About this file

This technical drawing is a detailed engineering schematic for a Remote Steam Drum Internal Davit and Details, produced by John Piché Company, Inc. for Lakeland Electric's Unit No. 5 Power Generation Project. The document is marked "Issued for Construction" and contains multiple detailed views and technical specifications for various mechanical components, including assembly drawings for items like the Manway/Davit Arm Assembly (Detail Items #1-#10). The drawing is specifically coded as WBS 25-1901-4029 and includes precise measurements, cross-sectional views, and technical annotations for what appears to be critical power generation infrastructure components.

The technical drawing provides intricate engineering specifications that align with Lakeland Electric's upcoming Spring Outage scheduled from February 22nd to May 5th, 2025. The level of detail suggests this is a critical component of a complex power generation maintenance and upgrade project, with precise manufacturing and installation requirements for HRSG (Heat Recovery Steam Generator) system components. The drawing demonstrates the technical complexity of the planned maintenance work, which involves specialized welding and fabrication of steam drum internal components, likely requiring contractors with advanced technical capabilities in industrial boiler and power generation infrastructure maintenance.

View the file

Other files

File Type Posted
Unit_5_Spring_2025_Outage_Contractor_Services_(Addendum_#6_Revision).pdf PDF
ATTACH_31_997003-CB-015_HP_Superheater_2_Back_Lower_Gas_Baffles.pdf PDF
ATTACH_30_997003-CB-014_HP_Superheater_3_Middle_Lower_Gas_Baffles.pdf PDF
ATTACH_29_997003-CB-013_Reheater_2_Front_Lower_Gas_Baffles.pdf PDF
ATTACH_28_997002-CA-11_Fabric_Expansion_Belt_for_12_Inch_Nozzle_and_997002-CA-012_PAcking_Gland_for_16_inch_Nozzle.pdf PDF
ATTACH_27_25-1300-4081_Fabric_Expansion_Belt_for_14_inch_Nozzle.pdf PDF
ATTACH_26_25-1300-4080_Fabric_Expansion_Belt_for_10_inch_nozzle.pdf PDF
City_of_Lakeland_Terms_-_2024.docx DOCX document
2025-RFP-002_Mandatory_Pre-Bid_Attendance_List.pdf PDF
ATTACH_09_25-1300-4069_NE_Field_Joint_Details_at_Floor.pdf PDF
ATTACH_06_25-1300-4028_NE_Floor_Field_Seam_Liners.pdf PDF
ATTACH_24_Bundle_Layout_Plan_View_Color.pdf PDF
ATTACH_17_25-1313-4121_NORFLEX_HRSG_Outlet_EJ.pdf PDF
ATTACH_02_25-1300-4003_-_HRSG_General_Arrangement_Left_Side.pdf PDF
ATTACH_14_25-1300-5031_NE_Nozzle_Penetrations_COLS_5_to_8_and_11_to_14.pdf PDF
ATTACH_20_997000_SH_E1_NEPIPINGDATA.pdf PDF
ATTACH_08_25-1300-4068_NE_Floor_Liner_Layout.pdf PDF
ATTACH_23_Bundle_Layout_Elevation_View_Color.pdf PDF
ATTACH_05_2024-REQ-343_Break_out_pricing.pdf PDF
ATTACH_01_25-1300-4002_-_HRSG_General_Arrangement_Right_side.pdf PDF
ATTACH_19_25-1317-5060_NE_INTERCONNECT_PIPING_SH_2.pdf PDF
ATTACH_18_25-1317-5059_NE_INTERCONNECT_PIPING_SH_1.pdf PDF
ATTACH_05_25-1300-4027_NE_Wall_Field_Seam_Liners.pdf PDF
ATTACH_13_25-1300-4100_NE_HP_Evaporator_Floor_Panel_COLS_7_to_8.pdf PDF
ATTACH_07_25-1300-4064_NE_Plan_View.pdf PDF
ATTACH_16_25-1313-4120_NORFLEX_Stack_Inlet_EJ.pdf PDF
ATTACH_11_25-1300-4087_NE_HP_EVAP_Casing_Assembly_Diagram_COL_7_to_8.pdf PDF
ATTACH_03_25-1300-4005_NE_HRSG_Elevation_View_Right_Side.pdf PDF
ATTACH_12_25-1300-4099_NE__Reheater_#1_&_HPSH_#1_Floor_Panel_COLS_6_to_7.pdf PDF
ATTACH_10_25-1300-4072_NE_Field_Corner_Angles.pdf PDF
ATTACH_22_2020031140-GA-100_10-HPDSHSPOOL.pdf PDF
ATTACH_21_2020031140-GA-007_10-HPDSHSPOOL.pdf PDF
ATTACH_04_25-1300-4006_NE_HRSG_Plan_View.pdf PDF
Indemnification_2025_Contractor.doc DOC document
PSM_-_Contractor_Annual_Audit_Form.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .