This is a Statement of Work (SOW) for roof replacement and coating projects at Tinker Air Force Base, Oklahoma, issued May 22, 2025. The work encompasses replacement of the trapezoidal metal roof system on Building 1049 and installation of a two-component silicone coating system on Building 7038. The contract is identified as Project WWYK090020, Work Task 13010773, Revision 0.

The scope includes furnishing limited design services, materials, labor, equipment, testing services, quality control, and incidentals necessary to complete both roofing projects. For Building 1049, the contractor must remove the existing metal roof system, roof curbs, ridge vent, and associated flashings, then install a new 24-gauge trapezoidal standing seam metal roof panel system rated for 90 MPH wind speeds with UL Class 90 rating and water infiltration compliance per ASTM E 1646. The system must include new ridge vents, 18-gauge galvanized curb pan and flashing, and new 24-gauge PVDF-coated gutters, downspouts, ridge cap, and trim components. Metal panels require factory-applied PVF2 coating with 1 mil dry film thickness and Solar Reflectance Index of 78 or greater, with final color determined by the Base Architect. For Building 7038, surface preparation includes power-washing existing panels at minimum 2,000 psi without detergent, followed by installation of a two-component silicone coating (type B, tan color) applied at 20 wet mils per coat with base coat at 1.50 gallons per 100 square feet and white silicone topcoat at 1.50 gallons per 100 square feet with 30 pounds per 100 square feet of broadcast granules.

Key personnel requirements include a Project Manager with minimum ten years' experience in construction management roles, Quality Control Manager meeting specification 01 45 00.00 10 requirements, Site Safety and Health Officer meeting Level One or Two SSHO qualifications per EM 385-1-1, and a Project Superintendent with minimum five years' construction experience including two years as superintendent on commercial projects. The contractor must maintain a presence at the site during all work hours and provide daily progress reports. Construction occurs during normal duty hours (0700-1600 Monday-Friday) with utility outages as exceptions; work outside these hours to meet schedule is at no additional cost to the Government. Both facilities remain occupied throughout construction, and the contractor must coordinate procedures and material staging with the Government Project Manager and Using Agency. The contractor must submit a baseline construction schedule within ten days of Notice to Proceed in Network Analysis Schedule/Critical Path Method format with cost loading totaling 100 percent of contract value, reserving minimum 10 percent of contract cost for final acceptance with no progress payments against this final 10 percent until closeout items are submitted, punch list items resolved, and final inspection completed. Submittal deadlines include Health and Safety Plan (21 days), Material Submittals (14 days), Storm Water Pollution Prevention Plan (21 days), and outage requests (21 days).

The contractor must provide 30-year no dollar limit roof system materials and installation workmanship warranty for Building 1049's metal roof system, and 20-year no dollar limit warranty for Building 7038's coating system, both covering non-watertight conditions, moisture intrusion, splits, cracks, delamination, and excessive weathering due to defective materials or workmanship. The roof system installer warrants for two years that installation is free from defects in workmanship. All contractor personnel require AFMC Form 387 identification badges issued at Building 6611, Pass and ID, and must complete Foreign Object Debris awareness and prevention training. The contractor is responsible for site investigation to verify existing conditions using assessment techniques such as thermal imaging or UAS/drone usage as approved by Air Force guidance. Affirmative procurement requirements apply to EPA-designated roofing materials, USDA-designated biobased roof coatings, and Energy Star roof products, with completed Recovered Materials Determination Forms required if designated products cannot be used. An Environmental Management survey confirms no asbestos-containing materials, heavy metals, or lead-based paint concerns for the work areas.

View the file

Other files

File Type Posted
ATT1_EM Survey B6601.pdf PDF
ATT2_B414_Roof.pdf PDF
WWYK090020 090032 240001 RFIs_COR.pdf PDF
ATT3_SOW_B1049 and B7038.pdf PDF
06601_RoofSections.pdf PDF
910243W.pdf PDF
840173.pdf PDF
20030059.pdf PDF
860072.pdf PDF
B414 As-Builts.pdf PDF
610107.pdf PDF
Solicitation - FA813726R0018.pdf PDF
Section L - Instructions to Offerors.pdf PDF
Section M - Evaluation Factors for Award.pdf PDF
Att9_090032_MAC BOA roof SOW.pdf PDF
Att10_240001_SOW.pdf PDF
Wage Determination 8APR2026.pdf PDF
Att11_090032_Drawings.pdf PDF
Att11_240001_Submittal Register.pdf PDF
Att10_090032_Submittal Register_ROOF.pdf PDF
Att9_090020_Submittal Register.pdf PDF
Att10_090020_Drawings.pdf PDF
EAL List - BLANK to Contractors.xlsx XLSX spreadsheet
Att12_240001_Drawings.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work - 1 of 25 MACB ROOF SOW_v0_Apr 25

STATEMENT OF WORK

Replace Multiple Roofs, B1049 & B7038

Project #: WWYK090020 Work Task #: 13010773

Revision: 0 Issued: 22 May 25

1. SCOPE

1.1 GENERAL

The work to be performed under the terms of this Order consists of furnishing limited design services, materials, labor, plant, tools, transportation, equipment, testing services, quality control and incidentals required to accomplish the replacement of the trapezoidal metal roof system on Building 1049 and install two component silicone coating system on Building 7038 at Tinker Air Force Base (AFB), Oklahoma (reference the project drawings for additional location information).

The Contractor shall perform a site investigation to verify existing conditions; specific assessment techniques, e.g. thermal imaging or Unmanned Aerial System (UAS)/drone usage and the decision/approvals to use these techniques, will be made in accordance with relevant Air Force guidance.

If necessary, additional as-built drawings are available from 72 ABW/CE - Engineering Support, located in B400.

