Attachment 11. Section 01 78 00 Closeout Submittals.pdf

PDF 153 KB Posted

Attached to
Design/Build Repair by Replacement Elevator Bldg. 395 Air Traffic Control Tower Federal contract opportunity
Solicitation number
FA466422R0001
Issued by
Department of the Air Force Reserve Command

About this file

This document provides closeout submittal requirements for a design-build project to replace an elevator in an Air Traffic Control Tower at March Air Reserve Base in California. The project requires removing the existing elevator, control system, electrical system and associated components; furnishing and assembling a new elevator; testing and commissioning the new elevator and associated components; and providing training. Closeout submittals must include as-built drawings, record drawings, shop drawings, specifications, warranty information, spare parts data, operation and maintenance manuals, and a DD Form 1354 for transfer of the facility. Warranties must address all equipment and systems for up to one year after project acceptance. The contractor must also conduct joint inspections at four and nine months and develop a warranty management plan for corrective actions and response times.

View the file

Other files for this federal contract opportunity

Other files attached to Design/Build Repair by Replacement Elevator Bldg. 395 Air Traffic Control Tower, newest first.
File Type Posted
Attachment 22. March ARB Questions (RFIs)-Answers 6-23-2022.pdf PDF
Solicitation Amendment FA466422R00010003 SF 30 CO Signed.pdf PDF
RFI NOTICE .docx DOCX document
Attachment 22. March ARB Questions (RFIs)-Answers 6-13-2022.pdf PDF
Solicitation Amendment FA466422R00010002 SF 30.pdf PDF
Attachment 24 - Layout Area_RFI 67.pdf PDF
Attachment 2. Revised SOW dated 20 May 2022.pdf PDF
Attachment 22. March ARB Questions (RFIs)-Answers.pdf PDF
Solicitation Amendment FA466422R00010001 SF 30 (1).pdf PDF
Attachment 16. Schedule Material Submittals, Amendment 1_.xlsx XLSX spreadsheet
Attachment 23. Appendix to March ARB Questions (RFIs) and Answers.pdf PDF
Solicitation Amendment FA466422R00010001 SF 30 (1).pdf PDF
FA466422R0001 Elevator Repair Amendment 1.zip ZIP file
Site Visit Notes Bldg. 395-Elevator Repair.docx DOCX document
Site Walk Attendees List - Elevator.xlsx XLSX spreadsheet
Site Visit Notes Bldg. 395-Elevator Repair.docx DOCX document
Solicitation - FA466422R0001.pdf PDF
Attachment 6. Section 01 10 01 General Conditions.pdf PDF
Attachment 7. Section 01 11 00 Summary of Work.pdf PDF
Attachment 14. Section 14 21 23 Electric Traction PassElevators.pdf PDF
Attachment 1. General Wage Decision 4-29-2022.pdf PDF
Attachment 2. SOW PDPG 21-1000_Repair by Replacement Elevator_ Bldg.395 (002).pdf PDF
Attachment 4. Video_1.mov MOV file
Attachment 8. Section 01 30 00 Administrative Requirements.pdf PDF
Attachment 12. Section 01 57 19 - MARB EPSG - May-2020.pdf PDF
Attachment 16. Elevator Repair Submittal Register.xlsx XLSX spreadsheet
Attachment 3. Note for Photos, Maps & Drawings.docx DOCX document
Attachment 9. Section 01 33 00 Submittal Procedures.pdf PDF
Attachment 13. EPP Template.docx DOCX document
Attachment 17. MARB FEP June 2016.pdf PDF
Attachment 20. List - Secondary forms of ID.pdf PDF
Attachment 21. OF 17 Offer Label.pdf PDF
Attachment 5. Video_2.mov MOV file
Attachment 10. Section 01 35 26 Gov Safety Requirements.pdf PDF
Attachment 15. Construction_Cost_Estimate_Breakdown.xlsx XLSX spreadsheet
Attachment 18. KTR Security Requirements.2022_V1_3.pdf PDF
Attachment 19. MARB Base Pass Request_2022_ v2.1 CUI_3.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 11 to

