Attachment_1_-_Specifications.pdf
PDF 6 MB Posted
- Solicitation number
- 140P1426R0013
About this file
This is a Project Specifications document for the Glacier National Park Polebridge Area Water System Rehabilitation project (PMIS No. 329234B), issued by the National Park Service in December 2025.
The project involves constructing a new public water system at the Polebridge Ranger Station Area in Glacier National Park's northwest corner, approximately 1.0 miles from Polebridge, Montana. Work consists of installing a new infiltration gallery drawing from Bowman Creek, a new water storage tank, water distribution mains and service lines to connect four housing units and two administrative buildings, a programmable logic controller, pump control panel, pump protection system, tank monitoring system, and fiber optic lines to five buildings. The existing chlorination treatment system remains in place. The project is divided into four contract line items (CLINs): Sub-CLIN 10.1 (Distribution System), Sub-CLIN 10.2 (Infiltration Gallery), Sub-CLIN 10.3 (Water Tank), Sub-CLIN 10.4 (Control System), and CLIN 20 (Fiber Optics), with payment based on percentage complete of contract lump sum price. Work phases are strictly scheduled: mobilization and vegetation clearing begin August 3, 2026; infiltration gallery and service line installation begins August 17, 2026; major disruptions to potable water service and tank installation occur after October 3, 2026; seasonal water service must be available by April 18, 2027; and substantial completion is required by June 21, 2027. The Contractor must manage all environmental protection, archaeological monitoring, safety compliance, waste management, stormwater pollution prevention, utility coordination with Montana 811, traffic control on park roads (including bridge weight restrictions of 57.0 tons on the North Fork Flathead River Bridge and 36.0 tons on the Bowman Creek Bridge), and coordination with NPS staff. Standard work hours are 7 a.m. to 6 p.m., Monday through Friday, with weekend or extended hours requiring advance written approval. All submittals require use of the NPS Transmittal Form (CM-16) and must be processed through the NPS management software website, with action submittals allowing 7 days for initial review and re-submittals.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GLACIER NATIONAL PARK
REHABILITATE THE POLEBRIDGE AREA WATER SYSTEM
PARK (GLAC)
PMIS NO. 329234B
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
December 2025
Docusign Envelope ID: A4A55C6B-41C5-847B-819C-34BB8635DA84
3/17/2026
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 01 00 SEAL PAGE
01 10 00 SUMMARY OF WORK
01 27 00 DEFINITION OF CONTRACT LINE ITEMS
01 31 00 PROJECT MANAGEMENT & COORDINATION
01 32 16 CONSTRUCTION SCHEDULE
01 32 33 PHOTOGRAPHIC DOCUMENTATION
01 33 23 SUBMITTAL PROCEDURES
SUBMITTAL TRANSMITTAL FORM
MATERIAL SUBMITTAL LIST
01 35 05 ENVIRONMENTAL PROTECTION…………………………………………………….
01 35 13.22 ARCHEOLOGICAL PROTECTION…………………………………………………….
01 35 23 SAFETY REQUIREMENTS
01 40 00 QUALITY REQUIREMENTS
01 43 33 ELECTRICAL TESTING
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 57 23 TEMPORARY STORM WATER POLLUTION PREVENTION
01 67 00 PRODUCT REQUIREMENTS
01 73 40 EXECUTION
RFI FORM
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PROJECT WASTE MANAGEMENT PLAN WORKSHEET
STANDARD SOLID WASTE CONVERSIONS
01 77 00 CLOSEOUT PROCEDURES
CLOSEOUT AND OPERATION & MAINTENANCE REQUIREMENTS………..
01 78 23 OPERATION AND MAINTENANCE DATA
01 79 00 DEMOSTRATION AND TESTING
DIVISION 02 – EXISTING CONDITIONS
02 41 16 STRUCTURE DEMOLITION
DIVISION 03 – CONCRETE
03 30 00 CAST IN PLACE CONCRETE
03 37 00 CONCRETE CURING
03 60 00 GROUTING
DIVISION 26 – ELECTRICAL
26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 29 13 MANUAL AND MAGNETIC MOTOR CONTROLLERS
DIVISION 27 – COMMUNICATION
27 13 23 COMMUNICATIONS FIBER OPTIC BACKBONE CABLING
DIVISION 31 – EARTHWORK
31 05 13 SOILS FOR EARTHWORK
31 05 16 AGGREGATES FOR EARTHWORK
31 10 00 SITE CLEARING
31 23 16 EXCAVATION
31 23 17 TRENCHING
31 23 18 ROCK REMOVAL
31 23 19 DEWATERING
31 23 23 FILL
31 23 24 FLOWABLE FILL
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 91 19.13 TOPSOIL PLACEMENT AND GRADING
DIVISION 33 – UTILITIES
33 05 17 PRECAST CONCRETE VALVE VAULT
33 14 13 BOWMAN CREEK INFILTRATION GALLERY
33 14 16 WATER DISTRIBUTION
33 14 17 TESTING OF WATER DISTRIBUTION
33 16 61 BURIED STORAGE TANK
33 16 61 STORM DRAIN PIPE
DIVISION 40 – PROCESS INTEGRATION
40 63 43 PLC
40 67 00 CONTROL SYSTEM EQUIPMENT PANELS AND RACKS
END OF INDEX
SECTION 01 11 00 - SUMMARY OF WORK
GLAC – 329234B
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. General Requirements
3. Attachments
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. All field work is located in the Polebridge Ranger Station Area, located in Glacier National Park’s northwest corner, approximately 1.0 miles from Polebridge, Montana.
B. Work generally consists of construction of a new public water system that includes a new infiltration gallery, new water storage tank, and new water main or service lines to service area buildings. Four housing units and two administrative buildings will be connected to the new potable water service.
A new programmable logic controller, pump control panel, pump protection system, and tank monitoring system will be installed. The chlorination treatment system will remain unchanged. Work also includes the installation of fiber optic lines to five buildings. Refer to the attached Civil Plans.
C. Refer to 01 27 00 Definition of Contract Line Items for a breakdown of Contract Line Items and how bid items are to be split out.
D. All work will be completed under a single prime contract.
1.3 GENERAL REQUIREMENTS
A. Wildlife Protection
1. Refer to Section 01 35 05 Environmental Protection and Special Controls.
B. Natural Resource Protection
1. Refer to Section 01 35 05 Environmental Protection and Special Controls for additional requirements.
a. Imported gravel, rip rap, rock, straw, and other natural materials must be certified weed-free and from a Park-approved source.
b. Vehicles and equipment shall be cleaned prior to entering the Park.
C. Archeological and Cultural Resource Protection
1. Refer to Section 01 35 13.22 Archeological Protection.
D. Visitor Management
1. Incorporate visitor management and traffic control precautions and procedures into the
Safety and Accident Prevention Plan.
a. The project area interacts with areas used by both visitors and NPS.
b. Visitors have access to the Ranger Station loop area, B#1842 Vault Toilet, the Inside
North Fork Road, and the Bowman Lake Road. The majority of traffic that enters the Park at the Polebridge Ranger Station turns north to visit Bowman Lake or Kintla Lake; traffic turning south towards Logging Creek is light. Expect to see moderate visitor vehicle and bicycle traffic on all roads. Visitation typically tails off in early October and is light in the late fall and winter months. The gate beyond the Ranger Station loop typically closes at the first notable snowfall and remains closed until late April, or whenever the roads are free of snow and dried out.
c. Approximately eight NPS employees live and work in the Polebridge housing and maintenance areas. Approximately seven other NPS employees (stationed at Kintla, Bowman, or Logging) use the housing and maintenance areas regularly. All but two employees are seasonal employees and will depart between mid-September to mid- October.
d. Take great caution while operating equipment to prevent hazards to visitors and
NPS.
2. The Contractor is responsible for jobsite safety and security. The Contractor shall secure the jobsite to prevent any potential hazards to visitors and NPS staff at all times.
3. Minimize interference with NPS operations, visitors, and traffic near the project area.
Coordinate with NPS.
E. Contractor Access to Park and Facilities
1. The Park does not provide lodging or campsites to Contractors. The Contractor shall not set up undesignated camps at (or near) the project site. The Contractor is responsible for arranging their own accommodations.
2. Coordinate with the COR for to obtain a Commercial Vehicle Non-Recreational Entrance Pass. An Entrance Pass is required to be displayed on the dashboard of all Contractor vehicles. Come to a full stop at the Entrance Station, show the Entrance Pass to the Park Ranger at the window, and they will wave you through. Entrance Passes are of no cost to the Contractor.
a. The Entrance Pass will be valid for entering the Park at the West Entrance (in West Glacier), Camas Entrance (Camas Road), and the Polebridge Entrance (Polebridge).
3. Coordinate with the COR for access to gates and buildings. The Contractor shall be responsible for safekeeping any loaned keys. The Contractor shall pay to replace lost or damaged keys.
4. Generally, work inside of Park buildings shall be supervised by NPS. Coordinate with NPS.
F. Contractor Use of Utilities
1. Refer to Section 01 50 00 Temporary Facilities and Controls for additional requirements.
2. Utility Access
a. No Contractor access to electrical service. Bring generators.
b. No Contractor access to telephone or internet service. Polebridge is far from cell service. The Park will loan a few portable radios for emergency use.
c. The Contractor may use the potable water service from the Polebridge water system at a rate of $20.936 per 1000 gallons. The Contractor may also obtain water from a fire hydrant in the West Glacier Headquarters area. Refer to Section 01 50 00 Temporary Facilities and Controls for additional requirements.
d. Surface water may be drafted from Bowman Creek. Refer to Section 01 35 05 - Environmental Protection and Special Controls and Section 01 50 00 Temporary Facilities and Controls for additional requirements.
e. The Contractor may use B#1842 Vault Toilet located in the Maintenance Area through the end of October 2026, on the condition that this facility is kept reasonably clean for visitor and NPS use. Sweep out mud and clean up messes immediately.
During the winter, NPS has limited staffing and no practical method to pump out the vault toilet. The Contractor shall use portable toilets for work in the winter months.
Vault toilets must be lockable to prevent wildlife access, firmly secured to the ground to prevent tipping, and maintained regularly. Refer to Section 01 35 05 - Environmental Protection and Special Controls for additional requirements.
