This document outlines the scope of work for the Fulton-Gibbs Refurbishment at the U.S. Merchant Marine Academy. The contractor shall provide all labor, materials, equipment, supervision, and disposal required to completely renovate Fulton and Gibbs Halls. Work includes roof and window replacement, upgrading hallway and classroom lighting, replacing emergency shower/eyewash stations, and repointing, patching and painting CMU walls. Additional tasks involve upgrading ventilation and air distribution in diesel and welding labs. The contractor must also assess and abate any asbestos. The solicitation was issued by the Department of Transportation Maritime Administration for the refurbishment located at the U.S. Merchant Marine Academy in Kings Point, New York. The schedule details ten phases of work to be completed over a three year period from March 2023 through March 2026, and estimates the total cost of the project to be $14,930,497.58.
View the file
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FG Schedule Reqts
| Government | Proposed | |||||||||
| ID | Task Name | Duration (Days) | Start | Finish | Resource Names | Cost | Duration (Days) | Start | Finish | |
| 1 | Fulton-Gibbs Refurbishment | 36.65 emo | Wed 3/1/23 | Wed 3/4/26 | $14,930,497.58 | |||||
| 2 | Acquisition | 19 days | Mon 5/1/23 | Fri 5/19/23 | $0.00 | |||||
| 3 | Contract Awarded | 1 day | Mon 5/1/23 | Mon 5/1/23 | $0.00 | |||||
| 4 | Kick-Of Meeting | 1 day | Wed 5/3/23 | Wed 5/3/23 | $0.00 | |||||
| 5 | Mobilization | 12 days | Mon 5/8/23 | Fri 5/19/23 | $0.00 | |||||
| 6 | Phase 1 (Roof & Windows) | 180 | 5/19/23 | 11/14/23 | $4,613,121.17 | 179 | 5/19/23 | 11/14/23 | ||
| 7 | Roof Repairs | 180 | 5/19/23 | 11/14/23 | Roof Replacement[56,195 SF] | $3,585,802.95 | 179 | 5/19/23 | 11/14/23 | |
| 8 | Demo Solar Panels | $0.00 | ||||||||
| 9 | Execution | $0.00 | ||||||||
| 10 | Windows | 60 | 5/19/23 | 7/17/23 | $826,749.32 | 59 | 5/19/23 | 7/17/23 | ||
| 11 | Window Caulking Interior | Window-Caulking Interior[5,875 LF | $16,097.50 | |||||||
| 12 | Window Caulking Exterior | Window-Caulking Exterior[5,875 LF | $100,462.50 | |||||||
| 13 | Window Replacement | Window-Replacement[10 EA] | $34,612.40 | |||||||
| 14 | Window Repair | Window-Repair[81 EA] | $119,176.92 | |||||||
| 15 | Window Film-Solar | Window-Solar Film[10,000 SF] | $556,400.00 | |||||||
| 16 | Eyewash Stations | 65 | 5/22/23 | 7/25/23 | Eyewash Station[6 EA] | $134,544.60 | 64 | 5/22/23 | 7/25/23 | |
| 17 | Atomic Lab 212 (Swing Space) | 65 | 5/22/23 | 7/25/23 | $66,024.30 | 64 | 5/22/23 | 7/25/23 | ||
| 18 | Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[683 | ||||||||
| SF],Industrial Hygienist[1 Day] | $6,397.61 | |||||||||
| 19 | Underlayment/Encapsulation | Underlayment-Epoxy[683 SF] | $8,571.65 | |||||||
| 20 | Epoxy Flooring | Flooring-Epoxy[683 SF] | $25,182.21 | |||||||
| 21 | Paint Ceiling | Ceiling-Paint[683 SF] | $1,140.61 | |||||||
| 22 | Lighting | Lighting[683 SF] | $19,356.22 | |||||||
| 23 | Paint | Wall-Paint[1,050] | $5,376.00 | |||||||
| 24 | Phase 2 (Summer Break) | 32 | 6/24/23 | 7/25/23 | $867,877.12 | 31 | 6/24/23 | 7/25/23 | ||
| 25 | Advanced Chemistry Lab (305) | 32 | 6/24/23 | 7/25/23 | $117,108.26 | 31 | 6/24/23 | 7/25/23 | ||
| 26 | Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[1,261 SF],Industrial Hygienist[1 Day] | $8,703.83 | |||||||
| 27 | Underlayment/Encapsulation | Underlayment-Epoxy[1,261 SF] | $15,825.55 | |||||||
| 28 | Epoxy Flooring | Flooring-Epoxy[1,261 SF] | $46,493.07 | |||||||
| 29 | Lighting | Lighting[1,261 SF] | $35,736.74 | |||||||
| 30 | Paint Ceiling | Ceiling-Paint[1,261 SF] | $2,105.87 | |||||||
| 31 | Paint | Wall-Paint[1,610] | $8,243.20 | |||||||
| 32 | Fume Hoods | $0.00 | ||||||||
| 33 | Chem Prep (306) | 32 | 6/24/23 | 7/25/23 | $59,823.43 | 31 | 6/24/23 | 7/25/23 | ||
| 34 | Abatement | Asbestos Disposal[1 CY],Asbestos-D | $3,248.57 | |||||||
| 35 | Underlayment/Encapsulation | Underlayment-Epoxy[642 SF] | $8,057.10 | |||||||
| 36 | Epoxy Flooring | Flooring-Epoxy[642 SF] | $23,670.54 | |||||||
| 37 | Lighting | Lighting[642 SF] | $18,194.28 | |||||||
| 38 | Paint Ceiling | Ceiling-Paint[642 SF] | $1,072.14 | |||||||
| 39 | Paint | Wall-Paint[1,090] | $5,580.80 | |||||||
| 40 | Fume Hoods | $0.00 | ||||||||
| 41 | Basic Chemistry Lab (307) | 32 | 6/24/23 | 7/25/23 | $129,485.33 | 31 | 6/24/23 | 7/25/23 | ||
| 42 | Abatement | Asbestos Disposal[1 CY],Asbestos-D | $6,460.52 | |||||||
| 43 | Underlayment/Encapsulation | Underlayment-Epoxy[1,447 SF] | $18,159.85 | |||||||
| 44 | Epoxy Flooring | Flooring-Epoxy[1,447 SF] | $53,350.89 | |||||||
| 45 | Lighting | Lighting[1,447 SF] | $41,007.98 | |||||||
| 46 | Paint Ceiling | Ceiling-Paint[1,447 SF] | $2,416.49 | |||||||
| 47 | Paint | Wall-Paint[1,580] | $8,089.60 | |||||||
| 48 | Fume Hoods | $0.00 | ||||||||
| 49 | Machinery Lab (107) | 32 | 6/24/23 | 7/25/23 | $230,644.84 | 31 | 6/24/23 | 7/25/23 | ||
| 50 | Underlayment/Encapsulation | Underlayment-Epoxy[2,728 SF] | $34,236.40 | |||||||
| 51 | Epoxy Flooring | Flooring-Epoxy[2,728 SF] | $100,581.36 | |||||||
| 52 | Lighting | Lighting[2,728 SF] | $77,311.52 | |||||||
| 53 | Paint Ceiling | Ceiling-Paint[2,748 SF] | $4,589.16 | |||||||
| 54 | Paint | Wall-Paint[2,720] | $13,926.40 | |||||||
| 55 | 1st Fl Hallways | 32 | 6/24/23 | 7/25/23 | $330,815.26 | 31 | 6/24/23 | 7/25/23 | ||
| 56 | Abatement | Asbestos-Removal[150 SF] | $523.50 | |||||||
| 57 | Flooring | Flooring-TCF[3,497 SF] | $87,739.73 | |||||||
| 58 | Lighting | Lighting[3,497 SF] | $99,104.98 | |||||||
| 59 | Ceiling | Ceiling-Acoustical[3,497 SF] | $112,778.25 | |||||||
| 60 | Paint | Wall-Paint[5,990] | $30,668.80 | |||||||
| 61 | Phase 3 (1st Trimester 23/24) | 93 | 7/26/23 | 10/26/23 | $1,069,132.81 | 92 | 7/26/23 | 10/26/23 | ||
| 62 | Machine Shop (F-G18) Phase 1 | 93 | 7/26/23 | 10/26/23 | $208,688.08 | 92 | 7/26/23 | 10/26/23 | ||
| 63 | Unerlayment | Underlayment-Epoxy[3,769 SF] | $47,300.95 | |||||||
| 64 | Epoxy Floor | Flooring-Epoxy[3,769 SF] | $138,963.03 | |||||||
| 65 | Install Eyewash Station | Eyewash Station[1 EA] | $22,424.10 | |||||||
| 66 | Welding Shop (F-G19) | 93 | 7/26/23 | 10/26/23 | $417,593.08 | 92 | 7/26/23 | 10/26/23 | ||
| 67 | Duct Work | $0.00 | ||||||||
| 68 | Lighting | Lighting[2,796 SF] | $79,238.64 | |||||||
| 69 | Exhaust Systems | Exhaust-Welding Lab[20 EA] | $283,923.20 | |||||||
| 70 | LVT Floor in Office | Flooring-VCT[160 SF] | $4,624.00 | |||||||
| 71 | Paint Corugated Ceiling | Ceiling-Paint[2,796 SF] | $4,669.32 | |||||||
| 72 | Walls-Paint | Wall-Paint[6,180] | $31,641.60 | |||||||
| 73 | Flooring-Paint | Wall-Paint[2,636] | $13,496.32 | |||||||
| 74 | Controls Lab (110) | 93 | 7/26/23 | 10/26/23 | $132,283.75 | 92 | 7/26/23 | 10/26/23 | ||
| 75 | Underlayment/Encapsulation | Flooring-Epoxy[1,201 SF] | $44,280.87 | |||||||
| 76 | Epoxy Flooring | Flooring-Epoxy[1,201 SF] | $44,280.87 | |||||||
| 77 | Lighting | Lighting[1,201 SF] | $34,036.34 | |||||||
| 78 | Paint Ceiling | Ceiling-Paint[1,201 SF] | $2,005.67 | |||||||
| 79 | Paint | Wall-Paint[1,500] | $7,680.00 | |||||||
| 80 | Circuits Lab (111) | 93 | 7/26/23 | 10/26/23 | $132,283.75 | 92 | 7/26/23 | 10/26/23 | ||
| 81 | Underlayment/Encapsulation | Flooring-Epoxy[1,201 SF] | $44,280.87 | |||||||
| 82 | Epoxy Flooring | Flooring-Epoxy[1,201 SF] | $44,280.87 | |||||||
| 83 | Lighting | Lighting[1,201 SF] | $34,036.34 | |||||||
| 84 | Paint Ceiling | Ceiling-Paint[1,201 SF] | $2,005.67 | |||||||
| 85 | Paint | Wall-Paint[1,500] | $7,680.00 | |||||||
| 86 | Classroom (F-101) | 93 | 7/26/23 | 10/26/23 | $51,955.18 | 92 | 7/26/23 | 10/26/23 | ||
| 87 | Lighting | Lighting[762 SF] | $21,595.08 | |||||||
| 88 | Ceiling | Ceiling-Acoustical[762 SF] | $24,574.50 | |||||||
| 89 | Paint | Wall-Paint[1,130] | $5,785.60 | |||||||
| 90 | Classroom (F-102) | 93 | 7/26/23 | 10/26/23 | $55,408.81 | 92 | 7/26/23 | 10/26/23 | ||
| 91 | Lighting | Lighting[819 SF] | $23,210.46 | |||||||
| 92 | Ceiling | Ceiling-Acoustical[819 SF] | $26,412.75 | |||||||
| 93 | Paint | Wall-Paint[1,130] | $5,785.60 | |||||||
| 94 | Classroom (F-115) | 93 | 7/26/23 | 10/26/23 | $70,920.16 | 92 | 7/26/23 | 10/26/23 | ||
| 95 | TCF | Flooring-TCF[762 SF] | $19,118.58 | |||||||
| 96 | Lighting | Lighting[762 SF] | $21,595.08 | |||||||
| 97 | Ceiling | Ceiling-Acoustical[762 SF] | $24,574.50 | |||||||
| 98 | Paint | Wall-Paint[1,100] | $5,632.00 | |||||||
| 99 | Phase 4 (2nd Trimester 23/24) | 112 | 11/14/23 | 3/4/24 | $377,615.56 | 111 | 11/14/23 | 3/4/24 | ||
| 100 | Classroom (G05) | 112 | 11/14/23 | 3/4/24 | $37,849.40 | 111 | 11/14/23 | 3/4/24 | ||
| 101 | TCF | Flooring-TCF[594 SF] | $14,903.46 | |||||||
| 102 | Lighting | Lighting[594 SF] | $16,833.96 | |||||||
| 103 | Paint Ceiling | Ceiling-Paint[594 SF] | $991.98 | |||||||
| 104 | Paint | Wall-Paint[1,000] | $5,120.00 | |||||||
| 105 | IME Storage (G12) | 112 | 11/14/23 | 3/4/24 | $15,217.08 | 111 | 11/14/23 | 3/4/24 | ||
| 106 | Abatement | Asbestos Disposal[1 CY],Asbestos-D | $4,119.32 | |||||||
| 107 | Underlayment | Underlayment-Epoxy[112 SF] | $1,405.60 | |||||||
| 108 | Epoxy Flooring | Flooring-Epoxy[112 SF] | $4,129.44 | |||||||
| 109 | Lighting | Lighting[112 SF] | $3,174.08 | |||||||
| 110 | Paint Ceiling | Ceiling-Paint[112 SF] | $187.04 | |||||||
| 111 | Paint | Wall-Paint[430] | $2,201.60 | |||||||
| 112 | IME Lab (G14) | 112 | 11/14/23 | 3/4/24 | $178,730.07 | 111 | 11/14/23 | 3/4/24 | ||
| 113 | Abatement | Asbestos Disposal[1 CY],Asbestos-D | $8,722.85 | |||||||
| 114 | Underlayment | Underlayment-Epoxy[2,014 SF] | $25,275.70 | |||||||
| 115 | Epoxy Flooring | Flooring-Epoxy[2,014 SF] | $74,256.18 | |||||||
| 116 | Lighting | Lighting[2,014 SF] | $57,076.76 | |||||||
| 117 | Paint Ceiling | Ceiling-Paint[2,014 SF] | $3,363.38 | |||||||
| 118 | Paint | Wall-Paint[1,960] | $10,035.20 | |||||||
| 119 | IME Office (G13) | 112 | 11/14/23 | 3/4/24 | $12,249.31 | 111 | 11/14/23 | 3/4/24 | ||
| 120 | VCT | Flooring-VCT[161 SF] | $4,652.90 | |||||||
| 121 | Lighting | Lighting[161 SF] | $4,562.74 | |||||||
| 122 | Paint Ceiling | Ceiling-Paint[161 SF] | $268.87 | |||||||
| 123 | Paint | Wall-Paint[540] | $2,764.80 | |||||||
| 124 | Nuclear Lab (F-G03) | 112 | 11/14/23 | 3/4/24 | $51,189.60 | 111 | 11/14/23 | 3/4/24 | ||
| 125 | VCT | Flooring-VCT[560 SF] | $16,184.00 | |||||||
| 126 | Lighting | Lighting[560 SF] | $15,870.40 | |||||||
| 127 | Repair Ceiling | Ceiling-Acoustical[560 SF] | $18,060.00 | |||||||
| 128 | 950 | Wall-Paint[210] | $1,075.20 | |||||||
| 129 | Steering Lab (F-G22) | 112 | 11/14/23 | 3/4/24 | $82,380.10 | 111 | 11/14/23 | 3/4/24 | ||
| 130 | Epoxy Flooring | Flooring-Epoxy[897 SF] | $33,072.39 | |||||||
| 131 | Lighting | Lighting[897 SF] | $25,420.98 | |||||||
| 132 | Paint Ceiling | Ceiling-Paint[897 SF] | $1,497.99 | |||||||
| 133 | Paint | Wall-Paint[1,200] | $6,144.00 | |||||||
| 134 | Univector | Mechanical-Mini Slplit[1 EA] | $16,244.74 | |||||||
| 135 | Phase 5 (3rd Trimester 23/24) | 89 | 3/18/24 | 6/14/24 | $420,424.03 | 88 | 3/18/24 | 6/14/24 | ||
| 136 | Refrigertaion Lab (G08, G09, G09A) | 89 | 3/18/24 | 6/14/24 | $178,680.96 | 88 | 3/18/24 | 6/14/24 | ||
| 137 | Abatement | Asbestos-Demo[1,771 SF],Asbestos | $10,055.23 | |||||||
| 138 | Underlayment | Underlayment-Epoxy[1,771 SF] | $22,226.05 | |||||||
| 139 | Epoxy Flooring | Flooring-Epoxy[1,771 SF] | $65,296.77 | |||||||
| 140 | Lighting | Lighting[1,771 SF] | $50,190.14 | |||||||
| 141 | Paint Ceiling | Ceiling-Paint[1,771 SF] | $2,957.57 | |||||||
| 142 | Paint | Wall-Paint[5,460] | $27,955.20 | |||||||
| 143 | Simulator Lab (F-105) | 89 | 3/18/24 | 6/14/24 | $35,949.32 | 88 | 3/18/24 | 6/14/24 | ||
| 144 | VCT Over Univector Space | Flooring-VCT[200 SF] | $5,780.00 | |||||||
| 145 | Lighting | Lighting[118 SF] | $3,344.12 | |||||||
| 146 | Ceiling | Ceiling-Acoustical[600 SF] | $19,350.00 | |||||||
| 147 | Paint | Wall-Paint[1,460] | $7,475.20 | |||||||
| 148 | Marine Proj Lab (F-114) | 89 | 3/18/24 | 6/14/24 | $80,877.43 | 88 | 3/18/24 | 6/14/24 | ||
| 149 | Underlayment | Underlayment-Epoxy[209 SF] | $2,622.95 | |||||||
| 150 | VCT | Flooring-VCT[209 SF] | $6,040.10 | |||||||
| 151 | Lighting | Lighting[1,082 SF] | $30,663.88 | |||||||
| 152 | Ceiling-ACT | Ceiling-Acoustical[1,082 SF] | $34,894.50 | |||||||
| 153 | Paint | Wall-Paint[1,300] | $6,656.00 | |||||||
| 154 | PLC Lab (F-109) | 89 | 3/18/24 | 6/14/24 | $124,916.32 | 88 | 3/18/24 | 6/14/24 | ||
| 155 | Abatement | Asbestos Disposal[1 CY],Asbestos-D | $7,774.16 | |||||||