FA466422R0001

Section 01 78 00 Page 1 of 11

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 78 00

CLOSEOUT SUBMITTALS

05/19

Closeout submittals including: revised project documents, warranty management, testing, adjusting and balancing, O & M manuals, and cleanup

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 As-Built Drawings

1.1.2 Record Drawings

1.2 SOURCE DRAWING FILES

1.2.1 Terms and Conditions

1.3 SUBMITTALS

1.4 SPARE PARTS DATA

1.5 WARRANTY MANAGEMENT

1.5.1 Warranty Management Plan

1.5.2 Performance Bond

1.5.3 Pre-Warranty Conference

1.5.4 Warranty Tags

PART 2 PRODUCTS 2.1 CERTIFICATION OF

EPA DESIGNATED ITEMS

PART 3 EXECUTION

3.1 AS-BUILT DRAWINGS

3.1.1 Markup Guidelines

3.1.2 As-Built Drawings Content

3.2 FINAL APPROVED SHOP DRAWINGS

3.3 CONSTRUCTION CONTRACT SPECIFICATIONS

3.4 OPERATION AND MAINTENANCE MANUALS

3.5 Transfer And Acceptance Of Military Real Property Form DD1354

3.6 CLEANUP

-- End of Section Table of Contents –

Section 01 78 00 Page 2 of 11

SECTION 01 78 00

CLOSEOUT SUBMITTALS

05/19

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 As-Built Drawings

As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the Contract

Documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications; official responses to submitted Requests for Information (RFI's); direction from the

Contracting Officer; design that is the responsibility of the Contractor, and differing site conditions. Maintain the as-builts throughout construction as red-lined hard copies on site. These files serve as the basis for the creation of the record drawings.

1.1.2 Record Drawings

The record drawings are the final compilation of actual conditions reflected in the as-built drawings.

1.2 SOURCE DRAWING FILES

Request the full set of electronic drawings, in the source format, for

Record Drawing preparation, after award and at least 30 days prior to required use.

1.2.1 Terms and Conditions

Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.

The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the

Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic CAD drawing files are not construction documents.

Differences may exist between the CAD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CAD files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source drawing files, the signed and sealed construction

Section 01 78 00 Page 3 of 11 documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the

Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Warranty Management Plan

Warranty Tags

Spare Parts Data

SD-08 Manufacturer's Instructions

Posted Instructions

SD-10 Operation and Maintenance Data

Operation and Maintenance Manuals

SD-11 Closeout Submittals

As-Built Drawings

Record Drawings

As-Built Record of Equipment and

Materials

Final Approved Shop Drawings

Construction Contract Specifications

Certification of EPA Designated Items

Transfer And Acceptance Of Military Real Property Form DD1354

1.4 SPARE PARTS DATA

Submit two copies of the Spare Parts Data list.

Section 01 78 00 Page 4 of 11

a. Indicate manufacturer's name, part number, nomenclature, and stock level required for maintenance and repair. List those items that may be standard to the normal maintenance of the system.

1.5 WARRANTY MANAGEMENT

1.5.1 Warranty Management Plan

Develop a warranty management plan which contains information relevant to

FAR 52.246-21 Warranty of Construction. At least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan narrative must contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract. The term "status" as indicated below must include due date and whether item has been submitted or was accomplished. Submit warranty information, made available during the construction phase, to the

Contracting Officer for approval prior to each monthly pay estimate.

Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period must begin on the date of project acceptance and continue for the full product warranty period. Conduct a joint 4 month and 9 month warranty inspection, measured from time of acceptance; with the Contractor, Contracting Officer and the Customer Representative. The warranty management plan must include, but is not limited to, the following:

a. Roles and responsibilities of personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the Contractors, subcontractors, manufacturers or suppliers involved.

b. For each warranty, the name, address, telephone number, and email of each of the guarantor's representatives nearest to the project location.

c. A list and status of delivery of Certificates of Warranty for extended warranty items, including roofs, HVAC balancing, pumps, motors, transformers, and for commissioned systems, such as fire protection and alarm systems, sprinkler systems, and lightning protection systems.

d. As-Built Record of Equipment and Materials list for each warranted equipment, item, feature of construction or system indicating:

(1) Name of item.

