Attach 4 - Division 01 JOC Specs.pdf

PDF 3 MB Posted

Attached to
Job Order Contract (JOC) Multi-Award IDIQ
Solicitation number
AOCACB24R0002
Issued by

About this file

This document outlines a Job Order Contract (JOC) Multi-Award Indefinite Delivery Indefinite Quantity (IDIQ) construction solicitation issued by the Architect of the Capitol. The JOC will involve a variety of construction projects including maintenance, repair, alteration, mechanical, electrical, heating/air conditioning, demolition, painting, paving, earthwork and historical preservation/restoration within the United States Capitol Complex and outlying sites in the District of Columbia, Virginia and Maryland. Outlying sites include off-site facilities such as climate control book storage facilities, data centers, security training facilities, child care centers and mail facilities. Work may also involve design/build projects as well as new construction of buildings or facilities. The solicitation number is AOCACB24R0002 and interested parties can request a "Non-Disclosure Agreement for Contract Employees (Sensitive but Unclassified Info)" to view a sample project.

View the file

Other files

File Type Posted
Attach 17 - Davis-Bacon Act Wage Determination.pdf PDF
Attach 2 - Instructions to Offerors.pdf PDF
AOCACB24R0002 A04.pdf PDF
Attach 22 - A04 RFIs AOCACB24R0002 JOC.pdf PDF
AOCACB24R0002 A03.pdf PDF
Attach 2 - Instructions to Offerors.pdf PDF
Attach 20 - Subconsultant List.xlsx XLSX spreadsheet
Attach 3 - Evaluation Criteria.pdf PDF
Attach 1 - Section C - Statement of Work (SOW).pdf PDF
Attach 21 - A03 RFIs AOCACB24R0002 JOC.pdf PDF
Attach 19 - A02 RFIs AOCACB24R0002 JOC.pdf PDF
Attach 19 - A02 RFIs AOCACB24R0002 JOC.pdf PDF
Attach 8 - CSI Bid Form Template.xlsx XLSX spreadsheet
AOCACB24R0002 A02.pdf PDF
Attach 17 - Davis-Bacon Act Wage Determination.pdf PDF
Subconsultant List (draft).xlsx XLSX spreadsheet
Attach 17 - Davis-Bacon Act Wage Determination.pdf PDF
AOCACB24R0002 A01.pdf PDF
Attach 9 - AOC Design Standards_Dec 2018.pdf PDF
Attach 18 - Sample Certificate of Insurance (COI).pdf PDF
Attach 6 - Safety Program Performance Questionnaire.docx DOCX document
Attach 11 - AOC BIM Guide_Dec 2014.pdf PDF
Attach 2 - Instructions to Offerors.pdf PDF
Attach 16 - Employee Rights under the Davis-Bacon.pdf PDF
Attach 5 - Sample Project.docx DOCX document
Attach 8 - CSI Bid Form Template.xlsx XLSX spreadsheet
Attach 1 - Section C - Statement of Work (SOW).pdf PDF
Attach 10 - A-E Design Manual_Dec 2013.pdf PDF
Attach 7 - Past Performance Questionnaire.rtf RTF text file
Attach 15 - USCP Vehicle Delivery Procedure Guide.pdf PDF
Attach 13 - Order 7-4 Information Technology Security.pdf PDF
Attach 14 - USCP Request for Criminal History.pdf PDF
Attach 3 - Evaluation Criteria.pdf PDF
AOCACB24R0002.pdf PDF
Attach 17 - Davis-Bacon Act Wage Determination.pdf PDF
Attach 12 - CUI Order 42-4 Security of Controlled Unclassified Information.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AOC P/N //CONTROLLED//

Project Name Submission Date 010000 GENERAL REQUIREMENTS Submission Type

A/E P/N. XXXXX 010000-1 of 9 Version Date: 1/1/2024

//CONTROLLED//

SECTION 010000 – GENERAL REQUIREMENTS

PART 1 - GENERAL

1.01 SUMMARY

A. The provisions of the Division 01 specifications apply to the entire work of the Contract.

B. This Section describes the following in general:

1. Definitions and terms.

2. Background information.

3. Summary of the Work.

4. Supervision and construction procedures.

5. Tax-Exempt work when applicable.

6. Examination of existing site conditions

7. Conflicting requirements.

8. Contract documents maintained on project site.

9. Confidentiality and security of documents.

10. Advertising and promotional materials.

11. Specification and Drawing conventions.

12. References.

C. Related Requirements include, but are not limited to the following:

1. Section 011000 “Summary” for project information, general scope of work, site restrictions, work restrictions, and coordination with occupants.

2. Section 013100 “Project Management and Coordination” for key staff, meetings, administrative submittals, PMIS, and Requests for Information (RFIs).

3. Section 013115 “Project Management Communication” requirements for use of

PMIS.

4. Section 013200 "Construction Progress Documentation" for construction progress schedule, progress reporting, field reports, and requests for extension of time.

5. Section 013300 “Submittal Procedures” for use of PMIS.

1.02 DEFINITIONS AND TERMS

A. The term “Government” means the United States of America and shall be represented by the Architect of the Capitol (AOC), who is the Contracting Officer (AOC52.202-2).

B. The term “Architect” as used in the Contract Documents shall mean the Architect of the Capitol.

C. The term “Associate Architect” shall mean the design professional(s) retained by the Government to prepare designated portions of the Contract Documents.

D. The term “Contracting Officer” (CO) as used in the Contract Documents means the Architect of the Capitol or his duly authorized representative (AOC52.202-2).