3. Utility Marking
a. The Contractor shall notify NPS of any ground disturbing work at least 10 business days in advance. Call Montana 811 at least five business days in advance of anticipated ground disturbance. The Contractor shall not proceed with any ground-disturbing work until explicit permission is granted by the COR after all NPS and outside utilities have been marked.
b. If ground disturbance is imminent in only a portion of the project area, the Contractor shall provide NPS with a map of the exact locations where utility markings are needed.
c. The Contractor shall ensure that all utilities are properly marked for the duration of ground disturbing work.
d. The Contractor shall verify the location of underground utilities prior to excavation work. Some utilities may only be locatable by potholing.
e. All existing utilities shall be protected in place by the Contractor; accidental damage or disruptions shall be remedied immediately at no cost to NPS.
4. Water System Testing and Winterization
a. Water service connections and main line installation will occur while the Polebridge area buildings are in “winter status.”
1) B#97 Ranger Residence and B#1451 Strissel Cabin are the only buildings that have year-round water service, under normal circumstances. B#1448 Fire Cache, Ranger Storage, Chlorinator has no domestic water service, but the chlorination equipment operates year-round.
2) B#98 Cabin, B#1454 Laundry and Shower, B#1455 Polebridge Ranger Station, B#1594 Dorm, and B#1865 School to Park Cabin have seasonal water service only. A new yard hydrant will used seasonally.
a) NPS will winterize the interior fixtures of these buildings.
b) The Contractor shall drain the water main or service lines to be abandoned or removed, remove the existing water service, make the new water service connection, test the new water lines and fixtures per Section 33 01 12 Testing of Water Distribution, and then fully remove all water from the service lines, main lines, and fixtures that are typically winterized.
G. Contractor Use of Site
1. Refer to the Civil Plans, Section 01 35 05 Environmental Protection and Special Controls, and Section 01 50 00 Temporary Facilities and Controls
H. Vehicles, Equipment, Parking, and Staging Areas
1. Refer to the Civil Plans and Staging Areas Exhibit for project limits and staging areas.
2. Vehicles and equipment shall be cleaned and inspected by NPS prior to entering the Park.
Refer to Section 01 35 05 Environmental Protection and Special Controls for additional details.
3. All project vehicles shall be driven at speeds within posted speed limits on existing roads and shall not exceed 20 mph within project boundaries.
4. Hauling vehicles greater than 20,000 gross vehicle weight travelling on approved roads within the Park between sunset and sunrise will be limited to speeds of no more than 10 miles per hour (mph) below the posted speed limit.
5. Comply with all local, State, and Federal loading, hauling, and road restrictions.
a. Hauling on Camas Road is not permitted. All hauling traffic should take the North
Fork Road to Polebridge.
6. Access to the project areas requires use of the following bridges:
a. North Fork Flathead River Bridge, Glacier Drive
1) Inventory Rating – 34.0 tons
2) Operating Rating – 57.0 tons
b. Bowman Creek Bridge, Inside North Fork Road
1) Inventory Rating – 21.0 tons
2) Operating Rating – 36.0 tons
c. Submit overload and oversize permits for non-legal loads transported within the park boundary to the CO utilizing the FLH Bridge Oversized or overload vehicle permit request form. The Government will make the form available under FAR Clause 52.236-4 – Physical Data. Allow 14 days for review of the permit application.
I. Material Handling and Waste
1. Refer to the Civil Plans, Section 01 35 05 Environmental Protection and Special Controls, 01 74 19 Construction Waste Management and Disposal for additional requirements.
2. The Contractor shall be present to inspect and accept all deliveries. On-site drop off locations may be arranged. NPS will not accept deliveries on the Contractor’s behalf – do not ship to an NPS building.
3. All waste must be immediately contained in bear-proof containers or dumpsters. Food waste and construction waste shall not be mixed.
J. Quality Control
1. Refer to 01 40 00 Quality Requirements for additional requirements.
2. All work shall be high quality, professional work. The work performed by each trade shall meet or exceed all quality standards published by their respective trades.
3. Where trades overlap, carefully coordinate work.
K. Safety and Accident Prevention
1. Refer to Section 01 35 05 Environmental Protection and Special Controls and Section 01
35 23 Safety Requirements.
L. Fire Prevention and Protection
1. Refer to Section 01 50 00 Temporary Facilities and Controls for additional requirements.
2. Should the Park enter Stage 2 Fire Restrictions during the period of performance, the contractor may be required to obtain a Stage 2 Fire Restriction Exemption Permit from the GLAC Fire Management Office. Additional firefighting tools may be required to be readily available during work.
M. Weather and Snow
1. Road Access
a. Polebridge is accessible year-round via the North Fork Road through Columbia Falls, MT. Expect the North Fork Road to be icy, bumpy, and slow-moving during the winter months. Travelers must be prepared.
b. Polebridge is accessible from West Glacier, MT via Camas Road until the first significant snowfall, typically in November or December, forces a closure of Camas Road.
2. Snow
a. The Inside North Fork Road or Bowman Lake Road are not plowed by NPS. These roads typically close to visitor vehicle traffic at the first significant snowfall and will not open until April or May, or whenever the roads are free of snow and dried out.
b. NPS typically plows snow around the Ranger Station loop, Maintenance Area, and Housing Area. Please coordinate with NPS on the location of snow piles to avoid interference with work.
c. Please note that snow removal performed by NPS may not be immediate – the Contractor may have to remove snow to continue working in an area.
3. Rain and Creek Flows
a. October and November can be extremely wet months. Expect a sharp increase in the flow of Bowman Creek in October. Bowman Creek flows year-round.
N. Work Phases, Anticipated Timelines, and Work Schedules
1. The following work shall be allowed in each timeframe:
a. Beginning on or later than August 3, 2026:
1) Mobilization
2) Vegetation clearing (note – please coordinate with NPS to survey the area for nesting birds prior to any vegetation clearing)
3) Installation of temporary erosion control measures
4) Work in the Chlorination Room of B#1448 Fire Cache, Storage, and
Chlorinator Building that can be performed without interrupting the existing water system’s operation
b. Beginning on or later than August 17, 2026:
1) Installation of the new infiltration gallery; disturbed area restoration work.
2) Installation of water supply, main, and service lines in housing and maintenance areas and up the hill to the Inside North Fork Road; disturbed area restoration work.
3) Electrical and communications related work in the housing and maintenance areas.
c. Beginning on or later than October 3, 2026:
1) Disruption of potable water service to all buildings served by the existing system, including demolition of existing water system infrastructure.
2) Water tank installation work; disturbed area restoration.
a) The Contractor may close the Inside North Fork Road from B#1455
Ranger Station heading south towards Logging Creek for this work.
The Contractor shall allow emergency vehicle traffic to pass through immediately, and other administrative traffic to pass through with a delay.
3) Installation of water supply, main, and distribution between the new water infiltration gallery, in front of B#1455 Ranger Station, and to B#1448 Fire Cache, Storage, and Chlorinator Building; road restoration work.
a) NPS will not collect fees at the window of B#1455 Ranger Station during this time.
b) Phase trenching work and set up temporary traffic control such that vehicle access to the Inside North Fork Road is available at all times.
The Contractor shall close one side of the loop around B#1455 Ranger Station and allow two-way traffic to pass through the other side of the loop to allow vehicle traffic to and from the Inside North Fork Road.
A maximum 15-minute traffic delay will be allowed. The Contractor shall allow emergency vehicle traffic to pass through immediately.
c) The Contractor should complete this trenching work in 10 working days or less. Coordinate with NPS at least two weeks prior to the anticipated closure.
4) Installation of water main lines, electrical lines, and communications lines along the Inside North Fork Road
a) This work requires a full closure of the Inside North Fork Road to all visitor and NPS vehicle traffic between the Ranger Station Area and the water tank area. NPS will stage a vehicle to the south of the water tank area and will access the vehicle by foot, if necessary. Please coordinate with NPS.
b) The Contractor should complete this trenching work in 10 working days or less. Coordinate with NPS at least two weeks prior to the anticipated closure.
c) Handhole installation work and road restoration work may be completed outside of this 10 working day trenching window, provided that the road is passable to NPS administrative traffic. A maximum 15-minute traffic delay will be allowed for road restoration work. The Contractor shall allow emergency vehicle traffic to pass through immediately.
d. No later than April 18, 2026:
1) Water service available for seasonal housing units (note – this date may be later in April or early May based on the move-in dates of 2026 seasonal employees).
di. Approximately May 1, 2026
1) North Fork area roads typically open to visitor vehicle traffic in early May, depending on weather and road conditions. Work in front of B#1455 Ranger Station and all road restoration work on the Inside North Fork Road shall be completed by early May.
dii. No later than May 14, 2027:
1) Potable water service to the Ranger Station shall be available by May 16, 2027.
diii. No later than June 21, 2027:
1) Substantial completion for all work.
2. Potable water is required to support the following NPS permanent residences, seasonal residences, and administrative buildings.
Only two buildings, B#97 Ranger Residence and B#1451 Strissel Cabin, have potable water service year-round under normal circumstances. After the October 3, 2026 date at which the Contractor is allowed to interrupt potable water service to all buildings, NPS Law Enforcement personnel will likely occupy these residences during their regularly scheduled work days, but not on their off days. NPS personnel will bring their own potable water jugs while potable water service is not available.
The Contractor should prioritize restoring potable water service to B#97 Ranger Residence and B#1451 Strissel Cabin for the convenience of NPS. Please seek to restore potable water service to these buildings in less than 60 days.
For seasonal residences, the 2026 Potable Water Close Date is the latest planned date for 2026 seasonal employees to move out; the 2027 Potable Water Open Date is the earliest expected date for 2027 seasonal employees to move in. These dates may vary slightly; coordinate with NPS.
Building Type 2026 Potable Water
Close Date 2027 Potable Water
Open Date B#97 Ranger Residence
Permanent Residence
Year-Round Use; potable water supply may be interrupted after October 3, 2026. The
Contractor should prioritize restoring potable water service in less than 60 days.
B#98 Cabin Seasonal Residence
No later than October 3, 2026
April 18, 2027 (anticipated)
B#1451 Strissel Cabin
Permanent Residence
Year-Round Use; potable water supply may be interrupted after October 3, 2026. The
Contractor should prioritize restoring potable water service in less than 60 days.
