Attachment 1 - Summary of Work.pdf
PDF 51 KB Posted
- Solicitation number
- 36E77620R0042
About this file
This solicitation package describes a competitive Service-Disabled Veteran-Owned Small Business set-aside contract for infrastructure retrofit work at the White City VA Southern Oregon Rehabilitation Center and Clinics. The project scope includes replacing approximately 14,020 linear feet of 8-inch potable water pipes, 6,840 linear feet of 6 to 12-inch gravity sanitary sewer pipes, and 17,250 linear feet of 6 to 36-inch gravity storm sewer pipes. It will also construct a new stormwater retention pond. Work will be conducted over nine phases to minimize disruption, with a stormwater facility constructed in phases one and two. The contractor must provide project management, materials, equipment, and labor to complete the work in accordance with drawings, specifications, and a $10-20 million budget. Construction must adhere to the statement of work and be completed by phase-specific deadlines. The Department of Veterans Affairs is the contracting agency.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The Retrofit Campus-Wide Infrastructure Systems project at the White City Veterans Affairs (VA) Southern Oregon Rehabilitation Center and Clinics (SORCC) will replace aging infrastructure facilities including potable water, sanitary sewer and storm sewer and add a new stormwater facility. This project intends to construct up to approximately 14,020 lineal feet of 8-inch potable water pipe, 6,840 lineal feet of gravity sanitary sewer pipe ranging between 6 and 12 inches, and 17,250 lineal feet of gravity storm sewer pipe ranging between 6 and 36 inches. Most of construction shall use trench methods for pipeline retrofit work. Portions of pipe will be constructed using trenchless methods typically beneath buildings, other structures or where high value surface amenities exist. A stormwater facility (wet pond with retention) consists of augmenting an existing pond (which is too small) by installing a new, bigger pond with flow control features.
Potable Water system construction will occur in three stages per phase. Stage 1 will construct and test retrofit facilities offset from existing pipe to maintain existing water system in service. Stage 2 will construct tie-ins to existing systems. VA buildings conducting critical services will be required to have temporary water service provisions to avoid disruption of water supply. Non-critical buildings will be allowed to have water service disrupted on a short-term basis. All water service interruptions for Stage 2 tie-ins shall be approved by VA prior to beginning work. Stage 3 construction will remove or abandon existing water system taken out of service.
Most of the sanitary sewer and storm sewer pipe will be constructed at a zero-foot horizontal offset from the existing pipe and will require concurrent pipe removal and installation operations. Sanitary sewer and storm sewer systems shall be maintained in service during retrofit construction. The contractor will be required to install temporary flow management facilities. The design and implementation of all temporary flow management facilities shall be the responsibility of the contractor.
Restoration of disturbed existing site surfacing shall be required. This will include but not be limited to concrete sidewalk, asphalt pavement, turf and landscaping. Surfacing shall be restored in accordance with the construction documents and VA design standards.
As authorized by the VA, construction shall be performed in nine predetermined phases, one phase at a time beginning with phase 1. The stormwater facility shall be constructed before or during phases 1 and
2. To minimize the disruption of site activities, extensive pre-construction planning, coordination and scheduling shall occur with VA prior to beginning each phase of work. Work plans shall be prepared in detail to facilitate VA review and approval of proposed retrofit work in each phase. Work in each phase shall be completed and accepted by the VA within a defined period of having started the next phase.
File details come from the government source that posted it. Updated .