This solicitation is for a munitions storage lighting replacement project at the 177th Fighter Wing in Egg Harbor Township, New Jersey. The contractor will demolish and remove existing exterior and interior lighting, including poles, bases, wiring, and wall packs as indicated on the demolition drawings. The contractor will then provide and install new exterior light fixtures, poles, concrete bases, wall mounted fixtures, electrical panels, and wiring to provide lighting in accordance with the project drawings. The contractor will also remove, replace, and provide interior lighting within the munitions bunker facilities as detailed on the interior lighting drawings. The total small business set-aside project has a magnitude between $500,000 and $1,000,000. Bidders must interpret the solicitation and attachments, including drawings, specifications, and statement of work to address all requirements. Bid, payment, and performance bonds are required for all proposals and contracts over $150,000.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIAL SUBMITTALS | Repair MUNS Lighting | AQRC162004 | |||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | Contractor | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||
| NUMBER OF COPIES REQUIRED | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | ||||||||||||||
| SUBMITTAL NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MFGR'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATION INSTRUCTION | PERFORMANCE TEST REPORT | OTHER | SUBMISSION DATE | DATE CONTRACTOR NOTIFIED | ||||||||
| ALL SUBMITTALS SHALL BE SUBMITTED THROUGH PROJECT MANAGEMENT SOFTWARE PER THE SOW | APPROVED | DISAPPROVED | |||||||||||||||||||
| 1 | Job Specific Safety Plan | x | Prior to NTP being issued | 1 | |||||||||||||||||
| 2 | Job Specific Quality Control Plan | x | Prior to NTP being issued | 2 | |||||||||||||||||
| 3 | AF 3064 (or equivalent)– Project Schedule | x | Prior to NTP being issued | 3 | |||||||||||||||||
| 4 | AF 3065 – Progress Report | x | Prior to NTP being issued | 4 | |||||||||||||||||
| 5 | Key Personnel Letter | x | Prior to NTP being issued | 5 | |||||||||||||||||
| 6 | MSDS Sheets as required | x | 6 | ||||||||||||||||||
| 7 | Type A Light Fixture per LED Lighting Fixture Schedule | x | x | x | x | x | 7 | ||||||||||||||
| 8 | Type F Light Fixture per LED Lighting Fixture Schedule | x | x | x | x | x | 8 | ||||||||||||||
| 9 | Type C Light Fixture per LED Lighting Fixture Schedule | x | x | x | x | x | 9 | ||||||||||||||
| 10 | Type J Light Fixture per LED Lighting Fixture Schedule | x | x | x | x | x | 10 | ||||||||||||||
| 11 | NEMA 3R Light Switch for type C | x | x | x | x | x | 11 | ||||||||||||||
| 12 | Photocells | x | x | x | x | x | 12 | ||||||||||||||
| 13 | Surface Mounted Switch | x | x | x | x | x | 13 | ||||||||||||||
| 14 | 3/4" GRS Conduit, electrical boxes, and other associated components | x | x | x | x | x | 14 | ||||||||||||||
| 15 | #12, #10, #8, #6 and other associated wiring | x | x | x | x | x | 15 | ||||||||||||||
| 16 | Lighting Control System | x | x | x | x | x | 16 | ||||||||||||||
| 17 | Light Poles | x | x | x | x | x | 17 | ||||||||||||||
| 18 | Light Pole Bases | x | x | x | x | x | 18 | ||||||||||||||
| Munitions Admin Electrical Rm Lay-Out Sketch | x | x | Sheet ES103 GN 4 | ||||||||||||||||||
| 19 | Other submittals as required by Specifications or Drawings | x | x | x | x | x | 19 | ||||||||||||||
| 20 | Site Area Restoration Materials | x | x | x | x | x | 20 | ||||||||||||||
| 21 | Field Test Reports | x | NLT 5 Days from date of test | 21 | |||||||||||||||||
| 22 | Close-out Documents - Electronic copies only | Prior to Final Acceptance & Payment | 22 | ||||||||||||||||||
| 23 | Contractor Warranties | 3 | Prior to Final Acceptance & Payment | 23 | |||||||||||||||||
| 24 | Record Drawings | 3 | Prior to Final Acceptance & Payment | 24 | |||||||||||||||||
| 25 | O&M Manual | 3 | 3 | 3 | 3 | Prior to Final Acceptance & Payment | 25 | ||||||||||||||
| 26 | Maintenance Summary Forms | 3 | Prior to Final Acceptance & Payment | 26 | |||||||||||||||||
| 27 | DD 1354 Worksheet | 1 | Prior to Final Acceptance & Payment | 27 |