This document outlines requirements for interpretive exhibit fabrication and installation services at the Hoover Dam Visitor Center. The solicitation seeks proposals for design, fabrication, shipping and installation of new interpretive exhibits, including audiovisual components, artifacts, models, and interactive elements. Proposals are due within 60 days of the pre-construction conference, with work to be completed within 425 calendar days of award. The contractor will coordinate exhibit installation with ongoing building renovation work. The solicitation includes specifications for submittals, safety plans, progress reporting, coordination with other contractors, and on-site requirements.
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. 140R3022R0014
SECTION 00 01 00
TABLE OF CONTENTS
DIVISION 00 INTRODUCTION
SECTION 00 01 00 TABLE OF CONTENTS
SECTION 00 02 00 INTRODUCTION
DIVISION 01 GENERAL REQUIREMENTS
SECTION 01 11 00 SUMMARY OF WORK
SECTION 01 26 13 CONTRACTOR’S REQUEST FOR INFORMATION
SECTION 01 26 14 REQUEST FOR INFORMATION - FORM
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 32 26 CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 01 33 00 SUBMITTAL PROCEDURES
SECTION 01 35 10 SAFETY AND DATA SHEETS
SECTION 01 35 20 SAFETY AND HEALTH
SECTION 01 40 00 QUALITY REQUIREMENTS
SECTION 01 43 39 MOCKUPS REQUIREMENTS
SECTION 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
SECTION 01 60 00 PRODUCT AND MATERIAL REQUIREMENTS
SECTION 01 60 50 SUBSTITUTION AND COMPARABLE PRODUCT - REQUEST FORM
SECTION 01 73 00 EXECUTION REQUIREMENTS
SECTION 01 73 29 CUTTING AND PATCHING
SECTION 01 74 19 CONSTRUCTION WASTE MANAGEMENT
SECTION 01 77 00 CLOSEOUT PROCEDURES
SECTION 01 78 23 OPERATION AND MAINTENANCE MANUALS
SECTION 01 78 39 PROJECT RECORD DOCUMENTS
DIVISION 02 GRAPHICS
SECTION 02 03 00 GRAPHIC FABRICATION
DIVISION 03 DIGITAL MEDIA
SECTION 00 01 00
TABLE OF CONTENTS
SECTION 03 01 00 DIGITAL MEDIA - ACQUISITION AND USAGE RIGHTS
SECTION 03 02 00 DIGITAL MEDIA - PRODUCTION
SECTION 03 03 00 DIGITAL MEDIA - EQUIPMENT
DIVISION 04 LIGHTING
SECTION 04 01 00 EXHIBIT LIGHTING
DIVISION 05 ARTIFACTS, OBJECTS, DISPLAY CASES AND MOUNTS
SECTION 05 01 00 ARTIFACT MOUNTS
SECTION 05 02 00 DISPLAY CASES
DIVISION 06 SPECIAL CONSTRUCTIONS
SECTION 06 02 00 REPLICATED ENVIRONMENTS & DIORAMAS
SECTION 06 03 00 MECHANICAL/ELECTRICAL EXHIBITS
SECTION 06 04 00 MODELS
SECTION 06 06 00 REPLICAS
SECTION 06 07 00 PROPS AND SET DRESSING
SECTION 06 08 00 SCENIC MURALS
DIVISION 07 MATERIALS AND FINISHES
SECTION 07 01 00 WOODWORK
SECTION 07 02 00 METALWORK
SECTION 07 03 00 GLASS
SECTION 07 04 00 PLASTICS
SECTION 07 06 00 FINISHES
SECTION 07 07 00 FINISH HARDWARE
SECTION 07 08 00 FABRICS
SECTION 07 09 00 ADHESIVES
SECTION 01 11 00
SUMMARY OF WORK
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation
PART 1 - GENERAL
1.1 SUMMARY
A. The work includes, but is not limited to, the furnishing of labor, materials and equipment to fabricate, ship and install complete and functioning interpretive exhibits as described in the Contract Documents.
B. This section includes: Administrative and procedural requirements, including but not limited to:
1. Project information.
2. Work covered by Contract Documents.
3. Government-furnished.
4. Access to site.
5. Work restrictions.
6. Specification and drawing conventions.
7. Miscellaneous provisions.
8. Protected Species
1.2 RELATED DOCUMENTS
A. Requirements of Sections in Division 01 apply to the Work of all Sections in the Specification. Where a more specific requirement is provided within an individual section, that specific requirement takes precedence over the Division 01 general requirement for that individual section only.
1.3 PROJECT INFORMATION
A. Project: Interpretive Exhibit Fabrication and Installation Services.
B. Project Location: Hoover Dam, Boulder City, NV
SUMMARY OF WORK
C. Owner/Government:
Bureau of Reclamation, Lower Colorado Region Regional Office 500 Fir Street Boulder City, NV 89005
Government’s Representative: (Contract Specialist) Veronica Rodriguez Contract Specialist Office: 928-343-8266 Email: vrodriguez@usbr.gov
D. Contracting Officer’s Representative (COR)
E. Project Manager (PM)
F. Contractor (Exhibit Contractor)
G. Design Authority (Exhibit Designer)
H. Architect (Building)
I. General Contractor (Building)
J. Base Proposal: The proposal shall include labor, material, equipment, services and transportation necessary for the fabrication and install of the Project.
K. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
L. Use of Site:
1. Limits: Limit use of Project site to work in areas indicated. Do not disturb portions of the Project site beyond areas in which the Work is indicated.
1.4 PARTIAL GOVERNMENT OCCUPANCY
A. Government Limited Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, before Substantial Completion, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the total work.
SUMMARY OF WORK
1. CO/COR will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied before Government occupancy.
2. Obtain a Certificate of Occupancy from authorities having jurisdiction before Government occupancy.
3. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, the Government will provide, operate, and maintain mechanical and electrical systems serving occupied portions of the building.
4. On occupancy, the Government will assume responsibility for maintenance and custodial service for occupied portions of the building.
1.5 WARRANTIES
A. General: The warranty period for all products and systems, including installer warranties, shall commence at Substantial Completion of the final phase of construction, regardless of whether the warrantied item was installed in an earlier phase.
1.6 GOVERNMENT FURNISHED
A. Government Furnished:
1. The following items are noted as “Not in Contract” (NIC) and will be furnished by Government:
a. Photographic Images;
1) The Government will provide high-resolution digital scans for all images as specified by the Design Authority.
b. Film and Video Footage
1) The Government will provide high-resolution digital files per the technical requirements specified by the Contractor.
SUMMARY OF WORK
B. Government Furnished and Government Installed:
1. The following items are noted as “Not in Contract” (NIC) and will be furnished and installed by Government:
a. Artifacts
2. Government’s Responsibilities:
a. Government is responsible for the removal of all artifacts from existing exhibit, their care, conservation, safekeeping and installation in coordination and cooperation with the Contractor.
b. The Government will provide the Contractor with access to the artifacts for measurement.
3. Contractor’s Responsibilities:
a. The Contractor is responsible for the design, fabrication and installation of custom artifact mounts.
b. The Contractor is responsible to verify all measurements, including weight of each artifact so ensure the custom mounts are suitably fabricated and installed.
c. Provide Government with written notice stating date(s) when Government-furnished items must be received at the job site to ensure Project completion in accordance with established schedule. Such dates shall be shown on the schedule.
d. Contractor is responsible for the coordination and interface of Government- Furnished and Installed work with Work of this Contract to provide all required mechanical and electrical rough-ins, openings, supports, dimensions, etc., as required for a complete installation.
C. Government Furnished and Contractor Installed:
1. The Contractor will remove from the existing exhibit installation, refurbish and reinstall the following replicas and models:
a. 4.2.2 Concrete Pour - Concrete Bucket (Existing Replica)
SUMMARY OF WORK
b. 4.2.3 Construction Model (Existing Model)
c. 5.2.3 Turbine Model (Existing Model)
d. Refer to the Production Reference Document for information.
2. Government’s Responsibilities:
a. Supervise the site removal for the replica and models.
3. Contractor’s Responsibilities:
a. Provide Government with written notice stating date(s) when Contractor will be on site to remove the replica and models. Such dates shall be shown on the schedule.
b. After removal, inspect items for damage with the Government present.
1.7 NOT USED
1.8 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction. Coordinate any additional restrictions with CO/COR.
B. Non-Smoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.
C. Do not build fires on Project Site.
D. Do not allow weapons on Project Site, except those carried by law enforcement officers or other uniformed security personnel who have been retained by the Government to provide security services
E. Do not load or permit any part of the structure to be loaded with a weight that will endanger its safety. Questions of structural loading as part of construction means and methods shall be addressed by a licensed structural engineer engaged by Contractor, subject to the review by CO/COR.
