Attachment 10. Section 01 35 26 Gov Safety Requirements.pdf

PDF 324 KB Posted

Attached to
Design/Build Repair by Replacement Elevator Bldg. 395 Air Traffic Control Tower Federal contract opportunity
Solicitation number
FA466422R0001
Issued by
Department of the Air Force Reserve Command

About this file

This is a solicitation for a design-build project to remove and replace an elevator in an Air Traffic Control Tower at March Air Reserve Base in California. The 452nd Mission Support Group Civil Engineers is seeking to contract for disassembly and removal of the existing elevator, control system, electrical system, and associated components; installation of a new elevator including modifications to electrical systems and controls; testing and commissioning of the new elevator and associated components; and training of base staff. The Department of the Air Force Reserve Command is the agency issuing this solicitation. Responses are due based on the solicitation schedule.

View the file

Other files for this federal contract opportunity

Other files attached to Design/Build Repair by Replacement Elevator Bldg. 395 Air Traffic Control Tower, newest first.
File Type Posted
Attachment 22. March ARB Questions (RFIs)-Answers 6-23-2022.pdf PDF
Solicitation Amendment FA466422R00010003 SF 30 CO Signed.pdf PDF
RFI NOTICE .docx DOCX document
Attachment 22. March ARB Questions (RFIs)-Answers 6-13-2022.pdf PDF
Solicitation Amendment FA466422R00010002 SF 30.pdf PDF
Attachment 24 - Layout Area_RFI 67.pdf PDF
Attachment 2. Revised SOW dated 20 May 2022.pdf PDF
Attachment 22. March ARB Questions (RFIs)-Answers.pdf PDF
Solicitation Amendment FA466422R00010001 SF 30 (1).pdf PDF
Attachment 16. Schedule Material Submittals, Amendment 1_.xlsx XLSX spreadsheet
Attachment 23. Appendix to March ARB Questions (RFIs) and Answers.pdf PDF
Solicitation Amendment FA466422R00010001 SF 30 (1).pdf PDF
FA466422R0001 Elevator Repair Amendment 1.zip ZIP file
Site Visit Notes Bldg. 395-Elevator Repair.docx DOCX document
Site Walk Attendees List - Elevator.xlsx XLSX spreadsheet
Site Visit Notes Bldg. 395-Elevator Repair.docx DOCX document
Solicitation - FA466422R0001.pdf PDF
Attachment 6. Section 01 10 01 General Conditions.pdf PDF
Attachment 7. Section 01 11 00 Summary of Work.pdf PDF
Attachment 14. Section 14 21 23 Electric Traction PassElevators.pdf PDF
Attachment 1. General Wage Decision 4-29-2022.pdf PDF
Attachment 2. SOW PDPG 21-1000_Repair by Replacement Elevator_ Bldg.395 (002).pdf PDF
Attachment 4. Video_1.mov MOV file
Attachment 8. Section 01 30 00 Administrative Requirements.pdf PDF
Attachment 11. Section 01 78 00 Closeout Submittals.pdf PDF
Attachment 12. Section 01 57 19 - MARB EPSG - May-2020.pdf PDF
Attachment 16. Elevator Repair Submittal Register.xlsx XLSX spreadsheet
Attachment 3. Note for Photos, Maps & Drawings.docx DOCX document
Attachment 9. Section 01 33 00 Submittal Procedures.pdf PDF
Attachment 13. EPP Template.docx DOCX document
Attachment 17. MARB FEP June 2016.pdf PDF
Attachment 20. List - Secondary forms of ID.pdf PDF
Attachment 21. OF 17 Offer Label.pdf PDF
Attachment 5. Video_2.mov MOV file
Attachment 15. Construction_Cost_Estimate_Breakdown.xlsx XLSX spreadsheet
Attachment 18. KTR Security Requirements.2022_V1_3.pdf PDF
Attachment 19. MARB Base Pass Request_2022_ v2.1 CUI_3.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 10 to

FA466422R0001

Section 01 35 26 Page 1 of 36

UNIFIED FACILITIES GUIDE SPECIFICATIONS

References are in agreement with UMRL dated January 2020

SECTION TABLE OF CONTENTS

DIVISION 01

GENERAL REQUIREMENTS

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

11/15

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.2.1 Competent Person (CP)

1.2.2 Competent Person, Confined Space

1.2.3 Competent Person, Cranes and Rigging

1.2.4 Competent Person, Excavation/Trenching

1.2.5 Competent Person, Fall Protection

1.2.6 Competent Person, Scaffolding

1.2.7 Competent Person (CP) Trainer

1.2.8 High Risk Activities

1.2.9 High Visibility Accident

1.2.10 Load Handling Equipment (LHE)

1.2.11 Medical Treatment

1.2.12 Near Miss

1.2.13 Operating Envelope

1.2.14 Qualified Person (QP)

1.2.15 Qualified Person, Fall Protection (QP for FP)

1.2.16 USACE Property and Equipment

1.2.17 Load Handling Equipment (LHE) Accident or Load Handling

Equipment Mishap

1.3 SUBMITTALS

1.4 MONTHLY EXPOSURE REPORTS

1.5 CONTRACTOR SAFETY SELF-EVALUATION CHECKLIST

1.6 REGULATORY REQUIREMENTS

1.6.1 Subcontractor Safety Requirements

1.6.1.1 Experience Modification Rate (EMR)

1.6.1.2 OSHA Days Away from Work, Restricted Duty, or Job Transfer

(DART) Rate

1.7 SITE QUALIFICATIONS, DUTIES, AND MEETINGS

1.7.1 Personnel Qualifications

1.7.1.1 Site Safety and Health Officer (SSHO)

1.7.1.1.1 Additional Site Safety and Health Officer (SSHO)

Requirements and Duties

1.7.1.2 Competent Person Qualifications

1.7.1.2.1 Competent Person for Confined Space Entry

1.7.1.2.2 Competent Person for Scaffolding

1.7.1.2.3 Competent Person for Fall Protection

1.7.1.3 Qualified Trainer Requirements

1.7.1.4 Requirements for all Contractor Jobsite Personnel Holding H-

1B or H-2B Visas:

