Attachment 2 Fulton Gibbs Schedule Requirement V8.xlsx
XLSX spreadsheet 31 KB Posted
- Attached to
- Fulton-Gibbs Refurbishment at the U. S. Merchant Marine Academy Federal contract opportunity
- Solicitation number
- 693JF723R000005
About this file
This document outlines a schedule of work requirements for the Fulton-Gibbs Refurbishment project at the U.S. Merchant Marine Academy. The contractor shall provide all labor, materials, equipment, supervision, transportation, and disposal for the complete renovation of Fulton and Gibbs Halls, including roof and window replacement, hallway and classroom lighting upgrades, replacement of emergency shower/eyewash stations, and assessment/abatement of asbestos. Work is broken into ten phases taking place between March 2023 and June 2025, and includes tasks such as flooring installation, painting, ceiling work, and HVAC upgrades in diesel/welding labs. The total cost of work is estimated at $3,983,735.31.
View the file
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Task Name | Duration | Start | Finish | Resource Names | Cost |
| Fulton-Gibbs Accredidation | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $14,734,204.44 | |
| Acquisition | $0.00 | ||||
| Solicitation Close Out | 1 day | Sun 4/16/23 | Sun 4/16/23 | $0.00 | |
| Contract Awarded | 1 day | Mon 5/22/23 | Mon 5/22/23 | $0.00 | |
| Kick-Of Meeting | 1 day | Tue 5/23/23 | Tue 5/23/23 | $0.00 | |
| Mobilization | 31 days | Wed 5/24/23 | Fri 6/23/23 | $0.00 | |
| Phase 1 (Roof & Windows) | 180 days | Mon 5/29/23 | Fri 11/24/23 | $4,613,121.17 | |
| Roof Repairs | 180 days | Mon 5/29/23 | Fri 11/24/23 | Roof Replacement[56,195 SF] | $3,585,802.95 |
| Demo Solar Panels | $0.00 | ||||
| Execution | $0.00 | ||||
| Windows | 60 days | Mon 5/29/23 | Thu 7/27/23 | $826,749.32 | |
| Window Caulking Interior | Window-Caulking Interior[5,875 LF] | $16,097.50 | |||
| Window Caulking Exterior | Window-Caulking Exterior[5,875 LF] | $100,462.50 | |||
| Window Replacement | Window-Replacement[10 EA] | $34,612.40 | |||
| Window Repair | Window-Repair[81 EA] | $119,176.92 | |||
| Window Film-Solar | Window-Solar Film[10,000 SF] | $556,400.00 | |||
| Eyewash Stations | 65 days | Mon 5/29/23 | Tue 8/1/23 | Eyewash Station[6 EA] | $134,544.60 |
| Atomic Lab 212 (Swing Space) | 65 days | Mon 5/29/23 | Tue 8/1/23 | $66,024.30 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[683 SF],Industrial Hygienist[1 Day] | $6,397.61 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[683 SF] | $8,571.65 | |||
| Epoxy Flooring | Flooring-Epoxy[683 SF] | $25,182.21 | |||
| Paint Ceiling | Ceiling-Paint[683 SF] | $1,140.61 | |||
| Lighting | Lighting[683 SF] | $19,356.22 | |||
| Paint | Wall-Paint[1,050] | $5,376.00 | |||
| Phase 2 (Summer Break) | 32 days | Sat 6/24/23 | Tue 7/25/23 | $867,877.12 | |
| Advanced Chemistry Lab (305) | 32 days | Sat 6/24/23 | Tue 7/25/23 | $117,108.26 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[1,261 SF],Industrial Hygienist[1 Day] | $8,703.83 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[1,261 SF] | $15,825.55 | |||
| Epoxy Flooring | Flooring-Epoxy[1,261 SF] | $46,493.07 | |||
| Lighting | Lighting[1,261 SF] | $35,736.74 | |||
| Paint Ceiling | Ceiling-Paint[1,261 SF] | $2,105.87 | |||
| Paint | Wall-Paint[1,610] | $8,243.20 | |||
| Fume Hoods | $0.00 | ||||
| Chem Prep (306) | 32 days | Sat 6/24/23 | Tue 7/25/23 | $59,823.43 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[642 SF] | $3,248.57 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[642 SF] | $8,057.10 | |||
| Epoxy Flooring | Flooring-Epoxy[642 SF] | $23,670.54 | |||
