This document is a Submittal Register for a roofing repair project (WWYK090032) at Building 414, Tinker Air Force Base, detailing all required contractor submissions throughout the project lifecycle.
The register specifies 93 line items of required submittals organized by construction phase and trade discipline. Preconstruction submittals include Health and Safety Plan, Storm Water Pollution Prevention Plan, Demolition/Deconstruction Plan, Baseline Construction Schedule (due within 10 days of Notice to Proceed), Quality Control Plan, and Submittal Register. Environmental and safety-related submittals include Hazardous Material Request/Authorization (AF Form 3952), Spray Painting Plan, Monthly Hazardous Material Usage Reports (due first week of each month), Safety Data Sheets, Construction Debris Analysis Plan, and Monthly Debris Management Reports. Schedule-related submittals require monthly updates and weekly 3-Week Look Ahead Schedules with Contract Progress Reports. Product data and shop drawings are required for all roofing materials and components, including EPDM sheet roofing system elements (cement, seam tape, bonding adhesive, flashings, fasteners, insulation), roof deck insulation (underlayment, insulation board, cover board, moisture control), fluid-applied waterproofing, rough carpentry (nailing strips, underlayment), and flashing and sheet metal work (gutters, downspouts, counterflashing, reglets, scuppers, copings, drip edge). Closeout submittals include Working As-Built Drawings (two electronic and two hard copies), Record Drawings (two electronic and one hard copy), Warranty letters, EPA and USDA Designated Items Certifications, and Low Volatile Organic Compounds Content documentation. The register requires weekly Contract Progress Reports (utilizing AF Form 3065 or equivalent) throughout the contract duration.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Line
Acti vity #
Trans mittal #
Specification Section
SD
Submittal Description Item Submitted
Paragraph # Classification: GOVT or A/E Reviewer
Submit
Approval Needed By
Material Needed By
Action Code
Date Of Action
Date FWD to APPR / Auth Date
RCD From
CONTR
Date FWD To Other Revwr
Date RCD From Other Reviewer
Action Code
Date Of Action
Mailed To CONTR/ Date
RCD From
APPR
Authority
Remarks
1 00 70 00 07 Certificates Welding, Cutting and Brazing Permit 1.4 G
2 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G
3 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4
4 00 72 00 01 Preconstruction Submittals Storm Water Pollution Prevention Plan 1.3.3.2 G
5 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous Material Request/Authorization
1.4 G
6 00 72 00 01 Preconstruction Submittals Spray Painting Plan 1.9 G
7 00 72 00 01 Preconstruction Submittals Environmental Management System Awareness Training
1.10
8 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement
1.3.9 G Provide only one. Reference specification for additional information
9 00 72 00 07 Cerificates Monthly Hazardous Material Usage Report 1.4 G Provide 1st week of each month during construction
10 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets
1.4
11 00 72 00 11 Closeout Submittals Notice of Termination (ODEQ Form 640-572) 1.3.3.2 G
12 00 72 00 - Attch 5 01 Preconstruction Submittals Construction Debris Analysis Plan 1.2.3 G
13 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction
14 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G Provide within 10 days of NTP.
15 01 32 16.00 20 07 Certificates Monthly Updates 1.4 Provide 1st week of each month during construction, or as directed by CO
16 01 32 16.00 20 07 Certificates 3-Week Look Ahead Schedule 1.6 Provide weekly with the Contract Progress Report
17 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G
18 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G
19 01 45 00.00 10 06 Test Reports QC Documentation 3.9 Provide weekly with the Contract Progress Report
20 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G
21 01 50 00 01 Preconstruction Submittals Photographic Record 1.3
22 01 78 00 03 Product Data Warranty Letter 1.7.1 G
23 01 78 00 08 Manufacturer's Instructions Instructions 1.7.1
24 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G Provide (2) electronic sets (optical media) and
(2) hard copies
25 01 78 00 11 Closeout Submittals Record Drawings 3.3 G Provide (2) electronic sets (optical media) and
(1) hard copy
26 01 78 00 11 Closeout Submittals Certification of EPA Designated Items 2.3 G
27 01 78 00 11 Closeout Submittals Certification Of USDA Designated Items 2.4 G