B#1454 Laundry and Shower
Administrative
No later than October 3, 2026
April 18, 2027 (anticipated)
B#1455 Ranger Station
Administrative September 8, 2026 May 14, 2027
B#1594 Dorm Seasonal Residence
No later than October 3, 2026
April 18, 2027 (anticipated)
B#1865 School to Park Cabin
Seasonal Residence
April 18, 2027 (anticipated)
3. Work shall generally be performed from 7 am to 6 pm, Monday to Friday. If the Contractor desires to work outside of these hours or on weekends and holidays, the Contractor shall submit a written narrative that outlines the work to be performed to the CO and COR for their approval at least two business days in advance of the anticipated work.
1.4 ATTACHMENTS
1. Civil Plans
2. Project Specifications
3. Polebridge Ranger Station Land Survey
4. Geotechnical Report
5. Site Photos
6. As-Built Drawings (1980, 1989, 1996, 2001, 2007)
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. This section explains, in general, how bidders shall break their prices out into separate work items to allow NPS to evaluate bid prices.
B. Measurement for payment will be based on percentage complete of items included in an approved schedule of values for these items.
C. Progressive payments will be made based on percent complete of the contract lump sum price.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. CLIN 10: Water System Improvements. Provide a price for each of the following Sub-CLIN items associated with CLIN 1.
1. Sub-CLIN 10.1 - Distribution System
a. This sub-item consists of construction of the following items:
1) All trench excavation, shoring, dewatering, pipe bedding, flowable fill, water pipes, tracer wire, detectable warning tape, foam insulation, trench backfilling, and related work.
2) All fittings, valves, curb stops, fire hydrants, blowoff hydrants, yard hydrants, low point drains, and related appurtenances throughout the project area.
3) All conduit, wiring, and handholes for the water control system between the infiltration gallery, Chlorination Room, and water tank.
4) Testing, disinfection, means for flushing and bleeding air from the water lines.
5) Existing pipe, curb stop, fire hydrant, valve, and related demolition work.
6) All gravel road restoration work.
7) All landscaped or vegetated area restoration work.
8) Temporary facilities including traffic control.
9) All mobilization, materials, tools, equipment, labor, and performance of all work necessary or incidental for the completion of this item.
2. Sub-CLIN 10.2: Infiltration Gallery
a. This item consists of construction of the following items:
1) All demolition of the existing infiltration gallery, valve vault, electrical breaker, tree removals, vegetation removals, and related removals work near the infiltration gallery.
2) All excavation, shoring, dewatering, bedding, and backfilling related work at the infiltration gallery.
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
3) All infiltration gallery casement pipe, infiltration pipe, geotextile fabric, and similar work.
4) All area restoration work.
5) All mobilization, materials, tools, equipment, labor, and performance of all work necessary or incidental for the completion of this item.
3. Sub-CLIN 10.3: Water Tank
a. This item consists of construction of the following items:
1) All existing water tank demolition work.
2) All excavation, shoring, dewatering, bedding, and backfilling related work.
3) All water tank installation related work.
4) All water tank overflow and drain line related work.
5) All mobilization, materials, tools, equipment, labor, and performance of all work necessary or incidental for the completion of this item.
4. Sub-CLIN 10.4: Control System
a. This item consists of construction of the following items:
1) Demolition of existing system controls inside of B#1448 Fire Cache, Storage, and Chlorination Building.
2) Replacement of the propane heater in the Chlorination Room.
3) All pump control panel, pump protection system, programmable logic controller, and hypochlorite feed pump related work.
4) All mobilization, materials, tools, equipment, labor, and performance of all work necessary or incidental for the completion of this item.
B. CLIN 20: Fiber Optics
1. This item consists of construction of the following items:
a. Material and installation costs of conduit, fiber optic cable, and detectable warning tape.
1) Where the fiber optic conduit is placed in the same trench as water lines, exclude trench excavation, bedding, backfilling, and handhole related work from CLIN 2 – the cost of this work should be included in CLIN 1.
2) Where the fiber optic conduit is not placed in the same trench as water lines, include the cost of trench excavation, bedding, backfilling, and restoration work in CLIN 2.
b. All fiber optic building connection related work.
c. All mobilization, materials, tools, equipment, labor, and performance of all work necessary or incidental for the completion of this item.
END OF SECTION 01 27 00
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Requests for Information (RFIs)
5. Project Meetings
6. Environmental Coordination
7. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 35 05 “Environmental Protection and Special Controls” for coordinating environmental requirements of the Contract.
3. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
4. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
5. Section 01 79 00 “Demonstration and Training” for coordinating training requirements for
Government staff on new equipment.
1.2 DEFINITIONS
A. Agency with Jurisdiction
B. Construction Permits – Contractor Provided
C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Refer to 01 40 00 “Quality Requirements”.
2. Provide Method of Procedure for all outages and coordination with NPS; provide step-by-step procedure, timelines, and critical involvement required by Contractor and NPS.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.4 SUBMITTALS
A. Division 1 documents:
1. Letter designating Project Superintendent
2. Construction Schedule
3. Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses
7. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Temporary Storm Water Pollution Prevention Plan (SWPPP)
11. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
B. Provide items listed to Contracting Officer at least one week prior to Pre-Construction
Conference, or as directed by Contracting Officer.
1. Failure to submit items may result in:
a. Construction conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies.
b. Work shall not commence until written Notice to Proceed has been issued and
Certificates of Insurance and SF1413 documents are received for Contractor and all
Subcontractors.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of
Contract Documents, Contractor shall prepare and submit an RFI to the Contracting Officer.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
2. Contracting Officer's action on RFIs may result in need for a change to Contract Time or
Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange a meeting with Contractor. The meeting agenda will include the following, at minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Coordination of Subcontractors
5. Labor law application
6. Modifications
7. Payments to Contractor
8. Payroll reports
9. Notice to proceed
10. Correspondence procedures
11. NPS/DSC Project website
12. Acceptance/rejection of work
13. Progress meetings
14. Submittal procedures
15. Environmental requirements
16. Permit requirements
17. As-constructed drawings/operation and maintenance (O&M) manuals.
18. Saturday, Sunday, holiday, and night work.
19. Reference materials
20. Value engineering
21. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the
Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Submittal status
b. Review of off-site fabrication and delivery schedules.
c. Requests for information (RFI) and other issues.
d. Modifications
e. Work in progress and projected.
f. Inspections of work in progress and projected
g. Construction Schedule update
h. Status of Project Record Drawings and O&M manuals
i. Other business relating to work
j. Permit requirements
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing
Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection. The Environmental Manager may be the same person as the Site
Superintendent or Quality Control Manager.
1. Qualifications: Minimum 3 years construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Implementation of the project specific elements in the NEPA. See Section 01 35 35
“Environmental Protection and Controls” for a copy of the NEPA.
b. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
c. Implementation of Waste Management Plan (WMP).
d. Implementation of Storm Water Pollution Prevention Plan (SWPPP).
e. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
f. Training for Contractor personnel in accordance with position requirements.
g. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Temporary Storm Water Pollution Prevention Environmental Management
4. Construction Waste Management
C. Contractor’s Environmental Training: Contractor shall provide environmental training for workers performing work on the project site. Training shall include:
1. Overview of environmental issues related to Project.
2. Review of site-specific procedures and management plans:
a. Wildlife Safety in accordance with trainings provided by the Park
b. Construction Waste Management
c. Temporary Storm Water Pollution Prevention
1.8 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the
Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the
Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. MT DEQ, Permit to Construct. No additional terms and conditions outside of these construction documents.
C. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist
Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work.
1. Stormwater Pollution Prevention Permit (SWPPP) – EPA
a. Developing a Stormwater Pollution Prevention Plan (SWPPP) | US EPA
2. MT DEQ Permits
a. (Water Permitting and Operator Assistance | Montana DEQ)
1) Stormwater Pollution Prevention Plan – MT DEQ (Must submit SWPPP to both agencies.)
2) Construction Dewatering Permit – MT DEQ
3. Oversize/Overweight Transportation Permit – Montana Dept of Transportation
a. Online Permits & Licenses | Montana Department of Transportation (MDT)
4. Well Construction/Abandonment Notification – MT DEQ
D. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
E. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
3. Upload permits to NPS/DSC management software website when permits are obtained.
END OF SECTION 01 31 00
https://www.epa.gov/npdes/developing-stormwater-pollution-prevention-plan-swppp https://deq.mt.gov/water/assistance https://www.mdt.mt.gov/business/permits.aspx
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
GLAC 329234B
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Construction Schedule
2. Construction Schedule Updates
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and
Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section
1.2 SUBMITTALS
A. Construction Schedule: After contract award and before Pre-Construction conference, submit a copy of the construction schedule using a Gantt Chart or similar methodology. List all major construction items. Note long lead time items, schedule restrictions, closures, and utility interruptions.
B. Three-Week Look Ahead: Prior to every regular construction progress meeting, provide a Three-
Week Look Ahead Schedule to provide the anticipated schedule of activities. Note closures, utility interruptions, and when the Contractor needs access to NPS facilities.
C. Construction Schedule Updates: If there are major revisions to the Construction Schedule, provide an updated schedule that includes revised dates for all remaining work items.
END OF SECTION 01 32 16
SECTION 01 32 33 – PHOTO DOCUMENTATION
01 32 33 - 1
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for:
1. Existing condition images
2. Periodic construction images
B. See Section 01 77 00 "Closeout Procedures" for a complete listing of closeout documents.
1.2 SUBMITTALS
A. Construction Images: Submit images electronically within 14 days of taking the image. Include:
1. Date, time, and number (sequentially number all images).
2. Description of vantage point, indicating location, direction.
3. Submit digital images exactly as originally recorded in digital camera, without alteration.
B. Closeout: Submit complete set of digital image electronic files as a Project Record Document.
1. Provide a .zip file containing all project photos. List each image as a file name with number, date, and time. Include description and or vantage point image was taken.
2. Submit images that have the same aspect ratio as the sensor, un-cropped.
PART 2 - EXECUTION
2.1 CONSTRUCTION IMAGES
A. General: Take digital images using the maximum range of depth of field, in-focus, to clearly show the Work. No blurry or out-of-focus areas accepted.
1. Maintain one set of images accessible in field office at Project site available for reference.
B. Existing Condition Images: Before starting construction, take color digital images of Project site and surrounding properties, including existing items to remain during construction, from different vantage points.
1. Flag construction limits before recording construction images.
2. Take images to show existing conditions adjacent to property before starting Work as follows:
a. Images every 50 feet along pipeline alignments to capture both sides of the alignment.
b. Images of every existing visible appurtenance (i.e. hydrant, meter pit, vault)
c. Images of existing surface features, hardscapes, surface improvements or construction obstructions.
d. Images of existing buildings adjacent to or affected by construction.
SECTION 01 32 33 – PHOTO DOCUMENTATION
01 32 33 - 2
e. Images of facilities proposed for demolition or modifications, from all sides.
f. Images of areas proposed for new facility construction (wells, buildings, appurtenances, tanks, etc.)
C. Periodic Construction Images: Take a minimum of 25 color, digital images weekly, 5 per day per work area. Select vantage points to show the status of construction and progress since the last images were taken.
D. Additional Images: Contracting Officer may issue requests for additional images.
1. Three days advance, where feasible.
2. In emergency situations, take additional images within 24 hours of request.
3. Circumstances that could require additional images include, but are not limited to:
a. Immediate follow-up when on-site events result in construction damage or losses.
b. Fabrication locations away from Project site.
END OF SECTION 01 32 33
C
ER
T.
/L
A B
T
ES
T
R
EP
O R
T/ C
A
LC
O
R P
LA
N
M fg
. D A
TA
IN
ST
R U
C
TI
O N
S
PE
R
M
IT
S
SH
O
P D
R A
W
IN
G
SA
M
PL
E
M fg
. D A
TA
IN
ST
R U
C
TI
O N
S
FI
EL
D
R
EP
O R
TS
Letter designating Project Superintendent X
Construction Schedule X
Schedule of Values X
Accident Prevention Plan X
List of Subcontractors for this Project X
Written Statements from Sub Certifying Compliance X
Certificates of Insurance for Contractor and Subs X
Waste Management Plan X
Quality Control Plan X
SWPPP and Permit X
01 32 33 1.3 Pre-construction & Pre-demolition Videos (digitals) X
01 35 05 1.3 Spill Prevention and Response Plan X
Quality Control Plan X
Qualification Data X
Contractor's Quality Control Daily Reports X
Test Reports X
Off-Site Inspection Reports X
Permits, Licenses and Certificates X X
01 43 33 1.03 Testing Forms X
SWPPP and Permit X
Inspection Schedule X
Erosion Control Products X
Environmental Data (for specified products) X
MSDS's Sheet (only for products listed in this Section) X
Chain of Custody (only for products listed in this Section) X
01 74 19 1.2 Waste Management Plan and required submittals X
01 78 23 1.3 O and M Manual X
Proposed Protection Measures X
Schedule of Demolition Activities X
Pre-demolition Video X
Detail and Descriptions of Temporary Equipment X
Concrete Mix Design X
Concrete Mix Results X
Concrete Mix Admixtures X
Concrete Delivery X
2.1 Conduit X X X
2.2 Conduit Support X X X
2.3 Outlet and Device Boxes X X X
2.4 Pull and Junction X X X
2.5 Junction Boxes X X X
2.10 Wire and Cable X X X
2.11 Wiring Devices X X X
2.14 Surge Protection X X X
2.2 Grounding Conductors X X
2.3 Connector Products X X
2.4 Ground Rods X X
26 05 29 2.2 Supporting Devices X X
2.1 Raceway Cable Identification Materials X X X
SUBMITTAL
02 41 16
Division 1
Division 2
01 40 00
1.3
01 67 00
1.4
1.3
A R
C H
(h rs
1.4
Description
INFORMATIONAL
01 31 00
01 57 23
Spec. Sec.
1.5
ACTION
EE
hr s)
PM
C oo r.
(h rs
LA
hr s)
C E
(h rs
M E
(h rs
REQUIREMENTS(indicate with an "X")
Par. No.
Division 3
03 30 00 1.6
A/E REVIEW TIME
(indicate number of hours)
SE
hr s)
Division 26
26 05 26
26 00 00
GRTE - 249645, 330091
01 33 23 - 1
SUBMITTAL PROCEDURES
T.
/L
A B
T
ES
T
R
EP
O R
T/ C
A
LC
O
R P
LA
N
M fg
. D A
TA
IN
ST
R U
C
TI
O N
S
PE
R
M
IT
S
SH
O
P D
R A
W
IN
G
SA
M
PL
E
M fg
. D A
TA
IN
ST
R U
C
TI
O N
S
FI
EL
D
R
EP
O R
TS
SUBMITTAL
A R
C H
(h rs
)Description
INFORMATIONAL
Spec. Sec.
ACTION
EE
hr s)
PM
C oo r.
(h rs
LA
hr s)
C E
(h rs
M E
(h rs
REQUIREMENTS(indicate with an "X")
Par. No.