| Lighting | Lighting[642 SF] | $18,194.28 | |||
| Paint Ceiling | Ceiling-Paint[642 SF] | $1,072.14 | |||
| Paint | Wall-Paint[1,090] | $5,580.80 | |||
| Fume Hoods | $0.00 | ||||
| Basic Chemistry Lab (307) | 32 days | Sat 6/24/23 | Tue 7/25/23 | $129,485.33 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[1,447 SF] | $6,460.52 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[1,447 SF] | $18,159.85 | |||
| Epoxy Flooring | Flooring-Epoxy[1,447 SF] | $53,350.89 | |||
| Lighting | Lighting[1,447 SF] | $41,007.98 | |||
| Paint Ceiling | Ceiling-Paint[1,447 SF] | $2,416.49 | |||
| Paint | Wall-Paint[1,580] | $8,089.60 | |||
| Fume Hoods | $0.00 | ||||
| Machinery Lab (107) | 32 days | Sat 6/24/23 | Tue 7/25/23 | $230,644.84 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[2,728 SF] | $34,236.40 | |||
| Epoxy Flooring | Flooring-Epoxy[2,728 SF] | $100,581.36 | |||
| Lighting | Lighting[2,728 SF] | $77,311.52 | |||
| Paint Ceiling | Ceiling-Paint[2,748 SF] | $4,589.16 | |||
| Paint | Wall-Paint[2,720] | $13,926.40 | |||
| 1st Fl Hallways | 32 days | Sat 6/24/23 | Tue 7/25/23 | $330,815.26 | |
| Abatement | Asbestos-Removal[150 SF] | $523.50 | |||
| Flooring | Flooring-TCF[3,497 SF] | $87,739.73 | |||
| Lighting | Lighting[3,497 SF] | $99,104.98 | |||
| Ceiling | Ceiling-Acoustical[3,497 SF] | $112,778.25 | |||
| Paint | Wall-Paint[5,990] | $30,668.80 | |||
| Phase 3 (1st Trimester 23/24) | 93 days | Wed 7/26/23 | Thu 10/26/23 | $1,079,659.27 | |
| Machine Shop (F-G18) Phase 1 | 93 days | Wed 7/26/23 | Thu 10/26/23 | $219,214.54 | |
| Unerlayment | Underlayment-Epoxy[3,982 SF] | $49,974.10 | |||
| Epoxy Floor | Flooring-Epoxy[3,982 SF] | $146,816.34 | |||
| Install Eyewash Station | Eyewash Station[1 EA] | $22,424.10 | |||
| Welding Shop (F-G19) | 93 days | Wed 7/26/23 | Thu 10/26/23 | $417,593.08 | |
| Duct Work | $0.00 | ||||
| Lighting | Lighting[2,796 SF] | $79,238.64 | |||
| Exhaust Systems | Exhaust-Welding Lab[20 EA] | $283,923.20 | |||
| LVT Floor in Office | Flooring-VCT[160 SF] | $4,624.00 | |||
| Paint Corugated Ceiling | Ceiling-Paint[2,796 SF] | $4,669.32 | |||
| Walls-Paint | Wall-Paint[6,180] | $31,641.60 | |||
| Flooring-Paint | Wall-Paint[2,636] | $13,496.32 | |||
| Controls Lab (110) | 93 days | Wed 7/26/23 | Thu 10/26/23 | $132,283.75 | |
| Underlayment/Encapsulation | Flooring-Epoxy[1,201 SF] | $44,280.87 | |||
| Epoxy Flooring | Flooring-Epoxy[1,201 SF] | $44,280.87 | |||
| Lighting | Lighting[1,201 SF] | $34,036.34 | |||
| Paint Ceiling | Ceiling-Paint[1,201 SF] | $2,005.67 | |||
| Paint | Wall-Paint[1,500] | $7,680.00 | |||
| Circuits Lab (111) | 93 days | Wed 7/26/23 | Thu 10/26/23 | $132,283.75 | |
| Underlayment/Encapsulation | Flooring-Epoxy[1,201 SF] | $44,280.87 | |||
| Epoxy Flooring | Flooring-Epoxy[1,201 SF] | $44,280.87 | |||
| Lighting | Lighting[1,201 SF] | $34,036.34 | |||
| Paint Ceiling | Ceiling-Paint[1,201 SF] | $2,005.67 | |||
| Paint | Wall-Paint[1,500] | $7,680.00 | |||
| Classroom (F-101) | 93 days | Wed 7/26/23 | Thu 10/26/23 | $51,955.18 | |
| Lighting | Lighting[762 SF] | $21,595.08 | |||
| Ceiling | Ceiling-Acoustical[762 SF] | $24,574.50 | |||
| Paint | Wall-Paint[1,130] | $5,785.60 | |||
| Classroom (F-102) | 93 days | Wed 7/26/23 | Thu 10/26/23 | $55,408.81 | |
| Lighting | Lighting[819 SF] | $23,210.46 | |||
| Ceiling | Ceiling-Acoustical[819 SF] | $26,412.75 | |||
| Paint | Wall-Paint[1,130] | $5,785.60 | |||
| Classroom (F-115) | 93 days | Wed 7/26/23 | Thu 10/26/23 | $70,920.16 | |
| TCF | Flooring-TCF[762 SF] | $19,118.58 | |||
| Lighting | Lighting[762 SF] | $21,595.08 | |||
| Ceiling | Ceiling-Acoustical[762 SF] | $24,574.50 | |||
| Paint | Wall-Paint[1,100] | $5,632.00 | |||
| Phase 4 (2nd Trimester 23/24) | 112 days | Tue 11/14/23 | Mon 3/4/24 | $377,615.56 | |
| Classroom (G05) | 112 days | Tue 11/14/23 | Mon 3/4/24 | $37,849.40 | |
| TCF | Flooring-TCF[594 SF] | $14,903.46 | |||
| Lighting | Lighting[594 SF] | $16,833.96 | |||
| Paint Ceiling | Ceiling-Paint[594 SF] | $991.98 | |||
| Paint | Wall-Paint[1,000] | $5,120.00 | |||
| IME Storage (G12) | 112 days | Tue 11/14/23 | Mon 3/4/24 | $15,217.08 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[112 SF],Industrial Hygienist[1 Day] | $4,119.32 | |||
| Underlayment | Underlayment-Epoxy[112 SF] | $1,405.60 | |||
| Epoxy Flooring | Flooring-Epoxy[112 SF] | $4,129.44 | |||
| Lighting | Lighting[112 SF] | $3,174.08 | |||
| Paint Ceiling | Ceiling-Paint[112 SF] | $187.04 | |||
| Paint | Wall-Paint[430] | $2,201.60 | |||
| IME Lab (G14) | 112 days | Tue 11/14/23 | Mon 3/4/24 | $178,730.07 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[2,014 SF] | $8,722.85 | |||
| Underlayment | Underlayment-Epoxy[2,014 SF] | $25,275.70 | |||
| Epoxy Flooring | Flooring-Epoxy[2,014 SF] | $74,256.18 | |||
| Lighting | Lighting[2,014 SF] | $57,076.76 | |||
| Paint Ceiling | Ceiling-Paint[2,014 SF] | $3,363.38 | |||
| Paint | Wall-Paint[1,960] | $10,035.20 | |||
| IME Office (G13) | 112 days | Tue 11/14/23 | Mon 3/4/24 | $12,249.31 | |
| VCT | Flooring-VCT[161 SF] | $4,652.90 | |||
| Lighting | Lighting[161 SF] | $4,562.74 | |||
| Paint Ceiling | Ceiling-Paint[161 SF] | $268.87 | |||
| Paint | Wall-Paint[540] | $2,764.80 | |||
| Nuclear Lab (F-G03) | 112 days | Tue 11/14/23 | Mon 3/4/24 | $51,189.60 | |
| VCT | Flooring-VCT[560 SF] | $16,184.00 | |||
| Lighting | Lighting[560 SF] | $15,870.40 | |||
| Repair Ceiling | Ceiling-Acoustical[560 SF] | $18,060.00 | |||
| 950 | Wall-Paint[210] | $1,075.20 | |||
| Steering Lab (F-G22) | 112 days | Tue 11/14/23 | Mon 3/4/24 | $82,380.10 | |
| Epoxy Flooring | Flooring-Epoxy[897 SF] | $33,072.39 | |||
| Lighting | Lighting[897 SF] | $25,420.98 | |||
| Paint Ceiling | Ceiling-Paint[897 SF] | $1,497.99 | |||
| Paint | Wall-Paint[1,200] | $6,144.00 | |||
| Univector | Mechanical-Mini Slplit[1 EA] | $16,244.74 | |||
| Phase 5 (3rd Trimester 23/24) | 89 days | Mon 3/18/24 | Fri 6/14/24 | $450,978.17 | |
| Refrigertaion Lab (G08, G09, G09A) | 89 days | Mon 3/18/24 | Fri 6/14/24 | $178,680.96 | |
| Abatement | Asbestos-Demo[1,771 SF],Asbestos-Removal[1 SF],Industrial Hygienist[1 Day] | $10,055.23 | |||
| Underlayment | Underlayment-Epoxy[1,771 SF] | $22,226.05 | |||
| Epoxy Flooring | Flooring-Epoxy[1,771 SF] | $65,296.77 | |||
| Lighting | Lighting[1,771 SF] | $50,190.14 | |||
| Paint Ceiling | Ceiling-Paint[1,771 SF] | $2,957.57 | |||
| Paint | Wall-Paint[5,460] | $27,955.20 | |||
| Simulator Lab (F-105) | 89 days | Mon 3/18/24 | Fri 6/14/24 | $35,949.32 | |
| VCT Over Univector Space | Flooring-VCT[200 SF] | $5,780.00 | |||
| Lighting | Lighting[118 SF] | $3,344.12 | |||
| Ceiling | Ceiling-Acoustical[600 SF] | $19,350.00 | |||
| Paint | Wall-Paint[1,460] | $7,475.20 | |||
| Marine Proj Lab (F-114) | 89 days | Mon 3/18/24 | Fri 6/14/24 | $80,877.43 | |
| Underlayment | Underlayment-Epoxy[209 SF] | $2,622.95 | |||
| VCT | Flooring-VCT[209 SF] | $6,040.10 | |||
| Lighting | Lighting[1,082 SF] | $30,663.88 | |||
| Ceiling-ACT | Ceiling-Acoustical[1,082 SF] | $34,894.50 | |||
| Paint | Wall-Paint[1,300] | $6,656.00 | |||
| PLC Lab (F-109) | 89 days | Mon 3/18/24 | Fri 6/14/24 | $124,916.32 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[1,028 SF],Industrial Hygienist[1 Day] | $7,774.16 | |||
