This solicitation is for the expansion of Building 1 for primary care at the Fargo VA Medical Center. The project involves rerouting part of the road between the medical center and the flood wall, relocating the flood wall basin and road further away from a new building addition to comply with standoff requirements. Foundation work will include installing helical piers to the specified depth. The two-story addition will create a whole health clinic on the first floor and mechanical space and offices for EMS in the basement. The solicitation requests bids for the construction work described to expand primary care facilities at the identified location by the specified date.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
M
FIRE ALARM DEVICE SYMBOLS
SPOT-TYPE SMOKE DETECTOR
SPEAKER STROBE - CEILING MOUNT
SPEAKER STROBE - WALL MOUNT
MANUAL PULL STATION
SPRINKLER TAMPER SWITCH MONITOR MODULE
SPRINKLER WATER FLOW MONITOR MODULEWF
T
SPEAKER - CEILING MOUNT
MAGNETIC DOOR HOLD RELAYDH
S DUCT-TYPE SMOKE DETECTOR
ISO ISOLATION MODULE
SPEAKER STROBE - WALL MOUNT WATER PROOFWP
STROBE - WALL MOUNT
1. THIS PROJECT INCLUDES THE DESIGN OF AN EXTENSION TO THE EXISTING ADDRESSABLE FIRE ALARM SYSTEM FOR THE NEW BUILDING ADDITION SHOWN ON THESE PLANS PER NFPA 72 (2019 ed.), LOCAL BUILDING CODES, AND THE VA FIRE PROTECTION DESIGN MANUAL (SEVENTH ed.).
NEW WIRING AND DEVICES WILL BE INSTALLED IN PROJECT AREAS ON ALL LEVELS.
2. FINAL DEVICE LOCATION AND CIRCUIT ROUTING IS TO BE DETERMINED BY THE
FIRE ALARM CONTRACTOR AND IS SUBJECT TO APPROVAL BY THE ENGINEER OF
RECORD.
3. REFER TO SPECIFICATION SECTION 28 31 00 FOR ADDITIONAL FIRE ALARM SYSTEM
INFORMATION.
4. ALL DEVICES SHALL BE UL LISTED AND FM APPROVED PER THE VA FIRE PROTECTION
DESIGN MANUAL. ALL NEW DEVICES SHALL BE PURCHASED FROM THE BUILDING FIRE ALARM
MAINTENANCE CONTRACTOR TO ENSURE COMPATIBILITY WITH BUILDING'S FIRE ALARM SYSTEM.
5. DEVICES ARE REQUIRED TO BE PROTECTED DURING PAINTING.
6. CEILING MOUNTED DEVICES SHALL BE LOCATED IN THE CENTER POINT OF SQUARE
CEILING TILES AND ALLOWED TO BE IN THE QUARTER AND/OR CENTER POINTS OF
RECTANGULAR CEILING TILES.
7. NOT ALL REQUIRED DEVICES AND WIRING ARE SHOWN. CONSIDERATION OF
ADDITIONAL DEVICES AND WIRING DUE TO INTERFERENCE WITH OTHER TRADES,
OBSTRUCTIONS, IMPROVED AESTHETICS, OR OWNER/AHJ REQUESTS SHALL BE MADE
PRIOR TO BID BY THE FIRE ALARM CONTRACTOR.
8. FIRE ALARM CONTRACTOR TO PROVIDE ALL NECESSARY MATERIAL TO PROVIDE
COMPLETE SYSTEM(S) TO COMPLY WITH NFPA 72, LOCAL BUILDING CODES, AND THE
VA FIRE PROTECTION DESIGN MANUAL. ANY AND ALL CLARIFICATIONS TO BID
DOCUMENTS SHALL BE MADE PRIOR TO BID.
9. THE FIRE ALARM CONTRACTOR SHALL INSPECT THE SITE PRIOR TO BID. NO
ALLOWANCES FOR EXTRA DEVICES ETC. WILL BE ALLOWED AFTER AWARD OF
CONTRACT DUE TO MISUNDERSTANDING OF WORK INVOLVED OR LACK OF KNOWLEDGE
OF ANY PROJECT SITE CONDITIONS.
10. CONTROL PANEL AND DEVICE LOCATIONS SHOWN ON THESE PLANS IS CONCEPTUAL
BUT IS TO BE CLOSELY FOLLOWED BY THE FIRE ALARM CONTRACTOR. ANY MAJOR
CHANGES TO WHAT IS BEING INDICATED ON THESE PLANS SHALL FIRST BE APPROVED
BY THE ARCHITECT AND ENGINEER OF RECORD.
11. ALL ARCHITECTURAL, STRUCTURAL, MECHANICAL, & ELECTRICAL FEATURES INDICATED
ON THE FA SHEETS SHALL BE VERIFIED BY CONSULTING THE A/S/M&E SHEETS.
12. ALL CALCULATIONS ARE THE RESPONSIBILITY OF THE FIRE ALARM CONTRACTOR. ANY
AND ALL CLARIFICATION TO BID DOCUMENTS SHALL BE MADE PRIOR TO BID.
13. SHOULD ANY EXISTING SYSTEM DEFICIENCIES NOT INDICATED ON THESE PLANS BE
DISCOVERED AS PART OF CONDUCTING THE WORK INCLUDED IN THIS SCOPE, THEY
SHALL BE BROUGHT TO THE ATTENTION OF THE ENGINEER OF RECORD IMMEDIATELY.
14. THESE PLANS SHALL BE USED AS A GENERAL GUIDE IN THE GENERATION OF THE FIRE
ALARM CONTRACTOR'S BID AND ARE NOT INTENDED TO INDICATE THE ENTIRE EXTENT
OF ALARM PROTECTION REQUIRED. ANY AREAS REQUIRED TO BE PROTECTED PER
NFPA 72 THAT MAY OR MAY NOT BE SHOWN WITH PROTECTION ON THESE PLANS SHALL
BE INCLUDED IN THE CONTRACTOR'S BID.
15. FIRE ALARM CONTRACTOR SHALL BE RESPONSIBLE FOR THE REMOVAL AND RE-INSTALLING
OF EXISTING CEILING TILE AND WALLS NOT REMOVED BY THE GENERAL
CONTRACTOR FOR THE DEMOLITION OF EXISTING FIRE ALARM DEVICES, WIRING, ETC.
ANY CEILING OR WALL COMPONENTS DAMAGED SHALL BE REPLACED OR PATCHED
WITH NEW BY THIS CONTRACTOR.
16. FIRE ALARM RISER DIAGRAM AND SHOP DRAWINGS, INCLUDING BATTERY CALCULATIONS AND NOTIFICATION APPLIANCE CIRCUIT VOLTAGE DROP ANALYSIS PLUS SEQUENCE OF OPERATIONS, SHALL BE PREPARED AND SUBMITTED BY THE FIRE ALARM CONTRACTOR.
FIRE ALARM CONTROL PANEL MATRIX
EVENT
MANUAL PULL STATION ACTIVATION
SMOKE DETECTOR ACTIVATION
DUCT SMOKE DETECTOR ACTIVATION
A N
N U
N C
IA
T
E O
N F
IR
E
A L A
R M
C O
N T
R O
L P
A N
E L
A C
T
IV
A T
E A
U D
IB
L E
N O
T
IF
IC
A
T
IO
N
S
IG
N A
L S
U P
E R
V
IS
IN
G
S T
A T
IO
N
IN
IT
IA
T
E R
E C
A L L E
L E
V A
T O
R
S H
U T
D O
W N
A S
S O
C
IA
T E
D A
IR
H
A N
D L E
R A
N D
C L O
S E
A S
S O
C
IA
T E
D F
/S D
A M
P E
R S
A C
T
IV
A T
E V
IS
IB
L E
N O
T
IF
IC
A
T
IO
N
C L O
S E
A S
S O
C
IA
T E
D S
M O
K E
D A
M P
E R
R E
L E
A S
E A
S S
O C
IA
T
E D
D O
O R
H O
L D
S
1. MATRIX SHALL FOLLOW PROVISIONS OF VA FIRE PROTECTION
DESIGN MANUAL FOR ZONED NOTIFICAITON REQUIREMENTS.
2. THE SAME SYSTEM RESPONSE SHALL BE USED IN THE ADDITION
AS WHAT IS CURRENTLY USED IN THE EXISITNG FACILITY.
SUMMIT FIRE CONSULTING
575 MINNEHAHA AVE WEST
ST. PAUL, MINNESOTA 55103
(612) 387-7050
CALIBRE
9090 S RIDGELINE BLVD, SUITE 105
HIGHLANDS RANCH COLORADO 80129
PHONE (303) 730-0434
ALBERTSON ENGINEERING, INC.
315 NORTH MAIN AVENUE, SUITE 200
SIOUX FALLS, SOUTH DAKOTA 57104
PH: (605) 274-0880
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA
57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COMFOURFRONT
D E S I G N I N C.
Office of Construction and Facilities Management
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
Approved: Project Director
ARCHITECTCONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
Department of
Veterans Affairsof
/1
/2
:1
:5
A
M
CONSTRUCTION DOCUMENTS
11/16/2021
FIRE ALARM COVER SHEET
FA1.00
EXPAND BLDG. 1 FOR
PRIMARY CARE
CJNB
2101 ELM STREET
FARGO, ND 58102FARGO VAHCS
437-315
123 128
GENERAL NOTES:
11-18-21
30 30
15 15
30 30
30 30
15 15
M
15 15
M
S P
S P
S P
S P
SPSP SPSP
S P
S P
S P
SPSP SPSPSPSPSP
S
P S
P S
P
S P
S P
S P
SP
S P
SP SPSP SP
S P
S P
S P
S P
M
SP SP
EXISTING TO REMAIN.
