs CTR to develop CWP

(hard copy) Using Work Orders

• CTR submits CWP to COR for review

Day 58 - 60: COR makes edits to proposed CWP (hardcopy) and submits back to CTR

CWP

Step 6: COR/ACOR Reviews CWP Day 77 - 81:

• Validates all CWP activities

• Reviews cost

• Revises Work Orders/CWP (as necessary)

• Prioritizes work activities

60 days 7 days 23 days

Step 7: COR/ACOR Finalizes CWP in WMS Day 82 - 89:

• COR submits CWP to Director in WMS

• Director validates CWP, adds funds, and submits to OBP

• OBP validates prioritized requirements and submits to BC

• Director marks CWP “Reviewed” and submits to COR Day 90: COR activates CWP in WMS

Step 4: COR/ACOR Meets w/CTR and Routes Final CWP to ENG/ENV/RE

Day 63 - 67:

• COR/ACOR holds discussions to:

- Outline requirements and expectations

- Ensure mutual understanding

• COR submits final CWP (hard copy) to ENG/ENV/RE for review

Slide Number 1