Attachment 2 Fulton-Gibbs Schedule Requirements (AMD0012).xlsx
XLSX spreadsheet 23 KB Posted
- Solicitation number
- 693JF723R000005
About this file
This document contains a schedule and requirements for the Fulton-Gibbs Refurbishment at the U.S. Merchant Marine Academy. The contractor shall provide all labor, materials, equipment, supervision, transportation, and disposal required for the complete renovation of Fulton and Gibbs Halls. Work includes roof and window replacement, hallway and classroom lighting upgrades, emergency shower/eyewash station replacement, CMU wall repairs and painting, upgrade of ventilation systems in diesel and welding labs. The schedule outlines nine phases of work to be completed over 36 months from August 2023 through July 2026. It includes detailed tasks and durations for renovations of classrooms, labs, offices and common areas. The total contract value is $18,797,791.35 according to the schedule. The solicitation was issued by the Department of Transportation Maritime Administration for the refurbishment work.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| $14,781,367.32 | Current | $678,999.30 | $26,076.00 |
| $3,270,408.78 | HVAC | $657,315.00 | $89,887.00 |
| $18,051,776.10 | Total Refurbish | $839,953.65 | $59,282.64 |
| $630,840.00 | $141,748.00 | ||
| $18,797,791.35 | CLIN Amount | $710,227.20 | $79,248.41 |
| $746,015.25 | Variance | $1,040,251.33 | |
| $687,492.00 | |||
| $79,248.41 | Engineering Studies | $737,602.40 | |
| $747,835.11 | CM | $747,835.11 | |
| $458,591.00 | Swing Space | ||
| $1,285,674.52 | Total Support Contracts | ||
| $539,659.27 |
Sheet2
| Task Name | Duration | Start | Finish |
| Fulton-Gibbs Accredidation | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Acquisition | |||
| Solicitation Close Out | 1 day | Fri 5/12/23 | Fri 5/12/23 |
| Contract Awarded | 1 day | Wed 7/19/23 | Wed 7/19/23 |
| Kick-Of Meeting | 1 day | Thu 7/20/23 | Thu 7/20/23 |
| Mobilization | 14 days | Fri 7/21/23 | Thu 8/3/23 |
| Phase 1 (Roof & Windows) | 180 days | Thu 8/3/23 | Mon 1/29/24 |
| Roof Repairs | 180 days | Thu 8/3/23 | Mon 1/29/24 |
| Demo Solar Panels | |||
| Windows | 60 days | Thu 8/3/23 | Sun 10/1/23 |
| Window Caulking Interior | |||
| Window Caulking Exterior | |||
| Window Replacement | |||
| Window Repair | |||
| Window Film-Solar | |||
| Phase 2 (1st Trimester 23/24) | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| Controls Lab (110) | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Circuits Lab (111) | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Classroom (F-101) | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| TCF | 56 days | Mon 7/24/23 | Sun 9/17/23 |
| Lead Time | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Classroom (F-102) | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| TCF | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| Lead Time | 56 days | Mon 7/24/23 | Sun 9/17/23 |
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Classroom (F-115) | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Eyewash Stations | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| Atomic Lab 212 (Swing Space) | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Paint Ceiling | |||
| Lighting | |||
| Paint Walls | |||
| 1st Fl Hallways | 85 days | Thu 8/3/23 | Thu 10/26/23 |
| Abatement | |||
| Flooring | |||
| Lighting | |||
| Linear Ceiling | |||
| Paint Walls | |||
| Phase 3 (2nd Trimester 23/24) | 112 days | Tue 11/14/23 | Mon 3/4/24 |
| Classroom (G05) | 112 days | Tue 11/14/23 | Mon 3/4/24 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| IME Storage (G12) | 112 days | Tue 11/14/23 | Mon 3/4/24 |
| Abatement | |||
| Underlayment | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| IME Lab (G14) | 112 days | Tue 11/14/23 | Mon 3/4/24 |
| Abatement | |||
| Underlayment | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| IME Office (G13) | 112 days | Tue 11/14/23 | Mon 3/4/24 |
| VCT | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Nuclear Lab (F-G03) | 112 days | Tue 11/14/23 | Mon 3/4/24 |
| VCT | |||
| Lighting | |||
| Repair Ceiling | |||
| Paint Walls | |||
| Steering Lab (F-G22) | 112 days | Tue 11/14/23 | Mon 3/4/24 |
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Univector Replacement | |||
| Phase 4 (3rd Trimester 23/24) | 89 days | Mon 3/18/24 | Fri 6/14/24 |
| Refrigertaion Lab (G08, G09, G09A) | 89 days | Mon 3/18/24 | Fri 6/14/24 |
| Abatement | |||
| Underlayment | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Simulator Lab (F-105) | 89 days | Mon 3/18/24 | Fri 6/14/24 |
| VCT (Univector Space) | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Marine Proj Lab (F-114) | 89 days | Mon 3/18/24 | Fri 6/14/24 |
| Underlayment | |||
| VCT | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| PLC Lab (F-109) | 89 days | Mon 3/18/24 | Fri 6/14/24 |
| Abatement | |||
| Underlayment Carpet | |||
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Crane Demo | |||
| Demo Area (F-104) | 89 days | Mon 3/18/24 | Fri 6/14/24 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Phase 5 (Summer Break 24) | 32 days | Mon 6/24/24 | Thu 7/25/24 |
| Steam Lab (F-G12) Phase 1 | 32 days | Mon 6/24/24 | Thu 7/25/24 |
| PVC Ceiling | |||
| Lighting | |||
| Exhaust Systems | |||
| Paint Walls | |||
| Diesel Lab (F-G09) Phase 1 | 32 days | Mon 6/24/24 | Thu 7/25/24 |
| PVC Ceiling | |||
| Lighting | |||
| Paint Walls | |||
| Exhaust Systems | |||
| Underlayment | |||
| Mezzanine Floor | |||
| Mezzanine Walls | |||
| Gas Turbine (G09A) | 32 days | Mon 6/24/24 | Thu 7/25/24 |
| PVC Ceiling | |||
| Lighting | |||
| Paint Walls | |||
| Exhaust Systems | |||
| Lecture Hall (G06) | 32 days | Mon 6/24/24 | Thu 7/25/24 |
| TCF | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Advanced Chemistry Lab (305) | 32 days | Sat 6/24/23 | Tue 7/25/23 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Fume Hoods | |||
| Chem Prep (306) | 32 days | Sat 6/24/23 | Tue 7/25/23 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Fume Hoods | |||
| Basic Chemistry Lab (307) | 32 days | Sat 6/24/23 | Tue 7/25/23 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Fume Hoods | |||
| Phase 6 (1st Trimester 24/25) | 93 days | Fri 7/26/24 | Sat 10/26/24 |
| Machine Shop (F-G18) | 93 days | Wed 7/26/23 | Thu 10/26/23 |
| Unerlayment | |||
| Epoxy Flooring | |||
| Install Eyewash Station | |||
| Duct Work | |||
| Acoustical Ceiling | |||
| Lighting | |||
| Exhaust Systems | |||
| Ventilation | |||
| Welding Shop (F-G19) | 93 days | Wed 7/26/23 | Thu 10/26/23 |
| Duct Work | |||
| Lighting | |||
| Exhaust Systems | |||
| VCT Office Floor | |||
| Paint Corugated Ceiling | |||
| Paint Walls | |||
| Paint Flooring | |||
| Graphics Classroom (F-201) | 93 days | Fri 7/26/24 | Sat 10/26/24 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Classroom (F-208) | 93 days | Fri 7/26/24 | Sat 10/26/24 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Classroom (F-209) | 93 days | Fri 7/26/24 | Sat 10/26/24 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Classroom (F-210) | 93 days | Fri 7/26/24 | Sat 10/26/24 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Classroom (F-212) | 93 days | Fri 7/26/24 | Sat 10/26/24 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Classroom (F-213) | 93 days | Fri 7/26/24 | Sat 10/26/24 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Classroom (F-214) | 93 days | Fri 7/26/24 | Sat 10/26/24 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Machinery Lab (107) | 93 days | Fri 7/26/24 | Sat 10/26/24 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Phase 7 (2nd Trimester 24/25) | 111 days | Thu 11/14/24 | Tue 3/4/25 |
| Classroom (204) | 111 days | Thu 11/14/24 | Tue 3/4/25 |
| TCF | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Special Projects Classroom (205) | 111 days | Thu 11/14/24 | Tue 3/4/25 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Heat Treating/Materials Lab (206/207/208/208A/209) | 111 days | Thu 11/14/24 | Tue 3/4/25 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Fume Hoods | |||
| Strength & Fluids Lab (215) | 111 days | Thu 11/14/24 | Tue 3/4/25 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Thermodynamics (F-203/203A) | 111 days | Thu 11/14/24 | Tue 3/4/25 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Fume Hoods | |||
| Classroom (F-204) | 111 days | Thu 11/14/24 | Tue 3/4/25 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Classroom (F-207) | 111 days | Thu 11/14/24 | Tue 3/4/25 |
| TCF | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Phase 8 (3rd Trimester 24/25) | 89 days | Tue 3/18/25 | Sat 6/14/25 |
| Instrument Lab (304) | 89 days | Tue 3/18/25 | Sat 6/14/25 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| VCT | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Fume Hoods | |||
