Att D - Vail-Tortolita_Project Specifications.pdf
PDF 1 MB Posted
- Solicitation number
- 89503124RWA000063
About this file
This document is a set of project specifications for the Vail-Tortolita Double-Circuit 230-kV Transmission Line Rebuild solicitation. The key details are:
The principal components of the work include constructing 59 miles of 230-kV double-circuit transmission line, constructing 5 miles of 230-kV single-circuit transmission line, removing 58 miles of single-circuit 115-kV transmission line, and installing fiber optic cable including optical overhead ground wire, fiber splicing, and associated equipment.
The solicitation includes detailed requirements for items such as removing existing transmission line components, clearing, access road repair and construction, concrete foundations, installing steel pole structures, conductor and overhead ground wire installation, vibration dampers, line markers, and bird diverters. Specific quantities and locations are provided for many of the required items. Estimated delivery dates and costs are included for government-furnished materials. The contractor is responsible for preparing and submitting various plans, schedules, and other submittals for approval. Construction schedule restrictions and electrical safety requirements are also detailed.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VAIL – TORTOLITA PROJECT
Revision 1
Spec. No. 1089 Revision 1
SECTION C
DESCRIPTION/SPECIFICATIONS
ARIZONA
Attachment D
VAIL-TORTOLITA PROJECT
REVISION 1
Section C
DESCRIPTION/SPECIFICATIONS
Vail-Tortolita Project
Revision 1
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT
B. DESCRIPTION OF WORK
C. DESCRIPTION OF BIDDING SCHEDULE ITEM
1. Bidding Schedule item “Mobilization and preparatory work”
D. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1. Submittal And Coorespondance Response Time
2. Outage Restrictions
3. Construction Schedule Restrictions
4. Protective Ground Leads
5. Maximum Available Fault Current
E. CONSTRUCTION SCHEDULE
1. Submittal Time
2. Format And Detail
F. MATERIAL
1. Points-Of-Delivery
2. Delivery Dates
G. RIGHTS-OF-WAY
1. General
2. Access Easements
3. Work On The Right-Of-Way
H. GEOLOGIC INVESTIGATIONS
I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES
J. WATER FOR CONSTRUCTION PURPOSES
K. EXPLOSIVES AND BLASTING
L. PUBLIC HEALTH AND SAFETY
1. Prior To Construction
M. BURIED UTILITIES
N. CONTRACTOR COMMUNICATIONS FOR WAPA USE
O. ELECTRICAL MINIMUM APPROACH DISTANCES
P. SUBMITTALS AND CORRESPONDENCE
1. General
2. Approval Time
3. Submittal Response
4. Physical Sample Submittals
5. Project Protocol
DIVISION 2 – SITEWORK
A. GENERAL
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item “Removing existing transmission line”
2. Bidding Schedule item “Nogales Substation demolition”
3. Bidding Schedule item “Clearing”
4. Bidding Schedule item “Access road repair”
5. Bidding Schedule item “New access roads”
6. Bidding Schedule item “Permanent gates in existing barbed wire fences”
7. Bidding Schedule item “Fence grounds”
8. Bidding Schedule Does Not Contain Separate Items
DIVISION 3 – CONCRETE
A. GENERAL
1. Material
2. Test For Potential Reactivity Of Sand And Coarse Aggregate
3. Mix Design
4. Curing
5. Rebar Development (LD) And Lap Length
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item “Concrete foundations for Government-Furnished base-plated (BP) transmission line steel pole structures”
DIVISION 5 – TRANSMISSION LINE STEEL POLE STRUCTURES
A. GENERAL
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item for installing dulled-galvanized BP Government-Furnished transmission line steel pole structures on concrete foundations
2. Bidding Schedule items for installing dulled-galvanized DE Government-Furnished transmission line steel pole structures with concrete backfill
C. SPECIAL STRUCTURE ORIENTATION
DIVISION 10 – TRANSMISSION LINE ELECTRICAL
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule items for installing Government-Furnished conductor insulator assemblies with Government-Furnished insulators
2. Bidding Schedule items for furnishing and installing conductor insulator assemblies with Government-Furnished insulators
3. Bidding Schedule items for installing Government-Furnished OGW assemblies
4. Bidding Schedule items for furnishing and installing OGW assemblies
5. Bidding Schedule items for installing Government-Furnished OPGW assemblies
6. Bidding Schedule items for furnishing and installing OPGW assemblies
7. Bidding Schedule item “Install six (6) Government-Furnished 1272 kcmil, ACSS/MA2, 54/19, PHEASANT conductors”
8. Bidding Schedule item “Install three (3) Government-Furnished 1272 kcmil, ACSS/MA2, 54/19, PHEASANT conductors”
9. Bidding Schedule item “Furnish and install six (6) 1272 kcmil, ACSS/MA2, 54/19, PHEASANT conductors”
10. Bidding Schedule item “Furnish and install three (3) 1272 kcmil, ACSS/MA2, 54/19, PHEASANT conductors”
11. Bidding Schedule item “Install one (1) Government-Furnished 1/2-inch, 7-strand, high-strength steel overhead ground wire”
12. Bidding Schedule item “Furnish and install one (1) 1/2-inch, 7-strand, high-strength steel overhead ground wire”
13. Bidding Schedule item “Install one (1) Government-Furnished 0.531-inch-diameter, 96-fiber optical overhead ground wire”
14. Bidding Schedule item “Install Government-Furnished vibration dampers for conductors, OGW, and OPGW on the Tortolita – DeMoss-Petrie / Saguaro – Tucson segment”
15. Bidding Schedule item “Furnish and install vibration dampers for conductors, OGW, and OPGW on the DeMoss-Petrie – Vail / Tucson – Apache Segment”
16. Bidding Schedule item “Install Government-Furnished line markers”
17. Bidding Schedule item “Furnish and install line markers”
18. Bidding Schedule item “Install Government-Furnished bird diverters”
19. Bidding Schedule item “Furnish and install bird diverters”
20. Bidding Schedule item “Spare parts”
DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION
A. CONTRACTOR-FURNISHED
1. Environmental Quality Protection
2. Special Conditions
3. Air And Water Pollution
4. Cultural And Paleontological
5. Biology
6. Contractor-Prepared Protection Measures
7. The Contractor Shall Prepare An Emergency Preparedness And Response Plan
DIVISION 14 – COMMUNICATION FACILITIES
A. FIBER OPTIC CABLE AND ASSOCIATED EQUIPMENT
1. Bidding Schedule item “Install and test fiber optic cable(s) and provide associated equipment”
DIVISION 15 – DRAWINGS
A. CONSTRUCTION DRAWINGS
1. General
B. AS-BUILT DRAWINGS
1. General
2. Recording Information
3. Drawing Markup
4. Drawing Review
5. As-Built Information To Be Recorded
C. REVIEW OF AS-BUILT DRAWINGS
1. As-Built Drawing Submittal
2. Review
3. Acceptance
LIST OF APPENDICES
Appendix A – Geotech Report
Appendix B – Avra Valley Laydown Yard Map
Appendix C – Camino Del Cerro Potential Laydown Yard Map
Appendix D – Del Bac Potential Laydown Yard Map
Appendix E – Nogales Potential Laydown Yard Map
Appendix F – Aerospace Parkway Potential Laydown Yard Map
Appendix G – Vail – Tortolita Access Maps
Appendix H – Geotech Report – Tumamoc Hill Reroute
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
Construct and complete the Vail – Tortolita Project, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; WAPA’s Construction Standards, including Standard 1 – General Requirements (March 2021), Standard 2 – Sitework (March 2021), Standard 3 – Concrete (March 2021), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (March 2021), Standard 5 – Transmission Line Steel Pole Structures (March 2021), Standard 6 – Light Duty Steel Pole Structures (March 2021), Standard 7 – Wood Poles (March 2021), Standard 8 – Glued Laminated Structures (March 2021), Standard 9 – Substation – Electrical (March 2021), Standard 10– Transmission Line – Electrical (March 2021), Standard 11 – Buildings (March 2021), Standard 12 – Painting (March 2021), Standard 13 – Environmental Quality Protection (March 2021), Standard 14 – Communication Facilities (March 2021), Standard 15 – Drawings (March 2021); Standard Drawings;
and these Project Specifications and Drawings.