The Contractor shall be responsible for identifying the necessary logistical, architectural, and structural work elements required to perform the work as described herein. Assemblies, framework, fixtures, or apparatus not readily identified on the project drawings, specifications, or this Statement of Work (SOW) shall be provided by the Contractor as required for a complete, fully operating, and functioning system or systems ready for use by the Government.

Information such as roof plan layouts and dimensions; structural, mechanical, and electrical data; and location of utilities provided by the Government for existing and new construction are based on available as-built documentation, field observation, and equipment selected as design basis by the Government. This information is to be considered approximate and shall be field verified by the Contractor.

1.2 DEFINITIONS

1.2.1 Contracting Officer (CO)

An individual with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the contracting officer acting within the limits of their authority as delegated by the CO.

The CO is the ONLY person authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the contract.

1.2.2 Contracting Officer’s Representative (COR)

An individual designated by the Contracting Officer to perform specific technical or administrative functions.

22 May 25 Statement of Work - 2 of 25 WWYK090020

The COR is not authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the Order. It shall be the Contractor’s responsibility to contact the CO concerning any matters where the Contractor believes that the direction received from the COR may affect price, quality, quantity, delivery, or any other term or condition of the Order prior to performing work or purchase of material.

1.3 CONTRACTOR PERSONNEL

1.3.1 General Requirements

The Contractor shall ensure that employees and subcontractor employees have current/valid licenses and certifications necessary to perform their functions. Any cost or time associated with obtaining licenses or certifications shall be at the Contractor’s expense.

Personnel shall be easily recognized as a Contractor employee or sub-contractor. This may be accomplished by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges that contain the company name and employee name. The badge shall be displayed on the outer clothing, on the front of the body between the neck and waist and must be visible at all times. The badge shall clearly identify the individual as a Contractor employee.

1.3.2 Key Personnel

The Contractor shall, at a minimum, provide the following key personnel. Submit resumes for personnel fulfilling each of the key positions described below within five (5) calendar days after

NTP.

Exceptions or variances to experience requirements require prior approval from the Contracting Officer (CO)/Contracting Officer's Representative (COR); exceptions/variances will be considered where the Contractor can demonstrate comparable experience and/or competency.

Forward any requests for variance to the CO; include resumes for personnel listing the qualifications to be considered (e.g. education, experience, professional certifications, etc.).

Required experience levels shall be maintained throughout the duration of the agreement.

When personnel changes are required, resumes and a revised organization chart shall be submitted to the CO within five (5) business days of a vacated or filled position.

One Contractor employee may hold up to two (2) key positions; exceptions are noted below (e.g. a project superintendent cannot fulfill the role of the Quality Control Manager). Contractor employees holding more than one key position must meet the minimum requirements for both positions.

1.3.2.1 Project Manager

The Project Manager (PM) is an employee of the Prime Contractor who is responsible for the overall performance of this Order. The PM shall have a minimum of ten (10) years combined experience in the following positions: Project Superintendent, Quality Control Manager, Project Manager, Project Engineer, or Construction Manager with general contracting firm(s) engaged in multi-trade commercial construction contracts.

The individual must have at least two (2) years' experience as a Project/Program Manager. Provide the name of PM, in writing, to the CO upon award of the Order.

The Contractor shall designate an Alternate PM who may act on behalf of the Contractor when the PM is absent. Qualifications for the Alternate(s) are the same as

22 May 25 Statement of Work - 3 of 25 WWYK090020 for the PM. Provide the name of the Alternate, in writing, to the CO upon award of the Order.

The PM or designated Alternate shall have direct oversight of project planning and construction activities. The PM shall provide overall Order management, including full authority to develop proposals, negotiate and sign modifications to Orders; provide subcontract administration; review material submittals and shop drawings; and shall attend all status meetings, site visits, and pre-final/final inspections.

The CO must be able to contact the PM or designated Alternate by phone at all times.

Throughout the life of this agreement, the PM or Alternate shall be available to meet with the CO, at Tinker AFB or via online collaboration/teleconference software (e.g.

Microsoft Teams), within one (1) hour of telephone notification during normal duty hours.

1.3.2.2 Quality Control Manager (QCM)

The QCM is an employee of the Prime Contractor who is responsible for management of the Contractor Quality Control (CQC) Program.. The QCM shall have the minimum qualifications set forth in specification section 01 45 00.00 10, Quality Control (for purposes of this SOW, QCM is equivalent to CQC System Manager).

The Contractor shall designate an Alternate QCM who may act on behalf of the Contractor when the QCM is absent. Qualifications for the Alternate(s) are the same as for the QCM.

Contractor may designate additional quality control (QC) staff as specified in 01 45 00.00 10 (e.g. Assistant QC Manager or QC specialists).

Provide the names of QC staff to the CO upon award of the Order, as a part of the Quality Control Plan.

The QCM and their staff shall coordinate and review all material and shop drawing submittals, including those of subcontractors, offsite fabricators, and suppliers;

prepare quality control (QC) reports; schedule and coordinate testing procedures; and attend all status meetings, site visits, and pre-final/final inspections.

The Contractor's QC staff shall maintain a presence at the site at all times when work is being performed to ensure that the materials and workmanship are in accordance with the project drawings and technical specifications, as well as approved shop drawings and material submittals. The QCM or Alternate shall visit the project site daily.

For additional information regarding the requirements for Contractor’s Quality Control Program, refer to specification section 01 45 00.00 10.

The QCM may serve as the Site Safety and Health Officer.

1.3.2.3 Site Safety and Health Officer (SSHO)

The SSHO is an employee of the Prime Contractor who is responsible for management of the Contractor Health and Safety Program. The SSHO shall meet the qualification requirements of a Level One or Two SSHO as set forth in U.S. Army Corps of Engineers (USACE) publication EM 385-1-1, Safety -- Safety and Occupational Health (SOH) Requirements.