| 156 | Underlayment Carpet | Underlayment-Carpet[1,028 SF] | $15,563.92 | |||||||
| 157 | TCF | Flooring-TCF[1,028 SF] | $25,792.52 | |||||||
| 158 | Lighting | Lighting[1,028 SF] | $29,133.52 | |||||||
| 159 | Ceiling | Ceiling-Acoustical[1,028 SF] | $33,153.00 | |||||||
| 160 | Paint | Wall-Paint[1,660] | $8,499.20 | |||||||
| 161 | Crane Demo | Crane Demo[1] | $5,000.00 | |||||||
| 162 | Phase 6 (Summer Break) | 32 | 6/24/24 | 7/25/24 | $1,013,587.25 | 31 | 6/24/24 | 7/25/24 | ||
| 163 | Steam Lab (F-G12) Phase 1 | 32 | 6/24/24 | 7/25/24 | $460,512.78 | 31 | 6/24/24 | 7/25/24 | ||
| 164 | Ceilings | Ceiling-Encapsulation Steam [4,975 | $222,581.50 | |||||||
| 165 | Lighting | Lighting[4,975 SF] | $140,991.50 | |||||||
| 166 | Exhaust Systems | Exhaust-Diesel Lab[2 EA] | $37,957.38 | |||||||
| 167 | Paint | Wall-Paint[11,520] | $58,982.40 | |||||||
| 168 | Diesel Lab (F-G09) Phase 1 | 32 | 6/24/24 | 7/25/24 | $338,964.17 | 31 | 6/24/24 | 7/25/24 | ||
| 169 | Ceilings | Ceiling-Encapsulation Diesel[3,055 | $137,138.95 | |||||||
| 170 | Lighting | Lighting[3,055 SF] | $86,578.70 | |||||||
| 171 | Paint | Wall-Paint[8,800] | $45,056.00 | |||||||
| 172 | Exhaust | Exhaust-Diesel Lab[2 EA] | $37,957.38 | |||||||
| 173 | Underlayment | Underlayment-Epoxy[591 SF] | $7,417.05 | |||||||
| 174 | Mezzanine Floor | Flooring-Epoxy[591 SF] | $21,790.17 | |||||||
| 175 | Mezzanine Walls | Wall-Paint[591] | $3,025.92 | |||||||
| 176 | Gas Turbine (G09A) | 32 | 6/24/24 | 7/25/24 | $90,529.20 | 31 | 6/24/24 | 7/25/24 | ||
| 177 | Ceilings | Ceiling-Encapsulation Diesel[634 SF | $28,460.26 | |||||||
| 178 | Lighting | Lighting[634 SF] | $17,967.56 | |||||||
| 179 | Paint | Wall-Paint[1,200] | $6,144.00 | |||||||
| 180 | Exhaust | Exhaust-Diesel Lab[2 EA] | $37,957.38 | |||||||
| 181 | Lecture Hall (G06) | 32 | 6/24/24 | 7/25/24 | $123,581.10 | 31 | 6/24/24 | 7/25/24 | ||
| 182 | TCF | Flooring-TCF[1,637 SF] | $41,072.33 | |||||||
| 183 | Lighting | Lighting[1,637 SF] | $46,392.58 | |||||||
| 184 | Paint Ceiling | Ceiling-Paint[1,637 SF] | $2,733.79 | |||||||
| 185 | Paint | Wall-Paint[6,520] | $33,382.40 | |||||||
| 186 | Phase 7 (1st Trimester 24/25) | 93 | 7/26/24 | 10/26/24 | $760,688.47 | 92 | 7/26/24 | 10/26/24 | ||
| 187 | Machine Shop Phase 2 | 93 | 7/26/24 | 10/26/24 | $228,363.71 | 92 | 7/26/24 | 10/26/24 | ||
| 188 | Duct Work | $0.00 | ||||||||
| 189 | Suspended Ceiling | Ceiling-Acoustical[3,769 SF] | $121,550.25 | |||||||
| 190 | Lighting | Lighting[3,769 SF] | $106,813.46 | |||||||
| 191 | Exhaust Systems | $0.00 | ||||||||
| 192 | Ventilation | $0.00 | ||||||||
| 193 | Graphics Classroom (F-201) | 93 | 7/26/24 | 10/26/24 | $139,344.74 | 92 | 7/26/24 | 10/26/24 | ||
| 194 | TCF | Flooring-TCF[400 SF] | $10,036.00 | |||||||
| 195 | Lighting | Lighting[1,966 SF] | $55,716.44 | |||||||
| 196 | Suspended Ceiling | Ceiling-Acoustical[1,966 SF] | $63,403.50 | |||||||
| 197 | Paint | Wall-Paint[1,990] | $10,188.80 | |||||||
| 198 | Classroom (F-208) | 93 | 7/26/24 | 10/26/24 | $63,929.92 | 92 | 7/26/24 | 10/26/24 | ||
| 199 | TCF | Flooring-TCF[684 SF] | $17,161.56 | |||||||
| 200 | Lighting | Lighting[684 SF] | $19,384.56 | |||||||
| 201 | Ceiling | Ceiling-Acoustical[684 SF] | $22,059.00 | |||||||
| 202 | Paint | Wall-Paint[1,040] | $5,324.80 | |||||||
| 203 | Classroom (F-209) | 93 | 7/26/24 | 10/26/24 | $77,824.72 | 92 | 7/26/24 | 10/26/24 | ||
| 204 | TCF | Flooring-TCF[839 SF] | $21,050.51 | |||||||
| 205 | Lighting | Lighting[839 SF] | $23,777.26 | |||||||
| 206 | Ceiling | Ceiling-Acoustical[839 SF] | $27,057.75 | |||||||
| 207 | Paint | Wall-Paint[1,160] | $5,939.20 | |||||||
| 208 | Classroom (F-210) | 93 | 7/26/24 | 10/26/24 | $67,990.32 | 92 | 7/26/24 | 10/26/24 | ||
| 209 | TCF | Flooring-TCF[729 SF] | $18,290.61 | |||||||
| 210 | Lighting | Lighting[729 SF] | $20,659.86 | |||||||
| 211 | Ceiling-ACT | Ceiling-Acoustical[729 SF] | $23,510.25 | |||||||
| 212 | Paint | Wall-Paint[1,080] | $5,529.60 | |||||||
| 213 | Classroom (F-212) | 93 | 7/26/24 | 10/26/24 | $66,533.76 | 92 | 7/26/24 | 10/26/24 | ||
| 214 | TCF | Flooring-TCF[712 SF] | $17,864.08 | |||||||
| 215 | Lighting | Lighting[712 SF] | $20,178.08 | |||||||
| 216 | Suspended Ceiling | Ceiling-Acoustical[712 SF] | $22,962.00 | |||||||
| 217 | Paint | Wall-Paint[1,080] | $5,529.60 | |||||||
| 218 | Classroom (F-213) | 93 | 7/26/24 | 10/26/24 | $67,904.64 | 92 | 7/26/24 | 10/26/24 | ||
| 219 | TCF | Flooring-TCF[728 SF] | $18,265.52 | |||||||
| 220 | Lighting | Lighting[728 SF] | $20,631.52 | |||||||
| 221 | Suspended Ceiling | Ceiling-Acoustical[728 SF] | $23,478.00 | |||||||
| 222 | Paint | Wall-Paint[1,080] | $5,529.60 | |||||||
| 223 | Classroom (F-214) | 93 | 7/26/24 | 10/26/24 | $48,796.66 | 92 | 7/26/24 | 10/26/24 | ||
| 224 | TCF | Flooring-TCF[762 SF] | $19,118.58 | |||||||
| 225 | Lighting | Lighting[762 SF] | $21,595.08 | |||||||
| 226 | Suspended Ceiling | Ceiling-Acoustical[76 SF] | $2,451.00 | |||||||
| 227 | Paint | Wall-Paint[1,100] | $5,632.00 | |||||||
| 228 | Phase 8 (2nd Trimester 24/25) | 111 | 11/14/24 | 3/4/25 | $742,231.39 | 110 | 11/14/24 | 3/4/25 | ||
| 229 | Classroom (204) | 111 | 11/14/24 | 3/4/25 | $39,939.30 | 110 | 11/14/24 | 3/4/25 | ||
| 230 | TCF | Flooring-TCF[631 SF] | $15,831.79 | |||||||
| 231 | Lighting | Lighting[631 SF] | $17,882.54 | |||||||
| 232 | Ceiling | Ceiling-Paint[631 SF] | $1,053.77 | |||||||
| 233 | Paint | Wall-Paint[1,010] | $5,171.20 | |||||||
| 234 | Special Projects Classroom (205) | 111 | 11/14/24 | 3/4/25 | $118,718.16 | 110 | 11/14/24 | 3/4/25 | ||
| 235 | TCF | Flooring-TCF[1,287 SF] | $32,290.83 | |||||||
| 236 | Lighting | Lighting[1,287 SF] | $36,473.58 | |||||||
| 237 | Ceiling | Ceiling-Acoustical[1,287 SF] | $41,505.75 | |||||||
| 238 | Paint | Wall-Paint[1,650] | $8,448.00 | |||||||
| 239 | Heat Treating/Materials Lab (206/20 | 111 | 11/14/24 | 3/4/25 | $119,894.97 | 110 | 11/14/24 | 3/4/25 | ||
| 240 | Abatement | Asbestos Disposal[1 CY],Asbestos-D | $4,465.52 | |||||||
| 241 | Underlayment/Encapsulation | Underlayment-Epoxy[1,143 SF] | $14,344.65 | |||||||
| 242 | Epoxy Flooring | Flooring-Epoxy[1,143 SF] | $42,142.41 | |||||||
| 243 | Lighting | Lighting[1,143 SF] | $32,392.62 | |||||||
| 244 | Ceiling | Ceiling-Paint[1,143 SF] | $1,908.81 | |||||||
| 245 | Paint | Wall-Paint[2,040] | $10,444.80 | |||||||
| 246 | Fume Hoods | Exhaust-Welding Lab[1 EA] | $14,196.16 | |||||||
| 247 | Strength & Fluids Lab (215) | 111 | 11/14/24 | 3/4/25 | $213,990.40 | 110 | 11/14/24 | 3/4/25 | ||
| 248 | Underlayment/Encapsulation | Underlayment-Epoxy[2,560 SF] | $32,128.00 | |||||||
| 249 | Epoxy Flooring | Flooring-Epoxy[2,560 SF] | $94,387.20 | |||||||
| 250 | Lighting | Lighting[2,560 SF] | $72,550.40 | |||||||
| 251 | Ceiling | Ceiling-Paint[2,560 SF] | $4,275.20 | |||||||
| 252 | Paint | Wall-Paint[2,080] | $10,649.60 | |||||||
| 253 | Thermodynamics (F-203) | 111 | 11/14/24 | 3/4/25 | $139,630.32 | 110 | 11/14/24 | 3/4/25 | ||
| 254 | Underlayment/Encapsulation | Underlayment-Epoxy[1,154 SF] | $14,482.70 | |||||||
| 255 | Epoxy Flooring | Flooring-VCT[1,154 SF] | $33,350.60 | |||||||
| 256 | Lighting | Lighting[1,154 SF] | $32,704.36 | |||||||
| 257 | Ceiling | Ceiling-Acoustical[1,154 SF] | $37,216.50 | |||||||
| 258 | Paint | Wall-Paint[1,500] | $7,680.00 | |||||||
| 259 | Fume Hoods | Exhaust-Welding Lab[1 EA] | $14,196.16 | |||||||
| 260 | Classroom (F-204) | 111 | 11/14/24 | 3/4/25 | $54,883.36 | 110 | 11/14/24 | 3/4/25 | ||
| 261 | TCF | Flooring-TCF[582 SF] | $14,602.38 | |||||||
| 262 | Lighting | Lighting[582 SF] | $16,493.88 | |||||||
| 263 | Ceiling | Ceiling-Acoustical[582 SF] | $18,769.50 | |||||||
| 264 | Paint | Wall-Paint[980] | $5,017.60 | |||||||
| 265 | Classroom (F-207) | 111 | 11/14/24 | 3/4/25 | $55,174.88 | 110 | 11/14/24 | 3/4/25 | ||
| 266 | TCF | Flooring-TCF[586 SF] | $14,702.74 | |||||||
| 267 | Lighting | Lighting[586 SF] | $16,607.24 | |||||||
| 268 | Ceiling | Ceiling-Acoustical[586 SF] | $18,898.50 | |||||||
| 269 | Paint | Wall-Paint[970] | $4,966.40 | |||||||
| 270 | Phase 9 (3rd Trimester 24/25) | 89 | 3/18/25 | 6/14/25 | $352,682.97 | 88 | 3/18/25 | 6/14/25 | ||
| 271 | Instrument Lab (304) | 89 | 3/18/25 | 6/14/25 | $56,452.59 | 88 | 3/18/25 | 6/14/25 | ||
| 272 | Abatement | Asbestos Disposal[1 CY],Asbestos-D | $6,190.13 | |||||||
