Attachment 1 -SOW Replace Fuel Tanks B2096 January 14th 2026.pdf

PDF 265 KB Posted

Attached to
Replace Fuel Tanks at building 2096
Solicitation number
W912D026Q0098
Issued by

About this file

This is a Scope of Work (SOW) for a federal construction task order to replace fuel tanks at Fort Wainwright, Alaska. The project, designated DPW-24035-4J, involves demolishing existing 300-gallon diesel and gasoline fuel tanks and installing new 500-gallon diesel and MOGAS fuel tanks, along with associated infrastructure and electrical systems. Work must commence no later than 10 days after receipt of Notice to Proceed, with all preconstruction requirements completed within 15 days and onsite construction starting no later than 30 days after NTP. The entire project must be 100% complete within 220 days of NTP.

The contractor is responsible for providing all materials, labor, and equipment necessary to complete site demolition, excavation, concrete pad installation (8' x 12'-6"), fuel tank installation, electrical work including power conduits and emergency shut-off systems, site improvements (personnel gate, signage, bollards), topsoil and seeding, and protection of existing communication lines. The SOW requires contractor quality control, adherence to applicable codes and standards, submission of detailed schedules and submittals, three-phase quality control inspections for definable features of work, environmental compliance including soil screening and contaminated material handling procedures, security clearances for all personnel, and comprehensive as-built documentation. The contractor must establish a formal project management software system, participate in coordination meetings, maintain a one-year warranty on all work with extended warranties for applicable equipment, and prepare final record drawings in AutoCAD format meeting USACE standards.

View the file

Other files

File Type Posted
Amendment 1 Repair Fuel Tanks COMBINED SYNOPSIS.pdf PDF
Attachment 2 - 482503_Final Construction 22x34 Drawings_1-9-2026 Replace Fuel Tanks B2096.pdf PDF
Attachment 14 - Solid Waste Reporting Requirements 2025.pdf PDF
Attachment 8 - Calculations Replace Fuel Tanks B2096.pdf PDF
Attachment 6 - BUILDER Contract Verbiage(New Contracts)(Jan26).docx DOCX document
Attachment 7 - BUILDER Inventory and Assessment Complete Guide (18 Jul 25).pdf PDF
Attachment 13 - FTW Environmental Requirements for Construction v9 for 2023 Update App.pdf PDF
Attachment 9 - Contractor Laydown Area for Replace Fuel Tanks B2096.docx DOCX document
Attachment 12 - Fort Wainwright Simplified Field Screening Plan.pdf PDF
Attachment 16 - Specifications Replace Fuel Tanks B2096.pdf PDF
Attachment 10 - Division 01 Specs Replace Fuel Tanks B2096.pdf PDF
Attachment 5 - BUILDER Catalog Spreadsheet(07AUG25).xlsx XLSX spreadsheet
Attachment 15 - SOP Manifest Requirements and Procedures MAR25_.pdf PDF
Repair Fuel Tanks COMBINED SYNOPSIS.docx DOCX document
Attachment 11 - Erosion and Sediment Control Plan (APP E).pdf PDF
Attachment 4 - Submittal Register B2096 Fuel Tank Replacement Jan 12th 2026.xlsx XLSX spreadsheet
Attachment 3 - Price Proposal Replace Fuel Tanks.docx DOCX document
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work Replace Fuel Tanks B2096 DPW-24035-4J January 14th 2026

SCOPE OF WORK

Replace Fuel Tanks B2096

DPW-24035-4J

January 14th 2026

1. GENERAL:

1.1. Provide all materials, labor, and equipment to complete the repairs necessary per this statement of work and the construction documents attached/enclosed.

1.2. Contractor shall comply with any current Operational Order which modifies or restricts access to Fort Wainwright.

2. PROJECT REQUIREMENTS:

2.1. Refer to project drawings, specifications, and all contract documents and appendices.

Anything mentioned in the scope of work and not shown on the drawings or shown on the drawings and not mentioned in the scope of work shall be of like effect as if shown or mentioned in both. Contractor shall be responsible for field verifying existing conditions, materials, dimensions, and quantities.

2.2. Contractor shall take measures during construction to preserve and protect against damage to all government and personal property. Property damaged during work, mobilization or demobilization shall be restored or replaced by contractor at no additional cost to Government. Contractor will ensure work site is clean, consolidated, and all tools and materials are secured daily after work for day is completed.

2.3. Work shall be completed in accordance with (IAW) all applicable, current codes, regulations, industry standards. In event of conflicting guidance, the more stringent guidance will be followed; This includes but is not limited to: Applicable United Facilities Criteria (UFC), International Building Codes (IBC, IPC, IMC, IECC), National Fire Protection Association (NFPA), American Standards Institute (ANSI), American Standards of Testing Materials (ASTM), National Electrical Code (NEC), Life Safety Code (NFPA 101).

2.4. Contractor shall coordinate with building manager regarding scheduling and access, and shall include government COR, QAR and PM on all communications.

2.5. General Overview/Summary:

2.5.1. Site Demolition

2.5.1.1. Demolish and remove a 300-gallon Diesel and a 300-gallon Gasoline Fuel Tank.

2.5.1.2. Clear and grub all trees in area as shown in Drawings.

2.5.2. Excavation

2.5.2.1. Excavate Area for concrete Pad and Underground electrical as shown in

Drawings. Confirm excavation locations with COR prior to execution.