22 May 25 Statement of Work - 4 of 25 WWYK090020

The SSHO must be at the work site (i.e. Tinker AFB) at all times while the Order is in progress, to implement and administer the Contractor's safety program and Government-accepted Accident Prevention Plan. If the SSHO is off-site for a period longer than 24 hours, an equally qualified alternate SSHO must be provided and must fulfill the same roles and responsibilities as the primary SSHO. Provide the names of the SSHO and Alternate to the CO upon award of the Order as a part of the Health and Safety Plan.

The SSHO as a minimum shall visit the Order/project site daily to ensure compliance with all health and safety requirements. The SSHO must arrive at project site within one (1) hour of telephone direction from the CO, COR, Contract Specialist, or Construction QA Inspector.

When the Contractor has multiple Order/project sites, provide a separate full-time Level Three SSHO for each project site; the Level Three SSHO may also serve as the Superintendent. A designated SSHO shall be at each project site at all times when work is being performed.

The SSHO may serve as Quality Control Manager.

1.3.2.4 Project Superintendent/Foreman

The Superintendent is an employee of the Prime Contractor who is responsible for managing and coordinating day-to-day production for this Order. The Superintendent must have a minimum of five (5) years experience in construction with at least two (2) of those years as a superintendent/foreman on commercial projects similar in size and complexity to the requirements of this Order. The individual must be qualified as a Level Three SSHO (competent person) per EM 385-1-1 and have experience in the areas of hazard identification and safety compliance.

The Superintendent shall be at the project site at all times when work is being performed. If the Superintendent must leave a project site for any length of time, an Alternate /Foreman must be provided and must fulfill the same roles and responsibilities as the Superintendent. Qualifications for Alternate/Foreman are the same as for the Superintendent, except previous experience as a superintendent is not required and the individual must be qualified as a Level Three SSHO (qualified person) as set forth in EM 385-1-1. Subcontractors may be used as the Alternate/ Foreman.

An individual Superintendent may be assigned to more than one Order; however, the Superintendent shall not be assigned to more than 5 active Orders at Tinker AFB unless approved by the CO. The Superintendent shall visit each Order/job site daily.

Alternates/Foremen may only be assigned to a single Order/job.

Provide the names of the Superintendent and the Alternate/Foreman to the CO upon award of the Order.

The Superintendent shall provide on-site supervision; submit progress reports;

schedule and coordinate subcontractors and material suppliers; and attend all status meetings, site visits and pre-final/final inspections.

The Superintendent must arrive at the job site within one (1) hour of telephone direction from the CO, Contract Specialist or Construction QA Inspector.

22 May 25 Statement of Work - 5 of 25 WWYK090020

When the Contractor has multiple projects sites, the Superintendent (or alternate/ foreman) can serve as the Level Three SSHO for their respective project sites (reference paragraph SITE SAFETY AND HEALTH OFFICER).

1.3.3 Subcontractors

Subcontractor firms performing work requiring registered professionals shall be authorized to offer engineering or architectural services in a US State or Territory. An Oklahoma license will not be required for individuals responsible for signing/sealing documents.

All subcontractor firms shall be licensed in their specialty where required; Contractor will provide a copy of these licenses as part of the QC Plan.

1.4 BADGES

AFMC Form 387, Air Force Material Command Identification Cards (i.e. contractor badges) are required for Contractor personnel to access/work on Tinker AFB. The Contractor must have all personnel badged prior to commencing work.

Contractor shall designate an employee to act as Certifying Official for all personnel requiring badges. The designated Certifying Official shall complete the Appointment of Security Representative letter and submit to the COR upon award of the Order; a Copy of this letter (Attachment 1) is included on the attached CD.

Upon approval, Contractor’s Certifying Official will be responsible for completing AFMC Form 496, Application for AFMC Identification Card, for all personnel requiring a contractor badge. Badges are issued at Bldg. 6611, Pass and ID.

Badges shall be displayed on the outer clothing, on the front of the body between the neck and waist and must be visible at all times.

1.5 QUALITY CONTROL

It is the Contractor’s responsibility to provide, inspect, and document the level of quality that has been established by the minimum standards of the project drawings, specifications, and this SOW. The QCM shall direct the execution of the Contractor’s QC Plan.

Quality control shall be executed in accordance with specification section 01 45 00.00 10. The QC program shall include, but is not limited to the following:

1.5.1 Inspection System

The Contractor shall establish an inspection system which monitors the execution of any task completed under this contract. The Contractor must specify the areas to be inspected on a scheduled or unscheduled basis, how often inspections will be accomplished, and titles of the individuals who will perform the inspections.

1.5.2 Deficiency Prevention

The Contractor shall establish a method for identifying, correcting, and preventing future recurrence of quality deficiencies.

1.5.3 Inspection Files

In accordance with specification section 01 45 00.00 10, the Contractor shall maintain records of all required inspections conducted by the QCM and the necessary corrective actions taken. This documentation shall be submitted to the Government weekly with the progress reports

22 May 25 Statement of Work - 6 of 25 WWYK090020

(reference section PROGRESS REPORTING elsewhere in this document) throughout the life of the contract.

1.6 HEALTH AND SAFETY

1.6.1 Commander’s Statement of Safety Intent

The safety of everyone on Tinker AFB is our top priority. All individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each contractor and government employee.

1.6.2 Occupational Safety and Health Administration (OSHA) Voluntary Protection Program (VPP)

The Contractor is hereby notified that TAFB has achieved or is pursuing VPP Star ratings across multiple sites. Additional information regarding VPP can be found at the following link:

http://www.osha.gov/dcsp/vpp/index.html

The Voluntary Protection Plan applies to all construction and service contracts that have Contractor employees working more than 1000 hours per quarter on Tinker AFB. Refer to specification section 00 71 00, General Safety Requirements for Construction on Tinker Air Force Base, for additional requirements related to VPP.

1.6.3 Emergency Evacuation Procedures

Contractor employees shall follow the direction of Government employees in regard to emergency evacuation procedures, i.e. fire, tornado, or bomb threats. It is the responsibility of the Contractor to provide guidance and establish procedures for responding to an emergency for their employees. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.

