UNITED STATES ARMY GARRISON DAEGU

OFFICE OF DIRECTORATE OF PUBLIC WORKS

ENGINEERING DIVISION

DESIGN AND TECHNICAL REVIEW BR

UNIT #15746

APO AP 96218-5746

AMIM-DAP-G 14 June 2022

STATEMENT OF WORK

FOR

CONSTRUCT PRE-ENGINEERED METAL LSA AT FOS

(WORK PLAN)

CAMP CARROLL*

PROJECT NO. H20-10054-2J

TABLE OF CONTENTS

1. Technical Provisions - I: General Description of work to be completed

2. Technical Provisions - II: Technical Detail Specifications

3. Technical Provisions - III: Special Conditions

4. Technical Exhibit - I: Deliverable Schedule

TECHNICAL PROVISIONS - I

GENERAL DESCRIPTION OF WORK TO BE COMPLETED

PROJECT NO TITLE LOCATION

H20-10054-2J Construct Pre-Engineered Metal LSA at FOS (Work Plan) Camp Carroll*

DESCRIPTION: The work to be performed shall be in accordance with all drawings and specifications provided under this contract.

a. Work by Contractor:

(1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and specifications.

(2) The contractor shall construct pre-engineered metal LSA at FOS, Camp Carroll* in accordance with the specifications and drawings.

b. Work by In-House Labor: Not applicable to this project.

c. Work by Troop Labor: Not applicable to this project.

(3) Performance Period: Shall be 150 calendar days, including 120 days for procurement of US origin materials after Notice to Proceed (NTP) is issued at the Post Award Conference (PAC). There will also be a Pre-Construction Conference (PCC) upon government’s acceptance of the 100% drawing package and respective design analysis.

PRINCIPAL FEATURES: This project shall include the following:

Work Plan Special Requirement

1. It is highly recommended for the contractor to attend the site orientation conducted by the contracting office and DPW to get a clear understanding of the site overview which could impact design and construction.

2. The contractor shall submit conceptual drawings, including scope of work to DPW, Area IV, Design branch via 411th Contracting Support Brigade (CSB) included with their proposal. The conceptual drawing will be reviewed for its acceptability during the technical evaluation stage.

3. The contractor shall submit 50% (Twenty (20) calendar days after the PAC) and 100% (Thirty (30) calendar days after the PAC) structural drawings and structural analysis by registered and certified engineer with bill of material and quantities for approval prior to commencing construction unless otherwise at government’s discretion. It will be up to the Government who may allow concurrent work such as demolition to be ongoing during the design phase.

4. The contractor shall consider that the proposed site layout plan may change depending on the site conditions and therefore, attendance at site survey during the solicitation phase is encouraged.

TP I-1

5. The contractor shall submit and get approval of shop drawings and detail drawings for construction.

6. Construction materials can be carried into the construction site every Tuesday through Thursday.

Schedule #I, Construction/ Alteration (L): All work shall be in accordance with the attached drawings and specifications.

A. Civil Work

1. Install fire water line (D=150, PVC), post indicator valve including tapping sleeve, tapping valve, valve box, other fittings, and necessary accessories, thrust blocks, and anchor blocks.

2. Install sewer lines, surface cleanout, and sewer manhole.

3. Construct sidewalk, concrete curbs, and pavement.

4. Construct storm drain lines and surface inlets, manholes curbs and gutters.

5. Construct landscaping.

B. Architectural Work

1. Construct reinforced concrete foundation and steel structure building

2. Install standing seam metal roof system, roof insulation panel, fasia and soffit, rain gutter, downspout, and wall insulation panel system with necessary accessories

3. Install canopy for 1st floor entrance.

4. Install concrete stoop for 1st floor entrance.

5. Install exterior steel structure type stairway and stair guard rail.

6. Install partition wall with metal stud, blanket insulation, gypsum board with necessary accessories.

7. Install door and door frame with door hardware.

8. Install aluminum window, blind and oak window sill.

9. Install ceiling suspension system with acoustical ceiling tile.

10. Install ceiling suspension system with gypsum board finish.

11. Paint interior surface.

12. Install stair rubber flooring.

13. Install vinyl composition tile and vinyl base.

TP I-2

14. Install epoxy finish flooring.

15. Install building signage and room signage.

C. Mechanical Work

1. Provide new split system heat pump units complete with associated refrigerant pipes, condensate pipes, insulation, insulation jacketing, thermostats, thermostat lock boxes, central controller, access doors, stainless steel wire-mesh screens, concrete pads, concrete splash blocks and all necessary accessories and parts.

2. Provide new ventilation system including dedicated outdoor air system, roof exhaust fan with associated ductwork, control panel, diffusers, registers, dampers, controllers, thermostats, emergency shut-off switches, concrete pads, refrigerant pipes, condensate pipes, insulation, access doors, concrete splash block and all necessary accessories and parts.