| Underlayment Carpet | Underlayment-Carpet[1,028 SF] | $15,563.92 | |||
| TCF | Flooring-TCF[1,028 SF] | $25,792.52 | |||
| Lighting | Lighting[1,028 SF] | $29,133.52 | |||
| Ceiling | Ceiling-Acoustical[1,028 SF] | $33,153.00 | |||
| Paint | Wall-Paint[1,660] | $8,499.20 | |||
| Crane Demo | Crane Demo[1] | $5,000.00 | |||
| Demo Area (F-104) | 89 days | Mon 3/18/24 | Fri 6/14/24 | $30,554.14 | |
| TCF | Flooring-TCF[437 SF] | $10,964.33 | |||
| Lighting | Lighting[44 SF] | $1,246.96 | |||
| Ceiling-ACT | Ceiling-Acoustical[437 SF] | $14,093.25 | |||
| Paint | Wall-Paint[830] | $4,249.60 | |||
| Phase 6 (Summer Break) | 32 days | Mon 6/24/24 | Thu 7/25/24 | $1,013,587.25 | |
| Steam Lab (F-G12) Phase 1 | 32 days | Mon 6/24/24 | Thu 7/25/24 | $460,512.78 | |
| Ceilings | Ceiling-Encapsulation Steam [4,975 SF] | $222,581.50 | |||
| Lighting | Lighting[4,975 SF] | $140,991.50 | |||
| Exhaust Systems | Exhaust-Diesel Lab[2 EA] | $37,957.38 | |||
| Paint | Wall-Paint[11,520] | $58,982.40 | |||
| Diesel Lab (F-G09) Phase 1 | 32 days | Mon 6/24/24 | Thu 7/25/24 | $338,964.17 | |
| Ceilings | Ceiling-Encapsulation Diesel[3,055 SF] | $137,138.95 | |||
| Lighting | Lighting[3,055 SF] | $86,578.70 | |||
| Paint | Wall-Paint[8,800] | $45,056.00 | |||
| Exhaust | Exhaust-Diesel Lab[2 EA] | $37,957.38 | |||
| Underlayment | Underlayment-Epoxy[591 SF] | $7,417.05 | |||
| Mezzanine Floor | Flooring-Epoxy[591 SF] | $21,790.17 | |||
| Mezzanine Walls | Wall-Paint[591] | $3,025.92 | |||
| Gas Turbine (G09A) | 32 days | Mon 6/24/24 | Thu 7/25/24 | $90,529.20 | |
| Ceilings | Ceiling-Encapsulation Diesel[634 SF] | $28,460.26 | |||
| Lighting | Lighting[634 SF] | $17,967.56 | |||
| Paint | Wall-Paint[1,200] | $6,144.00 | |||
| Exhaust | Exhaust-Diesel Lab[2 EA] | $37,957.38 | |||
| Lecture Hall (G06) | 32 days | Mon 6/24/24 | Thu 7/25/24 | $123,581.10 | |
| TCF | Flooring-TCF[1,637 SF] | $41,072.33 | |||
| Lighting | Lighting[1,637 SF] | $46,392.58 | |||
| Paint Ceiling | Ceiling-Paint[1,637 SF] | $2,733.79 | |||
| Paint | Wall-Paint[6,520] | $33,382.40 | |||
| Phase 7 (1st Trimester 24/25) | 93 days | Fri 7/26/24 | Sat 10/26/24 | $672,023.58 | |
| Machine Shop Phase 2 | 93 days | Fri 7/26/24 | Sat 10/26/24 | $139,698.82 | |
| Duct Work | $0.00 | ||||
| Suspended Ceiling | Ceiling-Acoustical[3,982 SF] | $128,419.50 | |||
| Lighting | Lighting[398 SF] | $11,279.32 | |||
| Exhaust Systems | $0.00 | ||||
| Ventilation | $0.00 | ||||
| Graphics Classroom (F-201) | 93 days | Fri 7/26/24 | Sat 10/26/24 | $139,344.74 | |
| TCF | Flooring-TCF[400 SF] | $10,036.00 | |||
| Lighting | Lighting[1,966 SF] | $55,716.44 | |||
| Suspended Ceiling | Ceiling-Acoustical[1,966 SF] | $63,403.50 | |||
| Paint | Wall-Paint[1,990] | $10,188.80 | |||
| Classroom (F-208) | 93 days | Fri 7/26/24 | Sat 10/26/24 | $63,929.92 | |
| TCF | Flooring-TCF[684 SF] | $17,161.56 | |||
| Lighting | Lighting[684 SF] | $19,384.56 | |||
| Ceiling | Ceiling-Acoustical[684 SF] | $22,059.00 | |||
| Paint | Wall-Paint[1,040] | $5,324.80 | |||
| Classroom (F-209) | 93 days | Fri 7/26/24 | Sat 10/26/24 | $77,824.72 | |
| TCF | Flooring-TCF[839 SF] | $21,050.51 | |||
| Lighting | Lighting[839 SF] | $23,777.26 | |||
| Ceiling | Ceiling-Acoustical[839 SF] | $27,057.75 | |||
| Paint | Wall-Paint[1,160] | $5,939.20 | |||
| Classroom (F-210) | 93 days | Fri 7/26/24 | Sat 10/26/24 | $67,990.32 | |
| TCF | Flooring-TCF[729 SF] | $18,290.61 | |||
| Lighting | Lighting[729 SF] | $20,659.86 | |||
| Ceiling-ACT | Ceiling-Acoustical[729 SF] | $23,510.25 | |||
