Attachment 10. Section 01 35 26 Gov Safety Requirements.pdf
PDF 324 KB Posted
- Attached to
- Design/Build Repair by Replacement Elevator Bldg. 395 Air Traffic Control Tower Federal contract opportunity
- Solicitation number
- FA466422R0001
About this file
This is a solicitation for a design-build project to remove and replace an elevator in an Air Traffic Control Tower at March Air Reserve Base in California. The 452nd Mission Support Group Civil Engineers is seeking to contract for disassembly and removal of the existing elevator, control system, electrical system, and associated components; installation of a new elevator including modifications to electrical systems and controls; testing and commissioning of the new elevator and associated components; and training of base staff. The Department of the Air Force Reserve Command is the agency issuing this solicitation. Responses are due based on the solicitation schedule.
View the file
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 10 to
FA466422R0001
Section 01 35 26 Page 1 of 36
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated January 2020
SECTION TABLE OF CONTENTS
DIVISION 01
GENERAL REQUIREMENTS
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
11/15
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
1.2.2 Competent Person, Confined Space
1.2.3 Competent Person, Cranes and Rigging
1.2.4 Competent Person, Excavation/Trenching
1.2.5 Competent Person, Fall Protection
1.2.6 Competent Person, Scaffolding
1.2.7 Competent Person (CP) Trainer
1.2.8 High Risk Activities
1.2.9 High Visibility Accident
1.2.10 Load Handling Equipment (LHE)
1.2.11 Medical Treatment
1.2.12 Near Miss
1.2.13 Operating Envelope
1.2.14 Qualified Person (QP)
1.2.15 Qualified Person, Fall Protection (QP for FP)
1.2.16 USACE Property and Equipment
1.2.17 Load Handling Equipment (LHE) Accident or Load Handling
Equipment Mishap
1.3 SUBMITTALS
1.4 MONTHLY EXPOSURE REPORTS
1.5 CONTRACTOR SAFETY SELF-EVALUATION CHECKLIST
1.6 REGULATORY REQUIREMENTS
1.6.1 Subcontractor Safety Requirements
1.6.1.1 Experience Modification Rate (EMR)
1.6.1.2 OSHA Days Away from Work, Restricted Duty, or Job Transfer
(DART) Rate
1.7 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.7.1 Personnel Qualifications
1.7.1.1 Site Safety and Health Officer (SSHO)
1.7.1.1.1 Additional Site Safety and Health Officer (SSHO)
Requirements and Duties
1.7.1.2 Competent Person Qualifications
1.7.1.2.1 Competent Person for Confined Space Entry
1.7.1.2.2 Competent Person for Scaffolding
1.7.1.2.3 Competent Person for Fall Protection
1.7.1.3 Qualified Trainer Requirements
1.7.1.4 Requirements for all Contractor Jobsite Personnel Holding H-
1B or H-2B Visas:
1.7.1.5 Dredging Contract Requirements
1.7.1.5.1 Dredging Safety Personnel Requirements
1.7.1.5.2 SSHO Requirements for Dredging
1.7.1.5.3 Collateral Duty Safety Officer (CDSO) Requirements for
Dredging
Section 01 35 26 Page 2 of 36
1.7.1.5.4 Safety Personnel Training Requirements for Dredging
1.7.1.6 Crane Operators/Riggers
1.7.2 Personnel Duties
1.7.2.1 Duties of the Site Safety and Health Officer (SSHO)
1.7.3 Meetings
1.7.3.1 Preconstruction Conference
1.7.3.2 Safety Meetings
1.8 ACCIDENT PREVENTION PLAN (APP)
1.8.1 Names and Qualifications
1.8.2 Plans
1.8.2.1 Confined Space Entry Plan
1.8.2.2 Standard Lift Plan (SLP)
1.8.2.3 Critical Lift Plan - Crane or Load Handling Equipment
1.8.2.3.1 Critical Lift Plan Planning and Schedule
1.8.2.3.2 Lifts of Personnel
1.8.2.4 Barge Mounted Mobile Crane Lift Plan
1.8.2.5 Multi-Purpose Machines, Material Handling Equipment, and
Construction Equipment Lift Plan
1.8.2.6 Fall Protection and Prevention (FP&P) Plan
1.8.2.7 Rescue and Evacuation Plan
1.8.2.8 Hazardous Energy Control Program (HECP)
1.8.2.9 Excavation Plan
1.8.2.10 Occupant Protection Plan
1.8.2.11 Lead Compliance Plan
1.8.2.12 Asbestos Hazard Abatement Plan
1.8.2.13 Site Safety and Health Plan
1.8.2.14 Polychlorinated Biphenyls (PCB) Plan
1.8.2.15 Site Demolition Plan
1.9 ACTIVITY HAZARD ANALYSIS (AHA)
1.9.1 AHA Management
1.9.2 AHA Signature Log
1.10 DISPLAY OF SAFETY INFORMATION
1.10.1 Safety Bulletin Board
1.10.2 Safety and Occupational Health (SOH) Deficiency Tracking
System
1.11 SITE SAFETY REFERENCE MATERIALS
1.12 EMERGENCY MEDICAL TREATMENT
1.13 NOTIFICATIONS and REPORTS
1.13.1 Mishap Notification
1.13.2 Accident Reports
1.13.3 LHE Inspection Reports
1.13.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and Rigging
1.13.5 Third Party Certification of Floating Cranes and
Barge-Mounted Mobile Cranes
1.14 HOT WORK
1.14.1 Permit and Personnel Requirements
1.14.2 Work Around Flammable Materials
1.15 RADIATION SAFETY REQUIREMENTS
1.15.1 Radiography Operation Planning Work Sheet
1.15.2 Site Access and Security
1.15.3 Loss or Release and Unplanned Personnel Exposure
1.15.4 Site Demarcation and Barricade
1.15.5 Security of Material and Equipment
1.15.6 Transportation of Material
1.15.7 Schedule for Exposure or Unshielding
1.15.8 Transmitter Requirements
1.16 CONFINED SPACE ENTRY REQUIREMENTS
Section 01 35 26 Page 3 of 36
1.16.1 Entry Procedures
1.16.2 Forced Air Ventilation
1.16.3 Sewer Wet Wells
1.16.4 Rescue Procedures and Coordination with Local Emergency
Responders
1.17 GAS PROTECTION
1.17.1 Gas Test Readings Record
1.17.2 Special Requirements
1.18 HIGH NOISE LEVEL PROTECTION
1.19 DIVE SAFETY REQUIREMENTS
1.20 SEVERE STORM PLAN
PART 2 PRODUCTS
2.1 CONFINED SPACE SIGNAGE
PART 3 EXECUTION
3.1 CONSTRUCTION AND OTHER WORK
3.1.1 Worksite Communication
3.1.2 Hazardous Material Use
3.1.3 Hazardous Material Exclusions
3.1.4 Unforeseen Hazardous Material
3.2 UTILITY OUTAGE REQUIREMENTS
3.3 OUTAGE COORDINATION MEETING
3.4 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
3.4.1 Safety Preparatory Inspection Coordination Meeting with the
Government or Utility
3.4.2 Lockout/Tagout Isolation
3.4.3 Lockout/Tagout Removal
3.5 FALL PROTECTION PROGRAM
3.5.1 Training
3.5.2 Fall Protection Equipment and Systems
3.5.2.1 Additional Personal Fall Protection
3.5.2.2 Personal Fall Protection Harnesses
3.5.3 Fall Protection for Roofing Work
3.5.4 Horizontal Lifelines (HLL)
3.5.5 Guardrails and Safety Nets
3.5.6 Rescue and Evacuation Plan and Procedures
3.6 SHIPYARD REQUIREMENTS
3.7 WORK PLATFORMS
3.7.1 Scaffolding
3.7.2 Elevated Aerial Work Platforms (AWPs)
3.8 EQUIPMENT
3.8.1 Material Handling Equipment (MHE)
3.8.2 Load Handling Equipment (LHE)
3.8.3 Machinery and Mechanized Equipment
3.8.4 Base Mounted Drum Hoists
3.8.5 Use of Explosives
3.9 EXCAVATIONS
3.9.1 Utility Locations
3.9.2 Utility Location Verification
3.9.3 Utilities Within and Under Concrete, Bituminous Asphalt, and
Other Impervious Surfaces
3.10 ELECTRICAL
3.10.1 Conduct of Electrical Work
3.10.2 Qualifications
3.10.3 Arc Flash
Section 01 35 26 Page 4 of 36
3.10.4 Grounding
3.10.5 Testing
-- End of Section Table of Contents --
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
11/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B30.3 (2016) Tower Cranes
ASME B30.5 (2018) Mobile and Locomotive Cranes
ASME B30.7 (2011) Winches
ASME B30.8 (2015) Floating Cranes and FloatingDerricks
ASME B30.9 (2018) Slings
ASME B30.20 (2018) Below-the-Hook Lifting Devices
ASME B30.22 (2016) Articulating Boom Cranes
ASME B30.23 (2011) Personnel Lifting Systems Safety
Standard for Cableways, Cranes, Derricks, Hoists, Hooks, Jacks, and Slings
ASME B30.26 (2015; INT Jun 2010 - Jun 2014) Rigging
Hardware
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.22 (2007; R 2017) Safety Requirements for
Rope-Guided and Non-Guided Workers’ Hoists
ASSP A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites
ASSP A10.44 (2014) Control of Energy Sources
(Lockout/Tagout) for Construction and
Demolition Operations
ASSP Z244.1 (2016) The Control of Hazardous Energy
Lockout, Tagout and Alternative Methods
ASSP Z359.0 (2012) Definitions and Nomenclature Used
Section 01 35 26 Page 5 of 36 for Fall Protection and Fall Arrest
ASSP Z359.1 (2016) The Fall Protection Code
ASSP Z359.2 (2017) Minimum Requirements for a
Comprehensive Managed Fall Protection
Program
ASSP Z359.3 (2017) Safety Requirements for Lanyards and Positioning Lanyards
ASSP Z359.4 (2013) Safety Requirements for
Assisted-Rescue and Self-Rescue Systems, Subsystems and Components
ASSP Z359.6 (2016) Specifications and Design
Requirements for Active Fall Protection
Systems
ASSP Z359.7 (2011) Qualification and Verification
Testing of Fall Protection Products
ASSP Z359.11 (2014) Safety Requirements for Full Body
Harnesses
ASSP Z359.12 (2009) Connecting Components for Personal
Fall Arrest Systems
ASSP Z359.13 (2013) Personal Energy Absorbers and
Energy Absorbing Lanyards
ASSP Z359.14 (2014) Safety Requirements for
Self-Retracting Devices for Personal Fall
Arrest and Rescue Systems
ASSP Z359.15 (2014) Safety Requirements for Single
Anchor Lifelines and Fall Arresters for
Personal Fall Arrest Systems
ASSP Z490.1 (2016) Criteria for Accepted Practices in
Safety, Health, and Environmental Training
ASTM INTERNATIONAL (ASTM)
ASTM F855 (2015) Standard Specifications for
Temporary Protective Grounds to Be Used on
De-energized Electric Power Lines and
Equipment
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 1048 (2003) Guide for Protective Grounding of
Power Lines
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017)
National Electrical Safety Code
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION (NASA)
Section 01 35 26 Page 6 of 36
NASA NPR 8621.1 (2006b; Change 7) NASA Procedural
Requirements for Mishap and Close Call
Reporting, Investigating, and Recordkeeping
NASA NPR 8715.3 (2008c; Change 9) NASA General Safety
Program Requirements
NASA-STD 8719.12 (2018a) Safety Standard for Explosives, Propellants, and Pyrotechnics