LIMITS OF PROJECT/CONSTRUCTION
UNDER THIS CONTRACT.
1. ALL EXISITNG DEVICES IN WORK AREA TO BE
REMOVED AND REPLACED PER THIS LAYOUT.
2. ALL NEW FIRE ALARM DEVICES TO TIE INTO
EXISTING FIRE ALARM PANEL.
3. CONFIRM NEW SMOKE ZONE BOUNDARIES WITH
ARCHITECT OF RECORD.
4. CONTRACTOR TO PROVIDE ALL PROGRAMMING,
MESSAGE CHIPS, ETC. REQUIRED FOR CHANGE TO
THE EXISTING FIRE ALARM SYSTEM.
A C EB D F G H
I
S S
DH DH
NEW SMOKE DETECTOR TO BE
ON EXISTING ZONE
MECHANICAL
BD - 117
804 SF
EQUIPMENT STORAGE
BD - 116
719 SF
CART STORAGE
BD - 115
764 SF
CORRIDOR
CO01
625 SF
EMS WORKROOM
BD - 112
357 SF
OFFICE
BD - 114
95 SF
OFFICE PROGRAM SUPPORT ASST
BD - 113
94 SF
MEN'S LOCKER ROOM
BD - 118
258 SF
WOMEN'S LOCKER ROOM
BD - 119
224 SF
MEN'S TOILET
BD - 118B
45 SF
WOMEN'S TOILET
BD - 119B
45 SF
GEMS STORAGE
BD - 120
284 SF
HOUSEKEEPING EXPENDABLES
BD - 121
288 SF
LEADS WORKROOM
BD - 122
222 SF
STAFF LOUNGE
BD - 123
288 SF
OFFICE SUPERVISORS
BD - 124
205 SF
OFFICE GEMS COORDINATOR
BD - 125
119 SF
SECRETARY OFFICE
BD - 126
220 SF
OFFICE EMS CHIEF
BD - 127
150 SF
OFFICE EMS ASST CHIEF
BD - 128
117 SF
OFFICE ADMIN OFFICER
BD - 129
126 SF
CONFERENCE ROOM
BD - 130
303 SF
OFFICE
BD - 131
114 SF
TOILET
BD - 132
75 SF
ELECTRICAL
BD - 130A
78 SF
WET ROOM
BD - 133
313 SF
STANDALONE PRIMARY
BD - 110
527 SF
STAIRWELL #24
CORRIDOR
CO02
434 SF
WF T
FIRE ALARM DEVICE SYMBOLS
SPOT-TYPE SMOKE DETECTOR
SPEAKER STROBE - CEILING MOUNT
SPEAKER STROBE - WALL MOUNT
MANUAL PULL STATION
SPRINKLER TAMPER SWITCH MONITOR MODULE
SPRINKLER WATER FLOW MONITOR MODULEWF
T
SPEAKER - CEILING MOUNT
MAGNETIC DOOR HOLD RELAYDH
S DUCT-TYPE SMOKE DETECTOR
ISO ISOLATION MODULE
SPEAKER STROBE - WALL MOUNT WATER PROOFWP
STROBE - WALL MOUNT
FIRE BARRIER SYMBOLS
1-HOUR FIRE BARRIER
2-HOUR FIRE BARRIER
SMOKE PARTITION
SUMMIT FIRE CONSULTING
575 MINNEHAHA AVE WEST
ST. PAUL, MINNESOTA 55103
(612) 387-7050
CALIBRE
9090 S RIDGELINE BLVD, SUITE 105
HIGHLANDS RANCH COLORADO 80129
PHONE (303) 730-0434
ALBERTSON ENGINEERING, INC.
315 NORTH MAIN AVENUE, SUITE 200
SIOUX FALLS, SOUTH DAKOTA 57104
PH: (605) 274-0880
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA
57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COMFOURFRONT
D E S I G N I N C.
Office of Construction and Facilities Management
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
Approved: Project Director
ARCHITECTCONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
Department of
Veterans Affairsof
/1
/2
:1
:5
A
M
CONSTRUCTION DOCUMENTS
11/16/2021
FIRE ALARM - BASEMENT LEVEL
FA1.01
EXPAND BLDG. 1 FOR
PRIMARY CARE
CJNB
2101 ELM STREET
FARGO, ND 58102FARGO VAHCS
437-315
124 128
NEW PLAN AREA LEGEND:
SHEET NOTES:
1/8" = 1'-0"
FIRE ALARM PLAN - BASEMENT LEVEL
15 15
30 30
M
S P
S P
S P
SP SP
S P
S P
S P
SPSP
S P
S P
S P
SP SPSP SP
SP SP
SPSP
S P
S P
S P
S P
SP SP
SP SP
M
SP SP
EXISTING TO REMAIN.
LIMITS OF PROJECT/CONSTRUCTION
UNDER THIS CONTRACT.