1.7.1.5 Dredging Contract Requirements

1.7.1.5.1 Dredging Safety Personnel Requirements

1.7.1.5.2 SSHO Requirements for Dredging

1.7.1.5.3 Collateral Duty Safety Officer (CDSO) Requirements for

Dredging

Section 01 35 26 Page 2 of 36

1.7.1.5.4 Safety Personnel Training Requirements for Dredging

1.7.1.6 Crane Operators/Riggers

1.7.2 Personnel Duties

1.7.2.1 Duties of the Site Safety and Health Officer (SSHO)

1.7.3 Meetings

1.7.3.1 Preconstruction Conference

1.7.3.2 Safety Meetings

1.8 ACCIDENT PREVENTION PLAN (APP)

1.8.1 Names and Qualifications

1.8.2 Plans

1.8.2.1 Confined Space Entry Plan

1.8.2.2 Standard Lift Plan (SLP)

1.8.2.3 Critical Lift Plan - Crane or Load Handling Equipment

1.8.2.3.1 Critical Lift Plan Planning and Schedule

1.8.2.3.2 Lifts of Personnel

1.8.2.4 Barge Mounted Mobile Crane Lift Plan

1.8.2.5 Multi-Purpose Machines, Material Handling Equipment, and

Construction Equipment Lift Plan

1.8.2.6 Fall Protection and Prevention (FP&P) Plan

1.8.2.7 Rescue and Evacuation Plan

1.8.2.8 Hazardous Energy Control Program (HECP)

1.8.2.9 Excavation Plan

1.8.2.10 Occupant Protection Plan

1.8.2.11 Lead Compliance Plan

1.8.2.12 Asbestos Hazard Abatement Plan

1.8.2.13 Site Safety and Health Plan

1.8.2.14 Polychlorinated Biphenyls (PCB) Plan

1.8.2.15 Site Demolition Plan

1.9 ACTIVITY HAZARD ANALYSIS (AHA)

1.9.1 AHA Management

1.9.2 AHA Signature Log

1.10 DISPLAY OF SAFETY INFORMATION

1.10.1 Safety Bulletin Board

1.10.2 Safety and Occupational Health (SOH) Deficiency Tracking

System

1.11 SITE SAFETY REFERENCE MATERIALS

1.12 EMERGENCY MEDICAL TREATMENT

1.13 NOTIFICATIONS and REPORTS

1.13.1 Mishap Notification

1.13.2 Accident Reports

1.13.3 LHE Inspection Reports

1.13.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and Rigging

1.13.5 Third Party Certification of Floating Cranes and

Barge-Mounted Mobile Cranes

1.14 HOT WORK

1.14.1 Permit and Personnel Requirements

1.14.2 Work Around Flammable Materials

1.15 RADIATION SAFETY REQUIREMENTS

1.15.1 Radiography Operation Planning Work Sheet

1.15.2 Site Access and Security

1.15.3 Loss or Release and Unplanned Personnel Exposure

1.15.4 Site Demarcation and Barricade

1.15.5 Security of Material and Equipment

1.15.6 Transportation of Material

1.15.7 Schedule for Exposure or Unshielding

1.15.8 Transmitter Requirements

1.16 CONFINED SPACE ENTRY REQUIREMENTS

Section 01 35 26 Page 3 of 36

1.16.1 Entry Procedures

1.16.2 Forced Air Ventilation

1.16.3 Sewer Wet Wells

1.16.4 Rescue Procedures and Coordination with Local Emergency

Responders

1.17 GAS PROTECTION

1.17.1 Gas Test Readings Record

1.17.2 Special Requirements

1.18 HIGH NOISE LEVEL PROTECTION

1.19 DIVE SAFETY REQUIREMENTS

1.20 SEVERE STORM PLAN

PART 2 PRODUCTS

2.1 CONFINED SPACE SIGNAGE

PART 3 EXECUTION

3.1 CONSTRUCTION AND OTHER WORK

3.1.1 Worksite Communication

3.1.2 Hazardous Material Use

3.1.3 Hazardous Material Exclusions

3.1.4 Unforeseen Hazardous Material

3.2 UTILITY OUTAGE REQUIREMENTS

3.3 OUTAGE COORDINATION MEETING

3.4 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)

3.4.1 Safety Preparatory Inspection Coordination Meeting with the

Government or Utility

3.4.2 Lockout/Tagout Isolation

3.4.3 Lockout/Tagout Removal

3.5 FALL PROTECTION PROGRAM

3.5.1 Training

3.5.2 Fall Protection Equipment and Systems

3.5.2.1 Additional Personal Fall Protection

3.5.2.2 Personal Fall Protection Harnesses

3.5.3 Fall Protection for Roofing Work

3.5.4 Horizontal Lifelines (HLL)

3.5.5 Guardrails and Safety Nets

3.5.6 Rescue and Evacuation Plan and Procedures

3.6 SHIPYARD REQUIREMENTS

3.7 WORK PLATFORMS

3.7.1 Scaffolding

3.7.2 Elevated Aerial Work Platforms (AWPs)

3.8 EQUIPMENT

3.8.1 Material Handling Equipment (MHE)

3.8.2 Load Handling Equipment (LHE)

3.8.3 Machinery and Mechanized Equipment

3.8.4 Base Mounted Drum Hoists

3.8.5 Use of Explosives

3.9 EXCAVATIONS

3.9.1 Utility Locations

3.9.2 Utility Location Verification

3.9.3 Utilities Within and Under Concrete, Bituminous Asphalt, and

Other Impervious Surfaces

3.10 ELECTRICAL

3.10.1 Conduct of Electrical Work

3.10.2 Qualifications

3.10.3 Arc Flash

Section 01 35 26 Page 4 of 36

3.10.4 Grounding

3.10.5 Testing

-- End of Section Table of Contents --

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

11/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME B30.3 (2016) Tower Cranes

