ATTACHMENT 1 - SUMMARY OF WORK.docx

DOCX document 24 KB Posted

Attached to
ADAL Civil Engineering, Buildings 151 & 119
Solicitation number
W50S8Q-20-B-0004
Issued by

About this file

This document summarizes a federal solicitation for construction services. The 178th Wing Contracting Office at Springfield Air National Guard Base is soliciting offers for Project No. WAAR152202 to remodel and add onto Buildings 151 and 119. Work includes mechanical, electrical, plumbing, communications, security, and finishes upgrades, as well as new construction connecting to Building 151. The total contract value is estimated between $5-10 million. The North American Industry Classification code is 236220. The pre-bid conference is September 1, 2020, with bids due September 24, 2020. The contract performance period is 360 calendar days from notice to proceed. The solicitation is set aside for 8(a) small businesses. Interested parties must register in the System for Award Management and monitor the Federal Business Opportunities website for solicitation documents and any amendments. The facility is located at Springfield Air National Guard Base in Springfield, Ohio.

View the file

Other files

File Type Posted
BID ABSTRACT 20-B-0004.pdf PDF
Sign-In Bid Opening 20-B-0004.pdf PDF
W50S8Q-20-B-0004-0003 ADAL CE SPANGB.pdf PDF
ADAL Amendment 0002.pdf PDF
ATTACHMENT 7A - Questions_ Answers 2.docx DOCX document
ATTACHMENT 7C - Typical Existing Restroom Elevations.pdf PDF
ATTACHMENT 7B - A-601 - Arch Door_Window Schedules.pdf PDF
ATTACHMENT 7D - B119 Mezz Location.pdf PDF
ATTACHMENT 6B - A0-5 Layout.pdf PDF
Site Visit SignIn Sheet 01 Sept 2020 (1).pdf PDF
20-B-0004 ATTACHMENT 6D - Arch Specs pg 12 08 71 00.pdf PDF
ATTACHMENT 6A - Questions Answers.docx DOCX document
20-B-0004 Site Visit SignIn Sheet 01 Sept 2020 (4).pdf PDF
ADAL Amemdment 0001.pdf PDF
20-B-0004 ATTACHMENT 6C - A-104 Architectural Roof Plan.pdf PDF
20-B-0004 Site Visit MFR.docx DOCX document
W50S8Q-20-B-0004 ADAL CE SPANGB 25AUG.pdf PDF
ATTACHMENT 3B - DRAWINGS (CIVIL SET).pdf PDF
ATTACHMENT 3J - CORRECTIONS (A102 A104 A601 AD102 F501).pdf PDF
ATTACHMENT 4 - Base Entry Request.pdf PDF
JA for Brand Names -Advantor Monaco Lochinvar-redo 18 Aug 20.pdf PDF
ATTACHMENT 3H - DRAWINGS (STRUCT SET).pdf PDF
ATTACHMENT 3C - DRAWINGS (ELECTRICAL SET).pdf PDF
ATTACHMENT 2A - SPEC BOOK VOL I.pdf PDF
ATTACHMENT 3A - DRAWINGS (ARCH SET).pdf PDF
ATTACHMENT 3I - DRAWINGS (TECHNOLOGY SET).pdf PDF
ATTACHMENT 3D - DRAWINGS (FIRE PROTECTION SET).pdf PDF
ATTACHMENT 5 - RFI.doc DOC document
ATTACHMENT 2B - SPEC BOOK VOL II.pdf PDF
ATTACHMENT 3G - DRAWINGS (PLUMBING SET).pdf PDF
ATTACHMENT 3F - DRAWINGS (MECHANICAL SET).pdf PDF
ATTACHMENT 3E - DRAWINGS (GEN SET).pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY OF WORK

ADAL Civil Engineering Building 151 & 119

PROJECT NO.

WAAR152202

DEPARTMENT OF THE AIR FORCE

178th CIVIL ENGINEER SQUADRON

SPRINGFILED-BECKLEY AIR NATIONAL GUARD BASE

SPRINGFIELD, OH

REV: 20200521

1. GENERAL INFORMATION

0. DEFINITION OF TERMS

0. GOVERNMENT refers to the United States GOVERNMENT and the United States Air Force as represented by the United States CONTRACTING OFFICER or their designated representative, the CONTRACTING OFFICER’s REPRESENTATIVE (COR) from the 178th Civil Engineer Squadron.

0. CONTRACTOR refers to the CONTRACTOR, the SUBCONTRACTOR for the CONTRACTOR, any and all CONTRACTOR and SUBCONTRACTOR employees or personnel, the CONTRACTOR’s tools, and the CONTRACTOR’s vehicles and equipment.

0. NOTICE TO PROCEED (NTP) provides written notification that the CONTRACTOR has provided adequate design submittals and approved by the CONTRACTING OFFICER. This shall allow the CONTRACTOR to begin ordering construction materials.

0. PERIOD OF PERFORMANCE (PoP) begins with the NOTICE TO PROCEED and ends after the final acceptance of the construction.

0. ABBREVIATIONS / ACRONYMS

KO:CONTRACTING OFFICER
COR:CONTRACTING OFFICER’s REPRESENTATIVE
PoP:Period of Performance
OTHERS:Workmen under the employ of Other CONTRACTORS or the GOVERNMENT.
GFE:GOVERNMENT Furnished Equipment
NTP:Notice To Proceed provided by the CONTRACTING OFFICER
SOW:Statement of Work
ECPsEntry Control Points
OSHA:Occupational Safety and Health Administration
ASTM:American Society for Testing and Materials
UFC:Unified Facilities Criteria (Design Manual)
UFGS:Unified Facilities Guide Specifications
QA/QC:Quality Assurance / Quality Control
EM:Environmental Manager
MSDS:Material Safety Data Sheet
VECP:Value Engineering Contract Proposal
DDC:Direct Digital Controls
HHW:Heating Hot Water

0. INSTALLATION STANDARDS

2. Repairs, replacements, new installations and re-installations shall conform to the “best practices” for building constructions, renovations and maintenance activities as specified by the installation Standards referenced below. The workmanship shall meet the requirements of these Standards and as normally provided by experienced trades personnel. The KO or COR must approve the workmanship as provided by representative samples from the CONTRACTOR prior to installation.

2. CONTRACTOR shall follow standards for electrical installations pertaining to fire protection and personnel safety found in the current US National Electric Code (NEC).

2. CONTRACTOR shall follow standards for worker safety found in Occupational Safety and Health Administration (OSHA) requirements, EM385-1-1, National Electric Safety Code, and other similar Standards.

2. CONTRACTOR is responsible for disposal of all solid waste to include non-hazardous and hazardous waste and shall comply with all Federal, State, and Local environmental laws and regulations and coordinate with Base Environmental Management Office (EMO).

2. CONTRACTOR shall adhere to all United States Air Force Unified Facilities Criteria (UFC) and Unified Facilities Guide Specifications (UFGS). The US National Electric Code (NEC), Plumbing Codes, International Building Code (IBC), and the Ohio Building Code (OBC) shall be the minimum construction standard allowed; however the UFC shall take precedence should conflict arise. A smoke/fire detection system and consideration for egress shall be provided per NFPA. Ohio Air National Guard Base Fire Department at Springfield, OH, requires a Monaco Fire Alarm panel system. Exterior walls, interior bearing walls (and/or columns) and roof assembly shall meet minimum blast and ballistic mitigation criteria as set forth by UFC 4-020-02FA. Finally, all concrete design shall be in accordance with ACI 318 Code Requirements for Structural Concrete.

2. CONTRACTOR shall perform site preparation as required, in accordance with drawings and specifications included within this Statement of Work (SOW). Questions pertaining to the depth and extent of the site preparation shall be directed to the COR. Alteration of existing surfaces or facilities, not identified by the GOVERNMENT, shall not occur. CONTRACTOR shall be responsible for any damage to any surfaces, structures or facilities not identified by the GOVERNMENT for alteration and shall be repaired to the COR’s approval at the CONTRACTOR’s expense.

2. CONTRACTOR shall provide all labor, material, tools, equipment, and supervision and all other items necessary to complete the work in accordance with any portion of the SOW. CONTRACTOR shall conduct all work in a professional manner, in accordance with traditionally recognized construction practices and techniques.

2. It is the CONTRACTOR’s responsibility to field verify all conditions and measurements provided in this statement of work. CONTRACTOR assumes full monetary responsibility for any and all additional work, materials, or equipment required to complete the project that was not included in the statement of work that a reasonable site inspection would have revealed. CONTRACTOR shall not be responsible for conditions that a reasonable site inspection would not have revealed.

2. CONTRACTOR is encouraged to develop, prepare, and submit Value Engineering Change Proposals (VECP’s) voluntarily. The Contractor shall share in any net acquisition savings realized from accepted VECP’s, in accordance with the incentive sharing rates in paragraph (f) of 52.248-1 in the FAR. If a VECP is accepted, the Contractor shall share in net acquisition savings of between 50 - 75 percent or as negotiated by KO and as described in the FAR.

2. CONTRACTOR shall pull all required state boiler permits and arrange a State of Ohio boiler inspection at time of completion prior to Pre-Final Inspection. The CONTRACTOR shall include any work required to obtain approval from the state boiler inspector in the cost of this proposal.

2. The CONTRACTOR shall complete a dd1354 break-out form for the work performed on project. The form must be completed satisfactorily and in a timely manner before the contractor’s invoice is processed for payment. Any questions from the contractor regarding completion of the form should be referred to the real property manager for assistance. Real Property Manager: Jordan Deady Email: jordan.t.deady.nfg@mail.mil phone: (937) 525-2586

0. STANDARD PRODUCTS

3. The KO must approve all material submittals prior to procurement. Materials substitution after submittal approvals shall not be allowed without review by the COR and approval by KO.

3. Materials such as sealants, adhesives, water-proofing or fire-proofing must comply with standards set forth by UL, ASTM, and IEC and listed for the specific use intended.

3. In the event of conflict among the Specifications, Drawings and/or Technical Instructions, the CONTRACTOR shall bring such conflict to the attention of the KO or COR for resolution before proceeding with the work involved.

3. Documentation shall be provided for each submittal. As a minimum, the documentation shall include a catalog sheet of the specific product and the product technical information. When required, a sample of the product/equipment or material must accompany the submission.

3. MSDS (Material Safety Data Sheet) shall be submitted for all chemical materials to be used for this SOW. Upon approval from the KO the CONTRACTOR shall store materials in accordance with Occupational Safety and Health Administration (OSHA) requirements.

0. SUBMITTALS

4. Material submittals are required unless approval from the KO has been granted otherwise. All Material Submittals, Design Drawings and Specifications are to be submitted to the KO with an Air Force Form 3000 (attached) for approval. Submittals, Drawings and Specifications shall be reviewed by the COR and approved by the KO prior to installing the approved material.

4. CONTRACTOR shall provide a detailed Project Schedule identifying milestone dates to KO and COR prior to issuance of NTP. A detailed Design and Construction Schedule in a CPM – Gantt style format shall be submitted for approval using Air Force Form 3064 (attached). If a change in the schedule is required, the CONTRACTOR shall resubmit the Progress Schedule for approval in both electronic and hard copy formats to the KO and COR.

4. CONTRACTOR shall provide Progress Reports submitted weekly to the COR using Air Force Form 3065 (attached). Progress Reports shall track the CONTRACTOR’s progress in relation to the approved Progress Schedule as well as assist in computing partial payments.

4. CONTRACTOR shall provide a list of names of all contracted personnel performing work on-base to COR using the Base Pass Information Required for Contractors template (attached) prior to issuance of NTP. List shall be submitted digitally in Word Format via email attachment or CD to COR.

4. CONTRACTOR shall provide a list of all chemical materials to be used on the project to the EM using Transient Organization Hazardous Material Inventory (attached) 30 days prior to use.

4. CONTRACTOR shall provide Material Safety Data Sheet (MSDS) with the Transient Organization Hazardous Material Inventory to COR 30 days prior to beginning construction. At the completion of the project, all unused hazardous materials must be removed from the installation by the CONTRACTOR. CONTRACTOR shall submit the total amount of materials used for the project to COR using the Transient Organization Hazardous Material Inventory Form.

4. CONTRACTOR shall track and report to COR the volume of solid waste (C & D) disposal and recycling costs incurred or fund received, disposal sites, and weigh tickets, using Post-Project Waste Diversion Report (attached) within 30 days from project completion-minimum 50% diversion.

4. CONTRACTOR shall abide by the Federal acquisition program for Green Procurement as outlined in USEPA Comprehensive Procurement Guideline website. CONTRACTOR shall provide a list of all recovered materials to the COR using Recovered Materials Determination Form & Recovered Materials Procurement Determination (attached) with the material submittals as outlined in 1.4.1.

0. PERMITS / CERTIFICATION

5. CONTRACTOR is responsible for obtaining all required base passes, dig permits, utility locates and all other permits required to complete the work described in this SOW.

5. CONTRACTOR must submit and obtain an approved dig permit from Ohio Utilities Protection Service (OUPS) prior to start of any site work. Permits request must be made 48 hours in advance by calling OUPS office at 1-800-362-2764. If damage or injury occurs from digging without a dig permit the CONTRACTOR shall be responsible for all repairs at no additional cost to the government. The CONTRACTOR shall keep a copy of approved dig permit on site at all times.

5. If total disturbed surface area of the project is greater than 1 acre CONTRACTOR must submit a Storm Water Pollution Prevention Plan (SWPPP) for approved by Clark County Engineer (30 day review process). CONTRACTOR shall then submit a Notice of Intent (NOI) to the Ohio Environmental Protection Agency (OEPA) 21 days prior to start of construction and receive the Director’s Authorization before construction begins. CONTRACTOR shall provide a copy of the NOI, Director’s Authorization, SWPPP, and SWPPP inspections to Environmental Management Office (EMO).

5. The CONTRACTOR shall obtain an Air Quality (EPA) permit from the Regional Air Pollution Control Agency (RAPCA) for Dayton, OH as required.

5. The CONTRACTOR shall employ and provide a licensed electrician prior to the start of any electrical work knowledgeable of the work and conforming to the requirements of the National Electrical Code (NEC). The licensed electrician must provide a current valid certification prior to the start of any electrical work.

0. QUALITY ASSURANCE / QUALITY CONTROL

6. The CONTRACTOR shall supply appropriate supervision and QA/QC for each task of the project to ensure the workmanship and product reflect the SOW and drawings. This project is commercial grade and only commercial type equipment and fixtures shall be accepted. The KO or COR may periodically perform QA checks as deemed necessary at any time during the PoP. These checks do not relieve the CONTRACTOR of the obligations under this section to provide a complete and working product.

0. PERSONNEL

7. CONTRACTOR shall identify a full time Superintendent who shall be responsible for all onsite activities. CONTRACTOR shall submit name(s) of Superintendent to KO and COR prior to issuance of NTP. The Superintendent shall have the authority to make in the field decisions (to be approved by COR), which may arise in day-to-day operations without delay that does not affect cost or scope of project.

7. CONTRACTOR is required to report this contract in the Contract Manpower Reporting Application.

7. The GOVERNMENT is not liable for any injury incurred by CONTRACTOR, CONTRACTOR personnel or other persons while they are on site. CONTRACTOR shall take full responsibility for the safety of all personnel within the project site.

7. The CONTRACTOR shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. The CONTRACTOR shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services, or local Security Office. The CONTRACTOR shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF, and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

7. CONTRACTOR and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation /facility access and local security policies and procedures (provided by government representative).

7. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities, and Controlled Access areas shall complete AT Level I awareness training within 30 calendar days after contract start date. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the KO. AT Level I Awareness Training is available at the following website: http://jko.jten.mil.

7. Violations of these policies may result in termination of the contract. Compliance with security requirements shall not be a basis for failing to complete work in the required period of performance.

7. CONTRACTOR shall recover base passes upon job completion and return to Government within five (5) days of Final Inspection.

0. ENVIROMENTAL AND SAFETY

8. CONTRACTOR is responsible for all costs incurred for clean-up, sampling analyses, and disposal of spill debris as a result of CONTRACTOR’S actions. CONTRACTOR shall report all spills to EMO. If appropriate, cost incurred for clean-up by the 178th WG for CONTRACTOR’S actions will be reimbursed to the 178th WG from CONTRACTOR.

8. CONTRACTOR shall ensure that all personnel receive Environmental Management System (EMS) Awareness training and a copy of the Base Environmental Policy. A copy of the training can be obtained from the 178th Base EMO.

8. CONTRACTOR shall abide by the Asbestos Notification Requirements as outlined on the OH EPA website. This includes notification of the OH EPA upon the disturbance of more than 260 LF of piping, 160 SF on other facility components, or 35 CF of contaminated material.

8. CONTRACTOR shall abide by the OH EPA Green Procurement Program as outlined on the USEPA website.

8. CONTRACTOR shall stop work and contact the 178th Base Environmental Management Office upon unearthing any historical or cultural artifacts during construction.

8. CONTRACTOR shall obtain all required permits and adhere to and abide by environmental requirements as stipulated by 178th Base EMO. This shall include but is not limited to the following forms:

0. Transient Organization Hazardous Material Inventory

0. Post-Project Waste Diversion Report

0. Recovered Materials Procurement Determination Form

0. Recovered Materials Determination Form

8. CONTRACTOR shall perform a jobsite cleanup each day and remove all debris and refuse from the site, to the satisfaction of the COR. Unoccupied areas to be broom swept daily. Occupied areas shall be kept free of dust and debris at all times.

8. CONTRACTOR shall ensure that employees are supplied and use proper safety equipment (i.e. gloves, safety boots) described in OSHA, EM 385 & EM 304 and follow safe work procedures, which protect CONTRACTOR employees and personnel in the vicinity of the job site in accordance with all current OSHA requirements. CONTRACTOR shall assume any liability for any injury incurred by CONTRACTOR personnel while working on site.

8. CONTRACTOR shall maintain awareness to all NATIONAL DISASTER RESPONSES including Lightning Watch / Lightning Warning / Hazmat Release / Severe Thunder Storm / Tornado Watch / Tornado Warning and shall:

1. Follow all Giant Voice Announcements as directed

1. Discontinue outside / inside work and seek shelter in designated shelter or building as directed

1. Follow directions from Shelter Manager or Senior Military Official

8. In case of base emergency, CONTRACTOR shall dial 911 then alert Base Security (BDOC) at 937-327-2221.

1. CONTRACT REQUIREMENTS

1. GENERAL WORK DESCRIPTION

0. Renovate facilities in accordance with drawings and specifications.

1. GOVERNMENT FURNISHED EQUIPMENT / PROPERTY

1. The GOVERNMENT shall provide basic/minimal documents describing the work required in this SOW. Drawings provided are to clearly identify know issues needing addressed. The CONTRACTOR shall be responsible to assess the job

1. The GOVERNMENT shall provide the CONTRACTOR access to the site to include all areas of work described in this SOW.

1. The GOVERNMENT shall provide no other equipment, services, or property.

1. PERIOD OF PERFORMANCE

2. CONTRACTOR shall have a maximum of 550 calendar days from the initial Notice to Proceed (NTP) to complete the project including any design and construction. Any changes or extensions to this time period need prior approval from the CONTRACTING OFFICER.

2. CONTRACTOR shall have access to the site from 7:00 am - 4:30 pm Monday - Friday. CONTRACTOR will not have access to the site on Weekends and Government Holidays unless approved by COR prior.

1. COMPLETION

3. The KO shall certify performance and final completion of this contract.

3. The CONTRACTOR shall restore any disturbed areas at the direction of the KO or the COR to include grading and reseeding using Truepointe Dura Turf seed (or approved equal) to prior site condition.

3. The CONTRACTOR shall schedule a Pre-Final Inspection with KO and COR 10 days prior to end of Period of performance. Any Punch List items will be identified and recorded at this time.

3. CONTRACTOR shall schedule a Final Inspection with KO and COR upon completion of Punch List and within 10 days of the Pre-Final Inspection. This inspection will confirm that all Punch List items have been corrected. Upon completion of the Final Inspection the GOVERNMENT shall take over ownership of the project.

1. REQUIRED WARRANTIES

4. The CONTRACTOR shall provide a 1-year warranty on all material, labor, installed equipment, and work performed in this SOW in addition to any manufacturer’s warranties.

1. DETAILED DESCRIPTION OF WORK

2. Construction and Safety practice

0. The CONTRACTOR will be required to photograph/document the existing site conditions prior to beginning work for record.

0. CONTRACTOR shall ensure that safe construction practices are used in accordance with current OSHA standards, EPA(RAPCA) requirements and base requirements. The Contractor shall submit a site safety plan prior to start of project. The Contractor shall maintain a clean job site at all times with daily clean-up.

0. CONTRACTOR shall field verify all measurements prior to execution.

0. CONTRACTOR shall provide all labor, material, and equipment to complete job as indicated in this Statement of work and Drawings.

0. The CONTRACTOR shall adhere to Ohio Building/Roofing Codes and Manufacturer installation requirements.

2. Renovation-Repair & Construction

1. Repair: Renovate Building 151 to house the 178th Communications Flight, Public Affairs to include Audio Visual, BCE Shops and Administration, and Emergency Management functions AND renovate Building 119 to house the Base Engineering Pavement Ground Facility. Renovate all of Building 151 to include reconfigured interior partitions to utilize open floor plan concept where feasible. Install communications equipment in Building 151 where required to support of the base’s comm system. Upgrade complete electrical systems, upgrade complete HVAC systems, replace windows, doors, rollup doors as required, all interior finishes including walls, demountable partitions, ceilings, and flooring to include raised flooring where required. Renovate Building 119 to include upgrading electrical systems and HVAC systems as necessary, replace all windows, doors, rollup doors as required, upgrade all interior finishes, ceilings, and floors where required. For Buildings 119 and 151 upgrade the exterior finishes including masonry, windows/frames, doors/frames and flashing as required. Modify existing parking lots as required.

1. Construction: Additions will be connected to Building 151 and the work shall include concrete foundation and slab, masonry walls, standing seam metal roof, fire protection, HVAC, and electrical. Interior construction will match Building 151 interior and will provide for office space. Building 151 will be altered to accommodate the addition. The site will be altered to accommodate the addition and includes paved access to roll up doors. Add lightning protection per Communication specifications. Air Conditioning: 20 Tons.

2. Warranty Requirements

2. The CONTRACTOR shall Supply the GOVERNMENT with a 1 year workmanship warranty from the date of completion.

1. CONTACT INFORMATION

3. POINT OF CONTACT

0. Contract Administrator: TSgt Samantha McKinney -- (937) 525-2575

(END SUMMARY OF WORK)