1.. ALL EXISITNG DEVICES IN WORK AREA TO BE
REMOVED AND REPLACED PER THIS LAYOUT.
2. ALL NEW FIRE ALARM DEVICES TO TIE INTO
EXISTING FIRE ALARM PANEL.
3. CONFIRM NEW SMOKE ZONE BOUNDARIES WITH
ARCHITECT OF RECORD. DEVICES TO BE TIED INTO
RESPECTIVE ZONES PER THEIR LOCATION.
4. CONTRACTOR TO PROVIDE ALL PROGRAMMING,
MESSAGE CHIPS, ETC. REQUIRED FOR CHANGE TO
THE EXISTING FIRE ALARM SYSTEM.
A C EB D F G H
I
DH DH
NEW DEVICES TO BE
ON EXISTING ZONE
BARIATRIC EXAM
1D -176
161 SF
EXAM
1D -175
162 SF
EXAM
1D -174
162 SF
EXAM
1D -172
162 SF
EXAM
1D -171
162 SF
EXAM
1D -177
135 SF
EXAM
1D -179
140 SF
EXAM
1D -181
138 SF
EXAM
1D -184
147 SF
EXAM
1D -185
150 SF
EXAM
1D -186
151 SF
EXAM
1D -187
150 SF
EXAM
1D -189
151 SF
EXAM
1D -190
151 SF EQUIP STG
1D -191A
234 SF
WELLNESS
1D -191
633 SF
BREAK ROOM
1D -188
188 SF
STAFF TLT
1D -188A
60 SF
WORK ROOM
1D -173
541 SF
SOILED LINEN
1D -183
67 SF
TOILET
1D -182
66 SF
CLEAN LINEN
1D -180
77 SF
HAC
1D -178
60 SF
CORRIDOR
CO04
927 SF
CORRIDOR
CO04
927 SF
CORRIDOR
CO06
377 SF
CONSULT PHARM
E1D -116
167 SF
WORK ROOM (P.C. DOC'S)
E1D -120
207 SF
RECEPTION/WAITING
1D -193
338 SF
PHARMACY OFFICE
1D -192
114 SF
LOGISTICS STG
1D -194
150 SF
ELECT
1D -195
74 SF
OFFICE
1D -196
106 SF
OFFICE
1D -197
107 SF
OFFICE
1D -198
104 SF
OFFICE
1D -199
108 SF
STAIRWELL #24
WF T
FIRE ALARM DEVICE SYMBOLS
SPOT-TYPE SMOKE DETECTOR
SPEAKER STROBE - CEILING MOUNT
SPEAKER STROBE - WALL MOUNT
MANUAL PULL STATION
SPRINKLER TAMPER SWITCH MONITOR MODULE
SPRINKLER WATER FLOW MONITOR MODULEWF
T
SPEAKER - CEILING MOUNT
MAGNETIC DOOR HOLD RELAYDH
S DUCT-TYPE SMOKE DETECTOR
ISO ISOLATION MODULE
SPEAKER STROBE - WALL MOUNT WATER PROOFWP
STROBE - WALL MOUNT
FIRE BARRIER SYMBOLS
1-HOUR FIRE BARRIER
2-HOUR FIRE BARRIER
SMOKE PARTITION
SUMMIT FIRE CONSULTING
575 MINNEHAHA AVE WEST
ST. PAUL, MINNESOTA 55103
(612) 387-7050
CALIBRE
9090 S RIDGELINE BLVD, SUITE 105
HIGHLANDS RANCH COLORADO 80129
PHONE (303) 730-0434
ALBERTSON ENGINEERING, INC.
315 NORTH MAIN AVENUE, SUITE 200
SIOUX FALLS, SOUTH DAKOTA 57104
PH: (605) 274-0880
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA
57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COMFOURFRONT
D E S I G N I N C.
Office of Construction and Facilities Management
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
Approved: Project Director
ARCHITECTCONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
Department of Veterans Affairsof
/1
/2
:1
:0
A
M
CONSTRUCTION DOCUMENTS
11/16/2021
FIRE ALARM - FIRST LEVEL
FA1.02
EXPAND BLDG. 1 FOR
PRIMARY CARE
CJNB
2101 ELM STREET
FARGO, ND 58102FARGO VAHCS
437-315
125 128
NEW PLAN AREA LEGEND:
SHEET NOTES:
1/8" = 1'-0"
FIRE ALARM PLAN - FIRST LEVEL
2-STORY
BUILDING
ADDITION
(8,400 sf per floor)
# BUILDING NUMBERS
LEGEND
FLOW HYDRANT
GAUGE HYDRANT
EXISTING UNDERGROUND
LEAD-IN
EXISTING 4" FIRE
PROTECTION
VALVE ASSEMBLY
NEW HYDRANT
LOCATION (SEE CIVIL
PLANS)
EXISTING UNDERGROUND
FIRE MAIN
NEW 6" UNDERGROUND
FIRE MAIN
NEW VALVES
EXISTING UNDERGROUND
FIRE MAIN TO BE REMOVED
(SEE CIVIL PLANS)
POINT WHERE OUTSIDE HOSE
ALLOWANCES SHALL BE TAKEN
EXISITNG FIRE DEPARTMENT
CONNECTION AND OUTSIDE ALARM
WATER SUPPLY EFFECTIVE
POINT FOR CALCULATIONS
1. FIRE PROTECTION CONTRACTOR'S SCOPE OF WORK INCLUDES INSTALLATION OF A
STANDPIPE SYSTEM TIED INTO THE EXISTING 4" VALVE ASSEMBLY AND WET SPRINKLER
PROTECTION AT BASEMENT LEVEL AND FIRST LEVEL OF THE NEW ADDITION. LIMITED
REWORK WITHIN THE EXISTING BUILDING IS REQUIRED.