ASME B30.5 (2018) Mobile and Locomotive Cranes

ASME B30.7 (2011) Winches

ASME B30.8 (2015) Floating Cranes and FloatingDerricks

ASME B30.9 (2018) Slings

ASME B30.20 (2018) Below-the-Hook Lifting Devices

ASME B30.22 (2016) Articulating Boom Cranes

ASME B30.23 (2011) Personnel Lifting Systems Safety

Standard for Cableways, Cranes, Derricks, Hoists, Hooks, Jacks, and Slings

ASME B30.26 (2015; INT Jun 2010 - Jun 2014) Rigging

Hardware

AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSP A10.22 (2007; R 2017) Safety Requirements for

Rope-Guided and Non-Guided Workers’ Hoists

ASSP A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites

ASSP A10.44 (2014) Control of Energy Sources

(Lockout/Tagout) for Construction and

Demolition Operations

ASSP Z244.1 (2016) The Control of Hazardous Energy

Lockout, Tagout and Alternative Methods

ASSP Z359.0 (2012) Definitions and Nomenclature Used

Section 01 35 26 Page 5 of 36 for Fall Protection and Fall Arrest

ASSP Z359.1 (2016) The Fall Protection Code

ASSP Z359.2 (2017) Minimum Requirements for a

Comprehensive Managed Fall Protection

Program

ASSP Z359.3 (2017) Safety Requirements for Lanyards and Positioning Lanyards

ASSP Z359.4 (2013) Safety Requirements for

Assisted-Rescue and Self-Rescue Systems, Subsystems and Components

ASSP Z359.6 (2016) Specifications and Design

Requirements for Active Fall Protection

Systems

ASSP Z359.7 (2011) Qualification and Verification

Testing of Fall Protection Products

ASSP Z359.11 (2014) Safety Requirements for Full Body

Harnesses

ASSP Z359.12 (2009) Connecting Components for Personal

Fall Arrest Systems

ASSP Z359.13 (2013) Personal Energy Absorbers and

Energy Absorbing Lanyards

ASSP Z359.14 (2014) Safety Requirements for

Self-Retracting Devices for Personal Fall

Arrest and Rescue Systems

ASSP Z359.15 (2014) Safety Requirements for Single

Anchor Lifelines and Fall Arresters for

Personal Fall Arrest Systems

ASSP Z490.1 (2016) Criteria for Accepted Practices in

Safety, Health, and Environmental Training

ASTM INTERNATIONAL (ASTM)

ASTM F855 (2015) Standard Specifications for

Temporary Protective Grounds to Be Used on

De-energized Electric Power Lines and

Equipment

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 1048 (2003) Guide for Protective Grounding of

Power Lines

IEEE C2 (2017; Errata 1-2 2017; INT 1 2017)

National Electrical Safety Code

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION (NASA)

Section 01 35 26 Page 6 of 36

NASA NPR 8621.1 (2006b; Change 7) NASA Procedural

Requirements for Mishap and Close Call

Reporting, Investigating, and Recordkeeping

NASA NPR 8715.3 (2008c; Change 9) NASA General Safety

Program Requirements

NASA-STD 8719.12 (2018a) Safety Standard for Explosives, Propellants, and Pyrotechnics

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA Z535.2 (2011) Environmental and Facility Safety

Signs

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2018; TIA 18-1) Standard for Portable

Fire Extinguishers

NFPA 51B (2014) Standard for Fire Prevention During

Welding, Cutting, and Other Hot Work

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;

TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;

TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;

TIA 17-11; TIA 17-12; TIA 17-13; TIA

17-14; TIA 17-15; TIA 17-16; TIA 17-17 )

National Electrical Code

NFPA 70E (2018; TIA 18-1; TIA 81-2) Standard for

Electrical Safety in the Workplace

NFPA 241 (2019) Standard for Safeguarding

Construction, Alteration, and Demolition

Operations

NFPA 306 (2019) Standard for the Control of Gas

Hazards on Vessels

TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-222 (2005G; Add 1 2007; Add 2 2009; Add 3

2014; Add 4 2014; R 2014; R 2016)

Structural Standards for Steel Antenna

Towers and Antenna Supporting Structures

TIA-1019 (2012; R 2016) Standard for Installation, Alteration and Maintenance of Antenna

Supporting Structures and Antennas

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements

Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

Section 01 35 26 Page 7 of 36

10 CFR 20 Standards for Protection Against Radiation

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-required Confined Spaces

29 CFR 1910.147 The Control of Hazardous Energy (Lock

Out/Tag Out)

29 CFR 1910.333 Selection and Use of Work Practices

29 CFR 1915 Confined and Enclosed Spaces and Other

Dangerous Atmospheres in Shipyard

Employment

29 CFR 1915.89 Control of Hazardous Energy

(Lockout/Tags-Plus)

29 CFR 1919 Gear Certification

29 CFR 1926 Safety and Health Regulations for

Construction

29 CFR 1926.16 Rules of Construction

29 CFR 1926.450 Scaffolds

29 CFR 1926.500 Fall Protection

29 CFR 1926.552 Material Hoists, Personal Hoists, Elevators

29 CFR 1926.553 Base-Mounted Drum Hoists

29 CFR 1926.1400 Cranes and Derricks in Construction

49 CFR 173 Shippers - General Requirements for

Shipments and Packagings

CPL 02-01-056 (2014) Inspection Procedures for Accessing

Communication Towers by Hoist

CPL 2.100 (1995) Application of the Permit-Required

Confined Spaces (PRCS) Standards, 29 CFR

1910.146

1.2 DEFINITIONS

1.2.1 Competent Person (CP)

The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.

Section 01 35 26 Page 8 of 36

1.2.2 Competent Person, Confined Space

The CP, Confined Space, is a person meeting the competent person requirements as defined EM 385-1-1 Appendix Q, with thorough knowledge of

OSHA’s Confined Space Standard, 29 CFR 1910.146, and designated in writing to be responsible for the immediate supervision, implementation and monitoring of the confined space program, who through training, knowledge and experience in confined space entry is capable of identifying, evaluating and addressing existing and potential confined space hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.3 Competent Person, Cranes and Rigging

The CP, Cranes and Rigging, as defined in EM 385-1-1 Appendix Q, is a person meeting the competent person, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the Crane and Rigging Program, who through training, knowledge and experience in crane and rigging is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.4 Competent Person, Excavation/Trenching

A CP, Excavation/Trenching, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and 29 CFR 1926, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the excavation/trenching program, who through training, knowledge and experience in excavation/trenching is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.5 Competent Person, Fall Protection

The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and in accordance with

ASSP Z359.0, who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.6 Competent Person, Scaffolding

The CP, Scaffolding is a person meeting the competent person requirements in EM 385-1-1 Appendix Q, and designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the scaffolding program. The CP for Scaffolding has enough training, knowledge and experience in scaffolding to correctly identify, evaluate and address existing and potential hazards and also has the authority to take prompt corrective measures with regard to these hazards. CP qualifications must be documented and include experience on the specific scaffolding systems/types being used, assessment of the base material that the scaffold will be erected upon, load calculations for materials and personnel, and erection and dismantling. The CP for scaffolding must have a documented, minimum of 8-hours of scaffold training to include training

Section 01 35 26 Page 9 of 36 on the specific type of scaffold being used (e.g. mast-climbing, adjustable, tubular frame), in accordance with EM 385-1-1 Section 22.B.02.

1.2.7 Competent Person (CP) Trainer

A competent person trainer as defined in EM 385-1-1 Appendix Q, who is qualified in the material presented, and who possesses a working knowledge of applicable technical regulations, standards, equipment and systems related to the subject matter on which they are training Competent

Persons. A competent person trainer must be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer must be appropriate to that specific industry.The competent person trainer must evaluate the knowledge and skills of the competent persons as part of the training process.

1.2.8 High Risk Activities

High Risk Activities are activities that involve work at heights, crane and rigging, excavations and trenching, scaffolding, electrical work, and confined space entry.

1.2.9 High Visibility Accident

A High Visibility Accident is any mishap which may generate publicity or high visibility.

1.2.10 Load Handling Equipment (LHE)

LHE is a term used to describe cranes, hoists and all other hoisting equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).

1.2.11 Medical Treatment

Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician.Medical treatment does not include first aid treatment even when provided by a physician or registered personnel.

1.2.12 Near Miss

A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).

1.2.13 Operating Envelope

The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this "envelope" is the crane, the operator, riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e. ground or rail), the load's rigging path, the lift and rigging procedure.

1.2.14 Qualified Person (QP)

The QP is a person designated in writing, who, by possession of a

Section 01 35 26 Page 10 of 36 recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.

1.2.15 Qualified Person, Fall Protection (QP for FP)

A QP for FP is a person meeting the requirements of EM 385-1-1 Appendix Q, and ASSP Z359.0, with a recognized degree or professional certificate and with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, and evaluating and specifying fall protection and rescue systems.

1.2.16 USACE Property and Equipment

Interpret "USACE" property and equipment specified in USACE EM 385-1-1 as

Government property and equipment.

1.2.17 Load Handling Equipment (LHE) Accident or Load Handling Equipment

Mishap

A LHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment; two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, or roll over).

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Accident Prevention Plan (APP); G

SD-06

Test Reports

Monthly Exposure Reports

Notifications and Reports

Accident Reports

LHE Inspection Reports

Section 01 35 26 Page 11 of 36

Gas Protection

Dive Operations Plan

SD-07 Certificates

Contractor Safety Self-Evaluation Checklist

Crane Operators/Riggers

Standard Lift Plan

Lift Plan

Naval Architecture Analysis

Activity Hazard Analysis (AHA)

Confined Space Entry Permit

Hot Work Permit

Certificate of Compliance

Third Party Certification of Floating Cranes and Barge-Mounted

Mobile Cranes

License Certificates

Radiography Operation Planning Work Sheet

Portable Gauge Operations Planning Worksheet

Machinery & Mechanized Equipment Certification Form

1.4 MONTHLY EXPOSURE REPORTS

Provide a Monthly Exposure Report and attach to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both Prime and subcontractor. Failure to submit the report may result in retention of up to 10 percent of the voucher.

CONTRACTOR SAFETY SELF-EVALUATION CHECKLIST

Contracting Officer will provide a "Contractor Safety Self-Evaluation checklist" to the Contractor at the pre-construction conference. Complete the checklist monthly and submit with each request for payment voucher.