| Paint | Wall-Paint[1,080] | $5,529.60 | |||
| Classroom (F-212) | 93 days | Fri 7/26/24 | Sat 10/26/24 | $66,533.76 | |
| TCF | Flooring-TCF[712 SF] | $17,864.08 | |||
| Lighting | Lighting[712 SF] | $20,178.08 | |||
| Suspended Ceiling | Ceiling-Acoustical[712 SF] | $22,962.00 | |||
| Paint | Wall-Paint[1,080] | $5,529.60 | |||
| Classroom (F-213) | 93 days | Fri 7/26/24 | Sat 10/26/24 | $67,904.64 | |
| TCF | Flooring-TCF[728 SF] | $18,265.52 | |||
| Lighting | Lighting[728 SF] | $20,631.52 | |||
| Suspended Ceiling | Ceiling-Acoustical[728 SF] | $23,478.00 | |||
| Paint | Wall-Paint[1,080] | $5,529.60 | |||
| Classroom (F-214) | 93 days | Fri 7/26/24 | Sat 10/26/24 | $48,796.66 | |
| TCF | Flooring-TCF[762 SF] | $19,118.58 | |||
| Lighting | Lighting[762 SF] | $21,595.08 | |||
| Suspended Ceiling | Ceiling-Acoustical[76 SF] | $2,451.00 | |||
| Paint | Wall-Paint[1,100] | $5,632.00 | |||
| Phase 8 (2nd Trimester 24/25) | 111 days | Thu 11/14/24 | Tue 3/4/25 | $745,325.19 | |
| Classroom (204) | 111 days | Thu 11/14/24 | Tue 3/4/25 | $39,939.30 | |
| TCF | Flooring-TCF[631 SF] | $15,831.79 | |||
| Lighting | Lighting[631 SF] | $17,882.54 | |||
| Ceiling | Ceiling-Paint[631 SF] | $1,053.77 | |||
| Paint | Wall-Paint[1,010] | $5,171.20 | |||
| Special Projects Classroom (205) | 111 days | Thu 11/14/24 | Tue 3/4/25 | $118,718.16 | |
| TCF | Flooring-TCF[1,287 SF] | $32,290.83 | |||
| Lighting | Lighting[1,287 SF] | $36,473.58 | |||
| Ceiling | Ceiling-Acoustical[1,287 SF] | $41,505.75 | |||
| Paint | Wall-Paint[1,650] | $8,448.00 | |||
| Heat Treating/Materials Lab (206/207/208/208A/209) | 111 days | Thu 11/14/24 | Tue 3/4/25 | $119,894.97 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[947 SF] | $4,465.52 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[1,143 SF] | $14,344.65 | |||
| Epoxy Flooring | Flooring-Epoxy[1,143 SF] | $42,142.41 | |||
| Lighting | Lighting[1,143 SF] | $32,392.62 | |||
| Ceiling | Ceiling-Paint[1,143 SF] | $1,908.81 | |||
| Paint | Wall-Paint[2,040] | $10,444.80 | |||
| Fume Hoods | Exhaust-Welding Lab[1 EA] | $14,196.16 | |||
| Strength & Fluids Lab (215) | 111 days | Thu 11/14/24 | Tue 3/4/25 | $213,990.40 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[2,560 SF] | $32,128.00 | |||
| Epoxy Flooring | Flooring-Epoxy[2,560 SF] | $94,387.20 | |||
| Lighting | Lighting[2,560 SF] | $72,550.40 | |||
| Ceiling | Ceiling-Paint[2,560 SF] | $4,275.20 | |||
| Paint | Wall-Paint[2,080] | $10,649.60 | |||
| Thermodynamics (F-203/203A) | 111 days | Thu 11/14/24 | Tue 3/4/25 | $142,724.12 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[1,180 SF] | $14,809.00 | |||
| Epoxy Flooring | Flooring-VCT[1,180 SF] | $34,102.00 | |||
| Lighting | Lighting[1,154 SF] | $32,704.36 | |||
| Ceiling | Ceiling-Acoustical[1,180 SF] | $38,055.00 | |||
| Paint | Wall-Paint[1,730] | $8,857.60 | |||
| Fume Hoods | Exhaust-Welding Lab[1 EA] | $14,196.16 | |||
| Classroom (F-204) | 111 days | Thu 11/14/24 | Tue 3/4/25 | $54,883.36 | |
| TCF | Flooring-TCF[582 SF] | $14,602.38 | |||
| Lighting | Lighting[582 SF] | $16,493.88 | |||
| Ceiling | Ceiling-Acoustical[582 SF] | $18,769.50 | |||
| Paint | Wall-Paint[980] | $5,017.60 | |||
| Classroom (F-207) | 111 days | Thu 11/14/24 | Tue 3/4/25 | $55,174.88 | |
| TCF | Flooring-TCF[586 SF] | $14,702.74 | |||
| Lighting | Lighting[586 SF] | $16,607.24 | |||
| Ceiling | Ceiling-Acoustical[586 SF] | $18,898.50 | |||
| Paint | Wall-Paint[970] | $4,966.40 | |||
| Phase 9 (3rd Trimester 24/25) | 89 days | Tue 3/18/25 | Sat 6/14/25 | $354,292.85 | |