If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.
WAPA’s Construction Standards, Standard Drawings and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.
WAPA Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.
B. DESCRIPTION OF WORK:
The principal components of work include construction of 59-miles of 230-kV double-circuit transmission line; construction of 5-miles of 230-kV single-circuit transmission line; removing 58-miles of single-circuit 115-kV transmission line; fiber optic installation including optical overhead ground wire (OPGW), fiber splicing and all associated fiber equipment.
The summary of “Bidding Schedule Items” are more fully described in the following divisions in this specification and in the Construction Standards listed in Division 1, Section A above.
The work is located on the transmission lines between Saguaro, Tortolita, Rattlesnake, Tucson, DeMoss-Petrie, Del Bac, Nogales and Vail Substations as shown on Drawings SGR 0015, SGR-TUC T150, RSK 0017, TUC 0015, TUC-APE T150, DLB 0015, NGL 0015 and TUC-APE T151.
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
a. Performing mobilization and preparatory work in accordance with Sections H and M of the contract clauses.
b. Prepare and submit a Construction Schedule and furnish a Safety and Health Program.
c. Providing jobsite office trailer and the items listed below. Prior to any jobsite work, the
Contractor shall provide the office trailer for the exclusive use of WAPA.
(1) Relocation: If the Contractor changes the location of his office during the term of the contract, then the Contractor shall also move the mobile office trailer provided for WAPA simultaneously with the transportation of his own unit.
(a) Installation: Install anchors and tie-downs for the trailer complying with local, State and Federal regulations. The office trailer and metallic appurtenances shall be grounded. Entry points to the trailer shall be provided with stairways complying with Occupational Safety and Health Administration
(OSHA) (29 CFR 1926.1052).
(b) Office Space Requirements:
1) Size and Arrangement: At least 250-square-feet (minimum) consisting of two (2) separate rooms (one (1) office and one (1) larger workroom).
2) Heating and Cooling: Heating and cooling unit sized to provide adequate heating and cooling.
3) Lighting and Electrical: Adequate lighting and 120V electrical outlets.
4) Utilities: Make all arrangements and pay all costs for providing utilities, including potable drinking water, electrical power and heating and cooling energy.
5) Toilet Facilities: Toilet facilities shall be provided in the immediate vicinity of the office and shall be maintained.
(2) Emergency Equipment: Provide and maintain the following emergency equipment:
(a) First aid kit that meets or exceeds ANSI Z308.1 (latest version) Class B, Type IV. Mount to the wall inside the workroom.
(b) Dry chemical fire extinguishers classified 4-A:60-B:C, one (1) to be located inside each entrance to the trailer.
(3) Window Coverings: Provide adjustable mini blinds.
(4) Office Furniture: Provide good quality, fully functional, office furniture as follows:
QUANTITY DESCRIPTION
Five (5) Folding Office Chairs.
One (1) Office desk (30-inches by 60-inches minimum).
Two (2) Office tables (30-inches by 60-inches minimum).
One (1) Five (5) drawer file cabinet.
One (1) Bookcase (30-inches by 13-inches by 48-inches).
Twelve (12) “Plan Hold” binders No. 1CB-24 (including one (1) plan rack).
D. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK: See FAR 52.211-10 in
Section F of the solicitation/contract.
1. SUBMITTAL AND COORESPONDANCE RESPONSE TIME: Except as otherwise provided for specific submittals, WAPA will require 40-calendar days for review of drawings or data submitted for approval.
2. OUTAGE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage restrictions shall apply:
a. Outages may be taken:
(1) Marana – Rattlesnake: March 3, 2025 to May 21, 2025.
(2) ED5 – Marana: May 22, 2025 to September 26, 2025.