1.6.4 Mishap Reporting

The Contractor shall notify the CO and the COR as soon as practical after any mishaps, including recordable accidents, incidents, and near misses, as defined in EM 385-1-1 Appendix Q; and any injuries, illness, or property damage which occur on the installation while performing work under this contract.

Refer to specification section 00 71 00 for additional requirements related to mishap reporting.

1.7 BIOENVIRONMENTAL REGULATIONS

(1) To assist in the evaluation of health hazards & to provide emergency medical treatment, Contractor must have Material Data Sheets (MDS) for hazardous materials reviewed and exchange of HAZCOM information accomplished prior to use. Process hazardous material in accordance with specification section 00 72 00, Environmental Requirements for Construction on Tinker AFB.

(2) Welding, cutting, or brazing operations must be in accordance with 29 CFR 1910.252. The Contractor shall not operate welders near chlorinated hydrocarbons.

(3) Hazardous noise levels in the vicinity of DoD Active Duty and Civilian personnel must be in accordance with OSHA 29 CFR 1910.95 and AFI 48-127, Occupational Noise and Hearing Conservation Program.

http://www.osha.gov/dcsp/vpp/index.html

22 May 25 Statement of Work - 7 of 25 WWYK090020

(4) Ensure measures are in place to prevent entry of airborne contaminants (such as debris generated during cutting; or sealant, tar, and isocyanate insulation vapors) from entering the building.

1.8 OUTAGES AND CLOSURES

Request utility outages and/or closures in accordance with TAFB Standard Operating Procedure Planned and Emergency Outages. Outages may be required to be performed outside of normal duty hours. The Contractor shall provide temporary lighting and power that may be required for continued performance of User's mission during outages.

1.9 EXISTING WORK

In accordance with FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, the Contractor shall take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government;

any damaged items shall be repaired or replaced as directed by the CO.

The Contractor shall remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

The Contractor shall repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the CO. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

2. PROJECT SPECIFIC REQUIREMENTS

2.1 GOVERNMENT OCCUPANCY OF FACILITIES

Both facilities will remain occupied throughout construction.

The construction area, a reasonable buffer area, and any approved staging areas will be cleared of all Government materials and personnel prior to the start of construction.

Contractor shall consult with the Government Project Manager/Construction QA Inspector and the Using Agency to coordinate procedures; means of access; space for storage of materials and equipment; and use of approaches, corridors, and stairways in such a way that accommodates the continued performance of the User’s mission during construction.

2.2 WORKING HOURS

In accordance with specification section 00 70 00, General Requirements for Construction on Tinker Air Force Base, construction shall take place during normal duty hours (0700 – 1600 Monday-Friday); utility outages will be the exception.

The Contractor has the responsibility to manage and maintain the construction schedule; the Contractor may request authorization to work weekends, holidays, and additional shifts as required to accomplish the work per their baseline schedule (reference section CONSTRUCTION SCHEDULE elsewhere in this document).

Work outside hours specified above to meet schedule will be performed at no additional cost to the Government; this is to include all testing, inspection, and acceptance actions.

2.3 PHASING

There is no Government-required construction phasing for this Order.

22 May 25 Statement of Work - 8 of 25 WWYK090020

2.4 FOD AWARENESS AND PREVENTION TRAINING

In accordance with specification section 00 71 00 all Contractor personnel working on this Order will be required to complete Foreign Object Debris (FOD) awareness and prevention training.

The work to be performed for this Order will not require Contractor personnel to work in or travel through areas near operational and/or production aircraft or related components.

2.5 AIRFIELD OPERATIONS

The work to be performed under this Order is not located in an airfield operations area.

2.6 CONTROLLED/RESTRICTED AREA(S)

Work to be performed under this Order is not located in a controlled/restricted area.

2.7 AFFIRMATIVE PROCUREMENT

The Government has determined that the following products listed in the EPA Comprehensive Procurement Guideline, USDA Biopreferred, Energy Star, or FEMP Low Standby Power programs are included in the scope of this Order:

(1) EPA-designated items

(a) Roofing materials

(2) USDA-designated biobased items – NA

(a) Roof Coatings

(3) Energy Star products

(a) Roof Products (Metal Panel, Roofing Insulation)

A copy of the Government’s Recovered Materials Determination Form (RMDF) has been provided as an attachment to this SOW (Attachment 3). If at any time during the Order, it is determined that an applicable, designated product cannot be used due to availability, price, or not meeting required performance specification, the Contractor shall complete Page 5 of the RMDF (for each product) to provide justification for not utilizing the designated product(s).

Forward the completed form to the CO and the COR for review and approval.

2.8 ENVIRONMENTAL MANAGEMENT (EM) SURVEY

An EM survey indicates there are no asbestos containing materials (ACM), heavy metals (HM), or lead based paint (LBP) concerns for area(s) where work is to be performed. If at any time the Contractor encounters suspect environmental conditions, they shall notify the CO and the COR.

3. PRECONSTRUCTION SERVICES BY CONTRACTOR

3.1 CORRESPONDENCE

All electronic correspondence related to the awarded Order shall be addressed to the CO, Contract Specialist, Government Project Manager, Construction QA Inspector, the COR, and the respective organizational workflow accounts. Hardcopy correspondence will be addressed to the CO, the Contract Specialist, and the COR.

Contact information for the above will be provided at the Pre-Construction meeting.

22 May 25 Statement of Work - 9 of 25 WWYK090020

All electronic correspondence from the Contractor regarding a specific Order shall follow a standardized subject line naming convention. Subject line for all electronic correspondence shall be as follows:

• WWYK###### Project Title: Subject of E-mail

3.2 DOCUMENTATION

All documents shall be submitted in accordance with specification section 01 33 00, Submittal Requirements. The Contractor shall submit all documents electronically via optical disk, e-mail, or a file transfer service such as DoD SAFE.

All documents submitted by the Contractor requiring a signature shall be submitted to the CO and the COR with an electronic digital signature. All documents submitted by the Contractor requiring further action and signature by the Government shall be capable of being digitally signed and saved by the Government representative(s) as required.

3.2.1 Document Format

3.2.1.1 Reports/Material Submittals

Reports for calculations, material submittals, warranty information, and similar documents shall be letter sized (8-1/2” x 11”), submitted in Adobe Acrobat (.pdf) format. Black and white documents are preferred but color copies will be accepted if they are necessary to convey intent.

3.2.1.2 Drawings

All drawings produced by the Contractor shall be created utilizing Computer-Aided Design and Drafting (CADD) software. The drawing files shall be in AutoCAD (.dwg) format and adhere to the drawing standards contained in Tri-Services A/E/C CADD Standard Release 6.0.

Drawing size shall be ANSI D (22” x 34”). Drawing scale shall be at least 1/8"=1'; text and other non-scale annotation elements shall be sized to produce clear and legible prints at half-size. Contractor shall use English scales and dimensions.

Drawings submitted by the Contractor shall be .pdf format; in addition, as-built record drawings shall be submitted in .dwg format. Hard copy submittals, when required, shall be printed at half-size (11" x 17").

Reference specification sections 01 33 00; 01 33 16.00 10, Design Data (Design After Award); and 01 78 00, Closeout Submittals, for additional requirements regarding developing and submitting design, shop, and as-built drawings.

3.2.2 File Naming Conventions

All documents submitted by the Contractor shall follow a standardized file naming convention as indicated below. File naming conventions shall be strictly adhered to and may only be modified by the Contracting Officer and/or the COR. File names shall have no spaces.

The following items in the below naming conventions are defined as followed:

• WWYK###### = Project number as defined by Civil Engineering Example: WWYK201234

• YYYYMMDD = Effective date of document or report

22 May 25 Statement of Work - 10 of 25 WWYK090020

• ZZZ = Contractor’s Company Initials

• 001 = Submittal Number or Serial Report Number

(1) RFIs:

WWYK######_RFI_001

(2) Submittals:

WWYK######_FORM#_001 (Brief Description of Submittal) Example: WWYK201234_AF3000_004 EDPM_Membrane

(3) Daily Reports:

WWYK######_Daily Report_001_YYYYMMDD

(4) Progress Reports:

WWYK######_PR_001_YYYYMMDD

(5) Other Miscellaneous Documents/Reports:

WWYK######_Form Name, Number, Or Description_YYYYMMDD

3.3 CONSTRUCTION SCHEDULE

In accordance with FAR 52.236-15, Schedules for Construction Contracts, the Contractor shall submit a baseline construction schedule to the COR for approval within ten (10) calendar days after the NTP is issued. An approved schedule will be required prior to commencement of work.

Contractor’s schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the Order performance period. The schedule shall consider the major work elements, as well as submittal reviews, mobilization, material delivery times, anticipated weather delays, and final inspection/closeout.

3.3.1 Schedule Format

The schedule shall be developed in accordance with specification section 01 32 16.00 20, Small Project Construction Progress Schedules, utilizing the Network Analysis Schedule/Critical Path Method format.

The schedule shall generally match the schedule submitted with the Contractor's accepted proposal, with the following additional information included:

(1) Order start (NTP) and end dates.

(2) Additional detail/breakdown of major work elements, as necessary.

(3) Cost loading data entered for all work items. Cost loading must total to 100 percent of the value of the Order.

Any partial progress payments for materials, as approved by the CO, shall be entered separately on the schedule.

The schedule will reserve, as a minimum, the final 10% of the Order cost for final acceptance. No progress payments will be made against this final 10% of the Order until all closeout items have been submitted, all punch list items have been resolved, and final inspection/acceptance has been completed.

22 May 25 Statement of Work - 11 of 25 WWYK090020

3.3.2 Schedule Updates

Contractor shall keep the schedule current, reflecting actual start and end dates for work elements, activity progress, and plan for completing the remaining work. The Contractor shall submit the updated schedule at monthly intervals, with the first progress report of the month.

Reference specification section 01 32 16.00 20 for additional information.

In addition, the Contractor shall submit updated baseline schedules when directed by the CO or the COR. Examples of when a new baseline schedule may be required include instances where the period of performance has been revised through modification to the Order; or as part of a 'get well plan' for construction that is significantly behind schedule.

3.3.3 Coordination with Government Activities

In developing the schedule, the Contractor shall account for the following milestones and Government review times in addition to construction activities:

DELIVERY SCHEDULE & SUBMITTALS

Item of Work & Deliverables Government Review Time

(calendar days) Remarks

Post-Award Conference/ Pre-construction Conference/ Notice to Proceed (NTP)

1 day At Tinker AFB

Baseline Construction Schedule and Schedule of Values/Draft Progress Report 14 days Provide within 10 days of

NTP

SD-01 Preconstruction Submittals (except as noted below) 14 days

Provide all preconstruction submittals within 15 days of

NTP

Health and Safety Plan 21 days

Request for Contractor Staging Area 30 days Must be approved prior to mobilization

Storm Water Pollution Prevention Plan (SWPPP) 21 days

Must be approved prior to submitting Tinker Excavation Permit Request

Chemical/Hazardous Material Request/Authorization 21 days

Material Submittals (SD-03, SD-04, SD-07, SD-08) 14 days Provide within 30 days of

NTP

Outages 21 days

22 May 25 Statement of Work - 12 of 25 WWYK090020

DELIVERY SCHEDULE & SUBMITTALS

Item of Work & Deliverables Government Review Time

(calendar days) Remarks

Construction Submittals (SD-06, SD-09) 14 days

Final/Closeout Submittals (SD-10, SD-11) 14 days Must be approved prior to final inspection.

Pre-final Inspection 7-day Minimum Notice

Contractor must have completed internal pre-final and resolved all punch list items from this inspection

Final Inspection 7-day Minimum Notice

All final/closeout submittals must be approved.

Contractor must have resolved all punch list items from pre-final inspection

Note: Information provided in this table is provided to assist the Contractor in developing the construction schedule. Review times may vary depending on the complexity of the submittal.

3.4 PROGRESS REPORTING

Progress reports are used for computing payments, and for monitoring the progress against the Contractor’s baseline schedule.

The Contractor shall develop a progress report utilizing the ‘Reports’ feature of the scheduling software. Contractor developed reports shall provide the same information as AF Form 3065, Contract Progress Report. The progress report shall utilize the same work elements and schedule of values/cost loading data developed for the construction Schedule.

Contractor shall submit a draft version of the progress report to the CO and the COR for approval within ten (10) calendar days after the NTP is issued (with the Baseline Schedule).

After approval, the Contractor shall submit progress reports weekly, or as directed by the CO, throughout the life of the Order. For each progress report, the Contractor shall include the following:

(1) Percentage of work completed for each work element during the reporting period.

(2) Cumulative percentage of work completed for each work element to date.

(3) Cumulative percentage of work completed for all work elements (percent of Order completion).

(4) Scheduled cumulative percentage of work completed for all work elements, based on the baseline construction schedule (scheduled percent of Order completion).

Progress report’s will be reviewed by the Construction QA Inspector and/or the Project Manager, who will in turn provide a recommendation to the COR to approve/disapprove the progress report; approval of the Contractor’s progress report does not constitute acceptance of

22 May 25 Statement of Work - 13 of 25 WWYK090020 the work as being 100% in compliance with the Order requirements (i.e. project specifications, drawings, and this SOW).

In the event the Contractor's reported progress deviates from the baseline schedule, the CO may elect to hold progress meetings.

3.5 WORKING DOCUMENTS

The Government has provided this SOW and the attached drawings for the Contractor’s use in preparing working documents for use during construction. Working documents shall provide sufficient detail to prevent construction errors or code violations and minimize general coordination errors.

The Contractor shall provide the following working documents:

(1) Roofing system shop drawings

Roof plan drawing depicting calculated wind uplift values and boundaries of enhanced perimeter and corner attachments of roof system components; spacing of perimeter, corner, and infield fasteners; and other details as applicable. The drawing must reflect the roof plan of each roof level and conditions indicated.

(2) Approved manufacturer’s assembly letter

Submit the roof system assembly wind uplift and fire rating classification listings.

(3) Lightning protection system installation/shop drawings.

Unless otherwise directed by the CO, the Contractor shall not begin construction activities until the required documents have been reviewed and approved by the Government.

3.6 MINIMUM GUIDANCE DOCUMENTS

Contractor generated working documents shall comply with the project documents (SOW, drawings, and specifications) and the most current editions of each of the publications listed below.

The term 'most current' is understood to mean, "Most current as of the date the solicitation is issued."

Codes/standards/regulations referenced by these publications are included as a part of this SOW to the extent referenced.

In case of conflict between the project documents, the Unified Facilities Criteria (UFC), the governing codes/standards, and the Tinker AFB Facility standards, the Contractor shall submit a request for information (RFI) to the Government for resolution.

3.6.1 General

(1) UFC 1-200-01, DoD Building Code

(2) UFC 1-200-02, High Performance and Sustainable Building Requirements

(3) Tinker AFB Facility Standard

3.6.2 Architectural

(1) UFC 3-101-01, Architecture

(2) UFC 3-110-03, Roofing

22 May 25 Statement of Work - 14 of 25 WWYK090020

3.6.3 Structural

(1) UFC 3-301-01, Structural Engineering

(2) ASCE/SEI-7, Design Loads for Buildings and Other Structures

(3) AISC Specification for Structural Steel Buildings

3.6.4 Mechanical

(1) UFC 3-410-01, Heating, Ventilating, and Air Conditioning Systems

(2) Tinker AFB Mechanical Standard

3.6.5 Electrical

(1) UFC 3-575-01, Lightning and Static Electricity Protection Systems

(2) Air Force Manual (AFMAN) 32-1065, Grounding and Electrical Systems

(3) Tinker AFB Electrical Standard

3.6.6 UNIFIED FACILITIES GUIDE SPECIFICATIONS

The UFGS shall be the basis for products/materials selected and the execution of the work not expressly covered in the project documents. A list of applicable UFGS sections has been included in Appendix B, SPECIFICATIONS for reference.

In those cases where a guide specification offers multiple options and the selection is not clearly defined in the governing UFCs, the Tinker AFB facility standards, or the SOW and drawings, the Contractor shall submit a request for information (RFI) to the Government for resolution.

3.7 SUBMITTAL REGISTER

Contractor has been provided with an editable version of the Government’s submittal register as a part of the solicitation.

Within ten (10) calendar days after issue of the NTP, or as otherwise directed by the CO, the Contractor shall review the submittal register, revise as necessary, and submit for approval.

Contractor is to recommend removal of items from the submittal register they do not believe are applicable to the project and add submittals for additional equipment or materials that they believe should be reviewed and approved by the Government.

• Contractor shall clearly indicate on the revised submittal register those items that are recommended for removal or addition. Utilize methods such as cell fill colors or text strikethrough; use separate colors for removals and additions.

• Contractor shall not make any changes to the submittal register which affects the original numbering, i.e. items approved for removal will not be deleted from the register and items approved for addition shall be inserted at the bottom of the register.

• For each item that the Contractor recommends removal, provide a separate written explanation as to why that submittal item should not be included; multiple submittal line items may be included in a single explanation.

• For each item that the contractor recommends removal, include a line on the TAFB Form 3000, Material Approval Submittal, for each item to be separately approved/disapproved for deletion.

22 May 25 Statement of Work - 15 of 25 WWYK090020

4. CONSTRUCTION SERVICES BY CONTRACTOR

The Contractor's construction shall fully comply with the Government's drawings and this SOW (reference paragraph GOVERNMENT FURNISHED DRAWINGS, SPECIFICATIONS & REFERENCES below); the most current editions of Tinker AFB Facility Standards; and any approved Contractor generated working documents.

Rubbish and debris shall be removed from Government property daily, unless otherwise directed, to avoid accumulation at the demolition site. Materials that cannot be removed daily shall be stored in areas specified by the CO.

It shall be the responsibility of the Contractor to provide screening/dust protection in the work area to ensure no migration of debris which could affect other areas or assets of the installation.

Contractor's work items include, but are not limited to:

4.1 ARCHITECTURAL DEMOLITION

B1049

(1) Remove the existing metal roof system down.

(2) Remove all capped and unused roof curbs below the new roof line.

(3) Remove existing ridge vent.

(4) Remove all associated flashings, gutters, downspouts, corner trim, rake trim and ridge cap.

(5) Remove any loose debris, trash or abandoned equipment parts from the work area.

(6) The Contractor shall provide adequate protection of Government property.

B7038

(1) Prepare existing metal panel roof surfaces per the manufacturer’s specifications.

(2) All surfaces to receive coating must be clean, dry and free from any foreign matter such as dirt, oils, grease or other debris that could inhibit the adhesion capabilities of the newly installed products.

(3) Power-wash the existing panels with minimum of 2,000 psi. No detergent must be used.

All spraying must strictly adhere to the Tinker AFB General Specifications, Section 00 72 00.

(4) Remove the gutters, downspouts, rake trim and corner trim.

(5) The Contractor shall provide adequate protection of government property.

4.2 ARCHITECTURAL CONSTRUCTION

4.2.1 Install New Trapezoidal standing seam roof panel. (B 1049)

(1) Furnish and install new 24-gauge trapezoidal standing seam panel roof system. Total roof system must be able to withstand a wind speed of 90 MPH, be a UL Class 90 rated system, and have a water infiltration rating in accordance with ASTM E 1646.

22 May 25 Statement of Work - 16 of 25 WWYK090020

(2) Install new ridge vents to match existing vent profile. New ridge vent shall be pre-manufactured, minimum 24-gauge metal, with a factory applied PVF2 coating (similar but not limited to Kynar 500). The PVF2 must be 1 mil dry film thickness consisting of 0.25 mil prime coat and 0.75 mil finish coat, minimum, applied by the continuous coil coating method. Paint resin, with noted exceptions, must be 70% PVF2 containing 100% inorganic pigments. Contractor to submit manufacturer's color chart with recommended color. Final color to be determined by Base Architect.

(3) Furnish and install 18-gauge galvanized curb pan and flashing. Curb pan and flashing shall be soldered.

(4) Furnish and install new 24-gauge PVDF coated gutter, downspouts, ridge cap, rake trim, corner trim, curb flashing, and curb cap.

(5) The existing attic insulation will remain.

(6) Metal Panels shall have factory applied PVF2 coating (similar but not limited to Kynar 500). The PVF2 must be 1 mil dry film thickness consisting of 0.25 mil prime coat and

0.75 mil finish coat, minimum, applied by the continuous coil coating method. Paint resin, with noted exceptions, must be 70% PVF2 containing 100% inorganic pigments.

Contractor to submit manufacturer's color chart with recommended color. Final color to be determined by Base Architect.

(7) PVF2 coating shall have a Solar Reflectance Index of 78 or greater.

(8) Metal panel system shall meet the FM 1-90 uplift requirements.

(9) The basis of design for metal wall panels is: Berridge Double-Lock Zee-Lock Panel.

Features Include:

(10) Coverage Width: 16 in.

(11) Seam Height: 2 in.

(12) Nominal Coated Thickness 0.028 inch/24 gauge

(13) Panel Surface: Smooth

4.2.2 Elastomeric Coating

(1) Install new type B, two component, silicone coating.

(2) Topcoat shall be tan in color.

(3) Silicone coating shall be applied at a rate of 20 wet mils per coat.

(4) Subsequent coats should be applied within 24 hours of prior applications to insure full and uniform adhesion. Coating must be evenly applied and pinhole-free. Before applying a subsequent coat of this product, the previous coat must be completely dry and cured. Apply second coat perpendicular to the first.

(5) Apply only when ambient temperatures are 50ºF and rising. Cold weather could result in uneven application and improper curing of product. Do not apply if there is a threat of inclement weather within 4 hours of application. Drying time is dependent on temperature, humidity and film thickness.

(a) Install per manufacturer’s instructions.

22 May 25 Statement of Work - 17 of 25 WWYK090020

(6) Do not thin product.

(7) Install new polyurethane caulking on all gutter joints and down spout drops.

(8) Furnish and install new elastomeric base coat at a rate of 1.50 gallons per 100 square feet.

(9) Furnish and install new white silicone topcoat at a rate of 1.50 gallons per 100 square feet while broad casting granules into the topcoat at a rate of 30 pounds per 100 square feet.

(10) All spraying must strictly adhere to Tinker AFB General Specifications, Section 00 72 00, and Environmental Requirements for Construction on Tinker AFB.

(11) Install new prefinished 24-guage metal, gutters, downspouts, rake trim and corner trim with polyvinylidene fluoride (PVDF) coating.

4.2.3 Warranty

Roof Trapezoidal Standing Seam Warranty

Furnish the roof membrane manufacturer's 30-year no dollar limit roof system materials and installation workmanship warranty for a watertight roof system. The warranty must state that:

1) If within the warranty period the roof system, as installed for its intended use in the normal climatic and environmental conditions of the facility, becomes non-watertight, shows evidence of moisture intrusion within the assembly, splits, cracks, delaminates, separates from substrate, shrinks to the point of bridging or tenting coating at transitions, or shows evidence of excessive weathering due to defective materials or installation workmanship, the repair or replacement of the defective and damaged materials of the roof system assembly and correction of defective workmanship must be the responsibility of the roof membrane manufacturer. The roof membrane manufacturer is responsible for all costs associated with the repair or replacement work.