| 273 | Underlayment/Encapsulation | Underlayment-Epoxy[631 SF] | $7,919.05 | |||||||
| 274 | Flooring VCT | Flooring-VCT[631 SF] | $18,235.90 | |||||||
| 275 | Lighting | Lighting[631 SF] | $17,882.54 | |||||||
| 276 | Ceiling | Ceiling-Paint[631 SF] | $1,053.77 | |||||||
| 277 | Paint | Wall-Paint[1,010] | $5,171.20 | |||||||
| 278 | Fume Hoods | $0.00 | ||||||||
| 279 | Physics (310) | 89 | 3/18/25 | 6/14/25 | $78,008.97 | 88 | 3/18/25 | 6/14/25 | ||
| 280 | Abatement | Asbestos-Demo[965 SF] | $3,850.35 | |||||||
| 281 | Underlayment/Encapsulation | Underlayment-Epoxy[965 SF] | $12,110.75 | |||||||
| 282 | Flooring VCT | Flooring-VCT[965 SF] | $27,888.50 | |||||||
| 283 | Lighting | Lighting[965 SF] | $27,348.10 | |||||||
| 284 | Ceiling | Ceiling-Paint[1 SF] | $1.67 | |||||||
| 285 | Paint | Wall-Paint[1,330] | $6,809.60 | |||||||
| 286 | Physics Prep (311) | 89 | 3/18/25 | 6/14/25 | $28,002.90 | 88 | 3/18/25 | 6/14/25 | ||
| 287 | Abatement | Asbestos-Demo[306 SF] | $1,220.94 | |||||||
| 288 | Underlayment/Encapsulation | Underlayment-Epoxy[306 SF] | $3,840.30 | |||||||
| 289 | Flooring VCT | Flooring-VCT[306 SF] | $8,843.40 | |||||||
| 290 | Lighting | Lighting[306 SF] | $8,672.04 | |||||||
| 291 | Ceiling | Ceiling-Paint[306 SF] | $511.02 | |||||||
| 292 | Paint | Wall-Paint[960] | $4,915.20 | |||||||
| 293 | Physics Lab (312) | 89 | 3/18/25 | 6/14/25 | $82,092.39 | 88 | 3/18/25 | 6/14/25 | ||
| 294 | Abatement | Asbestos Disposal[1 CY],Asbestos-D | $4,629.11 | |||||||
| 295 | Underlayment/Encapsulation | Underlayment-Epoxy[988 SF] | $12,399.40 | |||||||
| 296 | Flooring VCT | Flooring-VCT[988 SF] | $28,553.20 | |||||||
| 297 | Lighting | Lighting[988 SF] | $27,999.92 | |||||||
| 298 | Ceiling | Ceiling-Paint[988 SF] | $1,649.96 | |||||||
| 299 | Paint | Wall-Paint[1,340] | $6,860.80 | |||||||
| 300 | Hazardous Materials (F-301) | 89 | 3/18/25 | 6/14/25 | $46,344.25 | 88 | 3/18/25 | 6/14/25 | ||
| 301 | Underlayment/Encapsulation | Underlayment-Epoxy[535 SF] | $6,714.25 | |||||||
| 302 | Epoxy Flooring | Flooring-Epoxy[535 SF] | $19,725.45 | |||||||
| 303 | Lighting | Lighting[535 SF] | $15,161.90 | |||||||
| 304 | Ceiling | Ceiling-Acoustical[1 SF] | $32.25 | |||||||
| 305 | Paint | Wall-Paint[920] | $4,710.40 | |||||||
| 306 | Fume Hoods | $0.00 | ||||||||
| 307 | Science Storage (F-302) | 89 | 3/18/25 | 6/14/25 | $39,595.71 | 88 | 3/18/25 | 6/14/25 | ||
| 308 | Lighting | Lighting[569 SF] | $16,125.46 | |||||||
| 309 | Ceiling | Ceiling-Acoustical[569 SF] | $18,350.25 | |||||||
| 310 | Paint | Wall-Paint[1,000] | $5,120.00 | |||||||
| 311 | Seminar (F-303) | 89 | 3/18/25 | 6/14/25 | $22,186.16 | 88 | 3/18/25 | 6/14/25 | ||
| 312 | Lighting | Lighting[604 SF] | $17,117.36 | |||||||
| 313 | Paint | Wall-Paint[990] | $5,068.80 | |||||||
| 314 | Phase 10 (Summer Break) | 32 | 6/24/25 | 7/25/25 | $575,988.97 | 31 | 6/24/25 | 7/25/25 | ||
| 315 | Steam Lab (F-G12) Phase 2 | 32 | 6/24/25 | 7/25/25 | $251,095.40 | 31 | 6/24/25 | 7/25/25 | ||
| 316 | Underlayment | Underlayment-Epoxy[4,975 SF] | $62,436.25 | |||||||
| 317 | Epoxy Flooring | Flooring-Epoxy[4,975 SF] | $183,428.25 | |||||||
| 318 | Office Floor | Flooring-VCT[181 SF] | $5,230.90 | |||||||
| 319 | Diesel Lab (F-G09) Phase 2 | 32 | 6/24/25 | 7/25/25 | $121,770.88 | 31 | 6/24/25 | 7/25/25 | ||
| 320 | Underlayment | Underlayment-Epoxy[2,464 SF] | $30,923.20 | |||||||
| 321 | Epoxy Flooring | Flooring-Epoxy[2,464 SF] | $90,847.68 | |||||||
| 322 | Zero Deck Hallway | 32 | 6/24/25 | 7/25/25 | $203,122.69 | 31 | 6/24/25 | 7/25/25 | ||
| 323 | Underlayment | Underlayment-Epoxy[2,243 SF] | $28,149.65 | |||||||
| 324 | Flooring | Flooring-Epoxy[2,243 SF] | $82,699.41 | |||||||
| 325 | Lighting | Lighting[2,243 SF] | $63,566.62 | |||||||
| 326 | Ceiling | Ceiling-Paint[2,443 SF] | $4,079.81 | |||||||
| 327 | Paint | Wall-Paint[4,810] | $24,627.20 | |||||||
| 328 | Period of Performance | 1095 | 3/1/23 | 3/4/26 | $4,137,147.84 | 1099 | 3/1/23 | 3/4/26 | ||
| 329 | Hallways | 1095 | 3/1/23 | 3/4/26 | $587,833.60 | 1099 | 3/1/23 | 3/4/26 | ||
| 330 | 2nd Fl Hallways | 1095 | 3/1/23 | 3/4/26 | $242,783.23 | 1099 | 3/1/23 | 3/4/26 | ||