| Instrument Lab (304) | 89 days | Tue 3/18/25 | Sat 6/14/25 | $56,452.59 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[631 SF],Industrial Hygienist[1 Day] | $6,190.13 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[631 SF] | $7,919.05 | |||
| Flooring VCT | Flooring-VCT[631 SF] | $18,235.90 | |||
| Lighting | Lighting[631 SF] | $17,882.54 | |||
| Ceiling | Ceiling-Paint[631 SF] | $1,053.77 | |||
| Paint | Wall-Paint[1,010] | $5,171.20 | |||
| Fume Hoods | $0.00 | ||||
| Physics (310) | 89 days | Tue 3/18/25 | Sat 6/14/25 | $79,618.85 | |
| Abatement | Asbestos-Demo[965 SF] | $3,850.35 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[965 SF] | $12,110.75 | |||
| Flooring VCT | Flooring-VCT[965 SF] | $27,888.50 | |||
| Lighting | Lighting[965 SF] | $27,348.10 | |||
| Ceiling | Ceiling-Paint[965 SF] | $1,611.55 | |||
| Paint | Wall-Paint[1,330] | $6,809.60 | |||
| Physics Prep (311) | 89 days | Tue 3/18/25 | Sat 6/14/25 | $28,002.90 | |
| Abatement | Asbestos-Demo[306 SF] | $1,220.94 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[306 SF] | $3,840.30 | |||
| Flooring VCT | Flooring-VCT[306 SF] | $8,843.40 | |||
| Lighting | Lighting[306 SF] | $8,672.04 | |||
| Ceiling | Ceiling-Paint[306 SF] | $511.02 | |||
| Paint | Wall-Paint[960] | $4,915.20 | |||
| Physics Lab (312) | 89 days | Tue 3/18/25 | Sat 6/14/25 | $82,092.39 | |
| Abatement | Asbestos Disposal[1 CY],Asbestos-Demo[988 SF] | $4,629.11 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[988 SF] | $12,399.40 | |||
| Flooring VCT | Flooring-VCT[988 SF] | $28,553.20 | |||
| Lighting | Lighting[988 SF] | $27,999.92 | |||
| Ceiling | Ceiling-Paint[988 SF] | $1,649.96 | |||
| Paint | Wall-Paint[1,340] | $6,860.80 | |||
| Hazardous Materials (F-301) | 89 days | Tue 3/18/25 | Sat 6/14/25 | $46,344.25 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[535 SF] | $6,714.25 | |||
| Epoxy Flooring | Flooring-Epoxy[535 SF] | $19,725.45 | |||
| Lighting | Lighting[535 SF] | $15,161.90 | |||
| Ceiling | Ceiling-Acoustical[1 SF] | $32.25 | |||
| Paint | Wall-Paint[920] | $4,710.40 | |||
| Fume Hoods | $0.00 | ||||
| Science Storage (F-302) | 89 days | Tue 3/18/25 | Sat 6/14/25 | $39,595.71 | |
| Lighting | Lighting[569 SF] | $16,125.46 | |||
| Ceiling | Ceiling-Acoustical[569 SF] | $18,350.25 | |||
| Paint | Wall-Paint[1,000] | $5,120.00 | |||
| Seminar (F-303) | 89 days | Tue 3/18/25 | Sat 6/14/25 | $22,186.16 | |
| Lighting | Lighting[604 SF] | $17,117.36 | |||
| Paint | Wall-Paint[990] | $5,068.80 | |||
| Phase 10 (Summer Break) | 32 days | Tue 6/24/25 | Fri 7/25/25 | $575,988.97 | |
| Steam Lab (F-G12) Phase 2 | 32 days | Tue 6/24/25 | Fri 7/25/25 | $251,095.40 | |
| Underlayment | Underlayment-Epoxy[4,975 SF] | $62,436.25 | |||
| Epoxy Flooring | Flooring-Epoxy[4,975 SF] | $183,428.25 | |||
| Office Floor | Flooring-VCT[181 SF] | $5,230.90 | |||
| Diesel Lab (F-G09) Phase 2 | 32 days | Tue 6/24/25 | Fri 7/25/25 | $121,770.88 | |
| Underlayment | Underlayment-Epoxy[2,464 SF] | $30,923.20 | |||
| Epoxy Flooring | Flooring-Epoxy[2,464 SF] | $90,847.68 | |||
| Zero Deck Hallway | 32 days | Tue 6/24/25 | Fri 7/25/25 | $203,122.69 | |
| Underlayment | Underlayment-Epoxy[2,243 SF] | $28,149.65 | |||
| Flooring | Flooring-Epoxy[2,243 SF] | $82,699.41 | |||
| Lighting | Lighting[2,243 SF] | $63,566.62 | |||
| Ceiling | Ceiling-Paint[2,443 SF] | $4,079.81 | |||
| Paint | Wall-Paint[4,810] | $24,627.20 | |||
| Period of Performance | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $3,983,735.31 | |
| 2nd Fl Hallways | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $242,783.23 | |
| Abatement | Asbestos-Removal[247 SF] | $862.03 | |||