2) When the manufacturer or his approved applicator fail to perform the repairs within 72 hours of notification, emergency temporary repairs performed by others does not void the warranty.

Roof Coating Warranty

Furnish the roof membrane manufacturer's 20-year no dollar limit roof system materials and installation workmanship warranty for a watertight roof system. The warranty must state that:

1) If within the warranty period the roof system, as installed for its intended use in the normal climatic and environmental conditions of the facility, becomes non-watertight, shows evidence of moisture intrusion within the assembly, splits, cracks, delaminates, separates from substrate, shrinks to the point of bridging or tenting coating at transitions, or shows evidence of excessive weathering due to defective materials or installation workmanship, the repair or replacement of the defective and damaged materials of the roof system assembly and correction of defective workmanship must be the responsibility of the roof membrane manufacturer. The roof membrane manufacturer is responsible for all costs associated with the repair or replacement

22 May 25 Statement of Work - 18 of 25 WWYK090020 work. When the manufacturer or his approved applicator fail to perform the repairs within 72 hours of notification, emergency temporary repairs performed by others does not void the warranty.

2) When the manufacturer or his approved applicator fail to perform the repairs within 72 hours of notification, emergency temporary repairs performed by others does not void the warranty.

The roof system installer must warrant for a period of two (2) years that the roof system, as installed, is free from defects in installation workmanship, to include the roof membrane, flashing, insulation, accessories, attachments, and sheet metal installation integral to a complete watertight roof system assembly. The roof system installer is responsible for correction of defective workmanship and replacement of damaged or affected materials.

The roof system installer is responsible for all costs associated with the repair or replacement work.

(1) Continuance of Warranty

Perform repair or replacement work that becomes necessary within the warranty period in a manner that restores the integrity of the roof system assembly and maintain validity of the roof membrane manufacturer warranty for the remainder of the manufacturer warranty period.

(2) Contractor shall provide a sixteen-inch by sixteen-inch (16-in. x 16-in.) metal plaque which shall contain the information listed below. Fasteners to attach plaque shall be stainless steel. Location of plaque to be determined by 72 ABW/CE.

• Project Number and title

• Contractor name, phone number

• Subcontractor name, phone number and installer warranty expiration date

• Roof system, warranty information with expiration date

• Roof Manufacturer, phone number

4.3 STRUCTURAL DEMOLITION

4.3.1 Curbs

(1) Demolish and remove any existing curbs that have previously been abandoned or will not be required for the new construction.

4.4 STRUCTURAL CONSTRUCTION

4.4.1 Capping Openings

(1) Provide and install steel cover plate over existing opening(s) that have previously been abandoned or will not be required for new construction.

(2) Plate shall be able to resist all roof loads.

4.5 MECHANICAL DEMOLITION

(1) Remove HVAC equipment as required to allow for installation of new roofing materials.

22 May 25 Statement of Work - 19 of 25 WWYK090020

(2) Demolish any existing mechanical curbs and flashing.

(3) Demolish any abandoned mechanical penetrations (such as flues or vent piping) as indicated in the project drawings.

4.6 MECHANICAL CONSTRUCTION

(1) Provide shop-fabricated metal [supply] [[return] [exhaust] plenums to replace existing where required. Each plenum shall be sized to fit equipment outlets. Provide vibration isolation where required.

(2) Install HVAC equipment removed above on new roof curbs/supports.

4.6.2 Existing HVAC Equipment

(1) Disconnect existing HVAC equipment (power and controls) as required to allow removal of equipment for installation of new roofing materials.

(2) Examine equipment connection (conduit and conductors) for signs of wear, heat, or weather damage.

(a) If equipment connection shows signs of damage, remove conduit to the first disconnecting means or to the first junction box. Remove conductors to the first disconnecting means; if disconnecting means is integral to the equipment, demolish conductors back to source.

(b) If equipment connection shows no signs of damage, protect open end of conduit and exposed conductors for re-installation.

4.6.3 Existing HVAC Equipment

(1) Reconnect existing HVAC equipment removed above.

(2) As necessary, based on inspection above, provide new liquid tight flexible metal conduit (LFMC) and conductors.

4.7 ORDER OF PRECEDENCE

In the event of a conflict or inconsistency between any of the provisions of this Order, precedence shall be applied in the following order:

• Those portions of the accepted proposal which both conform to and exceed the requirements of the solicitation.

• The provisions of the solicitation, including:

- The Solicitation, Offer and Award

- Specifications

- Drawings

- SOW

• All other provisions of the accepted proposal.

• Any contractor generated working documents, including, but not limited to: plans, engineering studies and analyses, shop drawings, and equipment installation drawings.

22 May 25 Statement of Work - 20 of 25 WWYK090020

4.8 RECORD DRAWINGS

4.8.1 Working As-Built Drawings ('Redline' Set)

Working as-built drawings shall be maintained at the job site, and clearly indicate authorized field changes, updates based on existing conditions, and corrections to the drawings. Reference specification section 01 78 00 for additional information related to markups to be included in working as-built drawings.

Within five (5) days of substantial completion (i.e. completion of Contractor’s punch-out inspection) and prior to pre-final inspection, the Contractor shall submit working as-built drawings for Government use during the inspection. At the conclusion of the pre-final inspection, the Government and Contractor will identify any additional changes or corrections required for final approval.

4.8.2 Record Drawings

Within ten (10) days after the pre-final inspection and approval of the working as-built drawings, the Contractor shall incorporate the redlines into the CAD files and submit this final set as the Record Drawings.