An acceptable score of 90 or greater is required. Failure to submit the completed safety self-evaluation checklist or achieve a score of at least

90 may result in retention of up to 10 percent of the voucher.

1.5 REGULATORY REQUIREMENTS

In addition to the detailed requirements included in the provisions of this contract, comply with the most recent edition of USACE EM 385-1-1, and the following federal, state, and local laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, Section 01 35 26 Page 12 of 36 criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.

1.5.1 Subcontractor Safety Requirements

1.5.1.1 Experience Modification Rate (EMR)

Subcontractors on this contract must have an effective EMR less than or equal to 1.10, as computed by the National Council on Compensation

Insurance (NCCI) or if not available, as computed by the state agency's rating bureau in the state where the subcontractor is registered, when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier. The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable EMR range cannot be achieved. Relaxation of the EMR range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval.

Contractor's Site Safety and Health Officer (SSHO) must collect and maintain the certified EMR ratings for all subcontractors on the project and make them available to the Government at the Government's request.

1.5.1.2 OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART)

Rate

Subcontractors on this contract must have a DART rate, calculated from the most recent, complete calendar year, less than or equal to 3.4 when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier. The OSHA Dart Rate is calculated using the following formula:

(N/EH) x 200,000 where: N = number of injuries and illnesses with days away, restricted work, or job transfer

EH = total hours worked by all employees during most recent, complete calendar year

200,000 = base for 100 full-time equivalent workers (working 40 hours per week, 50 weeks per year)

The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable

OSHA Dart rate range cannot be achieved for a particular subcontractor.

Relaxation of the OSHA DART rate range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval. Contractor's Site Safety and Health

Officer (SSHO) must collect and maintain self-certified OSHA DART rates for all subcontractors on the project and make them available to the

Government at the Government's request.

1.7 SITE QUALIFICATIONS, DUTIES, AND MEETINGS

1.7.1 Personnel Qualifications

1.7.1.1 Site Safety and Health Officer (SSHO)

Provide an SSHO that meets the requirements of EM 385-1-1 Section 1. The

SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one

Section 01 35 26 Page 13 of 36 person at each project site to function as the Site Safety and Health

Officer (SSHO).The SSHO or an equally-qualified Alternate SSHO must be at the work site at all times to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO and Alternate SSHO must have the required training, experience, and qualifications in accordance with EM 385-1-1 Section 01.A.17, and all associated sub-paragraphs.

If the SSHO is off-site for a period longer than 24 hours, an equally-qualified alternate SSHO must be provided and must fulfill the same roles and responsibilities as the primary SSHO. When the SSHO is temporarily (up to 24 hours) off-site, a Designated Representative (DR), as identified in the AHA may be used in lieu of an Alternate SSHO, and must be on the project site at all times when work is being performed. Note that the DR is a collateral duty safety position, with safety duties in addition to their full time occupation.

1.7.1.1.1 Additional Site Safety and Health Officer (SSHO) Requirements and Duties

The SSHO may not serve as the Quality Control Manager. The SSHO may not serve as the Superintendent.

1.7.1.2 Competent Person Qualifications

Provide Competent Persons in accordance with EM 385-1-1, Appendix Q and herein. Competent Persons for high risk activities include confined space, cranes and rigging, excavation/trenching, fall protection, and electrical work. The CP for these activities must be designated in writing, and meet the requirements for the specific activity (i.e.

competent person, fall protection).

The Competent Person identified in the Contractor's Safety and Health

Program and accepted Accident Prevention Plan, must be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the

Competent Persons(s) to the Contracting Officer for information in consultation with the Safety Office.

1.7.1.2.1 Competent Person for Confined Space Entry

Provide a Confined Space (CP) Competent Person who meets the requirements of EM 385-1-1, Appendix Q, and herein. The CP for Confined Space Entry must supervise the entry into each confined space in accordance with

EM 385-1-1, Section 34.

Since this work involves operations that handle combustible or hazardous materials, this person must have the ability to understand and follow through on the air sampling, Personal Protective Equipment (PPE), and instructions of a Marine Chemist, Coast Guard authorized persons, or

Certified Industrial Hygienist. Confined space and enclosed space work must comply with NFPA 306, OSHA 29 CFR 1915, Subpart B, "Confined and

Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment," or as applicable, 29 CFR 1910.147 for general industry.

1.7.1.2.2 Competent Person for Scaffolding

Provide a Competent Person for Scaffolding who meets the requirements of

Section 01 35 26 Page 14 of 36

EM 385-1-1, Section 22.B.02 and herein.

1.7.1.2.3 Competent Person for Fall Protection

Provide a Competent Person for Fall Protection who meets the requirements of EM 385-1-1, Section 21.C.04, 21.B.03, and herein.

1.7.1.3 Qualified Trainer Requirements

Instructors are required to:

a. Prepare class presentations that cover construction-related safety requirements and includes topics covered in the NAVFAC Construction

Safety Hazard Awareness Course for Contractors.

b. Ensure that all attendees attend all sessions by using a class roster signed daily by each attendee. Maintain copies of the roster for at least five (5) years. This is a certification class and must be attended 100 percent. In cases of emergency where an attendee cannot make it to a session, the attendee can make it up in another class session for the same subject.

c. Update training course materials whenever an update of the EM 385-1-1 becomes available.

d. Provide a written exam of at least 50 questions. Students are required to answer 80 percent correctly to pass.

e. Request, review and incorporate student feedback into a continuous course improvement program.