2.5.3. Concrete Pad

2.5.3.1. Install 8’ x 12’-6’’ Concrete Pad as shown in Drawings.

2.5.4. Fuel Tanks

2.5.4.1. Install a 500-gallon Diesel Fuel and a 500-gallon MOGAS Fuel tank as shown in Drawings and specifications.

2.5.5. Electrical

2.5.5.1. Install Power Conduits, Type A Pole Area Light, and all other electrical systems shown in Drawings and specifications.

2.5.5.2. Provide an emergency fuel shut-off button and relays as shown on the Drawings.

2.5.5.3. Install a new pole mounted light near new fuel tanks as shown on the

Drawings. Refer to Drawings for light fixture rating and model. Provide new circuit breakers, conduits, and conductors to power the new light. See Drawings for conduit and conductor sizing.

2.5.5.4. Provide new circuit breakers, conduits, and conductors to power new fuel tank pumps as shown on the Drawings.

2.5.5.5. Provide a new typed circuit directory in the existing panelboard protected in a clear plastic sleeve. The contractor shall trace existing unknown loads and identify them on the new circuit directory and on the as-built Drawings.

2.5.5.6. Provide a tank grounding system as indicated on the Drawings.

2.5.6. Site Improvement

2.5.8.1. Install Personnel Gate, signage, bollards and anything else as specified in the

Drawings and specifications.

2.5.7. Topsoil and Seeding

2.5.7.1. Topsoil and seed disturbed area as per Drawings and specifications.

2.5.8. Protect Existing Communication Lines

2.5.8.1. Protect existing communication lines. No mechanical excavation is permitted within 2 feet of utilities. Hand-excavate or vacuum truck only within 2 feet of utilities.

Wherever excavating over existing communication lines, excavate to the depth of the communication line and encase in concrete prior to backfill. Wherever communication line is not already protected by duct, install new split duct along length of communication line and encase in concrete.

3. SCHEDULE:

3.1. Work shall commence no later than 10 days after receipt of Notice to Proceed (NTP). Submit as a deliverable, price breakdown of all work NLT 10 days after NTP (Use this language if more than one building in project to capture funding on real property for 1354). All preconstruction requirements shall be completed NLT 15 days after NTP. Onsite construction may commence upon NTP, but shall start NLT 30 days after NTP. Construction shall be 100% complete no later than 220 days following NTP. The Contractor’s preliminary schedule shall be submitted with the bid/proposal.

3.2. The Contractor’s initial schedule is required to be submitted within 10 days of award and at least two (2) weeks prior to beginning any on site construction work. The schedule shall be in the form of a Gantt progress chart of suitable scale and in sufficient detail to indicate the percentage of work scheduled for completion at any given date during the period. The schedule shall take into consideration but is not limited to: anticipated adverse weather that could preclude progress; long-lead equipment or materials critical to the completion of the project; review periods for submittal items requiring Government review and approval; review, distribution and approval of traffic control plans; construction phasing, and other events and milestones as applicable or necessary.

3.3. Updated schedule shall be provided monthly to the Government Contract Officer’s

Representative (COR), and copies provided to Government Quality Assurance Representative (QAR) and Government Project Manager.

3.4. Definable features of work: (DFOW) – Each DFOW will have a 3- phase quality control process (preliminary phase meeting, initial phase meeting, and follow up inspections Division 01 45 00.10 20 QC for Minor Construction). The 3-phase quality control process shall be included in the Quality Control Plan (Division 01 45 00.10 20-1.6 QUALITY CONTROL PLAN) and shall be coordinated with and subject to the acceptance of the Government COR. As a minimum, which may require amendments during the submittal process and/or the life of the project, the DFOW list shall include:

Demolition Excavation Concrete Pad Installation Fuel Tank Installation Bollard Installation Electrical Topsoil and Seeding

3.5. Reflect the number of anticipated adverse weather delays allocated to a weather sensitive activity in the activity's calendar.

3.5.1. The following schedule of monthly anticipated adverse weather delays workdays based on a five (5) day work week is based on NOAA data and will constitute the baseline for anticipate adverse weather.

Month Adverse Weather Days January 22 February 20 March 21 April 0 May 0 June 1 July 1 August 1 September 0 October 10 November 21 December 22

4. MEETINGS:

4.1. The Contractor shall participate in coordination meetings with the COR and other

Government representatives on an as needed basis, but at a minimum, the Contractor shall participate in a Post Award Meeting, Preconstruction Meeting, weekly progress meetings, Red Zone meeting and closeout meeting. Contractor shall be responsible for preparing the agenda in coordination with the COR, distributing the agenda, conducting the meeting, preparing the meeting minutes, distributing the minutes, and tracking action items for any coordination meetings other than the kickoff and preconstruction meeting. The Contractor's Project Manager, QC System Manager, and Superintendent shall attend each meeting. The Contractor shall conduct meetings IAW Division 01 UFGS specifications.

5. OCCUPANCY:

5.1. Contractor shall identify and submit for Government Approval Contractor’s proposed laydown area. A Government proposed laydown area is identified on the attached enclosure. All ground and snow maintenance within the proposed laydown area is the responsibility of the contractor. Upon completion of the project, remove all signs, barricades, haul roads, and any other temporary products from the site. After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including topsoil and seeding as necessary.

5.2. The buildings included in the scope of this contract will likely be occupied. The Contractor will schedule and perform work under this contract in such a manner as to allow the occupants of the building to continue their normal activities with the least amount of interference.