3. Provide new electric wall heater and unit heater as indicated.

4. Provide new drainage system for valve room including necessary accessories and parts.

5. Provide new wet pipe fire sprinkler system with all necessary accessories and parts as indicated.

(The fire sprinkler routing and pipe sizes indicated in this drawing are at conceptual level. The contractor shall submit drawing(s) with FPE`s (fire protection engineer) stamp in accordance with applicable codes and regulation prior to construction for approval from DPW and Fire Department. The contractor bears the full responsibility for respective costs in meeting these codes and associated regulations.)

D. Electrical Work

1. Install new led lighting fixtures including wiring, toggle switches, occupancy sensors, conduit, and necessary accessories.

2. Install new power system including transformer, watt hour meter, service lateral, panel board, branch circuit breakers, safety switch, motor starters, receptacles, wiring, conduit, and necessary accessories.

3. Install communication system including telephone/ Lan outlets, conduit, splice can, outside plant cable and necessary accessories.

4. Install lightning protection system including air terminal, down conductor, ground rod and necessary accessories.

5. Install new fire alarm system including fire alarm/mass notification control panel, building transceiver, fire alarm detectors, monitor modules, combination audio/visual signal strobes, conduit, wirings, and necessary accessories.

Schedule #II, Repair/ Maintenance (K): All work shall be in accordance with the attached drawings and specifications.

TP I-3

A. Civil Work

1. Remove existing trees, shrubs, boulders, earth berms and ground covers.

2. Remove existing pavers.

3. Remove existing concrete surface inlets.

4. Provide earth works.

5. Sod with top soil and solid sodding.

6. Reroute/relocate existing underground and aboveground utility lines.

B. Electrical Work

1. Replace existing high voltage cable including splice kit, conduit, and necessary accessories.

TP I-4

TECHNICAL PROVISIONS - II

TECHNICAL DETAIL SPECIFICATIONS

PROJECT NO TITLE LOCATION

H20-10054-2J Construct Pre-Engineered Metal LSA at FOS (Work Plan) Camp Carroll*

GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated 30 October 2015, issued by the Department of the Army, Installation Management Command. The most current specifications are available (for referral purposes only) on the USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.

TP II – 1

TECHNICAL PROVISIONS - III

SPECIAL CONDITIONS

PROJECT NO TITLE LOCATION

H20-10054-2J Construct Pre-Engineered Metal LSA at FOS (Work Plan) Camp Carroll*

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which is incorporated in-to the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours (Monday through Saturday) except for Korean Legal Holidays. Any proposed change in working hours must be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR). Please note that there will be an exception for night shift when working on the fire alarm system.

3. NOTIFICATION OF INSPECTION SECTION: The contractor shall also give the project inspector seven (7) working days’ notice prior to each concrete placement, field test, weld application, protective coating application, or any other work deemed by the Government to require inspection.

4. COORDINATION: The contractor shall coordinate his work with all others (subcontractor and government agencies) involved in this project and shall cooperate with all other contractors and government agencies so as to facilitate the general progress of the work. Before proceeding with any work, the contractor and/or subcontractor shall consult applicable drawings and specifications for each trade involved.

5. CONSTRUCTION: The contractor shall submit a request for the construction permit at least ten (10) working days prior to the starting of work. The request shall be submitted to the COR for approval.

6. MATERIALS COMPLIANCE: The contractor shall make certain all materials used meet the requirements of the contract and proof thereof upon request of the COR. Materials not meeting the requirements of the contract shall not be brought to the job site. All materials shall be new and the standard products of a manufacturer regularly engaged in the manufacturing of such materials.

7. HOISTING AND MOVING EQUIPMENT: The Contractor and each subcontractor shall provide and be responsible for all cranes, lifts, and other equipment necessary for proper and efficient movement of materials. The equipment shall be provided with proper guys, bracing, safety devices, and any other items, as required by law.

8. EQUIPMENT: All contractor equipment shall be subject to functional and safety inspection by the COR. Equipment not completely safe or functional shall be repaired and accepted by the government before work is initiated.

TP III – 1

9. RECORD DRAWINGS: During performance of work, the contractor shall accurately record and delineate on a set of full-size blue line prints of contract drawings any changes in such work which constitute any change from the original contract drawings per government’s approval. The set of drawings (one original and one blue line print), thus corrected and changed, usually referred to as “As-Built Drawings”, shall be delivered to the COR at the final acceptance/inspection of the completed work by the Government.

10. US ORIGIN MATERIALS: If applicable, all US Origin Materials will be ordered immediately after Notice to Proceed dependent on Government’s direction if such material is not yet determined.

11. RELEASE OF FACILITIES WITH U.S. ORIGIN MATERIALS: If applicable, Building/facility will not be released to the contractor by the COR until all U.S. origin building construction supplies are available or due within such a time frame that there will be no delay in project completion.