2. NEW ADDITION SHALL HAVE ENTIRELY NEW SPRINKLER ZONE SUPPLIED WITHIN NEW
STAIRWELL AS SHOWN ON DRAWINGS. THIS IS TO MAINTAIN CORRELATION OF NEW
SPRINKLER ZONES TO THE NEW SMOKE ZONE OF THE ADDITION.
3. ALL COMPONENTS OF THE SPRINKLER SYSTEM SHALL BE IN ACCORDANCE WITH VA
DESIGN GUIDELINES, NFPA 13 (2019), NFPA 14 (2019) AND NFPA 25 (2020) EDITION. REFER
TO SPECIFICATION SECTIONS 21 08 00 & 21 13 13 FOR ADDITIONAL FIRE SPRINKLER
SYSTEM INFORMATION.
4. ALL PATIENT CARE AREAS ASSUME LIGHT HAZARD PROTECTION IN ACCORDANCE WITH
NFPA 13 (2019). PARKING, MECHANICAL/ELECTRICAL ROOMS ORDINARY HAZARD GROUP
1 PROTECTION IN ACCORDANCE WITH NFPA 13 (2019). STORAGE AREAS, LAUNDRY,
ORDINARY HAZARD GROUP 2 PROTECTION IN ACCORDANCE WITH NFPA 13 (2019).
5. EXIT STAIRWELL TO BE PROVIDED WITH PLUGGED/CAPPED 2 1/2" OUTLETS FOR
POTENTIAL FUTURE STANDPIPE SYSTEM. ZONE CONTROL VALVES WILL BE PROVIDED
AT EACH LEVEL.
6. CONFIRM 3" ZONE CONTROL/MAINS AND 1 1/2" BRANCHLINES FOR SPRINKLER SYSTEM
PIPE SIZING VIA HYDRAULIC CALCULATIONS.
7. PROVIDE ALL SYSTEM COMPONENTS NECESSARY FOR A COMPLETE INSTALLATION.
SYSTEM COMPONENTS SHALL INCLUDE BUT ARE NOT LIMITED TO DISTRIBUTION PIPING,
SPRINKLER PIPING, SPRINKLERS, PIPE SUPPORTS, ALARMS, DRAINS, TEST
CONNECTIONS, CONTROL VALVES AND CHECK VALVES.
8. SEMI RECESSED SPRINKLERS REQUIRED IN AREAS WITH FINISHED CEILINGS.
CONCEALED SPRINKLERS ARE NOT ALLOWED IN LIGHT HAZARD OCCUPANCIES PER VA
GUIDELINES. UPRIGHTS IN EXPOSED AREAS TO BE BRASS FINISH.
9. TAMPER SWITCHES AND FLOW SWITCHES ARE TO BE PROVIDED AND INSTALLED BY THE
FIRE PROTECTION CONTRACTOR AND WIRED PER SPECIFICATION - DIVISION 28.
10. TESTING OF SPRINKLER PIPING SHALL BE IN ACCORDANCE WITH NFPA 13 - 200 PSI FOR
2 HRS
11. SHOP DRAWINGS SHALL BE APPROVED BY THE OWNER'S DESIGNATED
REPRESENTATIVE AND THE AHJ PRIOR TO FABRICATION
12. HANG ALL PIPING PER NFPA 13 - CHAPTER 9. CONTRACTOR SHALL INDICATE ALL PIPE
SUPPORTS.
13. STEEL PIPING IS REQUIRED IN ALL AREAS .
14. UNLESS NOTED OTHERWISE ALL AREAS INCLUDE WET SPRINKLER SYSTEMS.
TEMPERATURES MAINTAINED GREATER THAN OR EQUAL TO 40 DEGREES FAHRENHEIT
AT ALL TIMES.
15. ALL PENETRATIONS AT FIRE BARRIERS OR OTHER RATED ASSEMBLIES ARE REQUIRED
TO BE SEALED IN ACCORDANCE WITH THE 2018 INTERNATIONAL BUILDING CODE OR
OTHER APPROVED MEANS.