6. SUBMITTALS:

6.1. A preliminary submittal register is provided with solicitation. The submittal register provided by the Government contains the minimum submittals the Government sees as necessary and may not be all inclusive. Contractor will be responsible, as part of Contractor Quality Control responsibilities, to review the Government provided submittal register, the contract, Statement of Work (SOW), drawings, and all applicable specifications for this task order. Contractor shall supplement the Government provided submittal register with additional items required to be submitted as determined from the review. The supplemented/augmented submittal register shall be submitted to the Government for review NLT 10 business days after award and shall be updated and adjusted as necessary throughout the period of performance.

6.2. Contractor shall submit a (SOV) for partial payment processing. The SOV shall be submitted to the Government COR. The three phase inspection process, RFIs, major shift in schedule all are considered part of partial payment processing.

6.2.1. 10% of TO award value shall be allocated as closeout documents in SOV.

6.3. Task Order management requires utilization of a formal construction project management software beyond the capabilities of manual and paper-based correspondence (e.g. email and documentation) to automate the project management process (e.g. PROCORE or comparable). The software shall include the following features: project scheduling, project tracking, submittal management, and other document management requirements (i.e. daily reports, RFI’s, etc.). Access to the cloud-based construction project management software shall be provided to unlimited Government users within 10 days of NTP.

6.4. Submittals shall be accompanied by a completed ENG Form 4025-R or approved equivalent submittal cover page to include equivalent information required on ENG Form 4025-R.

Incomplete submittals will be rejected without action pending completion. Submittals shall be submitted directly to Government COR. When directed, or as specified, the Contractor shall provide information and/or submit samples of equipment and materials that the Contractor intends to incorporate in the work. All submittals shall be at the Contractor’s expense. All items on ENG Form 4025-R or equivalent submittal cover page shall be restricted to a single contract technical section. Contractor shall coordinate with Government COR for proper completion of this form.

6.5. Closeout Submittals:

6.5.1. All closeout Final As-Built Record Drawings, both ‘.pdf’ and AutoCAD ‘.dwg’ file types, shop drawings, equipment information, Operation and Maintenance (O&M) manuals, training videos, etc. shall be subject to final approval by Fort Wainwright Directorate of Public Works (DPW) Plans Vault personnel located in Building 3013.

6.5.2. Contractor shall submit all project related shop drawings, equipment information, material samples, Operation and Maintenance (O&M) manuals, training videos, etc.

to the Government COR. COR will route approval to the DPW Plans Vault personnel for approval. In the case of handwritten reports, scanned ‘.pdf’ files shall be submitted for acceptance. Submitted documents shall include a completed ENG Form 4025-R or approved equivalent submittal cover page.

6.5.3. All closeout submittal documents shall be submitted in a searchable digital format via electronic method(s) (e.g. DoD SAFE or Email). If electronic methods are not available, the closeout submittal shall instead be submitted in a searchable digital format on a single disc (i.e. CD/DVD) or external USB storage device at the Contractor’s expense. Contractor may choose to submit the digital submittal disc after the paper copies have been approved by the Government. All physical disc and external storage device media shall be labeled in accordance with FWA Security Requirements, to include: project number, project name, date, and Contractor company name.

6.5.4. As-built Record Drawing Management

• Contractor shall maintain at least one (1) drawing set of working As-built Drawings by “red-line” process to show As-built conditions during the execution of the project. Working As-built “red-line” Drawings shall be kept current on a regular basis (no less than weekly), and shall be available at the job site at all times or otherwise made available to the Government immediately upon request. All changes from the contract and shop drawings made during construction shall be accurately and neatly recorded as they occur by means of details, notes, and additional drawings, as necessary. The working As-built “red-line” Drawings shall be jointly reviewed for accuracy and completeness by the Contractor and the Government prior to submission of periodic pay requests.

• Final As-built Record Drawings shall be prepared after the completion of the work.

Contractor shall modify the Final As-built Record Drawings to accurately show the features of the project as they have been constructed by bringing the Final As-built Record Drawings into agreement with the approved working “red-line” As-built Drawings. The Final As-built Records Drawings shall be jointly reviewed for accuracy and completeness by the Government and Contractor prior to submission of final pay requests. When final revisions have been completed, each individual drawing set sheet shall be stamped with the wording “As-built [and/or] Record Drawing” followed by project number, project name, date, and Contractor company name. Final As-built Record Drawing set shall contain all design, references, and extensions of 100% Design Drawings used in the performance of the work.

6.5.5. As-Built Record Drawing Standards

• Contractor construction and engineering project field surveys shall conform to current U.S. Army Corps of Engineers (USACE) Engineering and Design Control and Topographic Surveying Engineer Manual (EM) Number 1110-1-1005 to the maximum extent possible. Field surveys shall conform to the current State of Alaska horizontal reference datum (i.e. NAD83) and the current horizontal reference datum epoch (i.e. 2011) in US Foot. Field surveys shall conform to the current State of Alaska vertical reference datum (i.e. North American Vertical Datum of 1988 or NAVD88) and the current Hybrid Geoid Model (i.e. GEOID12B).

• Contractor AutoCAD ‘.dwg’ files shall conform to current U.S. Army Engineer Research and Development Center (ERDC) and Information Technology Laboratory (ITL) standards to the maximum extent possible. AutoCAD ‘.dwg’ file coordinate system settings shall conform to the North American Datum (NAD) of 1983 Alaska State Plane Coordinates (ASPC), Zone 3, US Foot (i.e. AK83-3F).