12. UTILITY CUTOVERS AND INTERRUPTIONS: Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and U. S. Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours." Ensure that new utility lines are complete, except for the connection, before interrupting existing service. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption shall be limited to 4 hours. This time includes for deactivation and reactivation.

13. WORK OUTSIDE REGULAR HOURS: Work outside regular working hours requires Contracting Officer approval. Make request fourteen (14) calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During the period of darkness, associated level of work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours on Saturdays, Sundays, and U. S. Government holidays unless directed otherwise.

14. WINTERIZATION: The contractor may be required to perform the work during the winter season, which may cause the contractor additional cost. These additional incurred costs are contractor’s responsibility. The Contractor shall reflect these costs in the preparation of their proposal.

15. SAFETY: The safety plan must be approved before any work can be performed on this contract. Hard hats, suitable work boots and other necessary personnel protective gear per safety regulations are mandatory. Contractors are required to get a written permission from safety office (POC: Mr. To, Pong Uk, DSN: 768-8971) and Fire and Emergency Service (POC: Fire Communication office, DSN: 768-4120) prior to entering confined spaces (i.e., manholes). Contractors should be properly trained and equipped with PPEs, calibrated air monitoring instrument, to work at confined spaces to insure compliance with OSHA (Occupational Safety and Health Administration) 29 CFR 1910.146.

16. SECURITY: All prime contractor and subcontractor personnel will be required to obtain a station pass from the Base Security Office. It is the prime contractor’s responsibility to provide information to security regarding all prime and subcontractor personnel and a list of all vehicles that will be driven on the site.

TP III – 2

17. WARRANTY: The contractor shall be responsible for resolution on any defect/ failure on the contract during the one (1) year warranty period. The contractor shall provide services or/and repair and replacement to the satisfaction of the government. The one (1) year warranty starts the day after final inspection approval from the authorized government personnel.

18. ANTITERRORISM/OPRATIONS SECURITY REQUIREMENTS.

18.1. AT Level 1 Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

18.2. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area.

Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

18.3. For contractors that do not require CAC but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

18.4. iWATCH TRAINING. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

TP III – 3

19. ENVIRONMENTAL MANAGEMENT SYSTEM (EMS): Recycling all eligible material, including glass, paper (including magazines), plastic, aluminum, and cardboard to the maximum extent practicable;

Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content;

Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling;

Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must;

20. CONTAMINATION FIND CLAUSE: When contaminated soil is encountered during excavation work, contractor shall report the findings to the Environmental Office immediately and contractor will segregate contaminated soil from clean soil.

21. INADVERDENT FIND CLAUSE: When potential cultural or historic items are inadvertently found during construction activities, contractor shall cease activities in the vicinity of the discovery and report the findings to the Environmental Office immediately. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 12, Para 12-3 J)

22. FUEL TANK AND LINES: If applicable, underground piping associated with POL storage containers shall be tested for integrity and leaks at the time of installation, modification, construction, relocation, or replacement. New underground piping must be protected against corrosion IAW recognized industry standards. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 9, Para 9-3.b. (5))

23. Non-PCB TRANSFORMER CERTIFICATION: If applicable, before contractor replace/install any transformer at USAG Daegu, contractor shall submit two copies of non-PCB (Polychlorinated Biphenyl) transformer certification to COR for each installed transformer. New transformer will be installed after COR's approval for non-PCB transformer certification for each to be installed transformer.

TP III – 4

TECHNICAL EXHIBIT I: DELIVERABLE SCHEDULE

DELIVERABLE
FREQUENCY
FORMAT OF COPIES
SUBMIT TO
Preliminary Project Schedule
Within 5 calendar days after the NTP is acknowledged
Electronic copy.
COR
Initial Project Schedule
Within 30 calendar days after NTP
Electronic copy.
COR
Preconstruction Submittals
Within 15 days after NTP
Electronic copy.
COR
Quality control plan (QCP)
Within 15 days after NTP
Electronic copy.
COR

Safety Plan Para. TPIII. 15

Prior to the date of NTP
Electronic copy.
COR
Construction permission Para. TPIII. 5
10 working days prior to the starting of work
Electronic copy.
COR

Notification of need for inspection Para. TPIII. 3

7 working days prior to any work deemed by the Government to require inspection
Electronic copy.
COR

DD Form 1354, Transfer, and acceptance of DoD real property

Prior to final inspection
Electronic copy.
COR

As-built drawings Para. TPIII. 9

Prior to final inspection
Electronic copy.
COR
AT Level I Training Certificate Para. TPIII. 18.1
NLT 30 calendar days after contract

award

All Training Certificates
COR
iWATCH Training Certificate Para. TPIII. 18.4
NLT 30 calendar days after contract

award

All Training Certificates
COR

TE I – 1

SECTION 16711-1