16. COORDINATION IS REQUIRED WITH ALL TRADES. PROVIDE SPRINKLER PROTECTION
ABOVE AND BELOW ALL OBSTRUCTIONS.
16. COORDINATE SHUT DOWNS AND TIE IN WORK WITH AHJ AND GENERAL CONTRACTOR
AND VA FP ENGINEERING.
17. FLOW TEST PROVIDED FROM SUMMIT FIRE CONSULTING (SFC)
A. STATIC: 48 PSI
B. RESIDUAL: 39 PSI
C. FLOW: 809 GPM
D. DATE: 9/1/2021
E. EFFECTIVE POINT: WHERE THE NEW 6" FIRE MAIN TIES INTO THE EXISTING LOOP
MAIN SOUTH OF THE BUILDING.
F. HOSE ALLOWANCES SHALL BE TAKEN AT THE POINT OF CONNECTION TO THE
EXISTING LEAD-IN MAIN TO THE EXISTING OUTSIDE MAIN JUST WEST OF THE
EXISTING RISER.
SUMMIT FIRE CONSULTING
575 MINNEHAHA AVE WEST
ST. PAUL, MINNESOTA 55103
(612) 387-7050
CALIBRE
9090 S RIDGELINE BLVD, SUITE 105
HIGHLANDS RANCH COLORADO 80129
PHONE (303) 730-0434
ALBERTSON ENGINEERING, INC.
315 NORTH MAIN AVENUE, SUITE 200
SIOUX FALLS, SOUTH DAKOTA 57104
PH: (605) 274-0880
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA
57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COMFOURFRONT
D E S I G N I N C.
Office of Construction and Facilities Management
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
Approved: Project Director
ARCHITECTCONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
Department of
Veterans Affairsof
/1
/2
:1
:0
A
M
CONSTRUCTION DOCUMENTS
11/16/2021
FIRE PROTECTION COVER SHEET
FP1.00
EXPAND BLDG. 1 FOR
PRIMARY CARE
CJNB
2101 ELM STREET
FARGO, ND 58102FARGO VAHCS
437-315
126 128
1/32" = 1'-0"
SITE PLAN
GENERAL NOTES:
P
S P
S P
S P
SPSP SPSP
S P
S P
S P
SPSP SPSPSPSPSP
S P
S P
S P
S P
S P
S P
SP
S P
SP SPSP SP
S P
S P
S P
S P
SP SP
EXISTING TO REMAIN.
LIMITS OF PROJECT/CONSTRUCTION
UNDER THIS CONTRACT.
1. PIPE ROUTING TO BE VERIFIED DURING FIELD
SURVEY. ROUTE SHOWN IS SCHEMATIC.
2. COORDINATE ANY EXISTING CEILING TILE
REMOVAL IN EXISTING BUILDING FOR NEW PIPE
INSTALL.
3. COORDINATE WITH ALL TRADES TO AVOID
CONFLICTS. SPRINKLER MAINS AND SUPPLY TO
ROUTE AS TIGHT AS POSSIBLE TO BOTTOM OF
STRUCTURAL BEAMS TO AVOID MECHANICAL
EQUIPMENT.
4. DEMO WORK AT THIS LEVEL SHOULD INCLUDE THE
REMOVAL OF THE EXISTING ANTIFREEZE SYSTEM
AND BACKFLOW.
FIRST LEVEL
100' - 0"
BASEMENT LEVEL
88' - 0"
ZONE CONTROL
- FLOW SWITCH
- TEST & DRAIN
- PRESSURE RELIEF
- AIR/WATER GAUGE
CHECK VALVE
BUTTERFLY
VALVE -
SUPERVISED
2 1/2" OUTLET
CAPPED/PLUGGED FOR
POTENTIAL FUTURE
STANDPIPE
3'-6" AFF
4" VERTICAL SUPPLY
DRAIN PIPE
TO EXTERIOR
ZONE CONTROL
- FLOW SWITCH
- TEST & DRAIN
- PRESSURE RELIEF
- AIR/WATER GAUGE
CHECK VALVE
BUTTERFLY VALVE -
SUPERVISED
2 1/2" OUTLET CAPPED/PLUGGED FOR
POTENTIAL FUTURE STANDPIPE
3'-6" AFF
2" DRAIN LINE
CAP
DRAIN CAP
A C EB D F G H
I e9 e10
FP1.01
ROUTE UP TO FIRST
LEVEL
4" BUTTERFLY VALVE
SUPERVISED
4" SUPPLY ABOVE
CEILING @ APPROX
ELEVATION OF 9'-6"
TIE INTO EXISITNG 4"
VALVE ASSEMBLY.
PROVIDE NEW TEE,
SUPERVISED BLUTTERFLY
VALVE, AND FLOW SWITCH
(TIE INTO EXISITNG FIRE
ALARM CONTROL PANEL).