1.7.1.4 Dredging Contract Requirements

1.7.1.4.1 Dredging Safety Personnel Requirements

1.7.1.4.2 SSHO Requirements for Dredging

1.7.1.4.3 Collateral Duty Safety Officer (CDSO) Requirements for Dredging

1.7.1.4.4 Safety Personnel Training Requirements for Dredging

1.7.1.6 Crane Operators/Riggers

Provide Operators, Signal Persons, and Riggers meeting the requirements in

EM 385-1-1, Section 15.B for Riggers and Section 16.B for Crane Operators and Signal Persons. Provide proof of current qualification.

1.7.2 Personnel Duties

1.7.2.1 Duties of the Site Safety and Health Officer (SSHO)

The SSHO must:

a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the

Contractors' daily production report.

Section 01 35 26 Page 15 of 36

b. Conduct mishap investigations and complete required accident reports.

Report mishaps and near misses.

c. Use and maintain OSHA's Form 300 to log work-related injuries and illnesses occurring on the project site for Prime Contractors and subcontractors, and make available to the Contracting Officer upon request. Post and maintain the Form 300A on the site Safety Bulletin

Board.

d. Maintain applicable safety reference material on the job site.

e. Attend the pre-construction conference, pre-work meetings including preparatory meetings, and periodic in-progress meetings.

f. Review the APP and AHAs for compliance with EM 385-1-1, and approve, sign, implement and enforce them.

g. Establish a Safety and Occupational Health (SOH) Deficiency Tracking

System that lists and monitors outstanding deficiencies until resolution.

h. Ensure subcontractor compliance with safety and health requirements.

i. Maintain a list of hazardous chemicals on site and their material

Safety Data Sheets (SDS).

j. Maintain a weekly list of high hazard activities involving energy, equipment, excavation, entry into confined space, and elevation, and be prepared to discuss details during QC Meetings.

k. Provide and keep a record of site safety orientation and indoctrination for Contractor employees, subcontractor employees, and site visitors.

Superintendent, QC Manager, and SSHO are subject to dismissal if the above duties are not being effectively carried out. If Superintendent, QC

Manager, or SSHO are dismissed, project work will be stopped and will not be allowed to resume until a suitable replacement is approved and the above duties are again being effectively carried out.

1.7.3 Meetings

1.7.3.1 Preconstruction Conference

a. Contractor representatives who have a responsibility or significant role in accident prevention on the project must attend the preconstruction conference. This includes the project superintendent, Site Safety and Occupational Health officer, quality control manager, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses

(AHAs) and special plans, program and procedures associated with it).

b. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the

Section 01 35 26 Page 16 of 36

Contractor and the Contracting Officer as to which phases will require an analysis. In addition, establish a schedule for the preparation, submittal, and Government review of AHAs to preclude project delays.

c. Deficiencies in the submitted APP, identified during the Contracting

Officer's review, must be corrected, and the APP re-submitted for review prior to the start of construction. Work is not permitted to begin until an APP is established that is acceptable to the

Contracting Officer.

1.7.3.2 Safety Meetings

Conduct safety meetings to review past activities, plan for new or changed operations, review pertinent aspects of appropriate AHA (by trade), establish safe working procedures for anticipated hazards, and provide pertinent Safety and Occupational Health (SOH) training and motivation.

Conduct meetings at least once a month for all supervisors on the project location. The SSHO, supervisors, foremen, or CDSOs must conduct meetings at least once a week for the trade workers. Document meeting minutes to include the date, persons in attendance, subjects discussed, and names of individual(s) who conducted the meeting. Maintain documentation on-site and furnish copies to the Contracting Officer on request. Notify the

Contracting Officer of all scheduled meetings 7 calendar days in advance.

1.8 ACCIDENT PREVENTION PLAN (APP)

A qualified person must prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of EM 385-1-1, Appendix A, and as supplemented herein. Cover all paragraph and subparagraph elements in EM 385-1-1, Appendix A. The APP must be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP must interface with the

Contractor's overall safety and health program referenced in the APP in the applicable APP element, and made site-specific. Describe the methods to evaluate past safety performance of potential subcontractors in the selection process. Also, describe innovative methods used to ensure and monitor safe work practices of subcontractors. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP must be signed by an officer of the firm (Prime

Contractor senior person), the individual preparing the APP, the on-site superintendent, the designated SSHO, the Contractor Quality Control

Manager, and any designated Certified Safety Professional (CSP) or

Certified Health Physicist (CIH). The SSHO must provide and maintain the

APP and a log of signatures by each subcontractor foreman, attesting that they have read and understand the APP, and make the APP and log available on-site to the Contracting Officer. If English is not the foreman's primary language, the Prime Contractor must provide an interpreter.

Submit the APP to the Contracting Officer 10 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP. Once reviewed and accepted by the Contracting

Section 01 35 26 Page 17 of 36

Officer, the APP and attachments will be enforced as part of the contract.

Disregarding the provisions of this contract or the accepted APP is cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified. Continuously review and amend the APP, as necessary, throughout the life of the contract. Changes to the accepted

APP must be made with the knowledge and concurrence of the Contracting

Officer, project superintendent, SSHO and Quality Control Manager.

Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered. Should any severe hazard exposure

(i.e. imminent danger) become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard.

Notify the Contracting Officer within 24 hours of discovery. Eliminate and remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSP A10.34), and the environment.

1.8.1 Names and Qualifications

Provide plans in accordance with the requirements outlined in Appendix A of EM 385-1-1, including the following:

a. Names and qualifications (resumes including education, training, experience and certifications) of site safety and health personnel designated to perform work on this project to include the designated

Site Safety and Health Officer and other competent and qualified personnel to be used. Specify the duties of each position.

b. Qualifications of competent and of qualified persons. As a minimum, designate and submit qualifications of competent persons for each of the following major areas: excavation; scaffolding; fall protection;

hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents;

and personal protective equipment and clothing to include selection, use and maintenance.