E. The term “Contracting Officer’s Representative” (COR) as used in the Contract Documents means the individual delegated limited duties by the Contracting Officer in a contract specific COR appointment Letter. In no instance will the COR be delegated authority to order any change in the contractor's performance which would affect (a) cost or schedule for the contract or scope, or (b) scope, the completion date for intermediate phases or milestones, or overall completion date for contracts.

F. The term “Contract Documents” includes, collectively, the specifications, the contract drawings and the addenda and modifications thereto, if any (AOC52.202-2). These documents are not to be used separately for bid or construction as they represent the

010000 GENERAL REQUIREMENTS Submission Type

A/E P/N. XXXXX 010000-2 of 9 Version Date: 1/1/2024 entirety of the project. The Contractor is responsible for insuring that the documents are used together.

G. The term “Work” includes, but is not limited to, materials, labor, and manufacturer and fabrication of components (AOC52.202-2).

H. The term “Specifications” means the portion of the Contract Documents that consist of the written requirements for materials, equipment, construction systems, standards and workmanship for the Work, and performance of related services (AOC52.202-2).

I. The term “Drawings” means the graphic and pictorial portions of the Contract Documents, wherever located and whenever issued, that show the design, location and dimensions of the Work, and generally includes plans, elevations, sections, details, schedules and diagrams (AOC52.202-2).

J. “Informational Documents” include documents that are included for convenience with the Contract Documents but are not Contract Documents. They are indicated “For Information Only” and may include drawings, hazardous material reports, photographs, historic documents, and the Preservation Policy. The Contractor is expected to independently verify all information shown in informational drawings and to provide the Contractor’s own surveys, testing, and verification of conditions shown therein.

K. “Notice of Award” is the Government’s written confirmation of an award of a contract to the successful bidder, stating the award, award date, and including the COR letter.

L. “Notice to Proceed” is issued by the contracting Officer to the Contractor to begin the Work. Unless specifically authorized in writing, any steps taken in connection with the performance of, or the preparation to perform the Contract, prior to issuance of the Notice to Proceed, will be the responsibility of and at the risk of the Contractor, and without any cost whatsoever to the Government (AOC52.211-6).

M. “Substantial Completion” is defined in Section 017700 “Closeout Procedures.”

N. “Beneficial Occupancy” is defined in Section 017700 “Closeout Procedures.”

O. “Conditions for Final Acceptance” are specified in Section 017700 “Closeout Procedures.”

P. The “Project Management Information System” (PMIS) is defined in Section 013115

“Project Management Communications.”

Q. The terms “Must” and “Shall” are used interchangeably and denote the imperative. “May” denotes the permissive. However, the words “no person may…” mean that no person is required, authorized, or permitted to do the act described.

R. Unless noted otherwise, all number of days indicated are in calendar days.

1.03 BACKGROUND INFORMATION

A. AOC’s purview: The Architect of the Capitol (AOC) is responsible for the maintenance, operation, development, and preservation of over 17,400,000 square feet of building space and over 530 acres of land within the United States Capitol Complex and outlying sites.

AOC facilities are organized by Jurisdictions which include the United States Capitol, the House Office Buildings, and the Senate Office Buildings, the Library of Congress Buildings and Grounds, the United States Supreme Court, the United States Botanic Garden, the United States Capitol Power Plant, the Capitol Grounds, and the Capitol Police Buildings, Grounds and Security. AOC maintains off-site facilities in the District of Columbia and in Virginia and Maryland. Some off-site facilities include climate control book storage facilities, data centers, Security training facilities, child care centers and mail facilities.

B. Higher standard of care: Compared to a typical commercial project, an AOC project requires on the part of the Contractor a higher level of attentiveness and detail, a greater

010000 GENERAL REQUIREMENTS Submission Type

A/E P/N. XXXXX 010000-3 of 9 Version Date: 1/1/2024 amount of look-ahead and pre-planning, and a rigorous regard for security restrictions.

AOC projects seek to preserve the character and history of the Capitol, other Capitol Complex Buildings, or the United States Capitol Grounds. AOC’s design guidelines emphasize building longevity, security and safety, and historic preservation. The Contractor shall accord with these precepts by anticipating greater attention to detail and tighter coordination with stakeholders.

C. Coordination with Other Work: Contractor should anticipate and plan for concurrent projects with overlapping schedules and work areas. The Contractor shall be fully aware as to conditions relating to construction and labor under work by others that may affect the Project. The Contractor shall cooperate in every way with other parties doing work and provide, to the extent their work is affected by his work, all information necessary for the proper execution of their work, without delay (AOC52.236-2).

D. Irregularity of Capitol Complex operations: Capitol Complex operations are, at irregular and unanticipated times, interrupted due to events that can occur on the Capitol Complex, e.g. funerals in the Rotunda, closure of Congressional buildings due to unusual activities, etc. These events can impact Government contractor operations. Any Government contractor that becomes aware of an event that may affect its operations on the Capitol Complex may go to www.aoc.gov/business/contractors to receive current information of the operational status of the Capitol Complex. Before ceasing or limiting its operations, the Contractor must obtain written approval from the Government (AOC52.204-6).

1.04 SUMMARY OF THE WORK

A. Project/Work Identification

1. General: Project name is [PROJECT TITLE], [ADDRESS], Washington, D.C., as shown on Contract Documents prepared by the Government. Drawings and specifications are dated <Insert value>.

2. Summary by Reference: Work of the Contract can be summarized by references to the SCHEDULE, GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, Official Procedure for Making Changes in Contracts, Specification Sections, Drawings, Amendments and Modifications to the contract documents issued subsequent to the initial printing of this Specification and including, but not necessarily limited to, printed material referenced by any of these.