(2) Model and serial numbers.

(3) Location where installed.

(4) Name and phone numbers of manufacturers or suppliers.

(5) Names, addresses and telephone numbers of sources of spare parts.

(6) Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

Section 01 78 00 Page 5 of 11

(7) Cross-reference to warranty certificates as applicable.

(8) Starting point and duration of warranty period.

(9) Summary of maintenance procedures required to continue the warranty in force.

(10) Cross-reference to specific pertinent Operation and Maintenance manuals.

(11) Organization, names and phone numbers of persons to call for warranty service.

(12) Typical response time and repair time expected for various warranted equipment.

e. The plans for attendance at the 4 and 9 month post-construction warranty inspections conducted by the Government.

f. Procedure and status of tagging of equipment covered by extended warranties.

g. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty or safety reasons.

1.5.2 Performance Bond

The Performance Bond must remain effective throughout the construction period .

a. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

b. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the

Contractor's expense, the Contracting Officer will have the right to recoup expenses from the bonding company.

c. Following oral or written notification of required construction warranty repair work, respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

1.5.3 Pre-Warranty Conference

Prior to contract completion, and at a time designated by the Contracting

Officer, meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. At this meeting, establish and review communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty In connection with these requirements and at the time of the Contractor's quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company

Section 01 78 00 Page 6 of 11 which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contact must be located within the local service area of the warranted construction, be continuously available, and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in connection with other portions of this provision.

1.5.4 Warranty Tags

At the time of installation, tag each warranted item with a durable, oil and water resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also, submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector's signature

Construction Contractor

Address

Telephone number

Warranty contact

Address

Telephone number

Warranty response time priority code

WARNING - PROJECT PERSONNEL TO PERFORM ONLY OPERATIONAL MAINTENANCE DURING

THE WARRANTY PERIOD.

Section 01 78 00 Page 7 of 11

PART 2 PRODUCTS

2.1 CERTIFICATION OF EPA DESIGNATED ITEMS

Submit the Certification of EPA Designated Items as required by FAR

52.223-9 Estimate of Percentage of Recovered Material Content for EPA

Designated Items and FAR 52-223-17 Affirmative Procurement of EPA designated items in Service and Construction Contracts. Include on the certification form the following information: project name, project number, Contractor name, license number, Contractor address, and certification.

The certification will read as follows and be signed and dated by the

Contractor. "I hereby certify the information provided herein is accurate and that the requisition/procurement of all materials listed on this form comply with current EPA standards for recycled/recovered materials content.

The following exemptions may apply to the non-procurement of recycled/recovered content materials:

1) The product does not meet appropriate performance standards;

2) The product is not available within a reasonable time frame;

3) The product is not available competitively (from two or more sources);

4) The product is only available at an unreasonable price (compared with a comparable non-recycled content product)."

Recycled content values may be determined by weight or volume percent, but must be consistent throughout.

PART 3 EXECUTION

3.1 AS-BUILT DRAWINGS

3.1.1 Markup Guidelines

Make comments and markup the drawings complete without reference to letters, memos, or materials that are not part of the As-Built drawing.

Show what was changed, how it was changed, where item(s) were relocated and change related details. These working as-built markup prints must be neat, legible and accurate as follows:

a. Use base colors of red, green, and blue. Color code for changes as follows:

(1) Special (Blue) - Items requiring special information, coordination, or special detailing or detailing notes.

(2) Deletions (Red) - Over-strike deleted graphic items (lines), lettering in notes and leaders.

(3) Additions (Green) - Added items, lettering in notes and leaders.

b. Provide a legend if colors other than the "base" colors of red, green, and blue are used.

Section 01 78 00 Page 8 of 11

c. Add and denote any additional equipment or material facilities, service lines, incorporated under As-Built Revisions if not already shown in legend.

d. Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision.

e. Use legible lettering and precise and clear digital values when marking prints. Clarify ambiguities concerning the nature and application of change involved.

f. Wherever a revision is made, also make changes to related section views, details, legend, profiles, plans and elevation views, schedules, notes and call out designations, and mark accordingly to avoid conflicting data on all other sheets.

g. For deletions, cross out all features, data and captions that relate to that revision.

h. For changes on small-scale drawings and in restricted areas, provide large-scale inserts, with leaders to the applicable location.

i. Indicate one of the following when attaching a print or sketch to a markup print:

(1) Add an entire drawing to contract drawings

(2) Change the contract drawing to show

(3) Provided for reference only to further detail the initial design.

j. Incorporate all shop and fabrication drawings into the markup drawings.