OH1
OH2 OH2
OH2
OH2
OH1
PROVIDE SPRINKLERS AT
BOTTOM OF STAIRS
MECHANICAL
BD - 117
804 SF
EQUIPMENT STORAGE
BD - 116
719 SF
CART STORAGE
BD - 115
764 SF
MEN'S LOCKER ROOM
BD - 118
258 SF
WOMEN'S LOCKER ROOM
BD - 119
224 SF
MEN'S TOILET
BD - 118B
45 SF
WOMEN'S TOILET
BD - 119B
45 SF
GEMS STORAGE
BD - 120
284 SF
HOUSEKEEPING EXPENDABLES
BD - 121
288 SF
LEADS WORKROOM
BD - 122
222 SF
STAFF LOUNGE
BD - 123
288 SF
OFFICE SUPERVISORS
BD - 124
205 SF
OFFICE
BD - 114
95 SF
OFFICE PROGRAM SUPPORT ASST
BD - 113
94 SF
EMS WORKROOM
BD - 112
357 SF
STANDALONE PRIMARY
BD - 110
527 SF
WET ROOM
BD - 133
313 SF
TOILET
BD - 132
75 SF
OFFICE
BD - 131
114 SF
ELECTRICAL
BD - 130A
78 SF
CONFERENCE ROOM
BD - 130
303 SF
STAIRWELL #24
OFFICE ADMIN OFFICER
BD - 129
126 SF
OFFICE EMS ASST CHIEF
BD - 128
117 SF
OFFICE EMS CHIEF
BD - 127
150 SF
SECRETARY OFFICE
BD - 126
220 SF
OFFICE GEMS COORDINATOR
BD - 125
119 SF
CORRIDOR
CO01
625 SF
CORRIDOR
CO02
434 SF
OH2
BASEMENT ZONE
CONTROL LOCATION
2" DRAIN PIPE
FP1.01
EXISITNG ANTIFREEZE
SYSTEM AND BACKFLOW
TO BE COMPLETELY
REMOVED BACK TO MAIN
IN MECHANICAL ROOM.
CAP SYSTEM & PATCH ALL
HOLES. ALL PATCHES TO
MATCH FINISHES.
OH1 ORDINARY HAZARD GROUP 1: PARAMETERS IN ACCORDANCE WITH NFPA 13, 250GPM HOSE STREAM
ORDINARY HAZARD GROUP 2: PARAMETERS IN ACCORDANCE WITH NFPA 13, 250GPM HOSE STREAM
LIGHT HAZARD: 0.10 GPM/SF OVER 1,500SF, 100GPM HOSE STREAM
HAZARD CLASSIFICATIONS (PER NFPA 13)
OH2
AT NEW TEE: INSTALL 4" BUTTERFLY
VALVE, FLOW SWITCH AND DRAIN.
SEE FLOOR PLAN FOR ROUTE TO ADDTION.
EXISTING VALVE ASSEMBLY
SCALE: NO SCALE
FIRE BARRIER SYMBOLS
1-HOUR FIRE BARRIER
2-HOUR FIRE BARRIER
SMOKE PARTITION
DEMO GLYCOL FILLED
SPRINKLER SYSTEM UNDER
OVERHANG. REMOVE PIPING
BACK TO THE SYSTEM VALVE
ASSEMBLY AND CAP.
FILL STATION, ETC. TO BE
REMOVED.
PATCH ALL HOLES AND PROVIDE
FINISHES TO MATCH EXISTING.
DEMO - GLYCOL SPRINKLER SYSTEM
SCALE: NO SCALE
SUMMIT FIRE CONSULTING
575 MINNEHAHA AVE WEST
ST. PAUL, MINNESOTA 55103
(612) 387-7050
CALIBRE
9090 S RIDGELINE BLVD, SUITE 105
HIGHLANDS RANCH COLORADO 80129
PHONE (303) 730-0434
ALBERTSON ENGINEERING, INC.
315 NORTH MAIN AVENUE, SUITE 200
SIOUX FALLS, SOUTH DAKOTA 57104
PH: (605) 274-0880
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA
57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COMFOURFRONT
D E S I G N I N C.
Office of Construction and Facilities Management
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
Approved: Project Director
ARCHITECTCONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
Department of Veterans Affairsof
/1
/2
:1
:0
A
M
CONSTRUCTION DOCUMENTS
11/16/2021
FIRE PROTECTION - BASEMENT LEVEL
FP1.01
EXPAND BLDG. 1 FOR
PRIMARY CARE
CJNB
2101 ELM STREET
FARGO, ND 58102FARGO VAHCS
437-315
127 128
NEW PLAN AREA LEGEND:
SHEET NOTES:
1/2" = 1'-0"
ZONE DETAIL
1/8" = 1'-0"
FIRE PROTECTION PLAN - BASEMENT
P
S P
S P
SP SP
S P
S P
S P
SPSP
S P
S P
S P
SP SPSP SP
SP SP
SPSP
S P
S P
S P
S P
SP SP
SP SP
SP SP
EXISTING TO REMAIN.
LIMITS OF PROJECT/CONSTRUCTION
UNDER THIS CONTRACT.