3. General scope of work and other project information are described in Section 011000 “Summary.”

1.05 SUPERVISION AND CONSTRUCTION PROCEDURES

A. The Contractor shall supervise and direct the Work and be responsible for construction means and methods. Contractor is responsible for coordinating all portions of the Work and for jobsite safety.

B. Comply with governing regulations and the codes and standards imposed upon the work.

These requirements include the obtaining of permits, licenses, inspections, releases and similar documentation, as well as payments, statements and similar requirements associated with regulations, codes and standards.

1.06 TAX-EXEMPT WORK

A. For Work in District of Columbia: See AOC52.229-1 “Exclusion of DC Sales and Use Tax on Construction Projects” and FAR52.229-3 “Federal, State, and Local Taxes”.

B. For Work in Maryland & Virginia: See FAR52.229-3 “Federal, State, and Local Taxes”.

010000 GENERAL REQUIREMENTS Submission Type

A/E P/N. XXXXX 010000-4 of 9 Version Date: 1/1/2024

1.07 EXAMINATION OF EXISTING SITE CONDITIONS

A. Execution of the Contract by the Contractor is a representation that the Contractor has visited the Project site, become generally familiar with local conditions, and correlated personal observations with the requirements of the Contract Documents.

B. Contractor shall, before starting each portion of the Work, carefully review the relevant Contract Documents as well as information provided by the Government, shall take any necessary field measurements of existing conditions, and shall observe any conditions at the site affecting the Work.

1.08 CONFLICTING REQUIREMENTS

A. Contractor shall promptly inform the Government, in writing, of any discovered errors, omissions, discrepancies, conflicts, or ambiguities in the Contract Documents before proceeding with any work affected by such factors. Failure to do so will be at the risk of the Contractor (AOC52.211-3).

B. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, promptly submit a Request for Information (RFI) to the Government, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at the Contractor’s own risk and expense (AOC52.236-10). Delays necessitated by requests for interpretation shall not form the basis for a Change to the contract. The Government’s interpretation and decision shall be final.

C. Omissions from the drawings and specifications or the mis-description of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or mis-described details of the Work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications

(AOC52.236-10).

D. Industry Standards: Where compliance with two (2) or more industry standards or sets of requirements is specified, and overlapping of those different standards or requirements establishes different or conflicting minimums or levels of quality, the most stringent requirement is intended and will be enforced, unless specifically detailed language written into Contract Documents clearly indicates that a less stringent requirement is to be fulfilled.

Refer apparently-equal-but-different requirements, and uncertainties as to which level of quality is more stringent, to the Government for a decision before proceeding.

1.09 CONTRACT DOCUMENTS MAINTAINED ON PROJECT SITE

A. Contractor shall keep on the Project site a copy of the full-sized drawings and specifications, approved shop drawings, product data and samples, and shall at all times give the Government access thereto (AOC52.236-10).

B. As specified in Section 017839 “Project As-Built Documents,” store record documents and samples in the field office apart from the Contract Documents used for construction.

1.11 CONFIDENTIALITY AND SECURITY OF DOCUMENTS

A. Before dissemination to subcontractors or other personnel, all Government drawings and electronic copies thereof shall be considered at minimum to be Controlled Unclassified

(CUI).

010000 GENERAL REQUIREMENTS Submission Type

A/E P/N. XXXXX 010000-5 of 9 Version Date: 1/1/2024

1. The following statement shall be imprinted on each page of drawings: “PROPERTY

OF THE UNITED STATES GOVERNMENT. COPYING, DISSEMINATING, OR

DISTRIBUTING THESE DRAWINGS, PLANS OR SPECIFICATIONS TO

UNAUTHORIZED USERS IS PROHIBITED.”

2. Do not remove this notice.

3. Properly destroy documents when no longer needed.

B. Review and follow all additional required security processes and procedures for CUI as prescribed in AOC52.223-3. Pay particular attention to file encryption procedures that are required for most CUI data transfers.

C. Any information supplied to the Contractor by the Government shall be considered confidential and/or proprietary. Contractor shall not disclose such information to a third party without prior written consent of the Government (AOC52.203-5).

1.12 ADVERTISING AND PROMOTIONAL MATERIALS

A. Contractor shall not refer to the project in commercial advertising in such manner as to state or imply that the product or service provided is endorsed or preferred by the Government or is considered by the Government to be superior to other products and services. Submit to the Government for approval any proposed advertising or promotional copy connected in any manner with this Contract and/or the Capitol, other Capitol Complex Buildings, buildings outside of the Capitol Complex, or the United States Capitol Grounds

(AOC52.203-1).

1.13 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications.

The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing

Specification Section numbers found in this Specification.

C. Drawing Symbols: Except as otherwise indicated, graphic symbols used on drawings are those symbols recognized in the construction industry for purposes indicated. Where not otherwise noted, symbols are defined by "Architectural Graphic Standards", published by John Wiley & Sons, Inc., Ninth edition.

1. Mechanical/Electrical Drawings: Graphic symbols used on mechanical and electrical drawings are generally aligned with symbols recommended by ASHRAE. Where appropriate, these symbols are supplemented by more specific symbols as recommended by other recognized technical associations including ASME, ASPE, 010000 GENERAL REQUIREMENTS Submission Type

A/E P/N. XXXXX 010000-6 of 9 Version Date: 1/1/2024

IEEE and similar organizations. Refer instances of uncertainty to the Government for clarification before proceeding

D. Bolding and Underscoring in the Specifications: Are used strictly to assist reader of specification text in scanning text for key words (for quick recall). No emphasis on or relative importance is intended where bolding and underscoring are used.