AutoCAD ‘.dwg’ file line work shall represent the actual topographic (i.e.

geographic) location of existing and constructed (i.e. As-built) project ground conditions, and shall not schematically represent any civil line work on any site plan drawing set sheets.

• Contractor AutoCAD ‘.dwg’ file format Final As-built Record Drawings shall be saved in Release 2018 or older. Final Closeout submittal AutoCAD ‘.dwg’ file As-built Record Drawings shall match the ‘.pdf’ file version exactly. AutoCAD ‘.dwg’ files shall be purged, audited, and virus scanned prior to delivery. AutoCAD ‘.dwg’ files shall include all loaded and relevant external references, associated line types, fonts, blocks, plot style table ‘.ctb’ file(s), image file(s), etc. AutoCAD ‘.dwg’ files shall be ‘eTransmitted…’ or similarly delivered in order for the Government to gather all associated supporting AutoCAD file types.

• Contractor may opt to submit preliminary As-built Record Drawing files to the DPW Plans Vault for review prior to submitting the Final As-built Record Drawings to the Government. Correspondence may be kept between the Contractor and the DPW Plans Vault. Any preliminary As-built Record Drawing files submitted to the DPW Plans Vault shall be assessed to provide feedback to the Contractor and confirm the Final As-built Record Drawings meet contractual specifications.

Preliminary As-built Record Drawing files shall not require any transmittal forms.

Preliminary As-built Record Drawing files submitted for review shall not satisfy Final Closeout submittal contract requirements.

• Contractor supplied Final As-built Record Drawing submittal shall be accompanied with a completed DD Form 250, Material Inspection, and Receiving Report.

Contractor shall coordinate with Government COR for proper completion of this form.

6.6. BUILDER Sustainment Management System (SMS):

6.6.1. Contractor will provide a list, including all salient data, on all removed Systems, Components and Equipment (e.g. Description of Component/System/Equipment, Manufacturer, Model, Serial Number(s), Voltage, CFM, RPM, etc.).

6.6.2. Contractor will provide a list, including all salient data, on all newly installed Systems, Components and Equipment (e.g. Description of Component/System/Equipment, Manufacturer, Model, Serial Number(s), Voltage, CFM, RPM, etc.).

6.6.3. Contractor will physically tag all newly installed Systems/Components/Equipment.

Tagging will state Make, Model, Serial Number and Installation date.

6.6.4. Contractor will identify and list all removed and newly installed Systems/Components and Equipment, utilizing the attached Spreadsheet “BUILDER Catalog Spreadsheet”.

6.6.5. Contractor will take photos of all Systems/Components/Equipment that is identified within the Spreadsheet as needing an Inventory Photo.

7. TRAFFIC CONTROL:

7.1. Contractor shall submit to the Government as a For Information Only (FIO) traffic control plans (if applicable) prepared by a certified traffic control supervisor meeting all MUTCD, Alaska Sign Design Specifications (ASDS), and Alaska Traffic Manual (ATM).

7.2. As part of the traffic control plan, Contractor shall provide at all times channelized pedestrian access, emergency access to adjacent buildings, residential access, and cross traffic, unless otherwise approved. Contractor will also need to provide business access during business hours.

7.3. If the Contractor’s traffic control or work plan proposes temporary shutdown of parking lots adjacent to the work locations, the Contractor shall as part of the traffic control plan/work plan identify alternative parking locations for displaced vehicles during closures and identify proposed detour routes.

7.4. Contractor shall provide suitable for public distribution, road detour/closure plans, no less than 15 calendar days prior to planned road closures (if applicable).

7.5. Coordinate traffic control with other construction in the area.

7.6. Cover existing signs which conflict with construction signing.

8. WARRANTY:

8.1. All work shall be covered under the 1-year warranty of construction required by contract IAW FAR 52.246-21 Warranty of Construction. Contractor shall provide Government with phone numbers and email addresses of primary and alternate Warranty POC’s for both regular work days/duty hours warranty calls and also primary and alternate Warranty POC’s for holiday/weekend/after normal duty hours warranty calls.

8.2. In addition to the 1-year warranty of construction, the contractor shall obtain all extended warranties, greater than 1-year, that would normally be given in commercial practice and, upon final acceptance of the work (or before), provide a list to the Government of each extended warranted equipment item, feature of construction, or system. As applicable, the list shall include the status of delivery of all Certificates of Warranty for extended warranty items, to include but not limited to roofs, HVAC balancing, pumps, motors, transformers, HBOs, and for all commissioned systems such as fire protection and alarm systems, sprinkler systems, lightning protection systems, etc. The list shall indicate the following:

• Name of item.

• Model and Serial Number.

• Installed location.

• Name and phone numbers of manufacturers or suppliers.

• Names, addresses, and phone numbers of sources of spare parts.

• Warranties and terms of warranty. Items with warranties extending beyond the one-year warranty shall be indicated with separate warranty expiration dates.

• Start date and duration of warranty period.

• Summary of maintenance procedures required to continue the warranty in force with cross-reference to specific pertinent operation and maintenance manuals as applicable.

9. SAFETY:

9.1. Contractor shall use all appropriate safety equipment and apply sound safety practices.

Contractor shall fully comply with most current version of NFPA, OSHA, and Federal standards as applicable. Contractor shall obtain hot work permit from Fire Dept. for welding, cutting, brazing. Soldering.