| 331 | Abatement | Asbestos-Removal[247 SF] | $862.03 | |||||||
| 332 | TCF | Flooring-TCF[2,465 SF] | $61,846.85 | |||||||
| 333 | Lighting | Lighting[2,465 SF] | $69,858.10 | |||||||
| 334 | Ceiling | Ceiling-Acoustical[2,465 SF] | $79,496.25 | |||||||
| 335 | Paint | Wall-Paint[6,000] | $30,720.00 | |||||||
| 336 | 3rd Fl Hallways | 1095 | 3/1/23 | 3/4/26 | $274,679.10 | 1099 | 3/1/23 | 3/4/26 | ||
| 337 | Abatement | Asbestos-Removal[270 SF] | $942.30 | |||||||
| 338 | TCF | Flooring-TCF[2,770 SF] | $69,499.30 | |||||||
| 339 | Lighting | Lighting[2,770 SF] | $78,501.80 | |||||||
| 340 | Ceiling | Ceiling-Acoustical[2,770 SF] | $89,332.50 | |||||||
| 341 | Paint | Wall-Paint[7,110] | $36,403.20 | |||||||
| 342 | 4th Fl Hallways | 1095 | 3/1/23 | 3/4/26 | $70,371.27 | 1099 | 3/1/23 | 3/4/26 | ||
| 343 | Abatement | Asbestos-Removal[70 SF] | $244.30 | |||||||
| 344 | TCF | Flooring-TCF[689 SF] | $17,287.01 | |||||||
| 345 | Lighting | Lighting[689 SF] | $19,526.26 | |||||||
| 346 | Ceiling | Ceiling-Acoustical[698 SF] | $22,510.50 | |||||||
| 347 | Paint | Wall-Paint[2,110] | $10,803.20 | |||||||
| 348 | Fulton 3rd Fl Offices | 1095 | 3/1/23 | 3/4/26 | $417,019.20 | 1099 | 3/1/23 | 3/4/26 | ||
| 349 | TCF | Flooring-TCF[10,280 SF] | $257,925.20 | |||||||
| 350 | Ceiling | Ceiling-Paint[10,280 SF] | $17,167.60 | |||||||
| 351 | Paint | Wall-Paint[27,720] | $141,926.40 | |||||||
| 352 | Fulton 4th Fl Offices | 1095 | 3/1/23 | 3/4/26 | $124,974.04 | 1099 | 3/1/23 | 3/4/26 | ||
| 353 | TCF | Flooring-TCF[3,019 SF] | $75,746.71 | |||||||
| 354 | Ceiling | Ceiling-Paint[3,019 SF] | $5,041.73 | |||||||
| 355 | Paint | Wall-Paint[8,630] | $44,185.60 | |||||||
| 356 | Support Rooms | 1095 | 3/1/23 | 3/4/26 | $420,036.04 | 1099 | 3/1/23 | 3/4/26 | ||
| 357 | Instrument Storage (104) | $35,848.74 | ||||||||
| 358 | Abatement | Asbestos-Removal[40 SF] | $139.60 | |||||||
| 359 | Underlayment/Encapsulation | Underlayment-Epoxy[398 SF] | $4,994.90 | |||||||
| 360 | Epoxy Flooring | Flooring-Epoxy[398 SF] | $14,674.26 | |||||||
| 361 | Lighting | Lighting[398 SF] | $11,279.32 | |||||||
| 362 | Ceiling | Ceiling-Paint[398 SF] | $664.66 | |||||||
| 363 | Paint | Wall-Paint[800] | $4,096.00 | |||||||
| 364 | Elect Shop (105) | 1095 | 3/1/23 | 3/4/26 | $39,341.01 | 1099 | 3/1/23 | 3/4/26 | ||
| 365 | Underlayment/Encapsulation | Underlayment-Epoxy[477 SF] | $5,986.35 | |||||||
| 366 | Epoxy Flooring | Flooring-Epoxy[477 SF] | $17,586.99 | |||||||
| 367 | Lighting | Lighting[477 SF] | $13,518.18 | |||||||
| 368 | Ceiling | Ceiling-Paint[477 SF] | $796.59 | |||||||
| 369 | Paint | Ceiling-Paint[870 SF] | $1,452.90 | |||||||
| 370 | Sump Tank Rm (108) | 1095 | 3/1/23 | 3/4/26 | $18,244.92 | 1099 | 3/1/23 | 3/4/26 | ||
| 371 | Abatement | Asbestos-Demo[144 SF],Asbestos D | $4,247.00 | |||||||
| 372 | Underlayment/Encapsulation | Underlayment-Epoxy[144 SF] | $1,807.20 | |||||||
| 373 | Epoxy Flooring | Flooring-Epoxy[144 SF] | $5,309.28 | |||||||
| 374 | Lighting | Lighting[144 SF] | $4,080.96 | |||||||
| 375 | Ceiling | Ceiling-Paint[144 SF] | $240.48 | |||||||
| 376 | Paint | Wall-Paint[500] | $2,560.00 | |||||||
| 377 | Acid Waste (G11) | 1095 | 3/1/23 | 3/4/26 | $8,356.46 | 1099 | 3/1/23 | 3/4/26 | ||
| 378 | Underlayment/Encapsulation | Underlayment-Epoxy[82 SF] | $1,029.10 | |||||||
| 379 | Epoxy Flooring | Flooring-Epoxy[82 SF] | $3,023.34 | |||||||
| 380 | Lighting | Lighting[82 SF] | $2,323.88 | |||||||
| 381 | Ceiling | Ceiling-Paint[82 SF] | $136.94 | |||||||
| 382 | Paint | Wall-Paint[360] | $1,843.20 | |||||||
| 383 | Janitorial Lockers (F-G05) | 1095 | 3/1/23 | 3/4/26 | $30,712.46 | 1099 | 3/1/23 | 3/4/26 | ||
| 384 | Underlayment/Encapsulation | Underlayment-Epoxy[332 SF] | $4,166.60 | |||||||
| 385 | Epoxy Flooring | Flooring-Epoxy[322 SF] | $11,872.14 | |||||||
| 386 | Lighting | Lighting[332 SF] | $9,408.88 | |||||||
| 387 | Ceiling | Ceiling-Paint[332 SF] | $554.44 | |||||||
| 388 | Paint | Wall-Paint[920] | $4,710.40 | |||||||
| 389 | Tech Shop (F-G20) | 1095 | 3/1/23 | 3/4/26 | $116,081.92 | 1099 | 3/1/23 | 3/4/26 | ||
| 390 | Epoxy Flooring | Flooring-Epoxy[1,604 SF] | $59,139.48 | |||||||
| 391 | Lighting | Lighting[1,604 SF] | $45,457.36 | |||||||