E. Abbreviations: Actual word abbreviations of a self-explanatory nature have been included in texts. Singular words will be interpreted as plural and plural words will be interpreted as singular where applicable and where full context of the contract documents so indicates.

F. Minimum Quality/Quantity: In every instance, the quality level or quantity shown or specified is intended as minimum for the work to be performed or provided. Except as otherwise specifically indicated, actual work may either comply exactly with that minimum (within specified tolerances) or may surpass the quality of that minimum within reasonable limits. In complying with requirements, indicated numeric values are either minimum or maximums as noted or as appropriate for context of requirements. Refer instances of uncertainty to the Government for decision before proceeding.

G. Definitions: The following definitions are general for the work and may have more specific meanings in other parts of the Contract Documents:

1. Installer: The entity (person or firm) engaged by the Contractor, its subcontractor or sub-subcontractor for performance of a particular unit of work at the project site, including installation, erection, application and similar required operations.

Such entities (installers) shall be expert in the operations they are engaged to perform.

2. Testing Laboratory: An independent entity engaged to perform specific inspections or tests of the Work, either at the Project site or elsewhere, and to report, and (if required) interpret results of those inspections or tests.

3. Indicated: The term "indicated" is a cross-reference to graphic representations, notes or schedules on drawings, to other paragraphs or schedules in the specifications, and to similar means of recording requirements in contract documents. Where terms such as "shown," "noted," "scheduled," and "specified" are used in lieu of "indicated," it is for the purpose of helping the reader locate cross-reference, and no limitation is intended except as specifically noted.

4. Furnish: Except as otherwise defined in greater detail, the term "furnish" means to supply and deliver to the Project site, ready for unloading, unpacking, assembly, installation, etc., as applicable in each instance.

5. Install: Except as otherwise defined in greater detail, the term "install" describes operations at the Project site including unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning and similar operations, as applicable in each instance.

6. Provide: Except as otherwise defined in greater detail, the term "provide" means to furnish and install, complete and ready for intended use, as applicable in each instance.

7. Exposed: Describes an item or surface, exterior or interior, which can be seen by a person outside the building or a person inside a usable space within the building during normal activity.

a. Mechanical and electrical rooms, air handling rooms, storage rooms and penthouses shall be considered to have exposed surfaces, as shall the mechanical and electrical construction within them.

010000 GENERAL REQUIREMENTS Submission Type

A/E P/N. XXXXX 010000-7 of 9 Version Date: 1/1/2024

b. The interiors of closets and alcoves shall be considered exposed surfaces and shall be finished to match the finish of the adjoining room or space, unless another finish is otherwise indicated.

c. The interiors of cabinets shall be considered exposed, but a finish different from that of the exterior may be permitted or required by other sections.

8. Concealed: Describes an item or space not normally seen, occupied or used by building occupants or staff, such as shafts, hoistways, tunnels, ceiling plenums, attics, and crawls spaces.

9. Finished Space: Space normally used by the public, building occupants or staff for primary functions of the building, but does not include mechanical, electrical and elevator equipment rooms, hoistways, tunnels or mechanical penthouses, unless otherwise indicated.

10. Specialist: An individual or firm of established reputation (or, if newly organized, whose personnel have previously established a reputation in the same field), which is regularly engaged in, and which maintains a regular force of workers skilled in either (as applicable) manufacturing or fabricating items required by the contract, installing items required by the contract, or otherwise performing work required by the contract. Where the contract specification requires installation by a specialist, that term shall also be deemed to mean either the manufacturer of the item, an individual or firm licensed by the manufacturer, or an individual or firm who will perform the work under the manufacturer's direct supervision.

1.14 REFERENCES

A. Industry Standards

1. General: Except to the extent that more explicit or more stringent requirements are written directly into contract documents, applicable standards of the construction industry have the same force and effect (and are made a part of the contract documents by reference) as if copied directly into the contract documents, or as if published copies were bound herein, subject to the order of precedence previously stated.

2. Publication Dates: Except as otherwise indicated, where compliance with an industry standard is required, conform to the standard in effect on the date of the Invitation for Bids, or, if referred to in any Amendments, at the date of such Amendments.

3. Abbreviations and Names: The following acronyms or abbreviations as referenced in contract documents are defined to mean the associated names.

Both names and addresses are subject to change but are believed to be accurate as of the date of contract documents:

a. AIA - American Institute of Architects (The); www.aia.org; (202) 626-7300.

b. AISC - American Institute of Steel Construction; www.aisc.org; (800) 644-2400.

c. ANSI - American National Standards Institute; www.ansi.org; (202) 293-8020.

d. ASHRAE - American Society of Heating, Refrigerating and Air-Conditioning Engineers; www.ashrae.org; (800) 527-4723.

e. ASTM - American Society for Testing and Materials International; www.

astm.org; (610) 832-9585.