| TCF | Flooring-TCF[2,465 SF] | $61,846.85 | |||
| Lighting | Lighting[2,465 SF] | $69,858.10 | |||
| Ceiling | Ceiling-Acoustical[2,465 SF] | $79,496.25 | |||
| Paint | Wall-Paint[6,000] | $30,720.00 | |||
| 3rd Fl Hallways | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $274,679.10 | |
| Abatement | Asbestos-Removal[270 SF] | $942.30 | |||
| TCF | Flooring-TCF[2,770 SF] | $69,499.30 | |||
| Lighting | Lighting[2,770 SF] | $78,501.80 | |||
| Ceiling | Ceiling-Acoustical[2,770 SF] | $89,332.50 | |||
| Paint | Wall-Paint[7,110] | $36,403.20 | |||
| 4th Fl Hallways | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $70,371.27 | |
| Abatement | Asbestos-Removal[70 SF] | $244.30 | |||
| TCF | Flooring-TCF[689 SF] | $17,287.01 | |||
| Lighting | Lighting[689 SF] | $19,526.26 | |||
| Ceiling | Ceiling-Acoustical[698 SF] | $22,510.50 | |||
| Paint | Wall-Paint[2,110] | $10,803.20 | |||
| Fulton 3rd Fl Offices | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $259,454.40 | |
| TCF | Flooring-TCF[6,200 SF] | $155,558.00 | |||
| Ceiling | Ceiling-Paint[6,200 SF] | $10,354.00 | |||
| Paint | Wall-Paint[18,270] | $93,542.40 | |||
| Fulton 4th Fl Offices | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $79,153.12 | |
| TCF | Flooring-TCF[1,852 SF] | $46,466.68 | |||
| Ceiling | Ceiling-Paint[1,852 SF] | $3,092.84 | |||
| Paint | Wall-Paint[5,780] | $29,593.60 | |||
| Instrument Storage (104) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $35,848.74 | |
| Abatement | Asbestos-Removal[40 SF] | $139.60 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[398 SF] | $4,994.90 | |||
| Epoxy Flooring | Flooring-Epoxy[398 SF] | $14,674.26 | |||
| Lighting | Lighting[398 SF] | $11,279.32 | |||
| Ceiling | Ceiling-Paint[398 SF] | $664.66 | |||
| Paint | Wall-Paint[800] | $4,096.00 | |||
| Elect Shop (105) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $39,341.01 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[477 SF] | $5,986.35 | |||
| Epoxy Flooring | Flooring-Epoxy[477 SF] | $17,586.99 | |||
| Lighting | Lighting[477 SF] | $13,518.18 | |||
| Ceiling | Ceiling-Paint[477 SF] | $796.59 | |||
| Paint | Ceiling-Paint[870 SF] | $1,452.90 | |||
| Sump Tank Rm (108) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $18,244.92 | |
| Abatement | Asbestos-Demo[144 SF],Asbestos Disposal[1 CY],Industrial Hygienist[1 Day] | $4,247.00 | |||
| Underlayment/Encapsulation | Underlayment-Epoxy[144 SF] | $1,807.20 | |||
| Epoxy Flooring | Flooring-Epoxy[144 SF] | $5,309.28 | |||
| Lighting | Lighting[144 SF] | $4,080.96 | |||
| Ceiling | Ceiling-Paint[144 SF] | $240.48 | |||
| Paint | Wall-Paint[500] | $2,560.00 | |||
| Acid Waste (G11) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $8,356.46 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[82 SF] | $1,029.10 | |||
| Epoxy Flooring | Flooring-Epoxy[82 SF] | $3,023.34 | |||
| Lighting | Lighting[82 SF] | $2,323.88 | |||
| Ceiling | Ceiling-Paint[82 SF] | $136.94 | |||
| Paint | Wall-Paint[360] | $1,843.20 | |||
| Janitorial Lockers (F-G05) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $30,712.46 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[332 SF] | $4,166.60 | |||
| Epoxy Flooring | Flooring-Epoxy[322 SF] | $11,872.14 | |||
| Lighting | Lighting[332 SF] | $9,408.88 | |||
| Ceiling | Ceiling-Paint[332 SF] | $554.44 | |||
| Paint | Wall-Paint[920] | $4,710.40 | |||
| Tech Shop (F-G20) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $116,081.92 | |
| Epoxy Flooring | Flooring-Epoxy[1,604 SF] | $59,139.48 | |||
| Lighting | Lighting[1,604 SF] | $45,457.36 | |||