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA Z535.2 (2011) Environmental and Facility Safety
Signs
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2018; TIA 18-1) Standard for Portable
Fire Extinguishers
NFPA 51B (2014) Standard for Fire Prevention During
Welding, Cutting, and Other Hot Work
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;
TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;
TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;
TIA 17-11; TIA 17-12; TIA 17-13; TIA
17-14; TIA 17-15; TIA 17-16; TIA 17-17 )
National Electrical Code
NFPA 70E (2018; TIA 18-1; TIA 81-2) Standard for
Electrical Safety in the Workplace
NFPA 241 (2019) Standard for Safeguarding
Construction, Alteration, and Demolition
Operations
NFPA 306 (2019) Standard for the Control of Gas
Hazards on Vessels
TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)
TIA-222 (2005G; Add 1 2007; Add 2 2009; Add 3
2014; Add 4 2014; R 2014; R 2016)
Structural Standards for Steel Antenna
Towers and Antenna Supporting Structures
TIA-1019 (2012; R 2016) Standard for Installation, Alteration and Maintenance of Antenna
Supporting Structures and Antennas
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements
Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
Section 01 35 26 Page 7 of 36
10 CFR 20 Standards for Protection Against Radiation
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1910.147 The Control of Hazardous Energy (Lock
Out/Tag Out)
29 CFR 1910.333 Selection and Use of Work Practices
29 CFR 1915 Confined and Enclosed Spaces and Other
Dangerous Atmospheres in Shipyard
Employment
29 CFR 1915.89 Control of Hazardous Energy
(Lockout/Tags-Plus)
29 CFR 1919 Gear Certification
29 CFR 1926 Safety and Health Regulations for
Construction
29 CFR 1926.16 Rules of Construction
29 CFR 1926.450 Scaffolds
29 CFR 1926.500 Fall Protection
29 CFR 1926.552 Material Hoists, Personal Hoists, Elevators
29 CFR 1926.553 Base-Mounted Drum Hoists
29 CFR 1926.1400 Cranes and Derricks in Construction
49 CFR 173 Shippers - General Requirements for
Shipments and Packagings
CPL 02-01-056 (2014) Inspection Procedures for Accessing
Communication Towers by Hoist
CPL 2.100 (1995) Application of the Permit-Required
Confined Spaces (PRCS) Standards, 29 CFR
1910.146
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.
Section 01 35 26 Page 8 of 36
1.2.2 Competent Person, Confined Space
The CP, Confined Space, is a person meeting the competent person requirements as defined EM 385-1-1 Appendix Q, with thorough knowledge of
OSHA’s Confined Space Standard, 29 CFR 1910.146, and designated in writing to be responsible for the immediate supervision, implementation and monitoring of the confined space program, who through training, knowledge and experience in confined space entry is capable of identifying, evaluating and addressing existing and potential confined space hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.3 Competent Person, Cranes and Rigging
The CP, Cranes and Rigging, as defined in EM 385-1-1 Appendix Q, is a person meeting the competent person, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the Crane and Rigging Program, who through training, knowledge and experience in crane and rigging is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.4 Competent Person, Excavation/Trenching
A CP, Excavation/Trenching, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and 29 CFR 1926, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the excavation/trenching program, who through training, knowledge and experience in excavation/trenching is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.5 Competent Person, Fall Protection
The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and in accordance with
ASSP Z359.0, who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.6 Competent Person, Scaffolding
The CP, Scaffolding is a person meeting the competent person requirements in EM 385-1-1 Appendix Q, and designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the scaffolding program. The CP for Scaffolding has enough training, knowledge and experience in scaffolding to correctly identify, evaluate and address existing and potential hazards and also has the authority to take prompt corrective measures with regard to these hazards. CP qualifications must be documented and include experience on the specific scaffolding systems/types being used, assessment of the base material that the scaffold will be erected upon, load calculations for materials and personnel, and erection and dismantling. The CP for scaffolding must have a documented, minimum of 8-hours of scaffold training to include training
Section 01 35 26 Page 9 of 36 on the specific type of scaffold being used (e.g. mast-climbing, adjustable, tubular frame), in accordance with EM 385-1-1 Section 22.B.02.
1.2.7 Competent Person (CP) Trainer
A competent person trainer as defined in EM 385-1-1 Appendix Q, who is qualified in the material presented, and who possesses a working knowledge of applicable technical regulations, standards, equipment and systems related to the subject matter on which they are training Competent
Persons. A competent person trainer must be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer must be appropriate to that specific industry.The competent person trainer must evaluate the knowledge and skills of the competent persons as part of the training process.
1.2.8 High Risk Activities
High Risk Activities are activities that involve work at heights, crane and rigging, excavations and trenching, scaffolding, electrical work, and confined space entry.
1.2.9 High Visibility Accident
A High Visibility Accident is any mishap which may generate publicity or high visibility.
1.2.10 Load Handling Equipment (LHE)
LHE is a term used to describe cranes, hoists and all other hoisting equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).
1.2.11 Medical Treatment
Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician.Medical treatment does not include first aid treatment even when provided by a physician or registered personnel.
1.2.12 Near Miss
A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).
1.2.13 Operating Envelope
The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this "envelope" is the crane, the operator, riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e. ground or rail), the load's rigging path, the lift and rigging procedure.
1.2.14 Qualified Person (QP)
The QP is a person designated in writing, who, by possession of a
Section 01 35 26 Page 10 of 36 recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.
1.2.15 Qualified Person, Fall Protection (QP for FP)
A QP for FP is a person meeting the requirements of EM 385-1-1 Appendix Q, and ASSP Z359.0, with a recognized degree or professional certificate and with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, and evaluating and specifying fall protection and rescue systems.
1.2.16 USACE Property and Equipment
Interpret "USACE" property and equipment specified in USACE EM 385-1-1 as
Government property and equipment.
1.2.17 Load Handling Equipment (LHE) Accident or Load Handling Equipment
Mishap
A LHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment; two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, or roll over).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G
SD-06
Test Reports
Monthly Exposure Reports
Notifications and Reports
Accident Reports
LHE Inspection Reports
Section 01 35 26 Page 11 of 36
Gas Protection
Dive Operations Plan
SD-07 Certificates
Contractor Safety Self-Evaluation Checklist
Crane Operators/Riggers
Standard Lift Plan
Lift Plan
Naval Architecture Analysis
Activity Hazard Analysis (AHA)
Confined Space Entry Permit
Hot Work Permit
Certificate of Compliance
Third Party Certification of Floating Cranes and Barge-Mounted
Mobile Cranes
License Certificates
Radiography Operation Planning Work Sheet
Portable Gauge Operations Planning Worksheet
Machinery & Mechanized Equipment Certification Form
1.4 MONTHLY EXPOSURE REPORTS
Provide a Monthly Exposure Report and attach to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both Prime and subcontractor. Failure to submit the report may result in retention of up to 10 percent of the voucher.
CONTRACTOR SAFETY SELF-EVALUATION CHECKLIST
Contracting Officer will provide a "Contractor Safety Self-Evaluation checklist" to the Contractor at the pre-construction conference. Complete the checklist monthly and submit with each request for payment voucher.
An acceptable score of 90 or greater is required. Failure to submit the completed safety self-evaluation checklist or achieve a score of at least
90 may result in retention of up to 10 percent of the voucher.
1.5 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, comply with the most recent edition of USACE EM 385-1-1, and the following federal, state, and local laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, Section 01 35 26 Page 12 of 36 criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.5.1 Subcontractor Safety Requirements
1.5.1.1 Experience Modification Rate (EMR)
Subcontractors on this contract must have an effective EMR less than or equal to 1.10, as computed by the National Council on Compensation
Insurance (NCCI) or if not available, as computed by the state agency's rating bureau in the state where the subcontractor is registered, when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier. The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable EMR range cannot be achieved. Relaxation of the EMR range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval.
Contractor's Site Safety and Health Officer (SSHO) must collect and maintain the certified EMR ratings for all subcontractors on the project and make them available to the Government at the Government's request.
1.5.1.2 OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART)
Rate
Subcontractors on this contract must have a DART rate, calculated from the most recent, complete calendar year, less than or equal to 3.4 when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier. The OSHA Dart Rate is calculated using the following formula:
(N/EH) x 200,000 where: N = number of injuries and illnesses with days away, restricted work, or job transfer
EH = total hours worked by all employees during most recent, complete calendar year
200,000 = base for 100 full-time equivalent workers (working 40 hours per week, 50 weeks per year)
The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable
OSHA Dart rate range cannot be achieved for a particular subcontractor.
Relaxation of the OSHA DART rate range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval. Contractor's Site Safety and Health
Officer (SSHO) must collect and maintain self-certified OSHA DART rates for all subcontractors on the project and make them available to the
Government at the Government's request.
1.7 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.7.1 Personnel Qualifications
1.7.1.1 Site Safety and Health Officer (SSHO)
Provide an SSHO that meets the requirements of EM 385-1-1 Section 1. The
SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one
Section 01 35 26 Page 13 of 36 person at each project site to function as the Site Safety and Health
Officer (SSHO).The SSHO or an equally-qualified Alternate SSHO must be at the work site at all times to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO and Alternate SSHO must have the required training, experience, and qualifications in accordance with EM 385-1-1 Section 01.A.17, and all associated sub-paragraphs.
If the SSHO is off-site for a period longer than 24 hours, an equally-qualified alternate SSHO must be provided and must fulfill the same roles and responsibilities as the primary SSHO. When the SSHO is temporarily (up to 24 hours) off-site, a Designated Representative (DR), as identified in the AHA may be used in lieu of an Alternate SSHO, and must be on the project site at all times when work is being performed. Note that the DR is a collateral duty safety position, with safety duties in addition to their full time occupation.
1.7.1.1.1 Additional Site Safety and Health Officer (SSHO) Requirements and Duties
The SSHO may not serve as the Quality Control Manager. The SSHO may not serve as the Superintendent.
1.7.1.2 Competent Person Qualifications
Provide Competent Persons in accordance with EM 385-1-1, Appendix Q and herein. Competent Persons for high risk activities include confined space, cranes and rigging, excavation/trenching, fall protection, and electrical work. The CP for these activities must be designated in writing, and meet the requirements for the specific activity (i.e.
competent person, fall protection).
The Competent Person identified in the Contractor's Safety and Health
Program and accepted Accident Prevention Plan, must be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the
Competent Persons(s) to the Contracting Officer for information in consultation with the Safety Office.
1.7.1.2.1 Competent Person for Confined Space Entry
Provide a Confined Space (CP) Competent Person who meets the requirements of EM 385-1-1, Appendix Q, and herein. The CP for Confined Space Entry must supervise the entry into each confined space in accordance with
EM 385-1-1, Section 34.
Since this work involves operations that handle combustible or hazardous materials, this person must have the ability to understand and follow through on the air sampling, Personal Protective Equipment (PPE), and instructions of a Marine Chemist, Coast Guard authorized persons, or
Certified Industrial Hygienist. Confined space and enclosed space work must comply with NFPA 306, OSHA 29 CFR 1915, Subpart B, "Confined and
Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment," or as applicable, 29 CFR 1910.147 for general industry.
1.7.1.2.2 Competent Person for Scaffolding
Provide a Competent Person for Scaffolding who meets the requirements of
Section 01 35 26 Page 14 of 36
EM 385-1-1, Section 22.B.02 and herein.
1.7.1.2.3 Competent Person for Fall Protection
Provide a Competent Person for Fall Protection who meets the requirements of EM 385-1-1, Section 21.C.04, 21.B.03, and herein.
1.7.1.3 Qualified Trainer Requirements
Instructors are required to:
a. Prepare class presentations that cover construction-related safety requirements and includes topics covered in the NAVFAC Construction
Safety Hazard Awareness Course for Contractors.
b. Ensure that all attendees attend all sessions by using a class roster signed daily by each attendee. Maintain copies of the roster for at least five (5) years. This is a certification class and must be attended 100 percent. In cases of emergency where an attendee cannot make it to a session, the attendee can make it up in another class session for the same subject.
c. Update training course materials whenever an update of the EM 385-1-1 becomes available.
d. Provide a written exam of at least 50 questions. Students are required to answer 80 percent correctly to pass.
e. Request, review and incorporate student feedback into a continuous course improvement program.
1.7.1.4 Dredging Contract Requirements
1.7.1.4.1 Dredging Safety Personnel Requirements
1.7.1.4.2 SSHO Requirements for Dredging
1.7.1.4.3 Collateral Duty Safety Officer (CDSO) Requirements for Dredging
1.7.1.4.4 Safety Personnel Training Requirements for Dredging
1.7.1.6 Crane Operators/Riggers
Provide Operators, Signal Persons, and Riggers meeting the requirements in
EM 385-1-1, Section 15.B for Riggers and Section 16.B for Crane Operators and Signal Persons. Provide proof of current qualification.
1.7.2 Personnel Duties
1.7.2.1 Duties of the Site Safety and Health Officer (SSHO)
The SSHO must:
a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the
Contractors' daily production report.
Section 01 35 26 Page 15 of 36
b. Conduct mishap investigations and complete required accident reports.
Report mishaps and near misses.
c. Use and maintain OSHA's Form 300 to log work-related injuries and illnesses occurring on the project site for Prime Contractors and subcontractors, and make available to the Contracting Officer upon request. Post and maintain the Form 300A on the site Safety Bulletin
Board.
d. Maintain applicable safety reference material on the job site.
e. Attend the pre-construction conference, pre-work meetings including preparatory meetings, and periodic in-progress meetings.
f. Review the APP and AHAs for compliance with EM 385-1-1, and approve, sign, implement and enforce them.
g. Establish a Safety and Occupational Health (SOH) Deficiency Tracking
System that lists and monitors outstanding deficiencies until resolution.
h. Ensure subcontractor compliance with safety and health requirements.
i. Maintain a list of hazardous chemicals on site and their material
Safety Data Sheets (SDS).
j. Maintain a weekly list of high hazard activities involving energy, equipment, excavation, entry into confined space, and elevation, and be prepared to discuss details during QC Meetings.
k. Provide and keep a record of site safety orientation and indoctrination for Contractor employees, subcontractor employees, and site visitors.