010000 GENERAL REQUIREMENTS Submission Type

A/E P/N. XXXXX 010000-8 of 9 Version Date: 1/1/2024

f. AWI - Architectural Woodwork Institute; www.awinet.org; (800) 449-8811.

g. AWS - American Welding Society; www.aws.org; (800) 443-9353.

h. CDA - Copper Development Association Inc.; www.copper.org; (800)

232-3282.

i. FMG - FM Global (formerly FM - Factory Mutual System);

www.fmglobal.com; (401) 275-3000.

j. IEEE - Institute of Electrical and Electronics Engineers; www.ieee.org;

(212) 419-7900.

k. NAAMM - National Association of Architectural Metal Manufacturers;

www.naamm.org; (301) 657-3110.

l. NECA - National Electrical Contractors Association; www.necanet.org;

(301) 657-3110.

m. NEMA - National Electrical Manufacturers Association; www.nema.org;

(703) 841-3200.

n. NFPA - National Fire Protection Association; www.nfpa.org; (800)

344-3555.

o. NRCA - National Roofing Contractors Association; www.nrca.net; (800)

323-9545.

p. SMACNA - Sheet Metal and Air Conditioning Contractors' National

Association; www.sspc.org; (877) 281-7772.

q. SSPC - The Society for Protective Coatings; www.sspc.org; (877)

281-7772.

r. UL - Underwriters Laboratories Inc.; www.ul.com; (800) 704-4050.

s. WWPA - Western Wood Products Association; www.wwpa.org; (503)

224-3930.

B. Federal Government Agencies

1. Abbreviations and names: The following acronyms or abbreviations referenced in the Contract Documents indicate names of Standard- or Specification-producing agencies of the federal government. Names and addresses are subject to change but are believed to be accurate and as of the date of the Contract Documents:

a. CFR - Code of Federal Regulations; www.access.gpo.gov/nara/cfr; (202) 512-1530.

b. EPA - Environmental Protection Agency; www.epa.gov; (800) 438-2474.

c. FS - Federal Specification: Available from the following:

1) Defense Automated Printing Service:

www.astimage.daps.dla.mil/online; (215) 697-6257.

2) General Services Administration:

www.fss.gsa.gov/pub/fed-specs.cfm; (202) 619-8925.

3) National Institute of Building Sciences: www.nibs.org; (202) 289-7800.

d. OSHA - Occupational Safety and Health Administration;

www.osha.gov; (800) 321-OSHA.

C. District of Columbia Government Agencies

1. Abbreviations and names: The following acronyms or abbreviations referenced in the Contract Documents indicate names of Standard- or Specification-producing agencies of the DC government. Names and addresses are subject to change but are believed to be accurate as of the date of the Contract Documents:

010000 GENERAL REQUIREMENTS Submission Type

A/E P/N. XXXXX 010000-9 of 9 Version Date: 1/1/2024

a. Department of Energy and Environment (DOEE); 1200 First Street. N.E, Washington, DC 20002; doee.dc.gov; (202) 535-2600.

b. DDOT - District Department of Transportation; 2000 14th Street, NW, 6th Floor, Washington, DC 20009; ddot.dc.gov; (202) 673-6813.

c. DC Water - District of Columbia Water and Sewer Authority; 1385 Canal Street, S.E., Washington DC 20003; www.dcwater.com; (202) 787-2427.

D. Maryland Government Agencies

1. Abbreviations and names: The following acronyms or abbreviations referenced in the Contract Documents indicate names of Standard- or Specification-producing agencies of the Maryland government. Names and addresses are subject to change but are believed to be accurate as of the date of the Contract Documents:

a. Maryland Department of the Environment (MDE); 1800 Washington Boulevard, Baltimore, MD 21230; mde.maryland.gov; (410) 537-3000.

b. American Water Enterprises, LLC.; 1 Water St, Camden, NJ 08102;

www.amwater.com; (856) 955 – 4305

c. Maryland Department of Transportation (MDOT); 7201 Corporate Center Drive, Hanover, Maryland 21076; mdot.maryland.gov; (410) 865-1000.

d. Washington Suburban Sanitary Commission (WSSC); 14501 Sweitzer Ln, Laurel, MD 20707; www.wsscwater.com; (301) 206-4001.

E. Virginia Government Agencies

1. Abbreviations and names: The following acronyms or abbreviations referenced in the Contract Documents indicate names of Standard- or Specification-producing agencies of the Virginia government. Names and addresses are subject to change but are believed to be accurate as of the date of the Contract Documents:

a. Virginia Department of Transportation (VDOT); Northern Virginia office (Manassas and Prince William); 4975 Alliance Drive, Fairfax, Virginia 22030;

www.virginiadot.org; (800)-367-7623

b. Virginia Department of Transportation (VDOT); Northern Virginia office (Culpeper); 1601 Orange Road, Culpeper, Virginia 22701; www.virginiadot.org;

(540) 347-6441

c. Virginia American Water 2223 Duke Street Alexandria, VA 22314;

www.amwater.com; (800) 452-6863

d. Virginia Department of Environmental Quality (VDEQ); 13901 Crown Court Woodbridge, Virginia 22193; www.deq.virginia.gov; (703)-583-3800

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF 010000 – GENERAL REQUIREMENTS

http://www.amwater.com/

011000 SUMMARY Submission Type

A/E P/N. XXXXX 011000-1 of 10 Version Date: 1/1/2024

SECTION 011000 – SUMMARY

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.02 SUMMARY

A. Section includes:

1. Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Work by Government

5. Work under separate contracts.

6. Future Work.

7. Purchase Contracts.

8. Government-furnished products.

9. Contractor-furnished, Government-installed products.

10. Site access and restrictions.

11. Maintenance of Existing buildings and grounds.

12. Storage of materials.

13. Deliveries.

14. Coordination with occupants.

15. Work hours.

16. Work restrictions.

17. Conservation

18. Information Documents

B. Related Requirements include, but are not limited to, the following:

1. Section 010000 “General Requirements” for definitions.

2. Section 013000 “Safety and Health”

3. Section 013100 “Project Management and Coordination”

4. Section 013115 “Project Management Communications” for administrative copmmunications and documentation.

5. Section 013591 “Protection” for protecting Historic Material.

6. Section 015000 “Temporary Facilities and Controls" for limitations and procedures governing temporary use of Government facilities.