| 392 | Ceiling | Ceiling-Paint[1,604 SF] | $2,678.68 | |||||||
| 393 | Paint | Wall-Paint[1,720] | $8,806.40 | |||||||
| 394 | Faculty Lounge (405) | 1095 | 3/1/23 | 3/4/26 | $56,168.56 | 1099 | 3/1/23 | 3/4/26 | ||
| 395 | TCF | Flooring-TCF[597 SF] | $14,978.73 | |||||||
| 396 | Ceiling-Acoustical | Ceiling-Acoustical[597 SF] | $19,253.25 | |||||||
| 397 | Lighting | Lighting[597 SF] | $16,918.98 | |||||||
| 398 | Paint | Wall-Paint[980] | $5,017.60 | |||||||
| 399 | A/V Telecom Closets | 1095 | 3/1/23 | 3/4/26 | $35,825.09 | 1099 | 3/1/23 | 3/4/26 | ||
| 400 | Underlayment/Encapsulation | Underlayment-Epoxy[601 SF] | $7,542.55 | |||||||
| 401 | Epoxy Flooring | Flooring-Epoxy[601 SF] | $22,158.87 | |||||||
| 402 | Ceiling | Ceiling-Paint[601 SF] | $1,003.67 | |||||||
| 403 | Paint | Wall-Paint[1,000] | $5,120.00 | |||||||
| 404 | Janitorial Closets | 1095 | 3/1/23 | 3/4/26 | $79,456.88 | 1099 | 3/1/23 | 3/4/26 | ||
| 405 | Underlayment/Encapsulation | Underlayment-Epoxy[274 SF] | $3,438.70 | |||||||
| 406 | Epoxy Flooring | Flooring-Epoxy[274 SF] | $10,102.38 | |||||||
| 407 | Paint | Wall-Paint[1,980] | $10,137.60 | |||||||
| 408 | Ceiling | Ceiling-Paint[274 SF] | $457.58 | |||||||
| 409 | Lighting | Lighting[274 SF] | $7,765.16 | |||||||
| 410 | Storage/Mechanical | 1095 | 3/1/23 | 3/4/26 | $47,555.46 | 1099 | 3/1/23 | 3/4/26 | ||
| 411 | Underlayment/Encapsulation | Underlayment-Epoxy[1,158 SF] | $14,532.90 | |||||||
| 412 | Epoxy Flooring | Flooring-VCT[82 SF] | $2,369.80 | |||||||
| 413 | Paint | Wall-Paint[200] | $1,024.00 | |||||||
| 414 | Ceiling | Ceiling-Paint[82 SF] | $136.94 | |||||||
| 415 | Office (F-G11) | 1095 | 3/1/23 | 3/4/26 | $29,491.82 | 1099 | 3/1/23 | 3/4/26 | ||
| 416 | Underlayment/Encapsulati | Underlayment-Epoxy[82 SF] | $1,029.10 | |||||||
| 417 | Epoxy Flooring | Flooring-Epoxy[274 SF] | $10,102.38 | |||||||
| 418 | Paint | Wall-Paint[1,980] | $10,137.60 | |||||||
| 419 | Ceiling | Ceiling-Paint[274 SF] | $457.58 | |||||||
| 420 | Lighting | Lighting[274 SF] | $7,765.16 | |||||||
| 421 | Restrooms | 1095 | 3/1/23 | 3/4/26 | $95,212.26 | 1099 | 3/1/23 | 3/4/26 | ||
| 422 | Lighting | Lighting[1,946 SF] | $55,149.64 | |||||||
| 423 | Ceiling | Ceiling-Paint[1,946 SF] | $3,249.82 | |||||||
| 424 | Paint | Wall-Paint[7,190] | $36,812.80 | |||||||
| 425 | Stairwells | 1095 | 3/1/23 | 3/4/26 | $337,985.36 | 1099 | 3/1/23 | 3/4/26 | ||
| 426 | Abatement | Asbestos-Demo[3,644 SF],Asbestos | $49,291.76 | |||||||
| 427 | TCF | Flooring-TCF[3,644 SF] | $91,427.96 | |||||||
| 428 | Lighting | Lighting[3,644 SF] | $103,270.96 | |||||||
| 429 | Ceiling | Ceiling-Paint[3,644 SF] | $6,085.48 | |||||||
| 430 | Paint | Wall-Paint[9,260] | $47,411.20 | |||||||
| 431 | Bullnose | Bullnose[2,000 LF] | $36,320.00 | |||||||
| 432 | Riser | Riser[200 EA] | $4,178.00 | |||||||
| 433 | Doors | 1095 | 3/1/23 | 3/4/26 | $245,549.00 | 1099 | 3/1/23 | 3/4/26 | ||
| 434 | Replace/Keying | Door-Replace[100 EA] | $189,794.00 | |||||||
| 435 | Repair | Door-Repair[300 EA] | $55,755.00 | |||||||
| 436 | Fume Hoods (Study Dependent) | 1095 | 3/1/23 | 3/4/26 | Fume Hoods-Laboratory[1 EA] | $1,908,538.34 | 1099 | 3/1/23 | 3/4/26 | |
| 437 | Design | $0.00 | ||||||||
| 438 | Review | $0.00 | ||||||||
| 439 | Execution | $0.00 | ||||||||
| 440 | Retrofit Pneumatic Systems (Study D | 36.65 emo | Wed 3/1/23 | Wed 3/4/26 | $0.00 | 179 | 5/19/23 | 11/14/23 | ||
| 441 | Design | $0.00 | ||||||||
| 442 | Review | $0.00 | ||||||||
| 443 | Execution | $0.00 | ||||||||
| 444 | Ventilation Systems (Study Depende | 36.65 emo | Wed 3/1/23 | Wed 3/4/26 | $0.00 | 179 | 5/19/23 | 11/14/23 | ||
| 445 | Design | $0.00 | ||||||||
| 446 | Review | $0.00 | ||||||||
| 447 | Execution | $0.00 | ||||||||
| 448 | HVAC Upgrades (Study Dependent) | 36.65 emo | Wed 3/1/23 | Wed 3/4/26 | $0.00 | 179 | 5/19/23 | 11/14/23 | ||
| 449 | Design | $0.00 | ||||||||
| 450 | Review | $0.00 | ||||||||
| 451 | Execution | $0.00 | ||||||||
| 452 | Punch List | 36.65 emo | Wed 3/1/23 | Wed 3/4/26 | $0.00 | 179 | 5/19/23 | 11/14/23 | ||
| 453 | Walk Through | $0.00 | ||||||||
| 454 | Review | $0.00 | ||||||||
| 455 | Close | $0.00 |