Superintendent, QC Manager, and SSHO are subject to dismissal if the above duties are not being effectively carried out. If Superintendent, QC
Manager, or SSHO are dismissed, project work will be stopped and will not be allowed to resume until a suitable replacement is approved and the above duties are again being effectively carried out.
1.7.3 Meetings
1.7.3.1 Preconstruction Conference
a. Contractor representatives who have a responsibility or significant role in accident prevention on the project must attend the preconstruction conference. This includes the project superintendent, Site Safety and Occupational Health officer, quality control manager, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses
(AHAs) and special plans, program and procedures associated with it).
b. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the
Section 01 35 26 Page 16 of 36
Contractor and the Contracting Officer as to which phases will require an analysis. In addition, establish a schedule for the preparation, submittal, and Government review of AHAs to preclude project delays.
c. Deficiencies in the submitted APP, identified during the Contracting
Officer's review, must be corrected, and the APP re-submitted for review prior to the start of construction. Work is not permitted to begin until an APP is established that is acceptable to the
Contracting Officer.
1.7.3.2 Safety Meetings
Conduct safety meetings to review past activities, plan for new or changed operations, review pertinent aspects of appropriate AHA (by trade), establish safe working procedures for anticipated hazards, and provide pertinent Safety and Occupational Health (SOH) training and motivation.
Conduct meetings at least once a month for all supervisors on the project location. The SSHO, supervisors, foremen, or CDSOs must conduct meetings at least once a week for the trade workers. Document meeting minutes to include the date, persons in attendance, subjects discussed, and names of individual(s) who conducted the meeting. Maintain documentation on-site and furnish copies to the Contracting Officer on request. Notify the
Contracting Officer of all scheduled meetings 7 calendar days in advance.
1.8 ACCIDENT PREVENTION PLAN (APP)
A qualified person must prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of EM 385-1-1, Appendix A, and as supplemented herein. Cover all paragraph and subparagraph elements in EM 385-1-1, Appendix A. The APP must be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP must interface with the
Contractor's overall safety and health program referenced in the APP in the applicable APP element, and made site-specific. Describe the methods to evaluate past safety performance of potential subcontractors in the selection process. Also, describe innovative methods used to ensure and monitor safe work practices of subcontractors. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP must be signed by an officer of the firm (Prime
Contractor senior person), the individual preparing the APP, the on-site superintendent, the designated SSHO, the Contractor Quality Control
Manager, and any designated Certified Safety Professional (CSP) or
Certified Health Physicist (CIH). The SSHO must provide and maintain the
APP and a log of signatures by each subcontractor foreman, attesting that they have read and understand the APP, and make the APP and log available on-site to the Contracting Officer. If English is not the foreman's primary language, the Prime Contractor must provide an interpreter.
Submit the APP to the Contracting Officer 10 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP. Once reviewed and accepted by the Contracting
Section 01 35 26 Page 17 of 36
Officer, the APP and attachments will be enforced as part of the contract.
Disregarding the provisions of this contract or the accepted APP is cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified. Continuously review and amend the APP, as necessary, throughout the life of the contract. Changes to the accepted
APP must be made with the knowledge and concurrence of the Contracting
Officer, project superintendent, SSHO and Quality Control Manager.
Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered. Should any severe hazard exposure
(i.e. imminent danger) become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard.
Notify the Contracting Officer within 24 hours of discovery. Eliminate and remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSP A10.34), and the environment.
1.8.1 Names and Qualifications
Provide plans in accordance with the requirements outlined in Appendix A of EM 385-1-1, including the following:
a. Names and qualifications (resumes including education, training, experience and certifications) of site safety and health personnel designated to perform work on this project to include the designated
Site Safety and Health Officer and other competent and qualified personnel to be used. Specify the duties of each position.
b. Qualifications of competent and of qualified persons. As a minimum, designate and submit qualifications of competent persons for each of the following major areas: excavation; scaffolding; fall protection;
hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents;
and personal protective equipment and clothing to include selection, use and maintenance.
1.8.2 Plans
Provide plans in the APP in accordance with the requirements outlined in
Appendix A of EM 385-1-1, including the following:
1.8.2.1 Confined Space Entry Plan
Develop a confined or enclosed space entry plan in accordance with
EM 385-1-1, applicable OSHA standards 29 CFR 1910, 29 CFR 1915, and
29 CFR 1926, OSHA Directive CPL 2.100, and any other federal, state and local regulatory requirements identified in this contract. Identify the qualified person's name and qualifications, training, and experience.
Delineate the qualified person's authority to direct work stoppage in the event of hazardous conditions. Include procedure for rescue by contractor personnel and the coordination with emergency responders. (If there is no confined space work, include a statement that no confined space work exists and none will be created.)
1.8.2.2 Standard Lift Plan (SLP)
Plan lifts to avoid situations where the operator cannot maintain safe control of the lift. Prepare a written SLP in accordance with EM 385-1-1, Section 01 35 26 Page 18 of 36
Section 16.A.03, using Form 16-2 for every lift or series of lifts (if duty cycle or routine lifts are being performed). The SLP must be developed, reviewed and accepted by all personnel involved in the lift in conjunction with the associated AHA. Signature on the AHA constitutes acceptance of the plan. Maintain the SLP on the LHE for the current lift(s) being made. Maintain historical SLPs for a minimum of 3 months.
1.8.2.3 Critical Lift Plan - Crane or Load Handling Equipment
Provide a Critical Lift Plan as required by EM 385-1-1, Section 16.H.01, using Form 16-3. In addition, Critical Lift Plans are required for the following:
a. Lifts over 50 percent of the capacity of barge mounted mobile crane's hoist.
b. When working around energized power lines where the work will get closer than the minimum clearance distance in EM 385-1-1 Table 16-1.
c. For lifts with anticipated binding conditions.
d. When erecting cranes.
1.8.2.3.1 Critical Lift Plan Planning and Schedule
Critical lifts require detailed planning and additional or unusual safety precautions. Develop and submit a critical lift plan to the Contracting
Officer 30 calendar days prior to critical lift. Comply with load testing requirements in accordance with EM 385-1-1, Section 16.F.03.
1.8.2.3.2 Lifts of Personnel
In addition to the requirements of EM 385-1-1, Section 16.H.02, for lifts of personnel, demonstrate compliance with the requirements of
29 CFR 1926.1400 and EM 385-1-1, Section 16.T.
1.8.2.4 Barge Mounted Mobile Crane Lift Plan
Provide a Naval Architecture Analysis and include an LHE Manufacturer's
Floating Service Load Chart in accordance with EM 385-1-1, Section
16.L.03.
1.8.2.5 Multi-Purpose Machines, Material Handling Equipment, and Construction Equipment Lift Plan
Multi-purpose machines, material handling equipment, and construction equipment used to lift loads that are suspended by rigging gear, require proof of authorization from the machine OEM that the machine is capable of making lifts of loads suspended by rigging equipment. Written approval from a qualified registered professional engineer, after a safety analysis is performed, is allowed in lieu of the OEM's approval.
Demonstrate that the operator is properly trained and that the equipment is properly configured to make such lifts and is equipped with a load chart.
1.8.2.6 Fall Protection and Prevention (FP&P) Plan
The plan must comply with the requirements of EM 385-1-1, Section 21.D and ASSP Z359.2, be site specific, and address all fall hazards in the
Section 01 35 26 Page 19 of 36 work place and during different phases of construction. Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 1.8 m 6 feet. A competent person or qualified person for fall protection must prepare and sign the plan documentation. Include fall protection and prevention systems, equipment and methods employed for every phase of work, roles and responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods. Review and revise, as necessary, the Fall Protection and Prevention Plan documentation as conditions change, but at a minimum every six months, for lengthy projects, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and Prevention Plan documentation at the job site for the duration of the project. Include the Fall Protection and
Prevention Plan documentation in the Accident Prevention Plan (APP).
1.8.2.7 Rescue and Evacuation Plan
Provide a Rescue and Evacuation Plan in accordance with EM 385-1-1. Section
21.N and ASSP Z359.2, and include in the FP&P Plan and as part of the APP.
Include a detailed discussion of the following: methods of rescue;
methods of self-rescue; equipment used; training requirement; specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility.
1.8.2.8 Hazardous Energy Control Program (HECP)
Develop a HECP in accordance with EM 385-1-1 Section 12, 29 CFR 1910.147, 29 CFR 1910.333, 29 CFR 1915.89, ASSP Z244.1, and ASSP A10.44. Submit this HECP as part of the Accident Prevention Plan (APP).Conduct a preparatory meeting and inspection with all effected personnel to coordinate all HECP activities. Document this meeting and inspection in accordance with EM 385-1-1, Section 12.A.02.Ensure that each employee is familiar with and complies with these procedures.
1.8.2.9 Excavation Plan
Identify the safety and health aspects of excavation, and provide and prepare the plan in accordance with EM 385-1-1, Section 25.A and Section
31 00 00 EARTHWORK.
1.8.2.10 Occupant Protection Plan
Identify the safety and health aspects of lead-based paint removal, prepared in accordance with Section 02 83 00 LEAD REMEDIATION.
1.8.2.11 Lead Compliance Plan
Identify the safety and health aspects of lead work, and prepare in accordance with Section 02 83 00 LEAD REMEDIATION.
1.8.2.12 Asbestos Hazard Abatement Plan
Identify the safety and health aspects of asbestos work, and prepare in accordance with Section 02 82 00 ASBESTOS REMEDIATION.
1.8.2.13 Site Safety and Health Plan
Section 01 35 26 Page 20 of 36
Identify the safety and health aspects, and prepare in accordance with
Section 01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR
CONTAMINATED SITES.