3.1.2 As-Built Drawings Content

Show on the as-built drawings, but not limited to, the following information:

a. The actual location, kinds and sizes of all sub-surface utility lines.

In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, show by offset dimensions to two permanently fixed surface features the end of each run including each change in direction on the record drawings. Locate valves, splice boxes and similar appurtenances by dimensioning along the utility run from a reference point. Also record the average depth below the surface of each run.

b. The location and dimensions of any changes within the building structure.

c. Layout and schematic drawings of electrical circuits and piping.

d. Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities if any changes were made from contract plans.

Section 01 78 00 Page 9 of 11

e. Changes in details of design or additional information obtained from working drawings specified to be prepared or furnished by the

Contractor; including but not limited to shop drawings, fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment, and foundations.

f. The topography, invert elevations and grades of drainage installed or affected as part of the project construction.

g. Changes or Revisions which result from the final inspection.

h. Where contract drawings or specifications present options, show only the option selected for construction on the working as-built markup drawings.

i. If borrow material for this project is from sources on Government property, or if Government property is used as a spoil area, furnish a contour map of the final borrow pit/spoil area elevations.

j. Systems designed or enhanced by the Contractor, such as HVAC controls, fire alarm, fire sprinkler, and irrigation systems.

k. Changes in location of equipment and architectural features.

j. Modifications (include within change order price the cost to change working as-built markup drawings to reflect modifications).

l. Actual location of anchors, construction and control joints, etc., in concrete.

m. Unusual or uncharted obstructions that are encountered in the contract work area during construction.

n. Location, extent, thickness, and size of stone protection particularly where it will be normally submerged by water.

3.2 FINAL APPROVED SHOP DRAWINGS

Furnish final approved project shop drawings 10 days after transfer of the completed facility.

Text

3.3 Construction Contract Specifications

Furnish final record (as-built) construction contract specifications, including modifications thereto, 30 days after transfer of the completed facility.

3.4 OPERATION AND MAINTENANCE MANUALS

Provide project operation and maintenance manuals as specified in Section

01 78 23 OPERATION AND MAINTENANCE MANUALS DATA. Provide four electronic copies of the Operation and Maintenance Manual files. Submit to the Contracting Officer for approval within 14 calendar days of the

Beneficial Occupancy Date (BOD). Update and resubmit files for final approval at BOD.

Section 01 78 00 Page 10 of 11

3.5 Transfer And Acceptance Of Military Real Property Form DD1354 Near the completion of Project, but a minimum of 30 days prior to final acceptance of the work, complete and submit an accounting of all installed property with Transfer and Acceptance of Military Real

Property Form Dd1354. Include any additional assets/improvements/alterations from the Draft DD Form 1354. Contact the Contracting Officer for any project specific information necessary to complete the DD Form 1354. Refer to UFC 1-300-08 for instruction on completing the DD Form 1354. For information purposes, a blank DD Form

1354 (fill-able) in ADOBE (PDF) may be obtained at the following web site:

http://www.dtic.mil/whs/directives/infomgt/forms/eforms/dd1354.pdf

Submit the completed Checklist for Form DD1354 of Installed Building

Equipment items. Attach this list to the Interim Form DD1354.

3.6 CLEANUP

Leave premises "broom clean." Clean interior and exterior glass surfaces exposed to view; remove temporary labels, stains and foreign substances;

polish transparent and glossy surfaces; vacuum carpeted and soft surfaces.

Clean equipment and fixtures to a sanitary condition. Replace filters of operating equipment. Clean debris from roofs, gutters, downspouts and drainage systems. Sweep paved areas and rake clean landscaped areas.

Remove waste and surplus materials, rubbish and construction facilities from the site.

-- End of Section --