(3) Rattlesnake – Tucson: September 29, 2025 to May 29 2026.
(4) Tucson – Adams Tap: June 1, 2026 to June 30, 2027.
b. Outage requests must be made a minimum of 45-days prior to the desired start of the outage.
c. The electrical operation of the transmission lines is under the jurisdiction of WAPA’s Operations Office. Approval or denial of an individual outage request will be based on transmission system electrical loads, system operating configurations and weather conditions at the time the outage is scheduled to begin. At any time because of transmission system electrical loads, transmission system operation or reliability, WAPA may deny an outage request or direct the Contractor to return facilities to operating conditions and release the applicable Special Work Permit. Make all outage requests in writing to the Field Engineer a minimum of 45-days in advance. Meeting the minimum advance notice requirement of 45-days does not guarantee an outage will be approved. To improve the chances of an outage being approved, all outages should be submitted with as much advance notice as practicable. Weather conditions and other system conditions such as other scheduled and nonscheduled (forced) outages must be evaluated against an outage request before approval can be granted.
3. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:
a. Work shall be performed during daylight hours unless otherwise approved by the Contracting Officer’s Representative (COR).
4. PROTECTIVE GROUND LEADS: See WAPA Construction Standards, Standard 1 “General
Requirements”, Section 1.4.14.3(1).
5. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:
a. The maximum available fault current in the Saguaro (ED5) to Marana segment is
15,879-amps and the X/R ratio is 8.25.
b. The maximum available fault current in the Marana to Rattlesnake segment is 5,626-amps and the X/R ratio is 4.85.
c. The maximum available fault current in the Rattlesnake to Tucson segment is 5,503-amps and the X/R ratio is 4.85.
d. The maximum available fault current in the Tucson to Del Bac segment is 5,263-amps and the X/R ratio is 4.66.
e. The maximum available fault current in the Del Bac to Nogales segment is 4,065-amps and the X/R ratio is 5.2.
f. The maximum available fault current in the Nogales to Apache segment is 10,992-amps and the X/R ratio is 19.0.
g. The maximum available fault current in the Tortolita Substation area is 11,695-amps and the X/R ratio is 19.1.
h. The maximum available fault current in the DeMoss Petrie Substation area is 21,469-amps and the X/R ratio is 19.7.
i. The maximum available fault current in the Vail Substation area is 10,613-amps and the
X/R ratio is 6.1.
j. A minimum of 1 (number) 4/0 (size) grounds shall be used in all areas.
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer within 45-calendar days after date of Notice to Proceed.
2. FORMAT AND DETAIL: Dates for each item of Government-Furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.
F. MATERIAL: Furnish all material for completing the work, except material furnished by WAPA as listed below:
ITEM
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
One (1) 11,270-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-01
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$29,866
One (1) 21,770-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-02
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$57,691
One (1) 21,810-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-03
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$57,797
One (1) 18,030-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-04
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$47,780
One (1) 10,950-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-05
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$29,018
One (1) 19,250-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-06
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$51,013
One (1) 15,290-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-07
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$40,519
One (1) 17,970-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-08
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$47,621
One (1) 19,540-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-09
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$51,781
One (1) 13,990-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-10
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$37,074
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
One (1) 14,370-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-11
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$38,081
One (1) 13,860-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-12
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$36,729
One (1) 14,450-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-13
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$38,293
One (1) 10,190-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-14
TBD
See note 2
TBD
See note 1 $27,004
One (1) 21,220-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-15
TBD
See note 2
TBD
See note 1 $56,233
One (1) 10,280-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-16
TBD
See note 2
TBD
See note 1 $27,242
One (1) 18,360-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-17
TBD
See note 2
TBD
See note 1 $48,654
One (1) 11,840-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-18
TBD
See note 2
TBD
See note 1 $31,376
One (1) 20,570-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-19
TBD
See note 2
TBD
See note 1 $54,511
One (1) 13,860-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-20
TBD
See note 2
TBD
See note 1 $36,729
One (1) 18,840-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-21
TBD
See note 2
TBD
See note 1 $49,926
One (1) 19,750-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-22
TBD
See note 2
TBD
See note 1 $52,338
One (1) 13,440-FT reel of optical ground wire –SX-41/47/531 (DNO- 10744, 96 fiber) – Reel No. VT-23
TBD
See note 2
TBD
See note 1 $35,616
21 OPGW ground clamps, AFL P/N
OBCE2E21
2 ea.