1.8.2.14 Polychlorinated Biphenyls (PCB) Plan
Identify the safety and health aspects of Polychlorinated Biphenyls work, and prepare in accordance with Sections 02 84 33 REMOVAL AND DISPOSAL OF
POLYCHLORINATED BIPHENYLS (PCBs) and 02 61 23 REMOVAL AND DISPOSAL OF PCB
CONTAMINATED SOILS.
1.8.2.15 Site Demolition Plan
Identify the safety and health aspects, and prepare in accordance with
Section 02 41 00 [DEMOLITION] [AND] [DECONSTRUCTION] and referenced sources.
1.9 ACTIVITY HAZARD ANALYSIS (AHA)
Before beginning each activity, task or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an AHA. AHAs must be developed by the Prime Contractor, subcontractor, or supplier performing the work, and provided for Prime
Contractor review and approval before submitting to the Contracting
Officer. AHAs must be signed by the SSHO, Superintendent, QC Manager and the subcontractor Foreman performing the work. Format the AHA in accordance with EM 385-1-1, Section 1 or as directed by the Contracting
Officer. Submit the AHA for review at least working days prior to the start of each activity task, or DFOW. The Government reserves the right to require the Contractor to revise and resubmit the AHA if it fails to effectively identify the work sequences, specific anticipated hazards, site conditions, equipment, materials, personnel and the control measures to be implemented.
AHAs must identify competent persons required for phases involving high risk activities, including confined entry, crane and rigging, excavations, trenching, electrical work, fall protection, and scaffolding.
1.9.1 AHA Management
Review the AHA list periodically (at least monthly) at the Contractor supervisory safety meeting, and update as necessary when procedures, scheduling, or hazards change. Use the AHA during daily inspections by the SSHO to ensure the implementation and effectiveness of the required safety and health controls for that work activity.
1.9.2 AHA Signature Log
Each employee performing work as part of an activity, task or DFOW must review the AHA for that work and sign a signature log specifically maintained for that AHA prior to starting work on that activity. The SSHO must maintain a signature log on site for every AHA. Provide employees whose primary language is other than English, with an interpreter to ensure a clear understanding of the AHA and its contents.
1.10 DISPLAY OF SAFETY INFORMATION
Section 01 35 26 Page 21 of 36
1.10.1 Safety Bulletin Board
Within calendar day(s) after commencement of work, erect a safety bulletin board at the job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the
Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, may be deemed as meeting the requirement for a bulletin board. Include and maintain information on safety bulletin board as required by EM 385-1-1, Section 1.A.7. Additional items required to be posted include:
a. Confined space entry permit.
b. Hot work permit.
1.10.2 Safety and Occupational Health (SOH) Deficiency Tracking System
Establish a SOH deficiency tracking system that lists and monitors the status of SOH deficiencies in chronological order. Use the tracking system to evaluate the effectiveness of the APP.A monthly evaluation of the data must be discussed in the QC or SOH meeting with everyone on the project.
The list must be posted on the project bulletin board and updated daily, and provide the following information:
a. Date deficiency identified;
b. Description of deficiency;
c. Name of person responsible for correcting deficiency;
d. Projected resolution date;
e. Date actually resolved.
1.11 SITE SAFETY REFERENCE MATERIALS
Maintain safety-related references applicable to the project, including those listed in paragraph REFERENCES. Maintain applicable equipment manufacturer's manuals.
1.12 EMERGENCY MEDICAL TREATMENT
Contractors must arrange for their own emergency medical treatment in accordance with EM 385-1-1. Government has no responsibility to provide emergency medical treatment.
1.13 NOTIFICATIONS and REPORTS
1.13.1 Mishap Notification
Notify the Contracting Officer as soon as practical, but no more than twenty-four hours, after any mishaps, including recordable accidents, incidents, and near misses, as defined in EM 385-1-1 Appendix Q, any report of injury, illness, or any property damage. For LHE or rigging mishaps, notify the Contracting Officer as soon as practical but not more than 4 hours after mishap. The Contractor is responsible for obtaining appropriate medical and emergency assistance and for notifying fire, law enforcement, and regulatory agencies. Immediate reporting is required for
Section 01 35 26 Page 22 of 36 electrical mishaps, to include Arc Flash; shock; uncontrolled release of hazardous energy (includes electrical and non-electrical); load handling equipment or rigging; fall from height (any level other than same surface); and underwater diving. These mishaps must be investigated in depth to identify all causes and to recommend hazard control measures.
Within notification include Contractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured;
extent of property damage, if any; extent of injury, if known, and brief description of accident (for example, type of construction equipment used and PPE used).Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted. Assist and cooperate fully with the Government's investigation(s) of any mishap.
1.13.2 Accident Reports
a. Conduct an accident investigation for recordable injuries and illnesses, property damage, and near misses as defined in EM 385-1-1, to establish the root cause(s) of the accident. The Contracting
Officer will provide copies of any required or special forms.
b. Near Misses: Near miss reports are considered positive and proactive
Contractor safety management actions.
c. Conduct an accident investigation for any load handling equipment accident (including rigging accidents) to establish the root cause(s)of the accident. Complete the LHE Accident Report (Crane and Rigging Accident Report) form and provide the report to the
Contracting Officer within 30 calendar days of the accident.
This is the start of the file's text. The full file is on GovTribe.