Attachment 06 AF 66.pdf
PDF 303 KB Posted
- Attached to
- Construct Park and Ride Area Federal contract opportunity
- Solicitation number
- FA481921R0016
About this file
This document contains a schedule of material submittals for a federal construction project to repair ground antenna radars at Tyndall Air Force Base. The schedule outlines 15 required submittals at various stages of the project, including pricing schedules with the bid, project schedules, design submittals at 50% and 95% completion, work clearance and hazard material inventory forms, weekly progress reports, material approval forms, regulatory permits, construction testing reports, welding permits, draft property transfer documents, pre-final and final inspection reports, as-built drawings, and project closeout documents. Key due dates range from award+14 days for badging applications to the final inspection+7 days for as-built drawings. The schedule provides a framework for the contractor to meet submission requirements and for the Air Force to monitor and approve materials throughout the project lifecycle.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
XLWU 20-8182
REPAIR GATR HF ANTENNAS
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER SOLICITATION/CONTRACT NO.
FA4819-20-C-XXXX
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R T
IF
IC
A T
E
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S
W A
R R
A N
T Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
IN
S
T R
U C
T
IO
N S
A S
-B U
IL
T
D R
A W
IN
G
S
D
IS
K
D O
C U
M E
N T
A T
IO
N
A S
R E
Q U
IR
E
D
R E
Q U
IR
D
U
B M
IS
S
IO
N
D A
T E
D A
T
C
E
IV
E D
I N
C
O N
T R
A C
T
IN
G
D A
T E
T O
C
IV
IL
G
IN
E E
R
IN
G
R E
T U
R N
S U
S P
E N
T
E
S U
B M
IT
T
A L
N U
M B
E R
S
DATE CONTRACTOR NOTIFIED
C O
N T
R A
C T
S
U B
M
IT
T A
L
F
IN
A L
A P
P R
O V
A L
REMARKS
APPROVED DISAPPROVED
1 Pricing Schedule With Bid
2 Meeting Minutes (All Meetings) Meeting + 2
Days
3 Contractor Badging Applications Award + 14
Days
4 Project Schedule - AF Form 3064 NTP + 14 Days
5 50% Design Submittal NTP + 45 Days
6 95% Design Submittal NTP +70 Days
7 100% Design Submittal NTP + 90 Days
Work Clearance Request / Digging Permit - AF
Form 103
10 Days Prior to Commencing
Work
9 HAZMAT Inventory Form 81 & 82 14 Days Prior to
Commencing Work
Progress Report - AF Form 3065 Weekly
Material Approval - AF Form 3000 1 1 1 1 5 Days Prior to
Order
Regulatory Permit Application
Prior to submitting to
Permitting Agency
Construction Materials Testing Reports Upon Receipt
Welding/Burn Permit - As Required Prior to
Commencing Work
Draft DD 1354 - Transfer & Acceptance of Military Real Property
NTP + 90 Days
1 1
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT TITLE
XLWU 20-8182 REPAIR GATR HF ANTENNAS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
AF Form 66
PROJECT NUMBER SOLICITATION/CONTRACT NO.
FA4819-20-C-XXXX
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R T
IF
IC
A T
E
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S
W A
R R
A N
T Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
IN
S
T R
U C
T
IO
N S
A S
-B U
IL
T
D R
A W
IN
G
S
D
IS
K
D O
C U
M E
N T
A T
IO
N
Q U
IR
E
D
R E
Q U
IR
U
B M
IS
S
IO
N
D A
T E
D A
T
C
E
IV
E D
I
C
N
T R
A C
T
IN
G
D A
T E
T O
C
IV
IL
G
IN
E E
R
IN
G
R E
T U
R N
S U
S P
E N
T
E
S U
B M
IT
T
A L
N U
M B
E R
S
DATE CONTRACTOR NOTIFIED
C O
N T
R A
C T
S
U B
M
IT
T A
L
F
IN
A L
A P
P R
O V
A L
REMARKS
APPROVED DISAPPROVED
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT TITLE
XLWU 20-8182 REPAIR GATR HF ANTENNAS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
Pre-Final Inspection Report Pre-Final + 3
Days
Contractor Environmental Reporting Entry - TAFB Form 83
Prior to Final Inspection
Equipment Manuals and Parts Lists Prior to Final Inspection
Final DD 1354 - Transfer & Acceptance of Military Real Property
At Final Inspection
Final Inspection Report Final
Inspection + 5 Days
As-Built Drawings Final
Inspection + 7 Days
Acceptance/Installation 1 With Final Inspection Request
Project Close Out Documents 1 Final
Inspection + 7 Days
1 1 1 1 1
1 1 1 1 1
AF Form 66
File details come from the government source that posted it. Updated .