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$840
450 OPGW downlead clamps, AFL
P/N FDOA-B5B5
2 ea.
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$18,482
21 OPGW coil brackets, AFL P/N CB-
44-3AL
30 ea.
NST 8/9/2024
NLT 11/8/20242
Avra Valley Appendix B
$8,229
130 10,000-FT reels of 1272 kcmil, ACSS/MA2, 54/19, Pheasant conductor
16,337 ea.
NST 8/9/2024
NLT 11/8/2024
Avra Valley Appendix B
$6,097,000
21 10,000-FT reels of 1/2-inch, 7-strand, high-strength steel overhead ground wire
5170 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley
$623,202
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
972 single-string suspension insulator assemblies Type SI11-B (25,000 lbs), without insulators, suitable for 1272 kcmil, 54/19, Pheasant ACSS/MA2
10 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$240,665
153 single-string suspension insulator assemblies Type SI11-B (Jumper) (25,000 lbs), without insulators, suitable for 1272 kcmil, 54/19, Pheasant ACSS/MA2
160 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$62,520
348 double-string tension insulator assemblies Type T21-C (30,000 lbs) , without insulators, suitable for 1272 kcmil, 54/19, Pheasant ACSS/MA2
40 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$206,689
Nine (9) horizontal post insulator assemblies Type HF1-F (2000 lbs) , without insulators, suitable for 1272 kcmil, 54/19, Pheasant ACSS/MA2
10 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$12,885
Nine (9) double-string tension insulator assemblies Type T21-C (30,000 lbs), without insulators, suitable for 795 kcmil, ACSR/SD, Type 16, Drake/SD
40 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$6,746
Three (3) double-string tension insulator assemblies Type T21-C (30,000 lbs), without insulators, suitable for 795 kcmil, 26/7, Drake
ACSR
40 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$1,599
161 suspension assemblies Type OGW-SL (15,000 lbs) suitable for 1/2-inch, high strength or extra high strength, 7-strand steel overhead ground wire
10 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$35,541
52 tension assemblies Type OGW-TV (20,000 lbs) suitable for 1/2-inch, high strength or extra high strength, 7-strand steel overhead ground wire
13 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$11,375
Six (6) tension assemblies Type OGW- TV (20,000 lbs) suitable for 3/8-inch, high strength or extra high strength, 7-strand steel overhead ground wire
13 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$1,002
163 suspension assemblies Type OPGW-SL (15,000 lbs) suitable for 0.531-inch diameter optical overhead ground wire
10 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$39,214
66 tension assemblies Type OPGW- TV (20,000 lbs) suitable for 0.531-inch diameter optical overhead ground wire
13 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$33,266
200 conductor compression splices suitable for 1272 kcmil, 54/19, Pheasant ACSS/MA2
12 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley
$90,161
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
40 overhead ground wire compression splices suitable for 1/2-inch, high strength, 7-strand steel overhead ground wire
3 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$3,498
Vibration dampers for 1272 kcmil, 54/19, Pheasant ACSS/MA2, quantity for TLT-DP / SGR-TUC segment
20 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$870,230
Vibration dampers for 1/2-inch, high strength, 7-strand steel overhead ground wire, quantity for TLT-DP / SGR-TUC segment
6 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$145,038
Vibration dampers for 0.531-inch diameter optical overhead ground wire, quantity for TLT-DP / SGR-TUC segment
6 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$145,038
25 aerial marker balls, orange, 36-inch, suitable for 1/2-inch, high strength, 7-strand steel overhead ground wire
17 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$24,475
20 aerial marker balls, yellow, 36-inch, suitable for 1/2-inch, high strength, 7-strand steel overhead ground wire
17 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$19,580
20 aerial marker balls, white, 36-inch, suitable for 1/2-inch, high strength, 7-strand steel overhead ground wire
17 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$19,580
35 aerial marker balls, orange, 36-inch, suitable for 0.531-inch diameter optical overhead ground wire
17 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$36,238
20 aerial marker balls, yellow, 36-inch, suitable for 0.531-inch diameter optical overhead ground wire
17 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$20,707
20 aerial marker balls, white, 36-inch, suitable for 0.531-inch diameter optical overhead ground wire
17 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$20,707
71 bird flight diverters, PLP catalog number SFD-1140
0.70 ea.
NST 9/30/2024
NLT 1/20/2025
Avra Valley Appendix B
$1,299
1179 230-kV composite suspension insulators, with grading ring, for suspension assemblies and jumpers
22 ea.
NST 5/31/2024
NLT 1/20/2025
Phoenix Warehouse See note 1
$439,400
780 230-kV composite suspension insulators, with grading ring, for tension assemblies
22 ea.
NST 5/31/2024
NLT 1/20/2025
Phoenix Warehouse See note 1
$290,700
12-line post insulators, with grading ring, for jumpers
100 ea.
NST 5/31/2024
NLT 1/20/2025
Phoenix Warehouse See note 1
$7,400
915 230-kV composite suspension insulators, with grading ring, for suspension assemblies and jumpers
22 ea.
TBD
See note 2
TBD
See note 1 $341,000
858 230-kV composite suspension insulators, with grading ring, for tension assemblies
22 ea.
TBD
See note 2
TBD
See note 1 $319,800
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
3-line post insulators, with grading ring, for jumpers
100 ea.
TBD
See note 2
TBD
See note 1 $2,000
One (1) Type 291K-35 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cages
25,600
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$103,500
One (1) Type 291K-40 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cages
28,300
TBD
See note 2
TBD
See note 1 $114,650
One (1) Type 291K-55 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cages
39,100
TBD
See note 2
TBD
See note 1 $152,150
One (1) Type 291K-60 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cages
40,950
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$159,600
One (1) Type 291M-40 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cages
27,700
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$112,100
One (1) Type 291N-50 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
51,050
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$196,050
One (1) Type 291N-55 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
56,350
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$215,950
One (1) Type 291N-65 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
61,900
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$237,300
One (1) Type 291N-75 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
68,300
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$261,850
Three (3) Type 291N-85 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
77,950 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$298,300 ea.
One (1) Type 291N-90 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
79,950
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$306,100
One (1) Type 291N-95 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
85,050
NST 12/16/24
NLT 2/28/25
Avra Valley
$325,400
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
Two (2) Type 291S-80 (DE) with 36-FT embedment dulled-galvanized steel pole structures with maintenance provisions
23,150 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$96,400 ea.
One (1) Type 291Y-45 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
27,450 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$111,650 ea.
One (1) Type 291Y-45 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
27,450 ea.
TBD
See note 2
TBD
See note 1 $111,650 ea.
Two (2) Type 292A-55 (DE) with 37-FT embedment dulled-galvanized steel pole structures with maintenance provisions
41,250 ea.
TBD
See note 2
TBD
See note 1 $158,600 ea.
One (1) Type 292A-55 (DE) with 40-FT embedment dulled-galvanized steel pole structure with maintenance provisions
43,200
TBD
See note 2
TBD
See note 1 $165,850
One (1) Type 292A-70 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
42,700
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$165,400
One (1) Type 292A-70 (DE) with 30.5-FT embedment dulled-galvanized steel pole structure with maintenance provisions
45,250
TBD
See note 2
TBD
See note 1 $174,200
One (1) Type 292A-75 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
45,000
TBD
See note 2
TBD
See note 1 $174,350
One (1) Type 292A-80 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
47,250
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$183,050
One (1) Type 292A-85 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
52,750
TBD
See note 2
TBD
See note 1 $203,900
One (1) Type 292A-85 (DE) with 35-FT embedment dulled-galvanized steel pole structure with maintenance provisions
55,400
TBD
See note 2
TBD
See note 1 $212,900
One (1) Type 292A-85 (DE) with 42-FT embedment dulled-galvanized steel pole structure with maintenance provisions
57,850
TBD
See note 2
TBD
See note 1 $222,050
One (1) Type 292A-90 (DE) with 35-FT embedment dulled-galvanized steel pole structure with maintenance provisions
56,600
NST 12/16/24
NLT 2/28/25
Avra Valley
$217,600
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
One (1) Type 292D-55 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
57,300 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$219,450 ea.