SUMMARY OF WORK
F. Access to Site:
1. Hoover Dam is normally open to Visitor traffic from 5:00am to 9:00pm.
2. Contractor may request, through the COR, for Hoover Dam to adjust open periods to Visitor traffic for deliveries/work that cannot be scheduled between 9:00pm and 5:00am. The maximum delayed opening will be 7:30am and the earliest closure 6:30pm. Requests shall be submitted a minimum of two weeks in advance of the requested special hours event.
3. Contractor is not permitted to obstruct any roadway between the hours of 5:00am and 9:00pm without prior authorization from the COR. No lane closures shall be permitted after 8:00am and before 9:00pm or when the dam is closed to the public, whichever is later.
4. Contractor may request through the COR to close one lane of traffic up to 8:00am and after 6:00pm. Contractor is responsible for traffic control and traffic in both directions must be allowed through closure within 5 minutes or less.
5. Emergency vehicles must be allowed to pass freely at all times. Hoover Dam staff are onsite 24 hours per day and regardless of time vehicles shall not encounter delays greater than 5 minutes.
6. Around holidays lane closures between 5:00am and 9:00 pm may not be approved.
G. Contractor shall phase construction to allow for main tour Elevators E1 and E2 to remain in operation seven (7) days per week throughout construction.
1. Contractor shall coordinate closely with COR on access restrictions and alternate operations plans.
2. Elevators near restrooms providing service between Exhibit and Observation Levels shall remain accessible to the public to the maximum extent possible.
H. The Government will be issuing a separate contract for renovation of the visitor center simultaneous to this requirement. Therefore, the contractor shall be required to participate in regular coordination meetings with the Government and the General Contractor. Contractor shall work closely with Government and the General Contractor on all matters where work overlaps including scheduling, layout, access, potential installation conflicts, electrical and mechanical connections, and any other coordination activities throughout the period of performance of this contract.
SUMMARY OF WORK
1.9 CODES AND REGULATIONS
A. It is the intent of the Government that the Contract Documents are in accordance with applicable laws, statutes, building codes and regulations. Contractor shall notify CO/COR immediately if Contractor observes that the Contract Documents are at variance with this intent in any respect. Design Authority will make any necessary changes upon direction from CO/COR.
B. If the Contractor performs Work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the CO/COR and Government, the Contractor shall assume full responsibility therefore and shall bear attributable costs.
C. Government will coordinate deviations or waivers from applicable codes with the appropriate authority having jurisdiction.
1.10 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections.
1. Section Identification: The Specifications use Section numbers and titles to help cross-referencing in the Contract Documents. Consult the table of contents at the beginning of the Specification to determine numbers and names of Sections in the Contract Documents.
2. Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate.
SUMMARY OF WORK
Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by the Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
1.11 CONTRACT PERIOD
A. Work shall be completed within the time period indicated or as agreed upon with the Government.
B. Contract period is scheduled for no more than 425 calendar days from contract award.
Milestone schedule shall be coordinated with the contractor completing building renovation works. It is anticipated that the building renovation contract will be awarded approximately two weeks after award of this contract. It is further anticipated that construction will take approximately 180 days from NTP to include demo to a condition ready for exhibit installation. Total period of performance and anticipated milestones may require adjustment to optimize coordination between the two scopes of work.
1.12 PRODUCTS CONSTRUCTION PERIOD AND CONTRACTOR SCHEDULE
A. Mobilization to the Site will not be permitted until the following submittals (RSNs) have been provided by the Contractor and approved by the CO/COR:
1. RSN I-1; Proposed Schedule of Work (Bar Chart and/or Timeline)
a. Include: Tasks; Start/Finish Dates for Tasks; Project Completion Date, RSN I-3; Safety Program, including Site Specific Safety and Health Plan
2. RSN 01 14 10-1; Use of Site
B. Work Schedule
1. Contractor to determine work schedule required to accomplish work.
SUMMARY OF WORK
2. If the Contractor plans to work extended hours or multiple shifts, note this in the schedule so that Government inspection can be planned.
3. If the Contractor works at night, adequate temporary lighting must be provided to ensure a safe working area.
a. If the Contractor elects to work on holidays or weekends or nights, a request must be made to Reclamation at least 72 hours in advance so that Government inspection can be planned.
1.13 SECURITY REQUIREMENTS
A. Construction period for 180 days or more in a Federal facility.
1. A background investigation is required. See WBR 1452.237-80 Security Requirements – Bureau of Reclamation, Section I.13 of the clauses for additional information.
2. The Contractor shall submit the required documentation to complete the background investigation to include completion of the eQIP and enrolling for a PIV card.
3. The Contractor shall not allow employees to work on projects until they have received a favorable adjudication (cleared to work in Reclamation facilities) of their SAC from the LCB Region Personnel Security Specialist.
4. Contractors are permitted to work in Federal facilities while their background investigation is in progress; however, all Contractor personnel shall be escorted by a Federal employee, while waiting for their PIV Card and working in Federal facilities.
5. All Contractor employees shall display an orange "contractor no escort required" badge, while waiting for their PIV Card and working in Federal facilities.
6. All contractors not receiving a background investigation shall be escorted by a Federal employee at all times while working in Federal facilities. All contractors requiring an escort shall display a red “contractor escort required” badge at all times while working in Federal facilities.
7. All orange "contractor no escort required" badges, red "contractor escort required" badges and PIV cards shall be returned to the Contracting Officer Representative at the final closeout of the contract.
SUMMARY OF WORK
B. Construction Period for less than 180 days.
1. The Contractor shall be escorted by a PIV Card holder at all times while working on Reclamation property.
C. Responsibilities:
1. Protect work and existing facilities and Government's operations from unauthorized entry, theft, and vandalism.
2. Initiate a security program in coordination with Government's existing security procedures at job mobilization.
3. Maintain security throughout the construction period until acceptance of work by the CO or directed by the CO to terminate the security program.
D. Entry Control:
1. Protect work and operations from unauthorized entry, theft, and vandalism.
2. Restrict entrance of personnel into project site and existing facilities. Restrict entry to authorized persons with proper identification.
3. Maintain a continuous log of workmen and visitors and make available to the Government on request.
E. Contractor shall plan for night work and indicate in schedule when construction activities cannot be performed safely with public tours being conducted. The Visitor Center is open from 9:00am to 5:00pm daily.
F. Contractor shall comply with site use restrictions outlined herein scheduling deliveries, debris removal, and similar types of work that will impact traffic on the roadway or pedestrians.
1.14 ARCHITECTURAL BARRIERS ACT (ABA) ACCESSIBILITY STANDARDS
A. The ABA requires that facilities designed, built, altered, or leased with funds supplied by the United States Federal Government be accessible to the public.
SUMMARY OF WORK
B. The Contractor shall construct the facility to ensure accessibility as required by law for individuals with disabilities in accordance with the Architectural Barriers Act of 1968 (82 Stat. 718), as amended (42 U.S.C. 4151 et seq.), and the Rehabilitation Act of 1973, as amended (29 U.S.C. 794), including but not limited to Sections 504 and 508.
1.15 SUSTAINABILITY/ENVIRONMENTAL MANAGEMENT SYSTEM (SEMS)
CONTACTOR NOTIFICATION
A. The Bureau of Reclamation, Lower Colorado Region maintains a Sustainability/ Environmental Management System (SEMS) which aids in reducing environmental impacts of LCB operations by complying with applicable environmental laws, regulations, and directives.
1. Monitoring operational activities to ensure workplace practices conform to the Reclamation Environmental Policy, Directives and Standards, laws and regulations, set objectives, and targets.
2. Communication to employees, contractors, and the public as appropriate.
3. Fostering business practices for continual improvement and prevention of pollution throughout LCB.
B. The objectives include:
1. Energy and Water Conservation by evaluating opportunities to reduce energy and water usage and intensity.
2. Green procurement of raw materials, products, parts, and services wherever possible notwithstanding performance, cost, and schedule.
3. Greenhouse Gas Reduction by reducing fuel usage, energy usage, commuting, paper usage, electronic stewardship, and solid waste reduction.
1.16 DEFINITIONS
A. When specifications use a word or term defined in the Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.
SUMMARY OF WORK
1.17 ACRONYMS
A. The following acronyms apply to all divisions within this specification:
1. CO: Contracting Officer.
2. COR: Contracting Officer’s Representative
3. PM: Project Manager
1.18 PROTECTED SPECIES
A. Certain native species in the State of Nevada are protected plant or animal species under State law(s). The Government has ascertained that a variety of leopard frogs are protected species which do exist in the area to be disturbed by construction activities.
B. In accordance with State law, the Government may arrange for removal of protected species, and the Contractor shall cooperate with those performing such removal. If these species are not removed, cooperate with and abide by protection plans developed by appropriate State entities to avoid damage to or disturbance of protected species.
PART 2 - PRODUCTS
2.1 LIST OF EXHIBITS
A. The following table lists the individual exhibits that form the basis of this contract.
0. GENERAL
0.1 Audio Description
1. FLOWING WATERS
1.1 Lobby
1.1.1 Feature Wall
2. WHY WAS IT BUILT?
2.1 Introduction
2.1.1 Exhibit Introduction
2.2 Why Was it Built?
SUMMARY OF WORK
2.2.1 Harnessing the River
2.2.2 Hoover as Negotiator
3. MOBILIZATION
3.1 Passageway Experience
3.1.1 Passageway Experience
3.1.2 Passageway Immersive AV
3.1.3 Construction Audioscape
3.1.4 Joe McGee
4. HOW WAS IT BUILT?
4.1 Engineering Ingenuity
4.1.1 Six Companies
4.1.2 Pre-Construction/Diversion Tunnels
4.1.3 Design and Engineering Video
4.1.4 Design and Engineering
4.1.5 Design Materials and Finishes
4.1.6 Surveyor/Transit Views
4.2 Join the Crew
4.2.1 Prepping the Site/Highscalers
4.2.2 Concrete Pour
4.2.3 Construction Model
4.2.4 Construction Model Interactive
4.2.5 Dam Wall Timeline Projection
SUMMARY OF WORK
4.2.6 A Day on the Job
4.2.7 A Day on the Job Audio Stories
4.2.8 Rubble Wall and Dam Wall
4.3 From Ragtown to Boulder City
4.3.1 Ragtown
4.3.2 Ragtown Audio Stories
4.3.3 Boulder City
5. HOW DOES IT WORK?
5.1 Inner Workings
5.1.1 Inside the Dam
5.2 Water is Power
5.2.1 Turbine Photo-Op
5.2.2 Water Management
5.2.3 Turbine Model
5.3 Exit Displays
5.3.1 Exit Mural and Display Case
PART 3 - EXECUTION
3.1 NOT USED
END OF SECTION
SECTION 01 26 13
CONTRACTOR’S REQUEST FOR INFORMATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 26 13 - 1 Contractor’s Request for Information
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes: Administrative requirements for Request for Information.
1.2 DEFINITIONS
A. Request for Information: A document submitted by the Contractor requesting information or clarification of a portion of the Contract Documents that is required to properly perform the work, hereinafter referred to as an RFI.
1. Request shall clearly and concisely set forth the issue for which clarification or interpretation is sought and why a response is needed from the COR. In the RFI form the Contractor shall set forth their own interpretation or understanding of the requirement along with reasons why they have reached such an understanding.
B. Proper RFIs:
1. A properly prepared Request for Information shall include a detailed written statement that indicates the specific drawing or specification section in need of clarification and the nature of the clarification requested.
a. Drawing(s) shall be identified by drawing number and location on the drawing sheet.
b. Specification shall be identified by section number, page and paragraph.
1.3 RFI LOG
A. The Contractor shall prepare and maintain a log of RFIs. Upon request by the COR, the Contractor shall furnish copies of the log showing outstanding RFIs.
B. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly:
1. Project name
2. Name and address of Contractor
3. Name and address of Design Authority
CONTRACTOR’S REQUEST FOR INFORMATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 26 13 - 2 Contractor’s Request for Information
4. Name of COR
5. RFI number including RFIs that were dropped and not submitted
6. RFI description
7. Date the RFI was submitted
8. Date COR's response was received
9. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.
1.4 CONTRACTOR’S REQUEST FOR INFORMATION
A. Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
Contractor shall not collect or hold RFI’s. all together. All RFI’s must be submitted by the prime contractor to the COR.
Format:
1. RFI's shall be submitted on Document 01 26 14 included in the Project Manual or similar form approved by COR. An electronic version of Document 01 26 14 will be provided upon request.
2. Forms shall be completely filled in and shall be fully legible after transmission.
3. RFI’s shall be submitted in numerical order with no breaks in the consecutive numbering.
a. Subsequent RFI’s that request additional information or clarification from a previously submitted RFI shall be numbered with the original RFI number followed by “.1, .2, .3” so that related RFI’s can be identified. For example, if additional clarifications are required for RFI #96, the RFI shall be numbered “RFI #96.1, #96.2, #96.3 etc”.
4. Each page of attachments to RFI's shall bear the RFI number and shall be consecutively numbered in chronological order.
5. Submit RFI's via E-Mail in PDF format.
CONTRACTOR’S REQUEST FOR INFORMATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 26 13 - 3 Contractor’s Request for Information
a. Email Address: To be provided at a pre-construction meeting.
6. If the contractor has an urgent or critical RFI they should submit the RFI via email and inform the COR via phone call or text message as appropriate. BOR will make every effort to return the RFI as soon as possible.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of Design Authority
6. Name of COR
7. RFI number, numbered sequentially.
8. RFI subject.
9. Specification Section number and title and related paragraphs, as appropriate.
10. Drawing number and detail references, as appropriate.
11. Field dimensions and conditions, as appropriate.
12. Include Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
13. Contractor's signature.
14. Attachments: Include sketches, drawings, descriptions, measurements, photos, Product Data, Shop Drawings, and other information necessary to fully describe items.
CONTRACTOR’S REQUEST FOR INFORMATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 26 13 - 4 Contractor’s Request for Information
C. Contractor shall endeavor to keep the number of RFI's to a minimum. In the event that the process becomes unwieldy, in the opinion of the COR, because of the number and frequency of RFI's submitted, the COR may require the Contractor to abandon the process and submit future requests as either submittals, substitutions or requests for change.
D. Contractor shall endeavor to submit RFI’s to COR in a timely and regular manner and avoid submitting large quantities of RFI’s on a single day.
E. Contractor shall carefully study the Contract Documents to assure that the requested information is not available therein. RFIs which request information available in the Contract Documents will be deemed “frivolous” as defined herein.
F. In cases where RFIs are issued to request clarification of coordination issues, for example, pipe and duct routing, clearances, specific locations of work shown diagrammatically and similar items the Contractor shall fully lay out a suggested solution using drawings or sketches drawn to scale and submit same with the RFI.
RFIs which fail to include a suggested solution will be returned unanswered with a requirement that the Contractor submit a complete request.
G. RFIs shall not be used for the following purposes and will be returned without action:
1. To request approval of submittals.
2. To request approval of substitutions.
3. To request changes which entail additional cost or credit. If a response to RFI may have a cost impact, indicate this possibility where indicated on the form.
4. To request methods of performing work different than those shown or specified.
5. To request coordination information already indicated in the Contract Documents.
6. Requests for adjustments in the Contract Time or the Contract Sum.
7. Requests for interpretation of COR's actions on submittals.
8. Incomplete RFIs or RFIs with numerous errors shall be returned without action.
SECTION 01 26 14
REQUEST FOR INFORMATION - FORM
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 26 14 - 1 Request for Information - Form
Project: Hoover Dam Visitor Center R.F.I Number:
From:
To: Date: _________________________________
A/E Project Number: 043820001
Government Project Number:
Specification Section: Paragraph: Drawing Reference: Detail
Request:
* Requested Date/Time for Response:
Potential cost change related to this RFI: yes no
Signed by:
SECTION 01 26 14
REQUEST FOR INFORMATION - FORM
AldrichPears Associates
01 26 14 - 2 Request for Information - Form
Response:
Attachments
Response From: To: * Date Rec’d: * Date Ret’d:
Signed by:
Copies: __Government__ Consultants__ _________ __ _________ ___________ __ File
* Contractor shall allow up to 10 working days review and response time for RFI'S. (See Section 01 26 13 – Contractor’s Request for Information).
CONTRACTOR’S REQUEST FOR INFORMATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 26 13 - 5 Contractor’s Request for Information
1.5 COR’S RESPONSE TO RFIs
A. The COR is the only entity authorized to respond to RFI’s. An RFI response issued by any entity other than the COR is invalid and any actions taken in response to an invalid RFI are unauthorized.
B. Contractor shall allow 10 working days for the COR’s review and response time for RFIs, after receipt at COR’s office, however, the COR will endeavor to respond in less time. If additional time is required beyond the 10 working days allowed, the COR shall notify the Contractor in writing.
1. RFI shall state requested date/time for response, however, this requested date/time for response is not a guarantee that the RFI will be answered by that date/time if that date/time is too expeditious.
2. If review is required by multiple consultants, review and response period shall be 14 working days.
3. RFIs received after 1:00 p.m PT. will be considered as received the following working day.
C. COR will respond to properly prepared RFIs on one of the following forms:
1. Directly upon the RFI Form
2. Notice of Clarification (NOC)
3. Request for Proposal form.
D. At the COR’s discretion, Improper or frivolous RFIs may be returned with a notice that the information is already contained in the Construction Documents, or it is not the responsibility of the COR to provide.
E. The COR may opt to retain RFIs for discussion during regularly scheduled project meetings for inclusion of responses in meeting minutes in lieu of responding in written form.
F. Responses from the COR will not change any requirement of the Contract Documents.
In the event the Contractor believes that a response to a RFI will cause a change to the requirements of the Contract Documents, the Contractor shall immediately give written notice to the COR stating that the Contractor considers the response to be a Change Order. Failure to give written notice within 14 days shall waive the Contractor’s right to seek additional time or cost.
CONTRACTOR’S REQUEST FOR INFORMATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 26 13 - 6 Contractor’s Request for Information
1. Answered RFIs shall not be construed as approval to perform extra work.
G. On receipt of COR's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify COR within 5 working days if the Contractor disagrees with the response.
PART 2 - PRODUCTS
2.1 NOT USED
PART 3 - EXECUTION
3.1 NOT USED
SECTION 01 31 00
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 1 Project Management and Coordination
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes: Administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General project coordination procedures.
2. Conservation.
3. Coordination Drawings.
4. Administrative and supervisory personnel.
5. Project meetings.
1.2 COORDINATION
A. Coordination: Coordinate construction operations to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.
B. Prepare memorandum for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for COR and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 2 Project Management and Coordination
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
C. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.
D. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
2. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer for resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
3. Contracting Officer will furnish Contractor one set of digital data files of Drawings for use in preparing coordination digital data files.
a. Contracting Officer makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.
b. Contractor shall execute a data licensing agreement in the form of AIA Document C106 or similar.
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 3 Project Management and Coordination
4. Submittal Format: PDF
1.3 SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Use CSI Form 1.5A Subcontractors and Major Suppliers List or a similar form. Include the following information in tabular form:
1. Name, address, and telephone number of entities performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Staff Names: Submit a list of principal staff assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including emergency contact numbers. Provide names, addresses, and telephone numbers of individuals assigned as standbys in the absence of individuals assigned to Project.
1. Submit list a minimum of five (5) working days prior to mobilization to site.
2. Post copies of the list in the Project meeting room, in the temporary field office, and by each temporary telephone.
1.4 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
1. Notification: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify COR of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 4 Project Management and Coordination
3. Minutes: Contractor shall record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including COR, within 3 working days of the meeting.
4. Pre-construction Conference: Schedule and conduct a pre-construction conference before starting construction, at a time convenient to COR, but no later than 10 working days after execution of the Agreement. Hold the conference at the Project site or another convenient location. Conduct the meeting to review responsibilities and personnel assignments.
5. At a minimum attendees shall include:
a. COR
b. Design Authority
c. Architect
d. Contractor and its superintendent
e. Major subcontractors; manufacturers; suppliers; and other concerned parties.
f. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
6. Agenda: Discuss items of significance that could affect progress, including, but not limited to, the following:
a. Responsibilities and personnel assignments.
b. Tentative construction schedule.
c. Phasing.
d. Critical work sequencing and long lead items.
e. Designation of key personnel and their duties.
f. Lines of communications.
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 5 Project Management and Coordination
g. Use of web-based Project software.
h. Procedures for processing field decisions and Change Orders.
i. Procedures for RFIs.
j. Procedures for testing and inspecting.
k. Procedures for processing Applications for Payment.
l. Distribution of the Contract Documents.
m. Submittal procedures.
B. Pre-installation Conferences: Conduct a pre-installation conference at Project site to confirm exhibition areas are ready for the Contractor to take over. Meeting date and time shall be coordinated with COR.
1. At a minimum attendees shall include:
a. COR
b. Design Authority
c. General Contractor
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including, but not limited to, requirements for the following:
a. Exhibit Area Substantial Completion Punch List.
b. Deliveries.
c. Possible conflicts.
d. Time schedules.
e. Temporary facilities and controls.
f. Space and access limitations.
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 6 Project Management and Coordination
g. Regulations of authorities having jurisdiction.
h. Protection of construction and personnel.
i. Coordination with other work.
j. Protection of adjacent work.