| Physics (310) | 89 days | Tue 3/18/25 | Sat 6/14/25 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| VCT | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Physics Prep (311) | 89 days | Tue 3/18/25 | Sat 6/14/25 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| VCT | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Physics Lab (312) | 89 days | Tue 3/18/25 | Sat 6/14/25 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| VCT | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Hazardous Materials (F-301) | 89 days | Tue 3/18/25 | Sat 6/14/25 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Fume Hoods | |||
| Science Storage (F-302) | 89 days | Tue 3/18/25 | Sat 6/14/25 |
| Lighting | |||
| Acoustical Ceiling | |||
| Paint Walls | |||
| Seminar (F-303) | 89 days | Tue 3/18/25 | Sat 6/14/25 |
| Lighting | |||
| Paint Walls | |||
| Phase 9 (Summer Break 25) | 32 days | Tue 6/24/25 | Fri 7/25/25 |
| Steam Lab (F-G12) Phase 2 | 32 days | Tue 6/24/25 | Fri 7/25/25 |
| Underlayment | |||
| Epoxy Flooring | |||
| VCT (Office Floor) | |||
| Diesel Lab (F-G09) Phase 2 | 32 days | Tue 6/24/25 | Fri 7/25/25 |
| Underlayment | |||
| Epoxy Flooring | |||
| Zero Deck Hallway | 32 days | Tue 6/24/25 | Fri 7/25/25 |
| Underlayment | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceilng | |||
| Paint Walls | |||
| Period of Performance | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| 2nd Fl Hallways | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Abatement | |||
| TCF | |||
| Lighting | |||
| Linear Ceiling | |||
| Paint Walls | |||
| 3rd Fl Hallways | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Abatement | |||
| TCF | |||
| Lighting | |||
| Linear Ceiling | |||
| Paint Walls | |||
| 4th Fl Hallways | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Abatement | |||
| TCF | |||
| Lighting | |||
| Linear Ceiling | |||
| Paint Walls | |||
| Fulton 3rd Fl Offices | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| TCF | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Fulton 4th Fl Offices | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| TCF | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Instrument Storage (104) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Elect Shop (105) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Sump Tank Rm (108) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Abatement | |||
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Acid Waste (G11) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Janitorial Lockers (F-G05) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Tech Shop (F-G20) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Epoxy Flooring | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Faculty Lounge (405) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| TCF | |||
| Acoustical Ceiling | |||
| Lighting | |||
| Paint Walls | |||
| A/V Telecom Closets | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Janitorial Closets | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Paint Walls | |||
| Paint Ceiling | |||
| Lighting | |||
| Storage/Mechanical | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Paint Walls | |||
| Paint Ceiling | |||
| Office (F-G11) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Underlayment/Encapsulation | |||
| Epoxy Flooring | |||
| Paint Walls | |||
| Paint Ceiling | |||
| Lighting | |||
| Restrooms | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Lighting | |||
| Paint Ceiling | |||
| Paint | |||
| Stairwells | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Abatement | |||
| TCF | |||
| Lighting | |||
| Paint Ceiling | |||
| Paint Walls | |||
| Bullnose | |||
| Riser | |||
| Doors | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Replace/Keying | |||
| Repair | |||
| Fume Hoods (Study Dependent) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Design | |||
| Review | |||
| Execution | |||
| Retrofit Pneumatic Systems (Study Dependent) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Design | |||
| Review | |||
| Execution | |||
| Ventilation Systems (Study Dependent) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Design | |||
| Review | |||
| Execution | |||
| HVAC Upgrades (Study Dependent) | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Design | |||
| Review | |||
| Execution | |||
| Punch List | 36 emons | Thu 8/3/23 | Sat 7/18/26 |
| Walk Through | |||
| Review | |||
| Close |