1.8.2 Plans

Provide plans in the APP in accordance with the requirements outlined in

Appendix A of EM 385-1-1, including the following:

1.8.2.1 Confined Space Entry Plan

Develop a confined or enclosed space entry plan in accordance with

EM 385-1-1, applicable OSHA standards 29 CFR 1910, 29 CFR 1915, and

29 CFR 1926, OSHA Directive CPL 2.100, and any other federal, state and local regulatory requirements identified in this contract. Identify the qualified person's name and qualifications, training, and experience.

Delineate the qualified person's authority to direct work stoppage in the event of hazardous conditions. Include procedure for rescue by contractor personnel and the coordination with emergency responders. (If there is no confined space work, include a statement that no confined space work exists and none will be created.)

1.8.2.2 Standard Lift Plan (SLP)

Plan lifts to avoid situations where the operator cannot maintain safe control of the lift. Prepare a written SLP in accordance with EM 385-1-1, Section 01 35 26 Page 18 of 36

Section 16.A.03, using Form 16-2 for every lift or series of lifts (if duty cycle or routine lifts are being performed). The SLP must be developed, reviewed and accepted by all personnel involved in the lift in conjunction with the associated AHA. Signature on the AHA constitutes acceptance of the plan. Maintain the SLP on the LHE for the current lift(s) being made. Maintain historical SLPs for a minimum of 3 months.

1.8.2.3 Critical Lift Plan - Crane or Load Handling Equipment

Provide a Critical Lift Plan as required by EM 385-1-1, Section 16.H.01, using Form 16-3. In addition, Critical Lift Plans are required for the following:

a. Lifts over 50 percent of the capacity of barge mounted mobile crane's hoist.

b. When working around energized power lines where the work will get closer than the minimum clearance distance in EM 385-1-1 Table 16-1.

c. For lifts with anticipated binding conditions.

d. When erecting cranes.

1.8.2.3.1 Critical Lift Plan Planning and Schedule

Critical lifts require detailed planning and additional or unusual safety precautions. Develop and submit a critical lift plan to the Contracting

Officer 30 calendar days prior to critical lift. Comply with load testing requirements in accordance with EM 385-1-1, Section 16.F.03.

1.8.2.3.2 Lifts of Personnel

In addition to the requirements of EM 385-1-1, Section 16.H.02, for lifts of personnel, demonstrate compliance with the requirements of

29 CFR 1926.1400 and EM 385-1-1, Section 16.T.

1.8.2.4 Barge Mounted Mobile Crane Lift Plan

Provide a Naval Architecture Analysis and include an LHE Manufacturer's

Floating Service Load Chart in accordance with EM 385-1-1, Section

16.L.03.

1.8.2.5 Multi-Purpose Machines, Material Handling Equipment, and Construction Equipment Lift Plan

Multi-purpose machines, material handling equipment, and construction equipment used to lift loads that are suspended by rigging gear, require proof of authorization from the machine OEM that the machine is capable of making lifts of loads suspended by rigging equipment. Written approval from a qualified registered professional engineer, after a safety analysis is performed, is allowed in lieu of the OEM's approval.

Demonstrate that the operator is properly trained and that the equipment is properly configured to make such lifts and is equipped with a load chart.

1.8.2.6 Fall Protection and Prevention (FP&P) Plan

The plan must comply with the requirements of EM 385-1-1, Section 21.D and ASSP Z359.2, be site specific, and address all fall hazards in the

Section 01 35 26 Page 19 of 36 work place and during different phases of construction. Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 1.8 m 6 feet. A competent person or qualified person for fall protection must prepare and sign the plan documentation. Include fall protection and prevention systems, equipment and methods employed for every phase of work, roles and responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods. Review and revise, as necessary, the Fall Protection and Prevention Plan documentation as conditions change, but at a minimum every six months, for lengthy projects, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and Prevention Plan documentation at the job site for the duration of the project. Include the Fall Protection and

Prevention Plan documentation in the Accident Prevention Plan (APP).

1.8.2.7 Rescue and Evacuation Plan

Provide a Rescue and Evacuation Plan in accordance with EM 385-1-1. Section

21.N and ASSP Z359.2, and include in the FP&P Plan and as part of the APP.

Include a detailed discussion of the following: methods of rescue;

methods of self-rescue; equipment used; training requirement; specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility.

1.8.2.8 Hazardous Energy Control Program (HECP)

Develop a HECP in accordance with EM 385-1-1 Section 12, 29 CFR 1910.147, 29 CFR 1910.333, 29 CFR 1915.89, ASSP Z244.1, and ASSP A10.44. Submit this HECP as part of the Accident Prevention Plan (APP).Conduct a preparatory meeting and inspection with all effected personnel to coordinate all HECP activities. Document this meeting and inspection in accordance with EM 385-1-1, Section 12.A.02.Ensure that each employee is familiar with and complies with these procedures.

1.8.2.9 Excavation Plan

Identify the safety and health aspects of excavation, and provide and prepare the plan in accordance with EM 385-1-1, Section 25.A and Section

31 00 00 EARTHWORK.

1.8.2.10 Occupant Protection Plan

Identify the safety and health aspects of lead-based paint removal, prepared in accordance with Section 02 83 00 LEAD REMEDIATION.

1.8.2.11 Lead Compliance Plan

Identify the safety and health aspects of lead work, and prepare in accordance with Section 02 83 00 LEAD REMEDIATION.