Three (3) Type 292D-55 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
57,300 ea.
TBD
See note 2
TBD
See note 1 $219,450 ea.
One (1) Type 292D-60 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
63,800
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$243,850
Six (6) Type 292D-70 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
69,750 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$266,700 ea.
Five (5) Type 292D-70 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
69,750 ea.
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$266,700 ea.
Five (5) Type 292D-70 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
69,750 ea.
TBD
See note 2
TBD
See note 1 $266,700 ea.
Two (2) Type 292D-75 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
71,500 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$273,550 ea.
One (1) Type 292D-75 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
71,500 ea.
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$273,550 ea.
Four (4) Type 292D-75 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
71,500 ea.
TBD
See note 2
TBD
See note 1 $273,550 ea.
One (1) Type 292D-85 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
75,150 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$287,500 ea.
One (1) Type 292D-85 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
75,150 ea.
TBD
See note 2
TBD
See note 1 $287,500 ea.
One (1) Type 292D-135 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
114,300
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$436,400
Two (2) Type 292F-70 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
52,500 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley
$200,900 ea.
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
Four (4) Type 292F-75 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
58,950 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$225,250 ea.
One (1) Type 292F-105 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
77,650
TBD
See note 2
TBD
See note 1 $296,650
One (1) Type 292M-105 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
111,750
TBD
See note 2
TBD
See note 1 $424,050
One (1) Type 292N-50 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
76,300
TBD
See note 2
TBD
See note 1 $290,050
One (1) Type 292N-55 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
86,150 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$327,050 ea.
One (1) Type 292N-55 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
86,150 ea.
TBD
See note 2
TBD
See note 1 $327,050 ea.
Two (2) Type 292N-60 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
89,300 ea.
TBD
See note 2
TBD
See note 1 $339,100 ea.
One (1) Type 292N-65 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
93,000
TBD
See note 2
TBD
See note 1 $353,250
One (1) Type 292N-70 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
96,800 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$367,550 ea.
Three (3) Type 292N-70 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
96,800 ea.
TBD
See note 2
TBD
See note 1 $367,550 ea.
Two (2) Type 292N-75 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
102,300 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$388,550 ea.
Four (4) Type 292N-75 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
102,300 ea.
TBD
See note 2
TBD
See note 1 $388,550 ea.
Two (2) Type 292N-80 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
103,900 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley
$394,700 ea.
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
One (1) Type 292N-85 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
106,250
TBD
See note 2
TBD
See note 1 $403,750
One (1) Type 292N-95 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
113,400
TBD
See note 2
TBD
See note 1 $430,900
One (1) Type 292S-70 (DE) with 27-FT embedment dulled-galvanized steel pole structure with maintenance provisions
30,250
TBD
See note 2
TBD
See note 1 $118,400
One (1) Type 292S-75 (DE) with 27-FT embedment dulled-galvanized steel pole structure with maintenance provisions
32,200
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$126,050
One (1) Type 292S-75 (DE) with 31.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
33,300
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$130,150
One (1) Type 292S-75 (DE) with 36-FT embedment dulled-galvanized steel pole structure with maintenance provisions
35,300
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$137,600
Five (5) Type 292S-80 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
32,250 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$126,950 ea.
One (1) Type 292S-80 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
32,250 ea.
TBD
See note 2
TBD
See note 1 $126,950 ea.