28 02 41 00 1 Preconstruction Submittals Demolition/Deconstruction Plan 1.2.2 G
29 02 41 00 1 Preconstruction Submittals Existing Conditions 1.11
30 02 41 00 7 Certificates Notification 1.7 G
31 02 41 00 11 Closeout Submittals Receipts 3.3.4
32 6.10.00 2 Shop Drawings Nailing Strips 2.2.2 G
33 6.10.00 3 Product Data Underlayment 2.4 G 34 6.10.00 6 Test Reports Preservative-treated 1.4.5 G
35 7.14.00 3 Product Data Fluid-Applied Membrane 2.1 G 36 7.14.00 3 Product Data Membrane Primer 2.2 37 7.14.00 3 Product Data Elastomeric Sheet 2.8 38 7.14.00 11 Closeout Submittals Warranty 1.6 G
TITLE: Tinker AFB General Requirements Specification (Div 00-01) SUBMITTAL REGISTERJOB NAME: WWYK090032 - REPAIR ROOF BLDG 414 CE OPERATIONS
LOCATION: BLDG 414
CONTRACT NO:
CONTRACTOR:
APPROVING AUTHORITY
(d)
GENERAL REQUIREMENTS FOR CONSTRUCTION ON TINKER AIR FORCE
BASE
CONTRACTOR SCHEDULE
DATES
CONTRACTOR
ACTION
GENERAL SAFETY REQUIREMENTS FOR CONSTRUCTION ON TINKER AIR
FORCE BASE
GENERAL ENVIRONMENTAL REQUIREMENTS FOR CONSTRUCTION ON
TINKER AIR FORCE BASE
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
SUBMITTAL PROCEDURES
QUALITY CONTROL
CONTRACTOR FACILITIES
CLOSEOUT SUBMITTALS
DEMOLITION AND DECONSTRUCTION
ROUGH CARPENTRY
FLUID-APPLIED WATERPROOFING
39 7.14.00 11 Closeout Submittals Information Card 3.6
40 7.22.00 2 Shop Drawings Insulation Board Layout 1.3 G 41 7.22.00 2 Shop Drawings Verification of Existing Conditions 1.3 G 42 7.22.00 3 Product Data Insulation 2.2 G 43 7.22.00 3 Product Data Cover Board 1.4 G 44 7.22.00 3 Product Data Fasteners 2.7 G 45 7.22.00 3 Product Data Sheathing Paper 2.5 G 46 7.22.00 3 Product Data Moisture Control 2.6 G 47 7.22.00 6 Test Reports Flame Spread Rating 1.8.1 G 48 7.22.00 7 Certificates Volatile Organic Compounds (VOC)
Content
1.9 G
49 7.22.00 7 Certificates Installer Qualifications 1.6 G 50 7.22.00 8 Manufacturer's Instructions Fasteners 2.7 G 51 7.22.00 8 Manufacturer's Instructions Insulation 2.2 G 52 7.22.00 11 Closeout Submittals LOW Volatile Organic Compounds
(VOC) Content
1.9 S
53 07 53 23 2 Shop Drawings Roof Plan Drawing 1.3.1 G 54 07 53 23 2 Shop Drawings Wind Load Calculations 1.3.1 G 55 07 53 23 2 Shop Drawings Boundaries of Enhanced Perimeter 1.3.1 G 56 07 53 23 2 Shop Drawings Corner Attachments of Roof System
Components
1.3.1 G
57 07 53 23 2 Shop Drawings Location of Perimeter Half-Sheets 58 07 53 23 2 Shop Drawings Spacing of Perimeter, Corner, and
Infield Fasteners
1.3.1 G
59 07 53 23 2 Shop Drawings Slopes and Drain Locations 1.3.1 G 60 07 53 23 3 Product Data Cement 2.2 61 07 53 23 3 Product Data EPDM Sheet 2.1.1 G 62 07 53 23 3 Product Data Seam Tape 2.1.2 G 63 07 53 23 3 Product Data Bonding Adhesive 2.1.4 G 64 07 53 23 3 Product Data Lap Splice Adhesive 2.1.3 G 65 07 53 23 3 Product Data Water Cutoff Mastic/Water Block 2.1.6 G 66 07 53 23 3 Product Data Lap Cleaner, Lap Sealant, and Edge
Treatment
2.1.5 G
67 07 53 23 3 Product Data Flashings 3.3 G 68 07 53 23 3 Product Data Flashing Accessories 2.1.7 G 69 07 53 23 3 Product Data Flashing Tape 2.1.7.1 G 70 07 53 23 3 Product Data Fasteners and Plates 2.1.8 G 71 07 53 23 3 Product Data Roof Insulation G 72 07 53 23 3 Product Data Walk Pads G 73 07 53 23 3 Product Data Pre-Manufactured Accessories 2.1.9 G 74 07 53 23 3 Product Data warranty 1.8 G 75 07 53 23 5 Design Data Wind Uplift Calculations 1.4.5 G 76 07 53 23 7 Certificates Qualification of Manufacturer 1.4.1 77 07 53 23 7 Certificates Qualification of Applicator 1.4.2 78 07 53 23 7 Certificates Wind Uplift Resistance 1.4.5 G 79 07 53 23 7 Certificates Fire Resistance 1.4.4 G 80 07 53 23 8 Manufacturer's Instructions Cold Weather 1.6 G 81 07 53 23 11 Closeout Submittals Warranty 1.8 G 82 07 53 23 11 Closeout Submittals Information Card 3.1 G
83 07 60 00 2 Shop Drawings Gutters 3.1.17 G 84 07 60 00 2 Shop Drawings Downspouts 3.1.18 G 85 07 60 00 2 Shop Drawings Expansion joints 3.1.26 G 86 07 60 00 2 Shop Drawings Gravel stops and fascias 3.1.15 G 87 07 60 00 2 Shop Drawings Splash pans 3.1.22 G 88 07 60 00 2 Shop Drawings Counterflashing 3.1.12 G 89 07 60 00 2 Shop Drawings Reglets 3.1.13 G 90 07 60 00 2 Shop Drawings Scuppers 3.1.20 G 91 07 60 00 2 Shop Drawings Copings 3.1.30 G 92 07 60 00 2 Shop Drawings Drip edge 3.1.16 G 93 SOW 07 Certificates Contract Progress Report(s) 2.4 G Provide weekly throughout life of contract. Utilize AF
Form 3065, Contract Progress Report (or equal)
ROOF AND DECK INSULATION
ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING
FLASHING AND SHEET METAL
Table 1