9.2. The contractor shall comply with 01 35 26 Government Safety Requirements, 29 CFR part 1926, 29 CFR part 1910, all state and local occupational safety and health requirements, and the requirements of latest version of EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual.

9.3. Prior to the start of work, the contractor shall submit for approval a site specific Site Safety and Health Plan (SSHP) also referred to elsewhere in this contract as an Accident Prevention Plan (APP). The plan shall be developed by a qualified person and be signed by a competent person and a representative of the prime contractor’s project management team. The plan shall meet the minimum basic outline requirements contained in EM 385-1-1, Appendix A.

The plan shall be job-specific and shall include work to be performed by subcontractors and measures to be taken by the contractor to control hazards associated with materials, services, or equipment provided by suppliers. The accident prevention plan shall include procedures for frequent safety inspections, conducted by competent persons, of the work sites, material, and equipment to ensure compliance with the plan and other referenced standards. Unless otherwise approved, the Site Safety and Health Officer, required by base contract SOW, will conduct safety inspections, operations and do safety documentation.

9.3.1. Due to the limited scope of this project, the Contractor may submit to the Government for approval, an abbreviated APP. The abbreviated APP shall meet the requirements set forth in EM 385-1-1 and follow the format outlined in Form A-01 of EM 385-1-1.

10. ENVIRONMENTAL PROTECTION:

10.1. All work shall be completed in accordance with applicable environmental laws, regulations, and latest version of IMFW-PWE document Environmental Requirements for Construction and Renovation Projects. The document identifies the requirements for Contractors handling of wastewater, backflow prevention, hazardous waste and hazardous material, solid waste, spill reporting, air quality, fuel storage, natural resources, and cultural resources. A copy of this document is provided as an Attachment.

10.2. The Contractor will be required to obtain a dig permit (Excavation Clearance Request, ECR) for this project that is approved by the Environmental Division.

10.3. The submission of a Construction General Permit Notice of Intent (NOI) for a Storm Water Pollution Prevention Plan (SWPPP) to the State of Alaska prior to initiation if the total project disturbance is 1 acre or more. The Contractor shall submit an Erosion and Sediment Control Plan (ESCP) to the Environmental Division if the total project disturbance is less than one acre but greater than 5000 SF. An example ESCP may be found in Appendix E of the Environmental Requirements for Construction, Demolition and Renovation Projects. If total disturbance is less than 5000 SF, best management practices as identified in the Fort Wainwright Storm Water Management Plan, Dec 2016 should be used to prevent sediment and other pollutants from entering waters of the U.S. adjacent to the project area.

10.4. Projects involving excavation of soils in areas of known contamination are required to adhere to a Work Plan, prepared by a qualified environmental professional in accordance with the Uniform Federal Policy for Quality Assurance Project Plans (UFP-QAPP), approved by Alaska Department of Environmental Conservation (ADEC) and/or Environmental Protection Agency (EPA), coordinated through the FWA Environmental Division prior to the start of work.

Approval of UFP-QAPP for projects involving excavation in areas of suspected contamination shall be approved by the FWA Environmental Division. Work Plans must be approved prior to Environmental Division approval of the ECR. Work Plans typically include field screening for petroleum products and/or other identified contaminants of concern and associated sampling and analysis. Regulatory review of the work plan can take up to 30 days for each submittal or re-submittal. Soils shall be managed in accordance with Appendix C, Handling/Management of Soil on Fort Wainwright. Projects involving excavation of soils that are not within known or suspected contamination, shall require submittal of a Simplified Field Screening Plan. The contractor shall screen for evidence of contamination based on presence of sheen, odor, staining, debris, or other evidence of contamination. If the contractor discovers evidence of contamination, work shall cease in the area of contamination and the contractor shall provide notifications as directed in the ECR. Work within the contaminated area shall not resume until clearance is given by the COR in consultation with DPW Environmental.

10.5. Encountered Contaminated Materials:

10.5.1. Contaminated soils may be encountered at any time during the duration of the project.

10.5.2. If required by contract or in case of modification for unanticipated contaminated soil, provide a CY unit price, valid for the entire duration of the project, for handling an estimated quantity of up to 100 CY of contaminated soil, and providing full rounds/banks of sampling/tests IAW the requirements of latest version of IMFW-PWE document Environmental Requirements for Construction, Demolition and Renovation Projects, and Appendix C Handling / Management of Contaminated Soil.

• The unit price shall provide for, among other things required by JA-15, Appendix

C, having a qualified environmental professional on site during all excavation to field screen and segregate soils; constructing two temporary holding cells within the project boundary (one for soil with photoionization detector (PID) readings of 20-99 PPM and one for soil with PID readings greater than 100); excavation, loading and transporting contaminated soil to temporary cells; contaminated soil placement in cells, maintaining cells, and cleaning of equipment/trucks used to handle, transport, and place contaminated soil. The unit price will also include but is not limited to; sampling and laboratory analysis of stockpile soils for waste characterization and left in place soils for confirmation sampling; obtaining, hauling, placement, and compaction of appropriate quantities of clean soil to replace contaminated soils that were planned to be used on site but could not be used on site due to contamination; proper handling of stockpiled soils upon waste characterization i.e. hazardous waste (HW) soils remain on site, non-HW contaminated soil is to be hauled to the contaminated soil yard and placed in constructed storage cells, petroleum contaminated soils hall be shipped for thermal treatment in state and returned as clean after treatment, clean soils are to be hauled and spread at the clean soil yard; and preparation of closure report documenting all environmental activities,

• Non-HW contaminated soil contaminated soil yard will be within five (5) miles of the construction site. Haul distance to thermally treat and then return clean soils to post shall not be longer than 25 miles one way.

• Samples shall be tested for gasoline-range organics (GRO), diesel-range organics (DRO), residual-range organics (RRO), volatile organic compounds (VOCs), semi-volatile organic compounds (SVOCs), and Resource Conservation and Recovery Act (RCRA) metals, and Toxicity Characteristic Leaching Procedure (TCLP) for RCRA metals. The number samples collected to characterize excavated soil stockpiles shall be in accordance with Table 2A the number samples of confirmation samples in area of contamination in accordance with Table 2B of ADEC Field Sampling Guidance, October 2019.

10.5.3. Paragraph 10.5 and subsequent subparagraphs will be exercised if contaminated soils are encountered at any time during the duration of the project and will be subject to the provisions of FAR 52.211-18 Variation in Estimated Quantity.

11. CONTRACTOR QUALITY CONTROL (CQC):

11.1. The contractor is responsible for quality control and shall establish and maintain an effective quality control system. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product that complies with the Scope of Work herein and any enclosed drawings and all codes, applicable industry standards, UFC’s. At least ten (10) work days before commencing work and prior to preconstruction/kick off meeting, submit a Quality controls plan for Government review. The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. The plan shall include a general list of the definable features of work (DFOW) identified by the contractor. A definable feature of work is a task which is separate and distinct from other tasks, has separate quality control and safety requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. The plan will ensure that, in accordance with contract clauses on Material and Workmanship, all equipment, materials and articles incorporated into the work shall be new and of the most suitable grade for the purpose intended; and all work under this contract shall be performed in a skillful and workman like manner. Contractor will provide COR, QAR, and PM a daily progress report for each day of onsite work, “No Work” daily reports for individual days without onsite work performed, or “No Work” reports per week for entire weeks without onsite work being performed. Format shall be jointly agreed upon between COR and contractor. A contractor Quality Control Manager is required.

11.2. Only personnel who are competent, qualified, and have demonstrated experience in using accepted trade practices for the type work for which they are to be employed on this contract shall be used. All field work shall be done to journeyman-level standards; work failing to meet this standard as determined by the Government COR shall be re-performed at no additional cost to the Government. The Government reserves the right to require written verification of personnel qualifications from the Contractor or his sub-contractors.

11.3. Materials and equipment shall be a standard product of a manufacturer regularly engaged in the production of that product that have been in satisfactory use for at least 2 years prior to award of this contract. Materials and equipment shall be installed in accordance with the manufacturers written instructions, and fully satisfy the government requirements – otherwise they shall be replaced at no additional cost to the government. Any reference by brand and/or specific product contained herein is for the purpose of establishing quality and performance standards only and is not intended to limit competition.

11.4. The contractor shall obtain specific approval for all materials and equipment that vary from the standards established herein.

11.5. Commissioning of major systems (e.g., HVAC, fire protection, etc.) is required, unless otherwise noted.

11.6. Upon completion, but prior to final acceptance, contractor shall submit installed equipment list listing all major equipment, systems, features of work. List shall include manufacturer’s name, model number, service manual, parts list, brief description of all equipment and basic operating features. Also at same time, contractor will submit operation and maintenance

(O&M) information/procedure for all major equipment, systems, features of work. Manuals shall have same info as info on installed equipment list and will also have piping and layout diagrams, control and wiring diagrams, required maintenance procedures/schedules, POC for extended warranty. O&M data shall be consolidated and submitted in one three ring binder, tabbed and indexed; as well as being submitted electronically as a PDF file.

11.7. The contractor shall place all systems and major pieces of equipment and features of work into operation and, with the O&M manuals, instruct the government’s operation and maintenance personnel on the proper operation and maintenance of the new equipment/systems. The contractor shall coordinate and schedule on site training with government COR, QAR, and PM at least two (2) weeks before the proposed date. The session(s) shall be memorialized in contractor prepared minutes of the training conducted.

Minutes shall be submitted to Government for review before being finalized.

12. REQUIRED STAFFING:

12.1. The Base Award Contract SOW details all required positions and corresponding standards, and “dual-hat” staffing of required positions is not acceptable without prior approval from the Government.

12.2. For this Task Order only, one (1) staff member may fulfill the roles of no more than two (2) required positions (PM, QC, SSHO, Superintendent).

12.2.1. Superintendent shall only be required if Task Order value is equal to or greater than

$250,000.

12.2.2. Staff member shall meet the required Performance Standards for both positions for which they are fulfilling. See 3.1.1 Required Technical and Administrative Staff of the MATOC SOW for Performance Standards.

13. GOVERNMENT OWNED INFRASTRUCTURE:

13.1. Contractor shall verify all utility locations prior to excavating, including the Government owned communication lines.

13.2. Where construction requires excavation beneath existing Government owned communications or electrical ducts or conduits larger than 2.5”, the exposed utility shall be supported to prevent structural failure. The support system shall be designed by the Contractor and submitted to the Government for approval no less than one (1) week before the affected line is undermined.

13.3. If Government owned fiber optic cable is damaged by the Contractor, the Contractor shall replace the cable from splice point to splice point at no additional cost to the Government.