1. COORDINATE WITH ALL TRADES TO AVOID
CONFLICTS. SPRINKLER MAINS AND SUPPLY TO
ROUTE AS TIGHT AS POSSIBLE TO BOTTOM OF
STRUCTURAL BEAMS TO AVOID MECHANICAL
EQUIPMENT.
A C EB D F G H
I
FP1.01
FED FROM BELOW
1ST FLOOR ZONE
CONTROL LOCATION
OH2
OH1OH2
OH2
OH2
PROVIDE SPRINKLER
AT TOP OF STAIRS
BARIATRIC EXAM
1D -176
161 SF
EXAM
1D -175
162 SF
EXAM
1D -174
162 SF
EXAM
1D -172
162 SF
EXAM
1D -171
162 SF
EXAM
1D -177
135 SF
EXAM
1D -179
140 SF
EXAM
1D -181
138 SF
EXAM
1D -184
147 SF
EXAM
1D -185
150 SF
EXAM
1D -186
151 SF
EXAM
1D -187
150 SF
EXAM
1D -189
151 SF
EXAM
1D -190
151 SF
EQUIP STG
1D -191A
234 SF
HAC
1D -178
60 SF
CLEAN LINEN
1D -180
77 SF
TOILET
1D -182
66 SF
SOILED LINEN
1D -183
67 SF
WORK ROOM
1D -173
541 SF
BREAK ROOM
1D -188
188 SF
STAFF TLT
1D -188A
60 SF
WELLNESS
1D -191
633 SF
PHARMACY OFFICE
1D -192
114 SF
LOGISTICS STG
1D -194
150 SF
ELECT
1D -195
74 SF
OFFICE
1D -196
106 SF
OFFICE
1D -197
107 SF
OFFICE
1D -198
104 SF
OFFICE
1D -199
108 SF
STAIRWELL #24
CORRIDOR
CO06
377 SF
RECEPTION/WAITING
1D -193
338 SF
CORRIDOR
CO04
927 SF
CORRIDOR
CO04
927 SF
OH2
REVIEW CEILING DETAIL FOR
POSSIBLE SPRINKLER
OBSTRUCTION
2" DRAIN PIPE
EXISTING SPRINKLERS IN
EXISITNG BUILDING TO REMAIN IN
EXISISTNG ZONE.
OH1 ORDINARY HAZARD GROUP 1: PARAMETERS IN ACCORDANCE WITH NFPA 13, 250GPM HOSE STREAM
ORDINARY HAZARD GROUP 2: PARAMETERS IN ACCORDANCE WITH NFPA 13, 250GPM HOSE STREAM
LIGHT HAZARD: 0.10 GPM/SF OVER 1,500SF, 100GPM HOSE STREAM
HAZARD CLASSIFICATIONS (PER NFPA 13)
OH2
FIRE BARRIER SYMBOLS
1-HOUR FIRE BARRIER
2-HOUR FIRE BARRIER
SMOKE PARTITION
EXISITNG SPRINKLER SYSTEM
PIPE & SPRINKLER HEADS TO
REMAIN IN DEMOED AREA.
DURING DEMO, SPRINKLER
HEADS AND BRANCHLINES
SHALL BE TURNED UP TO
PROVIDE COVERAGE WITH NO
CEILING. CHANGE OUT EXISTING
SPRINKLER HEADS DURING
DEMO IF CODE REQUIRES.
ONCE NEW CEILING IS
INSTALLED, TURN SPRINKLER
HEADS AND BRANCHLINES BACK
DOWN TO PROTECT BELOW
CEILING.
DEMO - EXISTING SPRINKLER SYSTEM
SCALE: NO SCALE
SUMMIT FIRE CONSULTING
575 MINNEHAHA AVE WEST
ST. PAUL, MINNESOTA 55103
(612) 387-7050
CALIBRE
9090 S RIDGELINE BLVD, SUITE 105
HIGHLANDS RANCH COLORADO 80129
PHONE (303) 730-0434
ALBERTSON ENGINEERING, INC.
315 NORTH MAIN AVENUE, SUITE 200
SIOUX FALLS, SOUTH DAKOTA 57104
PH: (605) 274-0880
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA
57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COMFOURFRONT
D E S I G N I N C.
Office of Construction and Facilities Management
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
Approved: Project Director
ARCHITECTCONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
Department of Veterans Affairsof
/1
/2
:1
:0
A
M
CONSTRUCTION DOCUMENTS
11/16/2021
FIRE PROTECTION - FIRST LEVEL
FP1.02
EXPAND BLDG. 1 FOR
PRIMARY CARE
CJNB
2101 ELM STREET
FARGO, ND 58102FARGO VAHCS
437-315
128 128
NEW PLAN AREA LEGEND:
SHEET NOTES:
1/8" = 1'-0"
FIRE PROTECTION PLAN - FIRST LEVEL
File details come from the government source that posted it. Updated .