3. Record significant conference discussions, agreements, and disagreements including required corrective measures and actions. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest possible date.
4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.
C. Pre-Progress Meeting: If requested by COR, conduct a pre-progress meeting prior to Progress Meeting.
1. Attendees: COR, Design Authority, Contractor, Architect and General Contractor.
D. Progress Meetings: Conduct progress meetings at weekly intervals. Coordinate dates of meetings with preparation of payment requests.
1. Attendees:
a. COR
b. Contractor
c. Design Authority
d. Architect
e. General Contractor
f. Each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 7 Project Management and Coordination
g. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to the Contractor's Construction Schedule.
Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
b. Review present and future needs of each entity present, including, but not limited to the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Work hours.
10) Hazards and risks.
11) Progress cleaning.
12) Quality and work standards.
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 8 Project Management and Coordination
13) Field observations.
14) RFI’s
15) Status of proposal requests.
16) Status of pending changes and Change Orders.
17) Quality and work standards.
18) Change Orders.
19) Documentation of information for payment requests.
3. Minutes: COR will record and distribute to Contractor meeting minutes.
4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present. Include a brief summary, in narrative form, of progress since the previous meeting and report.
a. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
E. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to COR.
1. Conduct the conference to review requirements and responsibilities related to Project closeout.
2. Attendees: COR, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of record documents.
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 9 Project Management and Coordination
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Submittal of written warranties.
d. Requirements for preparing operations and maintenance data.
e. Requirements for delivery of material samples, attic stock, and spare parts.
f. Requirements for demonstration and training.
g. Preparation of Contractor's punch list.
h. Procedures for processing Applications for Payment at Substantial Completion and for final payment.
i. Submittal procedures.
j. Coordination of separate contracts.
k. Government's partial occupancy requirements.
l. Installation of Government's furniture, fixtures, and equipment.
m. Responsibility for removing temporary facilities and controls.
4. Minutes: Entity conducting meetings will record and distribute meeting minutes.
1.5 DELAYS AND REQUESTS FOR EXTENSION OF TIME – SEVERE WEATHER
A. The determination for an extension of the Contract Time related to severe weather will be reviewed by the COR and make recommendation to the CO.
B. Time Extensions for Unusually Severe Weather:
1. If unusually severe weather conditions are the basis for a request for an extension of the Contract Time, such request shall be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the critical activities of the scheduled construction.
PROJECT MANAGEMENT AND COORDINATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 31 00 - 10 Project Management and Coordination
2. On days where adverse weather is encountered, the Contractor shall list all critical activities under progress and shall indicate the impact adverse weather had, if any, on the progress of such activities. This information must be presented at the end of the adverse weather day to the Contracting Officer or its authorized representative for its review and approval.
3. If Contractor is found eligible for an extension of the Contract Time, the Contracting Officer will issue a modification extending the time for Contract completion. The extension of time will be made on a calendar day basis.
C. Required Submittals:
1. Provide time-impact analysis that illustrates impact during update period in which event occurred, that event has been mitigated to greatest possible extent, and that event still impacts overall completion of Project.
2. Include with request, two copies of submittal of impacted schedule, in electronic format, and photocopies of all relevant documents that support the claim.
3. Submit all required items within the following time periods:
a. 10 working days of event occurrence.
b. 10 working days of Contractor's knowledge of impact.
c. 14 working days of written request by the Contracting Officer.
d. Expiration of time periods without submittal shall constitute forfeiture of rights for these specific impacts.
PART 2 - PRODUCTS
2.2 NOT USED
PART 3 - PRODUCTS
3.2 NOT USED
SECTION 01 32 26
CONSTRUCTION PROGRESS DOCUMENTATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 32 26 - 1 Construction Progress Documentation
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes: Administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Monthly Progress Reports.
3. Construction photographs.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the schedule of values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum unless otherwise approved by COR.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships.
Network calculations determine when activities can be performed and the critical path of the Project.
D. Critical Path: The longest continuous chain of activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Float: The measure of leeway in starting and completing an activity.
CONSTRUCTION PROGRESS DOCUMENTATION
AldrichPears Associates Hoover Dam Visitor Center Exhibit Level Interpretive Fabrication and Installation 01 32 26 - 2 Construction Progress Documentation
1. Float time is not for the exclusive use or benefit of either Government or Contractor, but is a jointly owned, expiring Project resource available to both…
This is the start of the file's text. The full file is on GovTribe.