Replacement shall include spare cable in each manhole. The amount of spare cable will be determined by the Contracting Officer but will be no more than 60' in each manhole. After replacement, end to end attenuation shall be measured with an optical power meter and OTDR is to be performed on each cable at 1310 nm and 1550 nm. The OTDR shall be in one direction for fibers not intended to be terminated and bi-directional for all others.

Measurement procedures shall comply with EIA/TIA. Failures to achieve EIA/TIA compliant results shall be remedied by the Contractor at no additional cost to the government. Digital and paper records of the attenuation and OTDR results shall be furnished to the Government in a timely manner. Repairs/replacement shall be completed within 24 hours or as approved by the Contracting Officer.

13.4. If Government owned communications lines, other than fiber optic lines, are damaged by the contractor, repairs shall be made in a manner acceptable to the contracting officer. The contracting officer may disapprove underground splicing in which case the damaged section of cable shall be replaced and a new manhole or new pedestals shall be provided for splicing.

The following tests and measurements shall be made on all communications lines repairs:

insulation resistance, shorts / crosses, grounds, opens, reversals, splits, transpositions, shield continuity, loop resistance, insertion and capacitance. Digital and paper records of these tests and measurements shall be furnished to the Government.

13.5. Measurement procedures shall comply with RUS standards. Failures to achieve RUS compliant results shall be remedied by the contractor at no additional cost to the government.

Digital and paper records of the tests and measurements shall be furnished to the government in a timely manner. Repairs / replacement shall be completed within 24 hours or as approved by the contracting officer.

13.6. Contractor is responsible for movement of construction machinery and equipment over telecommunications infrastructure during construction and shall protect the infrastructure.

Where excavated material is removed over or to the sides of the infrastructure, the duct system, sub-duct and fabric mesh shall be verified prior to construction and at the completion of compaction, by means of pulling a test mandrel along with replacement pull cord thru the vacant conduits / fabric. The Government representative shall witness duct verifications.

Where direct cable plant is exposed, split duct conduit shall be provided and concrete encased.

14. INSPECTION:

14.1. All work is subject to inspection and testing by the Government at all places and at all reasonable times before acceptance, as required by the contract. Government inspections and tests do not relieve the contractor of the responsibility for providing adequate quality control measures, nor does it constitute or imply Government acceptance of the work. The presence or absence of a Government inspector does not relieve the Contractor of complying with the specified requirements, nor is the Government inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

14.2. Failure to obtain inspection for designated work may result in a requirement for re-performance of installed work (at no additional cost to the Government) to prove compliance before approving progress payments, at the discretion of the Contracting Officer.

14.3. The Government may require the Contractor to “hold” construction (construction hold point) after installing pre-identified work so the Government may verify conformance to the specifications. In order to prevent unreasonable downtime, the Contractor shall coordinate the date/time that the subject work will be ready for inspection with the Government COR, QAR, and PM a minimum of 48 hours in advance of reaching the estimated construction hold point. The Contractor shall keep the Government COR, QAR, and PM updated on progress after the 48-hour notification so a site inspection can be accurately scheduled. The Contractor shall hold subsequent work on the affected features until the designated construction has been accepted by the Government. If the Government elects to require hold points for designated features of work, those features of work will be identified at or prior to the pre-construction meeting or as agreed upon between the Contractor and the Government during construction.

14.4. Beneficial Occupancy Inspection/Pre-Final Inspection, Final Inspection and Acceptance:

14.4.1. It is anticipated there will have to be Beneficial Occupancy Inspections (BOIs) and pre-final inspections for each phase of work and then upon completion of final phase the formal final inspections for the entire project will be conducted. The Contractor's Quality Control personnel, Superintendent or other primary management person, and the Government shall be in attendance at the BOIs, pre-final inspections, and the final acceptance inspection.

Prior to each BOI/pre-final inspection, Contractor will conduct a punch-out inspection to identify any work still required to be done, identify work that needs to be corrected, and identify any work that cannot be completed. Contractor will record results of inspection and correct or complete as many of the items on the punch-out inspection as possible. For any items that cannot be completed, Contractor will annotate all such items with anticipated date for completion/correction. Once as many deficiencies as possible have been completed, the Contactor may request a BOI/pre-final inspection. Contractor shall provide an annotated punch-out inspection list with the request and shall give the Government at least five (5) working days advance notice before the requested date of BOI and/or pre-final inspection.

The Contractor shall record the results of the BOI/pre- final inspections. Any items noted on the BOI/pre-final inspection shall be corrected in a timely manner or the uncorrected items shall be annotated with a projected date for correction.

14.4.2. Notice shall be given to the Government at least 14 calendar days prior to the final acceptance inspection and shall include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable/needing correction, along with all remaining work performed under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection.

Contractor will consolidate and record results of all punch-out and BOI/pre-final inspections and correct or complete as many of the items on the punch-out and pre-final inspection as possible. For any items that cannot be completed, Contractor will annotate all such items with anticipated date for completion/correction. Once as many deficiencies as possible have been completed, the Contactor may request a final inspection. Contractor shall provide an annotated consolidated punch-out and pre-final inspection list with the request and shall give the Government at least five

(5) working days advance notice before the requested date of final inspection.

14.4.3. The final acceptance inspection will be formally scheduled by the Contractor based upon results of the BOIs and pre-final inspections. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer (KO) to bill the Contractor for the Government's additional inspection cost in accordance with the requirements set forth in the contract.

14.4.4. Upon acceptance, Contractor shall provide COR with primary and alternate warranty

POCs.

15. SITE MAINTENANCE:

15.1. Clean Up: The contractor shall at all times keep the work area, including storage areas, free from accumulation of waste materials. All trash will be removed from the site on a daily basis.

Upon completion of the project, all equipment, materials and other items associated with the project will be removed from the project site and the site will be left clean. All property, including buildings, site improvements, utilities and vegetation at or adjacent to the work site, and which might be damaged during the course of the required work, shall be adequately protected by the Contractor for the duration of the contract. The Contractor shall not operate heavy construction equipment on drives, sidewalks, or lawns without installing suitable protection on these surfaces. The Contractor shall repair all damage determined to be due to his negligence at no additional expense to the Government. Contractor shall take all possible precautions to maintain the work site in a condition that will prevent damage or injury to personnel and real property. The above precautions shall include protection from elements of weather.

15.2. Temporary Storage: For contractor site admin trailer and storage area, Contractor must submit proposed site plan showing proposed location/layout and method of obtaining power NLT ten (10) days before the date the Contractor intends to set trailer or set up storage area.

The Contractor shall be responsible for the safety, security, and maintenance associated with storage areas. Storage areas shall be fenced with six (6) foot chain link fence and kept clean and in a neat and organized appearance at all times. If the storage area is not maintained, the KO may direct the Contractor to store materials off the Installation. See section UTILITIES in this document for specific information regarding Contractor coordination for power to trailer and storage area. Contractor shall complete all temporary electrical work in accordance with applicable codes and standards and DU requirements. Temporary wiring and devices shall be removed at project completion.

15.3. Solid Waste Reporting: Government policy is to apply sound environmental principles in the design, construction and use of facilities. As part of the implementation of that policy: (1) practice efficient waste management when sizing, cutting, and installing products and materials and (2) use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling or reuse.

15.3.1. A minimum of 60 percent by weight of total project solid waste shall be diverted from landfills when reasonable and practicable.

15.3.2. Fort Wainwright Landfill is not available for any construction and/or demolition waste generated by this project.

15.3.3. Contractor is required to comply with Fort Wainwright Solid Waste Reporting requirements as outlined in “Fort Wainwright Solid Waste Reporting Requirements.”

16. UTILITIES:

16.1. Temporary Utilities: Where available, the Contractor may obtain temporary utilities from the systems on the Installation. If available and requested by contractor, the Government may allow the use of existing utilities as temporary utilities (electrical, steam, sewer, and water) available for the Contractor's use during construction at no charge for quantities consumed/used to the contractor. The Contractor shall carefully conserve any utilities furnished without charge. If temporary connections by DU are required to use existing utilities, the costs of temporary connections to be made by DU shall be worked out between the contractor and DU directly.

The utility systems infrastructure for electrical, steam, sewer, water, and condensate on Fort Wainwright have been privatized and are owned by Doyon Utilities, LLC (DU).

The Contractor shall be responsible for coordinating all temporary Utility Requirements/connections directly through their government assigned Contracting Officer’s Representative (COR) to DPW Utilities Privatization Division (UP). For temporary utilities, the Contractor shall be responsible for submitting the correct DU Forms. Contractor shall copy furnish the Government’s COR, QAR, and Project Manager (PM) with any correspondence/communication with DPW UP and/or DU regarding connections/disconnections for any temporary utilities desired or required. The Contractor shall be responsible to pay DU directly for the costs of any work DU must do to make any connections and/or disconnections required for any temporary utilities desired or required.

Once temporary connection is made, the Government will make temporary utilities (electrical, steam, sewer, and water) available for the Contractor's use during construction at no charge to the Contractor for the quantities of temporary utilities consumed. The service application process can take anywhere between 90 and 120 days depending on time of year. The fillable forms and DU required standards for connections to DU infrastructure may be found at:

http://www.doyonutilities.com/dustandards/forms or can be obtained from COR.

a. Utility Service Request also known as service request: Contractor temporary utility connections that are not energized on project site and/or other utility work (upgrades, relocation) required to complete each project/task order. Connections to the DU provided points of demarcation and beyond will the responsibility of the contractor. Contractor shall complete all temporary electrical work in accordance with applicable codes and standards and DU requirements. Temporary wiring and devices shall be removed at project completion.

All temporary utility infrastructure shall meet DU Design and Construction Standards.

These most current version of these standards can be found at:

http://www.doyonutilities.com/dustandards or can be obtained from COR.

b. Utility Disconnect Request: Contractor shall allow a minimum of five (5) working days’ notice to DU prior to the requested disconnect. If disconnect requires outages of multiple facilities or buildings contractor shall request a minimum of two (2) weeks’ notice to DU.

c. Utility Outage Request: Contractor shall allow for the following notices to DU:

• For routine outages, DU requires two weeks prior notice.

• DU will notify the COR at least two (2) weeks prior to any routine work requiring service interruption.

• DU will provide the Contractor with a list of affected buildings. The Contractor shall be responsible for notifying building occupants a minimum of 48 hours before the scheduled outage.

• DU will schedule and notify affected customers in the event that the outages are due to repairs for which DU is conducting.

16.2. Permanent Utilities: Permanent utility systems (electrical, steam, sewer, water, and condensate) will be installed by DU up to the point of demarcation (tie-in points) as indicated by DU at http://www.doyonutilities.com/dustandards. Connections to these tie-in points and beyond shall be the responsibility of the contractor.

The Contractor shall keep the project government COR, QAR,…