1.8.2.12 Asbestos Hazard Abatement Plan

Identify the safety and health aspects of asbestos work, and prepare in accordance with Section 02 82 00 ASBESTOS REMEDIATION.

1.8.2.13 Site Safety and Health Plan

Section 01 35 26 Page 20 of 36

Identify the safety and health aspects, and prepare in accordance with

Section 01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR

CONTAMINATED SITES.

1.8.2.14 Polychlorinated Biphenyls (PCB) Plan

Identify the safety and health aspects of Polychlorinated Biphenyls work, and prepare in accordance with Sections 02 84 33 REMOVAL AND DISPOSAL OF

POLYCHLORINATED BIPHENYLS (PCBs) and 02 61 23 REMOVAL AND DISPOSAL OF PCB

CONTAMINATED SOILS.

1.8.2.15 Site Demolition Plan

Identify the safety and health aspects, and prepare in accordance with

Section 02 41 00 [DEMOLITION] [AND] [DECONSTRUCTION] and referenced sources.

1.9 ACTIVITY HAZARD ANALYSIS (AHA)

Before beginning each activity, task or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an AHA. AHAs must be developed by the Prime Contractor, subcontractor, or supplier performing the work, and provided for Prime

Contractor review and approval before submitting to the Contracting

Officer. AHAs must be signed by the SSHO, Superintendent, QC Manager and the subcontractor Foreman performing the work. Format the AHA in accordance with EM 385-1-1, Section 1 or as directed by the Contracting

Officer. Submit the AHA for review at least working days prior to the start of each activity task, or DFOW. The Government reserves the right to require the Contractor to revise and resubmit the AHA if it fails to effectively identify the work sequences, specific anticipated hazards, site conditions, equipment, materials, personnel and the control measures to be implemented.

AHAs must identify competent persons required for phases involving high risk activities, including confined entry, crane and rigging, excavations, trenching, electrical work, fall protection, and scaffolding.

1.9.1 AHA Management

Review the AHA list periodically (at least monthly) at the Contractor supervisory safety meeting, and update as necessary when procedures, scheduling, or hazards change. Use the AHA during daily inspections by the SSHO to ensure the implementation and effectiveness of the required safety and health controls for that work activity.

1.9.2 AHA Signature Log

Each employee performing work as part of an activity, task or DFOW must review the AHA for that work and sign a signature log specifically maintained for that AHA prior to starting work on that activity. The SSHO must maintain a signature log on site for every AHA. Provide employees whose primary language is other than English, with an interpreter to ensure a clear understanding of the AHA and its contents.

1.10 DISPLAY OF SAFETY INFORMATION

Section 01 35 26 Page 21 of 36

1.10.1 Safety Bulletin Board

Within calendar day(s) after commencement of work, erect a safety bulletin board at the job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the

Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, may be deemed as meeting the requirement for a bulletin board. Include and maintain information on safety bulletin board as required by EM 385-1-1, Section 1.A.7. Additional items required to be posted include:

a. Confined space entry permit.

b. Hot work permit.

1.10.2 Safety and Occupational Health (SOH) Deficiency Tracking System

Establish a SOH deficiency tracking system that lists and monitors the status of SOH deficiencies in chronological order. Use the tracking system to evaluate the effectiveness of the APP.A monthly evaluation of the data must be discussed in the QC or SOH meeting with everyone on the project.

The list must be posted on the project bulletin board and updated daily, and provide the following information:

a. Date deficiency identified;

b. Description of deficiency;

c. Name of person responsible for correcting deficiency;

d. Projected resolution date;

e. Date actually resolved.

1.11 SITE SAFETY REFERENCE MATERIALS

Maintain safety-related references applicable to the project, including those listed in paragraph REFERENCES. Maintain applicable equipment manufacturer's manuals.

1.12 EMERGENCY MEDICAL TREATMENT

Contractors must arrange for their own emergency medical treatment in accordance with EM 385-1-1. Government has no responsibility to provide emergency medical treatment.

1.13 NOTIFICATIONS and REPORTS

1.13.1 Mishap Notification

Notify the Contracting Officer as soon as practical, but no more than twenty-four hours, after any mishaps, including recordable accidents, incidents, and near misses, as defined in EM 385-1-1 Appendix Q, any report of injury, illness, or any property damage. For LHE or rigging mishaps, notify the Contracting Officer as soon as practical but not more than 4 hours after mishap. The Contractor is responsible for obtaining appropriate medical and emergency assistance and for notifying fire, law enforcement, and regulatory agencies. Immediate reporting is required for

Section 01 35 26 Page 22 of 36 electrical mishaps, to include Arc Flash; shock; uncontrolled release of hazardous energy (includes electrical and non-electrical); load handling equipment or rigging; fall from height (any level other than same surface); and underwater diving. These mishaps must be investigated in depth to identify all causes and to recommend hazard control measures.

Within notification include Contractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured;

extent of property damage, if any; extent of injury, if known, and brief description of accident (for example, type of construction equipment used and PPE used).Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted. Assist and cooperate fully with the Government's investigation(s) of any mishap.

1.13.2 Accident Reports

a. Conduct an accident investigation for recordable injuries and illnesses, property damage, and near misses as defined in EM 385-1-1, to establish the root cause(s) of the accident. The Contracting

Officer will provide copies of any required or special forms.

b. Near Misses: Near miss reports are considered positive and proactive

Contractor safety management actions.

c. Conduct an accident investigation for any load handling equipment accident (including rigging accidents) to establish the root cause(s)of the accident. Complete the LHE Accident Report (Crane and Rigging Accident Report) form and provide the report to the

Contracting Officer within 30 calendar days of the accident.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .