Sol_140P1426R0013_Amd_0005.pdf

PDF 207 KB Posted

Attached to
Rehabilitate the Polebridge Water System, Glacier
Solicitation number
140P1426R0013
Issued by

About this file

This is Amendment 0005 to Solicitation No. 140P1426R0013 issued by the National Park Service, Intermountain Region (NPS, IMR) - Northern Rockies MABO for the rehabilitation of the Polebridge Water System at Glacier National Park. The amendment clarifies the Period of Performance for the construction project, which runs from October 17, 2026, through December 17, 2027.

The amendment specifies that construction may begin during the unrestricted period between October 17, 2026, and April 18, 2027, with work permitted on the water tank, water lines, communications lines, and other project components, including closure of the Inside North Fork Road as needed. Water service to housing units must be operational no later than April 18, 2027. An August 19, 2027, Notice to Proceed date referenced in Attachment 12 does not establish the beginning of the overall construction period; rather, revised Section 01 11 00 establishes specific project milestones and work restrictions for 2027, including restrictions on work in front of the Ranger Station from May 7 through October 16, 2027. Contractors may commence work during unrestricted periods once necessary materials are available and delivered to the site. The Government will provide direction regarding material procurement and authorization for delivery or storage. Payment for materials will not be issued until materials are inspected and accepted by the Government. Proposal submission deadline is September 10, 2026, at 1:00 p.m. MDT. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Stacy Vallie

See continuation page

NPS, IMR - Northern Rockies MABO PO Box 168 Mammoth Supply Center / 22 Stable St Yellowstone NP WY 82190

PIR

140P1426R0013

09/09/2026

07/15/2026

1 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P1426R0013/0005

PROJECT TITLE: Rehabilitate Polebridge Water

System, Glacier National Park

Amendment 0005 to Solicitation No.

140P1416R0013 is hereby issued to clarify the

Period of Performance.

The Period of Performance is intended to allow construction to begin in 2026. Specifically, there are no work restrictions between October

17, 2026, and April 18, 2027. During this period, the Contractor may perform work on the water tank, water lines, communications lines, and other portions of the project, including closing the Inside North Fork Road as necessary to perform the work.

The August 19, 2027, Notice to Proceed date referenced in Attachment 12 is not intended to establish the beginning of the overall construction period. The revised Period of

Performance begins October 17, 2026. Revised

Section 01 11 00 establishes the specific project milestones and work restrictions applicable during 2027. For example, water service to the housing units must be operational no later than April 18, 2027, and work in front of the Ranger Station is restricted from May 7 through October 16, 2027.

The Contractor may begin work during the unrestricted period as soon as the necessary materials are available and delivered to the project site. Accordingly, construction activities could begin this fall, winter, or next spring, depending on the Contractor's schedule and material availability.

The Government will provide additional direction regarding material procurement and any authorization for delivery or storage of materials, as applicable. Payment for materials will not be made until the materials have been inspected and accepted by the Government.

Proposals are due no later than 1:00 p.m. MDT on September 10, 2026.

Continued...

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P1426R0013/0005

Except as modified by this amendment, all other terms and conditions of the solicitation remain unchanged.

END OF AMENDMENT 0005

Period of Performance: 10/17/2026 to

12/17/2027

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet