About this file

This document provides details on a federal solicitation for renovation work at two buildings on the campus of the U.S. Merchant Marine Academy. The solicitation seeks a contractor to complete work at both the Fulton and Gibbs Halls, including roof and window replacement, lighting upgrades, emergency equipment repairs and installation, masonry repairs and painting, ventilation system upgrades, and asbestos assessment and abatement. The solicitation is issued by the Department of Transportation Maritime Administration for general construction services including labor, materials, equipment and disposal. The work tasks outlined are to fully renovate both buildings identified.

View the file

Other files for this federal contract opportunity

Other files attached to Fulton-Gibbs Refurbishment at the U. S. Merchant Marine Academy, newest first.
File Type Posted
693JF723R000005 Fulton-Gibbs RFP (AMD0012).pdf PDF
Attachment 2 Fulton-Gibbs Schedule Requirements (AMD0012).xlsx XLSX spreadsheet
Attachment 1 Fulton-Gibbs Refurbishment SOW (AMD0012).pdf PDF
Attachment 3 Fulton-Gibbs Refurbishment Pricing (AMD0012).xlsx XLSX spreadsheet
693JF723R00000500011.pdf PDF
693JF723R0000050010.pdf PDF
Refurbish-693JF723000005 RFI Response 5.docx DOCX document
Attachment 3 Fulton-Gibbs Refurbishment Pricing 2.0.xlsx XLSX spreadsheet
693JF723R0000050009.pdf PDF
693JF723R0000050008.pdf PDF
Attachment 2 Fulton Gibbs Schedule Requirement V8.xlsx XLSX spreadsheet
Refurbish-693JF723000005 RFI Response 4.docx DOCX document
Fume hoods.xlsx XLSX spreadsheet
Material Examples.zip ZIP file
Refurbish-693JF723000005 RFI Response 3 30MAR23.docx DOCX document
Fulton-Gibbs Refurbishment SOW.pdf PDF
693JF723R0000050007.pdf PDF
Fulton A10 -M5.zip ZIP file
Gibbs M1-7.zip ZIP file
Gibbs S1-6.zip ZIP file
Fulton A1-9.zip ZIP file
Fulton M6-15.zip ZIP file
Fulton M16 - P9.zip ZIP file
Fulton L1-SP1.zip ZIP file
Gibbs A10 - E11.zip ZIP file
Gibbs M8 - P10.zip ZIP file
693JF723R0000050006.pdf PDF
Fulton P10-S1.zip ZIP file
Fulton E11-20.zip ZIP file
Fulton E1-10.zip ZIP file
Gibbs A1-9.zip ZIP file
Gibbs E12 - L3.zip ZIP file
693JF723R0000050005.pdf PDF
693JF723R0000050004.pdf PDF
693JF723R0000050003.pdf PDF
693JF723R00000500002.pdf PDF
693JF723R000005 Fulton-Gibbs RFP (AMD1).pdf PDF
Attachment 1 Fulton-Gibbs Refurbishment SOW (AMD1).pdf PDF
Attachment 6 Reports Drawings and Other Docs.zip ZIP file
693JF723R000005001.pdf PDF
Attachment 3 Fulton-Gibbs Refurbishment Pricing.xlsx XLSX spreadsheet
Attachment 5 Question and Answer Response Form.docx DOCX document
Attachment 1 Fulton-Gibbs Refurbishment SOW.pdf PDF
Attachment 4 Wage Determination Davis Bacon Act WD NY20230012.pdf PDF
Attachment 2 Fulton-Gibbs Schedule Requirements.xlsx XLSX spreadsheet
693JF723R000005 Fulton-Gibbs RFP.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ceiling-Floor Finishes