A/E REVIEW TIME
(indicate number of hours)
SE
hr s)
2.2 Conductors and Communication - and Control - Cable
Identrification Materials X X X
2.3 Equipment Identification Nameplates X X X
2.4 Equipment Identification Labels X X X
2.5 Miscellaneous Identification Products X X X
2.5 Underground-Line Warning Tape X X X
26 29 13 2.2 Manual and Magnetic Motor Controllers X X X
27 13 23 2.1 Fiber Optic Cable X
Material Sources X X
Fill Material - Weed Free Certification X X
2.2 Weed Free Certification for all Products X
2.3 Aggregates for Drains X X
2.4 Imported Aggregate Base Course X X
2.5 Structural Fill X X
2.5 Cobble Rock X X
2.7 Granular Fill X X
2.8 Aggregates for Pervious Backfill Material X X
2.10 Type 1 Pipe Bedding X X
2.11 Type 2 Pipe Bedding X X
Video and Photographic Documentation prior to Site Clearing X
Record Drawings of Subsurface Structures and Utilities. X
1.5 Construction Plan for Bowman Creek Infiltration X
2.2 Underground warning tape X
3.6 Field Testing of Backfill X X
31 23 18 1.4 Rock Removal Method (if required) X
Bowman Creek Infiltration Gallery Plan X
Dewatering Pumps X
Monitoring Reports X X
2.2 Geotextile Fabric X
3.7 Field Testing of Backfill X X
31 23 24 2.1 Flowable Fill Mix Design X X
32 91 19 2.1 Topsoil Weed Free Certification X
33 05 17 2.1 & 2.2 Concrete Vault and Manholes, incl. Frame, Cover, Access Hatches, Eye Bolts, Steps, Grout and Sealants. X X
SWPPP Plan X Certificate of Qualification for HDPE Pipe Fusion Foreman X
Project Record Documents of Installation X
2.1 PVC Pipe and Fittings X
2.2 PVC Pre Packed Screen X
2.4 Geotextile Fabric X
2.5 Pipe Material X
2.6 Pump X
Manufacturer Recommended Fusion Procedures X Certificate of Qualification for HDPE Pipe Fusion Foreman X
Project Record Documents of Installation X
2.1 &
2.2 HDPE Water Pipe and Fittings X
Gate Valves X
1.5
Division 31
31 05 13 1.4
31 05 16
31 10 00 1.5
31 23 17
Division 27
33 14 13
1.3
1.4 & 1.5
Division 33
26 05 53
31 23 23
2.3
Division 32
31 23 19
GRTE - 249645, 330091
T.
/L
A B
T
ES
T
R
EP
O R
T/ C
A
LC
O
R P
LA
N
M fg
. D A
TA
IN
ST
R U
C
TI
O N
S
PE
R
M
IT
S
SH
O
P D
R A
W
IN
G
SA
M
PL
E
M fg
. D A
TA
IN
ST
R U
C
TI
O N
S
FI
EL
D
R
EP
O R
TS
SUBMITTAL
A R
C H
(h rs
)Description
INFORMATIONAL
Spec. Sec.
ACTION
EE
hr s)
PM
C oo r.
(h rs
LA
hr s)
C E
(h rs
M E
(h rs
REQUIREMENTS(indicate with an "X")
Par. No.
A/E REVIEW TIME
(indicate number of hours)
SE
hr s)
Valve Boxes X
2.4 Curb Stop X
2.5 Curb Boxes X
2.6 Flange Coupling Adapters X
2.7 Couplings and Sleeves X
2.8 Flange and Mechanical Joint Hardware X
Water Service Pipe X
Service Saddles X
Corporation Stop X
Pump Out Drains X
2.10 Fire Hydrants X
2.11 Flushing Hydrant X
2.12 Insulation X
2.15 Tracer Wire X
2.16 Yard Hydrant X
2.17 Drain Drywell and Tank Drains X
Written Plan and Procedures X
Disinfection Reports (Pipelines and Tanks) X X
Disinfection Chemicals X
De-chlorination Chemicals X
2.1 Storage Tank X X
2.2 Tank Bedding Material X
2.3 Yard Piping X
2.4 Tank Drain/Overflow Outlet X
2.5 Tank Level Control X
33 41 00 2.1 Culvert Pipe X
2.1 PLC X X
2.3 UPS X
2.5 Enclosure X X
40 67 00 1.4 Panel Fabrication X X
Total0 0 0 0 0 0 0Note:(See color coded instructions on page 2 - Instructions)
33 14 16
Division 40
1.3
40 63 43
2.9
33 14 17
2.3
33 16 61
GRTE - 249645, 330091
SECTION 01 33 23 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.2 DEFINITIONS
A. Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.
B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.
1.3 GENERAL SUBMITTAL PROCEDURES
A. General: Prepare and submit submittals required by individual Specification Sections and in some cases as requested in drawings. Types of submittals are indicated in individual specific sections.
1. Contracting Officer (CO) reserves the right to require submittals in addition to those called for in individual sections.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review for legibility, accuracy, completeness, and compliance with
Contract Documents.
C. Submittal List: Submittal list is attached to the end of this Specification Section. The intent is to provide an overall summary of submittal requirements. The requirements of individual
Specification Sections and terms and conditions of the Contract still apply regardless of what is shown on submittal list.
D. Processing Time: Allow time for submittal review, including time for re-submittals, as follows.
Time for review shall commence when e-mail notification is received by Contracting Officer (or designee) indicating submittal has been posted on NPS management software website and is ready for review. When Contracting Officer has completed review, e-mail notification will be sent to
Contractor indicating submittal has been processed. No extension of Contract Time will be authorized because of failure to transmit submittals in advance of Work to permit processing, including re-submittals.
1. Action Submittals
a.…