7. Section 017300 “Execution”

1.03 PROJECT INFORMATION

A. Project Identification: <Insert Project Title and Number directly as identified in e- Builder>.

1. Project Location: <Insert Project location (street address, city, and state)>.

B. Owner: The United States of America C. Government: Office of the Architect of the Capitol (AOC) D. Associate Architect: The Architect has retained the following design professionals who have prepared designated portions of the Contract Documents:

011000 SUMMARY Submission Type

A/E P/N. XXXXX 011000-2 of 10 Version Date: 1/1/2024

1. < Insert title of design discipline>: <Insert name and contact information for consultant. DO NOT LIST PHONE NUMBER>.

E. Other Consultants: The Government has retained the following design professionals who have prepared designated portions of the Contract Documents:

1. < Insert title of design discipline>: <Insert name and contact information for consultant. DO NOT LIST PHONE NUMBER>.

a. < Insert description of scope of service for other Government consultant>.

F. Web-based Project Software administered by the Government will be used for purposes of managing communication and documents during the construction stage. Refer to Section 013115 “Project Management Communications.”

1.04 WORK COVERED BY CONTRACT DOCUMENTS

A. General scope of work: Briefly and without force and effect upon the contract documents, the work of the Contract can be summarized as follows: [brief description of Project indicating the size, code classification for occupancy and construction type, and general description of major building assemblies]:

1. [The Work includes construction of ..]

2. [The Work includes normal concrete work..]

3. [The Work also requires certain items of equipment, including ..]

4. [Government will provide…]

B. Delivery Method: Design/Bid/Build:

1. Project will be constructed under a single prime contract.

2. Project will be constructed under a single base contract with <number> options.

a. Base Contract: <Insert a brief description>.

b. Option 1: <Insert a brief description>.

c. Option 2: <Insert a brief description>.

1.05 PHASED CONSTRUCTION

A. A/E EDIT AS DIRECTED BY AOC PM: Contractor shall achieve substantial completion (defined as Substantial Completion #1) of all work required to complete/deliver Phase 1 of the Work per the contract documents within XXX calendar days of the issuance of the

NTP.

Further, that Contractor shall achieve substantial completion (defined as Substantial Completion #2) of all work required to complete/deliver Phase 2 of the Work per the contract documents within XXX calendar days of the issuance of the NTP.

Work required to achieve Substantial Completion 1 and 2 may overlap, however Contractor shall achieve Substantial Completion #2 ninety (90) calendar days prior to Final Acceptance. In the event Contractor is able to achieve Substantial Completion #1 and #2 simultaneously within XXX calendar days of the issuance of the NTP and the Government accepts Contractor’s CPM schedule illustrating the same, the Contractor shall achieve Substantial Completion ninety (90) calendar days to Final Acceptance.

B. The Government reserves the right to hold retainage for actual costs incurred by the Government for the Contractor’s failure to achieve Final Acceptance within the time allowed by contract between Substantial Completion and Final Acceptance

C. Retain one of two subparagraphs below.

011000 SUMMARY Submission Type

A/E P/N. XXXXX 011000-3 of 10 Version Date: 1/1/2024

D. No phasing plan is included in the Contract Documents. The Contractor is expected to complete all work sequentially to provide the minimum disruption of parking and normal building operations in the area.

E. Provide a Phasing Plan, as specified in Section 013100 “Project Management and Coordination.”

1.06 WORK BY GOVERNMENT

A. General:

1. Cooperate fully with the Government so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Government.

Coordinate the Work of this Contract with work performed by Government.

2. The Government’s staff will need to perform general maintenance work in areas adjacent to or within the boundaries of this contract.

3. The Government’s staff may be remodeling spaces in areas adjacent to Work being performed by this contract.

4. The Government’s staff may be preparing for special events in areas adjacent to Work being performed by this contract.

B. Preceding Work: Government will perform the following construction operations at Project site. Those operations are scheduled to be substantially complete before work under this Contract begins.

1. < Insert a brief description of work performed by Government>

C. Concurrent Work: Government will perform the following construction operations at Project site. Those operations will be conducted simultaneously with Work under this Contract.

1. < Insert a brief description of work performed by Government>.

D. Subsequent Work: Government will perform the following additional work at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory Work under this Contract.

1. < Insert a brief description of work performed by Government>

1.07 WORK UNDER SEPARATE CONTRACTS

A. General

1. Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying Work under this Contract or other contracts.

2. Coordinate the Work of this Contract with work performed under separate contracts.

Schedule and phase all work activities accordingly.

3. Failure to coordinate with others will not be reason for a change in contract time or price.

B. Preceding Work: Government [has awarded] [will award] [will not award] separate contract(s) for the following construction operations at Project site. Those operations are scheduled to be substantially complete before Work under this Contract begins

1. < Insert name of the Contract>: To <Insert name of separate Contractor> [to] [for]

<Insert a brief description of work performed under separate contract>.

C. Concurrent Work: Government [will not award] [has awarded] [will award] [and will assign to Contractor] separate contract(s) for the following construction operations at

011000 SUMMARY Submission Type

A/E P/N. XXXXX 011000-4 of 10 Version Date: 1/1/2024

Project site. Those operations will be conducted simultaneously with work under this Contract.

1. < Insert name of the Contract>: To <Insert name of separate Contractor> [to] [for]

<Insert a brief description of work performed under separate contract>.

D. Subsequent Work: Government [will not award] [has awarded] [will award] separate contract(s) for the following additional work to be performed at site following Substantial Completion. Completion of that work will depend on successful completion of preparatory Work under this Contract.

1. < Insert name of the Contract>: To <Insert name of separate Contractor> [to] [for]

<Insert a brief description of work performed under separate contract>.

1.08 FUTURE WORK

A. The Contract Documents include requirements that will allow the Government to carry out future work following completion of this Project; provide for the following future work:

1. < Insert description of future work requiring consideration during construction of the

Work of this Contract>

1.09 GOVERNMENT-FURNISHED PRODUCTS

A. Government will furnish products indicated. The Work includes receiving, unloading, handling, storing, protecting, and installing Government-furnished products [and making building services connections].

B. Government-furnished Products:

1. <Insert description, in separate subparagraphs, for each Government-furnished product>.

1.10 CONTRACTOR-FURNISHED, GOVERNMENT-INSTALLED PRODUCTS

A. Contractor shall furnish products indicated. The Work includes unloading, handling, storing, and protecting Contractor-furnished products as directed and turning them over to Government at Project closeout, or before project closeout as directed by Government

B. Contractor- Furnished, Government-Installed Products:

1. < Insert description, in separate subparagraphs, for each Contractor-furnished, Government-installed product>.

1.11 SITE ACCESS AND RESTRICTIONS

A. Access to Site: All vehicles and contents, used by the Contractor and its subcontractors, which enter or leave United States Government property during the performance of the Work, will be subject to clearance, inspection and identification procedures conducted by the United State Capitol Police (USCP) (AOC52.223-5 & AOC52.223-8) for projects in DC & Virginia or the United States Army for Maryland Projects.

B. Areas of Use: Limit use of site to the areas indicated on Drawings and as indicated by requirements of this Section. Do not disturb portions of Project site beyond areas in which Work is being performed. Do not assume Contractor has access to any other site or facility.

1. Limits: Refer to Section 015500 “Security Requirements.”

2. Construction Compound: Refer to Section 015500 “Security Requirements.”

3. Secure areas: Refer to Section 015500 “Security Requirements.”

C. Driveways, Walkways and Entrances

011000 SUMMARY Submission Type

A/E P/N. XXXXX 011000-5 of 10 Version Date: 1/1/2024

1. Keep driveways, parking garage, loading areas, and entrances serving premises clear and available to Government’s staff and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.

2. Existing accessible entrances and accessible paths of travel must remain open and accessible at all times.

3. Public streets, driveways, and walkways adjacent to the Project Site shall not be blocked or obstructed at any time during the performance of the Work without proper authorization.

4. Walkways: Government will coordinate the use of sidewalks and other pedestrian walkways with other stakeholders.

5. Maintain driveways between and around combustible material storage piles at least 15 feet wide and free of accumulation or rubbish, equipment and materials. Maintain access for fire-fighting equipment.

D. Construction Parking: Parking space for personal vehicles and construction vehicles is not available on the Project site.

1. A worker’s Government badge may be removed if Government policies, such as restricted parking, are violated.

E. Signs and Advertising: No signs, other than safety signs and project identification signs, may be erected at the Project site. Refer to requirements in Section 015000 “Temporary Facilities and Controls.”

1.12 MAINTENANCE OF EXISTING BUILDING AND GROUNDS

A. Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

B. Comply with requirements for protection of installed construction and existing facilities, as specified in requirements of Section 017300 “Execution” and Section 013591 “Protection” for protection of historic materials and fine art.

C. Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1. Contractor is responsible for all grounds maintenance within the construction compound.

D. Maintain clearances from physical infrastructure such as security devices and fire hydrants.

1.13 STORAGE OF MATERIALS

A. Storage and Loading Plan: Submit a plan that itemizes proposed storage and handling of materials if the Government has approved a storage area. The Government does not normally provide or approve a storage locations unless specifically identified in the awarded Drawings.

B. Storage of Materials: Materials shall be stored in a dry location, off the ground and in such manner as to prevent damage or intrusion of foreign matter and to avoid interference with the activities of the Government.

1. Materials, equipment, tools, and appliances shall be stored only at locations previously approved by the Government.

011000 SUMMARY Submission Type

A/E P/N. XXXXX 011000-6 of 10 Version Date: 1/1/2024

2. Keys/combinations to all locked containers or storage units shall be provided to the Government whom will provide them to Emergency Personnel when required.

3. Removed items indicated to remain the property of the Government shall be stored on site where directed by the Government.

C. Materials and equipment to be demolished or removed from Project site:

1. All materials which, in the opinion of the Government, have become damaged or otherwise unfit for use during delivery or storage shall be immediately removed from the Project site and replaced by the Contractor at no additional cost to the Government.

2. Existing materials and equipment that are removed as part of construction operations and that are not to be reused or salvaged as Government property shall become the property of the Contractor and shall be removed from the Project site. Storage or sale of excess salvageable materials and equipment is not permitted on site.

D. Storage of excess fuel on the Project site is prohibited. Fuel quantity that can be consumed in one 24-hour period is allowed on site.

1.14 DELIVERIES

A. Schedule and Log

1. Schedule deliveries to minimize use of driveways and entrances by construction operations.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

3. Work in any one area shall not commence until all materials and resources are available to execute the work in one continuous operation and with minimum disturbance.

4. A/E: ONLY LEAVE THE BELOW NOTE IN WHEN WORK IS AT THE CAPITOL ON

THE PLAZA, IF NOT DELETE ENTIRELY. Monthly Delivery Schedule: Submit a monthly delivery narrative 5 business days prior to the first business day of each month for all vehicles that require access to park on the plaza for any period of time.

a. Narrative shall include parking location, date and hours, reason for request to park on the plaza, summary of materials that will be in the vehicle, and the list of drivers with vehicle information from the weekly log.

b. Coordinate with Monthly Storage and Loading Plan.

5. Weekly Log: Provide the driver and vehicle information in a weekly log no less than 5 business days prior to the delivery so that the vehicle and driver can be screened and cleared for delivery.

a. Provide the driver’s name; date of birth; social security number; vehicle’s make, model, year, color, VIN #, license plate number and state; and company name on the side of the vehicle, if any.

b. Information for vehicles carrying hazardous materials or flammable materials must to be submitted on a separate log.

c. Driver and vehicle information must remain the same as the information submitted. If a different driver or vehicle will be used, the delivery must be rescheduled. Update driver and vehicle information no less than 5 business days in advance of the scheduled delivery or as directed by the USCP for projects in DC or United States Army for projects in Maryland and Virginia

011000 SUMMARY Submission Type

A/E P/N. XXXXX 011000-7 of 10 Version Date: 1/1/2024

B. Delivery Screening: Refer to Section 015500 “Security Requirements” and AOC52.223-8 “Delivery Vehicle Inspection Requirements ”.

C. Hours of Delivery

1. Normal material deliveries shall be made to the <Insert appropriate Building’s

Loading doc that will be used, obtain from Jurisdiction Rep> between <Insert value from AOC Design Standard 2018, Table 1.6.1-1> and <Insert value from AOC Design Standard 2018, Table 1.6.1-1> , Monday through Friday. Deliveries that will disrupt the flow of traffic, both vehicular and pedestrian, must take place prior to 7 AM or after 7 PM. All deliveries must be schedule a minimum of 5 business days in advance of arrival and must be screened at a capitol police screening facility prior to arrival at the site

2. Flammable fuel deliveries must occur through the <Insert location from Jurisdiction Rep> between 12 PM and 3 AM. Such deliveries include small tanks or cans transported by pick-up trucks or other vehicles. USCP will only allow fuel onsite that will be used within a 24 hour period. Notify the Government a minimum of 48 hours in advance of the delivery to obtain approval and access by the USCP for projects in DC and Virginia or United States Army for projects in Maryland.

D. Traffic Control

1. Where the normal flow of traffic will be disrupted, provide a sufficient number of flagmen to control all lanes of traffic for vehicular deliveries. Contractor shall request approval by the Government for vehicles to use the sidewalk.Vehicles will not be permitted on the sidewalks without sufficient number of flagmen present.

2. Contractor shall coordinate flagger operations with Government to avoid any impacts to USCP.

1.15 COORDINATION WITH OCCUPANTS

A. [Full] [Partial] Occupancy: Government will occupy site and [existing] [adjacent] building(s) during entire construction period, [with the exception of areas under construction].

1. Coordinate with Government during construction operations to minimize conflicts and facilitate usage. Perform the Work so as not to interfere with staff day-to-day operations. Comply with the requiremements of Section 014126 “Permit Requirements” regarding “Work Authorization Plans” (WAP) submission requirements before disturbing occupants or disrupting utilities. Schedule interruptions during times when the facility is unoccupied.

2. Take all precautions necessary to protect the building and its occupants during the construction period.

3. Maintain building in a safe and weather-tight condition throughout the construction period.

4. Clear passage:

a. Maintain existing exits unless otherwise indicated.

b. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.

c. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and approval of authorities having jurisdiction.

011000 SUMMARY Submission Type

A/E P/N. XXXXX 011000-8 of 10 Version Date: 1/1/2024

5. Temporary Elevator Use: The Government may designate elevators available for use by Contractor’s personnel. Use of other than designated elevators is prohibited.

B. Beneficial Occupancy of Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Final Acceptance of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the Work.

1. Contracting Officer shall issue a Certificate of Substantial Completion for each specific portion of the Work to be occupied if occupation peceeds final acceptance of the Work.

2. Obtain an Occupancy Permit from the Building Official before any Beneficial Occupancy.

3. Before Beneficial Occupancy can be agreed to, the requirements for “Substantial Completion” in Section 017700 must be met.

4. On Beneficial Occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of Work.

1.16 WORK HOURS

A. Standard On-site Working Hours

1. Other than Noise-producing Work as defined in this Section, Work may be conducted from <Insert value> to <Insert value> Monday through Friday. No work under this Contract shall be performed on Saturdays, Sundays or Federal holidays and, for work performed in the District of Columbia, Presidential Inaugural Day, except with prior approval of the Government.

2. Submit to the Government a written request to perform off-hours work at least 7 calendar days in advance.

3. Noise-producing Work

a. Noise-producing Work includes, but is not limited to, the erection and removal of scaffold, the use of grinders, saws, pneumatic tools, hammers, drills or other noise-producing equipment at the face of the building within 10 feet of any door or window opening.

b. The maximum allowable decibel level is 40-45 dB for interior work areas and 60 dB from the property line.

c. Noise-producing work shall be conducted between <AM/PM>, and <7AM/PM>, or anytime on weekends.

4. Sunday hours: Work may be allowed at all hours with 14 days prior notice and approval of the Government.

B. Suspension of Work

1. Due to special events or <Insert value> work at <Insert value>, it may be necessary to stop work.

2. Stop work directions will be issued by the Contracting Officer and will not exceed a total of <Insert value> work hours (not man hours) per year.

3. Stop work may be for only a few hours or for several days.

4. Track all Stop Work time…

This is the start of the file's text. The full file is on GovTribe.