Floor TypeFinal FinishCeiling TypeFinal Finish
Fulton Zero Deck
G01PaintPaintPaintPaint
G03VCTVCT Over2x2Repair
G04PaintPaintPaintPaint
G05VCTEpoxyPaintPaint
G06PaintPaintPaintPaint
G06ATileRemainPaintPaint
G09EpoxyEpoxyTectumEncapsulate
G09AEpoxyEpoxyTectumEncapsulate
G10VCTEpoxyTectumEncapsulate
G11VCTVCT Over1x1Paint
G12EpoxyEpoxyTectumEncapsulate
G18EpoxyEpoxyTectumSuspended Ceiling
G18AWoodRemainTectumSuspended Ceiling
G19ConcreteRemainCorrugatedPaint
G19ACarpetLVTCorrugatedPaint
G19BConcreteRemainCorrugatedPaint
G20PaintEpoxyPaintPaint
G21APaintPaintPaintPaint
G22EpoxyEpoxyPaintPaint
G23PaintPaintPaintPaint
CorridorVCTGC IdentifiedVariesGC Identified
Fulton 1st Deck
101VCTRemain2x42x2
102VCTRemain2x42x2
103
104VCTTCFTectumSuspended Ceiling
105Raised FloorMinor VTC OverSuspended/TectumEncapsulate/Suspend
107PaintPaintPaintPaint
107ACeramic TileRemainPaintPaint
108PaintEpoxyTectumEncapsulate
109VCTTCFTectumEncapsulate
111VCTVCTPaintPaint
114New VCTRemainTectumSuspended Ceiling
115VCTTCF2x42x2
118VCTVCTPaintPaint
120VCTVCTPaintPaint
120AVCTVCTPaintPaint
CorridorVCTTCFParaline 1Paraline 3
Fulton 2nd Deck
201Raised Floor/VCTTCFTectumSuspended Ceiling
203VCTEpoxyTectumSuspended Ceiling
203AVCTEpoxyPaintPaint
204VCTTCFTectumSuspended Ceiling
206VCTVCTPaintPaint
206ACeramic TileRemainPaintPaint
207VCTTCF2x42x2
208VCTTCF2x42x2
209New VCTTCF2x42x2
210VCTTCF2x42x2
212VCTTCFTectumSuspended Ceiling
213VCTTCFTectumSuspended Ceiling
214VCTTCFTectumSuspended Ceiling
215VCTVCTPaintPaint
216VCTVCTPaintPaint
CorridorVCTTCFParaline 1Paraline 3
Fulton 3rd Deck
301EpoxyEpoxyTectumSuspended Ceiling
302New VCTRemainTectumSuspended Ceiling
303Raised FloorRemain2x2Remain
304VCTTCF1x1Paint
305VCTTCF1x1Paint
306VCTTCF1x1Paint
307VCTTCF1x1Paint
309VCTVCTPaintPaint
309ACeramic TileRemainPaintPaint
310VCTTCF1x1Paint
311VCTTCF1x1Paint
312VCTTCF1x1Paint
314VCTTCF1x1Paint
315VCTTCF1x1Paint
316VCTTCF1x1Paint
317VCTTCF1x1Paint
318VCTTCF1x1Paint
319VCTTCF1x1Paint
320VCTTCF1x1Paint
321VCTTCF1x1Paint
322VCTTCF1x1Paint
323VCTTCF1x1Paint
325VCTTCF1x1Paint
326VCTTCF1x1Paint
327VCTTCF1x1Paint
328VCTTCF1x1Paint
329VCTTCF1x1Paint
330VCTTCF1x1Paint
331VCTTCF1x1Paint
332VCTTCF1x1Paint
333VCTTCF1x1Paint
334VCTTCF1x1Paint
335VCTTCF1x1Paint
336VCTTCF1x1Paint
337VCTTCF1x1Paint
338VCTTCF1x1Paint
339VCTTCF1x1Paint
340VCTTCF1x1Paint
341VCTTCF1x1Paint
342VCTVCTTectumRepair
343VCTVCTTectumPaint
CorridorVCTTCFParaline 1Paraline 3
Fulton 4th Deck
401VCTVCTPaintPaint
405CarpetReplaceTectumSuspended Ceiling
405ACeramic TileRemainPaintPaint
405BCeramic TileRemainPaintPaint
406VCTTCF1x1Paint
407VCTTCF1x1Paint
408VCTTCF1x1Paint
409VCTTCF1x1Paint
410VCTTCF1x1Paint
411VCTTCF1x1Paint
412VCTTCF1x1Paint
413VCTTCF1x1Paint
414VCTTCF1x1Paint
415VCTTCF1x1Paint
416VCTTCF1x1Paint
CorridorVCTTCFParaline 1Paraline 3
Gibbs Zero Deck
G03VCTVCTPaintPaint
G03ACeramic TileRemainPaintPaint
G03BCeramic TileRemainPaintPaint
G05VCTVCTPaintPaint
G06CareptReplacePaintPaint
G08 (CR)VCTVCTPaintPaint
G09VCTEpoxyPaintPaint
G09AVCTVCTPaintPaint
G11PaintEpoxyPaintPaint
G12VCTEpoxyPaintPaint
G13VCTVCTPaintPaint
G14VCTEpoxyPaintPaint
CorridorTerrazoRemainParaline 1Paraline 3
Gibbs 1st Deck
103VCTVCTPaintPaint
103ACeramic TileRemainPaintPaint
104VCTEpoxyPaintPaint
105VCTEpoxyPaintPaint
105 (Office)VCTTCFPaintPaint
107VCTEpoxyPaintPaint
108
110VCTEpoxyPaintPaint
111VCTEpoxyPaintPaint
CorridorVCTTCFParaline 1Paraline 3
Gibbs 2nd Deck
203VCTVCTPaintPaint
203ACeramic TileRemainPaintPaint
204VCTTCFPaintPaint
205New VCTRepair2x42x2
206VCTEpoxyPaintPaint
207VCTEpoxyPaintPaint
208VCTVCTPaintPaint
208AVCTVCTGypsumPaint
209VCTVCT1x1Paint
212VCTEpoxyPaintPaint
215VCTEpoxyPaintPaint
215AVCTEpoxyPaintPaint
CorridorVCTTCFParaline 1Paraline 3
Gibbs 3rd Deck
303
303ACeramic TileRemainPaintPaint
304VCTEpoxyPaintPaint
305VCTEpoxyPaintPaint
306VCTEpoxyPaintPaint
307VCTEpoxyPaintPaint
308VCTEpoxyPaintPaint
310VCTVCTPaintPaint
311VCTVCTPaintPaint
312VCTVCTPaintPaint
CorridorVCTTCFParaline 1Paraline 3