| Ceiling | Ceiling-Paint[1,604 SF] | $2,678.68 | |||
| Paint | Wall-Paint[1,720] | $8,806.40 | |||
| Faculty Lounge (405) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $56,168.56 | |
| TCF | Flooring-TCF[597 SF] | $14,978.73 | |||
| Ceiling-Acoustical | Ceiling-Acoustical[597 SF] | $19,253.25 | |||
| Lighting | Lighting[597 SF] | $16,918.98 | |||
| Paint | Wall-Paint[980] | $5,017.60 | |||
| A/V Telecom Closets | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $21,077.68 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[152 SF] | $1,907.60 | |||
| Epoxy Flooring | Flooring-Epoxy[152 SF] | $5,604.24 | |||
| Ceiling | Ceiling-Paint[152 SF] | $253.84 | |||
| Paint | Wall-Paint[2,600] | $13,312.00 | |||
| Janitorial Closets | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $31,901.42 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[274 SF] | $3,438.70 | |||
| Epoxy Flooring | Flooring-Epoxy[274 SF] | $10,102.38 | |||
| Paint | Wall-Paint[1,980] | $10,137.60 | |||
| Ceiling | Ceiling-Paint[274 SF] | $457.58 | |||
| Lighting | Lighting[274 SF] | $7,765.16 | |||
| Storage/Mechanical | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $82,784.24 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[1,422 SF] | $17,846.10 | |||
| Epoxy Flooring | Flooring-VCT[1,442 SF] | $41,673.80 | |||
| Paint | Wall-Paint[4,080] | $20,889.60 | |||
| Ceiling | Ceiling-Paint[1,422 SF] | $2,374.74 | |||
| Office (F-G11) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $29,491.82 | |
| Underlayment/Encapsulation | Underlayment-Epoxy[82 SF] | $1,029.10 | |||
| Epoxy Flooring | Flooring-Epoxy[274 SF] | $10,102.38 | |||
| Paint | Wall-Paint[1,980] | $10,137.60 | |||
| Ceiling | Ceiling-Paint[274 SF] | $457.58 | |||
| Lighting | Lighting[274 SF] | $7,765.16 | |||
| Restrooms | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $95,212.26 | |
| Lighting | Lighting[1,946 SF] | $55,149.64 | |||
| Ceiling | Ceiling-Paint[1,946 SF] | $3,249.82 | |||
| Paint | Wall-Paint[7,190] | $36,812.80 | |||
| Stairwells | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $337,985.36 | |
| Abatement | Asbestos-Demo[3,644 SF],Asbestos-Removal[3,644 SF],Asbestos Disposal[6 CY],Industrial Hygienist[6 Day] | $49,291.76 | |||
| TCF | Flooring-TCF[3,644 SF] | $91,427.96 | |||
| Lighting | Lighting[3,644 SF] | $103,270.96 | |||
| Ceiling | Ceiling-Paint[3,644 SF] | $6,085.48 | |||
| Paint | Wall-Paint[9,260] | $47,411.20 | |||
| Bullnose | Bullnose[2,000 LF] | $36,320.00 | |||
| Riser | Riser[200 EA] | $4,178.00 | |||
| Doors | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $245,549.00 | |
| Replace/Keying | Door-Replace[100 EA] | $189,794.00 | |||
| Repair | Door-Repair[300 EA] | $55,755.00 | |||
| Fume Hoods (Study Dependent) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | Fume Hoods-Laboratory[1 EA] | $1,908,538.34 |
| Design | $0.00 | ||||
| Review | $0.00 | ||||
| Execution | $0.00 | ||||
| Retrofit Pneumatic Systems (Study Dependent) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $0.00 | |
| Design | $0.00 | ||||
| Review | $0.00 | ||||
| Execution | $0.00 | ||||
| Ventilation Systems (Study Dependent) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $0.00 | |
| Design | $0.00 | ||||
| Review | $0.00 | ||||
| Execution | $0.00 | ||||
| HVAC Upgrades (Study Dependent) | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $0.00 | |
| Design | $0.00 | ||||
| Review | $0.00 | ||||
| Execution | $0.00 | ||||
| Punch List | 36.65 emons | Wed 3/1/23 | Wed 3/4/26 | $0.00 | |
| Walk Through | $0.00 | ||||
| Review | $0.00 | ||||
| Close | $0.00 |