One (1) Type 292S-80 (DE) with 26-FT embedment dulled-galvanized steel pole structure with maintenance provisions
33,600
TBD
See note 2
TBD
See note 1 $131,450
Nineteen (19) Type 292S-80 (DE) with 29.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
34,450 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$134,600 ea.
Twelve (12) Type 292S-80 (DE) with 29.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
34,450 ea.
TBD
See note 2
TBD
See note 1 $134,600 ea.
Fifteen (15) Type 292S-80 (DE) with 31-FT embedment dulled-galvanized steel pole structures with maintenance provisions
34,850 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$136,100 ea.
Nine (9) Type 292S-80 (DE) with 34.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
35,700 ea.
TBD
See note 2
TBD
$139,250 ea.
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
One (1) Type 292S-80 (DE) with 36.5- FT embedment dulled-galvanized steel pole structure with maintenance provision
36,850 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$143,550 ea.
Five (5) Type 292S-80 (DE) with 36.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
36,850 ea.
TBD
See note 2
TBD
See note 1 $143,550 ea.
Two (2) Type 292S-80 (DE) with 39.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
37,600 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$146,350 ea.
Two (2) Type 292S-80 (DE) with 43-FT embedment dulled-galvanized steel pole structures with maintenance provisions
38,450 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$149,500 ea.
Two (2) Type 292S-80 (DE) with 47-FT embedment dulled-galvanized steel pole structures with maintenance provisions
39,500 ea.
TBD
See note 2
TBD
See note 1 $153,400 ea.
Eleven (11) Type 292S-85 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
33,800 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$133,100 ea.
Twelve (12) Type 292S-85 (DE) with 28.5-ft embedment dulled-galvanized steel pole structures with maintenance provisions
35,550 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$139,100 ea.
Four (4) Type 292S-85 (DE) with 28.5-ft embedment dulled-galvanized steel pole structures with maintenance provisions
35,550 ea.
TBD
See note 2
TBD
See note 1 $139,100 ea.
Eight (8) Type 292S-85 (DE) with 31.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
36,300 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$141,850 ea.
Four (4) Type 292S-85 (DE) with 35- FT embedment dulled-galvanized steel pole structures with maintenance provisions
37,200 ea.
TBD
See note 2
TBD
See note 1 $145,200 ea.
Two (2) Type 292S-85 (DE) with 36.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
39,700 ea.
TBD
See note 2
TBD
See note 1 $154,500 ea.
Nine (9) Type 292S-85 (DE) with 40- FT embedment dulled-galvanized steel pole structures with maintenance provisions
40,600 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$157,850 ea.
One (1) Type 292S-85 (DE) with 40-FT embedment dulled-galvanized steel pole structure with maintenance provision
40,600 ea.
TBD
See note 2
TBD
$157,850 ea.
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
One (1) Type 292S-85 (DE) with 43-FT embedment dulled-galvanized steel pole structure with maintenance provisions
41,400
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$160,850
Five (5) Type 292S-90 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
35,900 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$141,100 ea.
Two (2) Type 292S-90 (DE) with 27.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
38,150 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$148,950 ea.
Four (4) Type 292S-90 (DE) with 31.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
39,200 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$152,850 ea.
One (1) Type 292S-90 (DE) with 35-FT embedment dulled-galvanized steel pole structure with maintenance provisions
40,150
TBD
See note 2
TBD
See note 1 $156,400
One (1) Type 292S-90 (DE) with 36.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
41,100
TBD
See note 2
TBD
See note 1 $159,900
One (1) Type 292S-90 (DE) with 38.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
41,650
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$161,950
Two (2) Type 292S-90 (DE) with 43.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
43,000 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$167,000 ea.
One (1) Type 292S-95 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
37,250
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$146,500
One (1) Type 292S-95 (DE) with 28-FT embedment dulled-galvanized steel pole structure with maintenance provisions
39,650
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$154,900
Two (2) Type 292S-100 (DE) with 32.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
41,700 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$162,700 ea.
One (1) Type 292S-135 (DE) with 42- FT embedment dulled-galvanized steel pole structure with maintenance provisions
62,750
TBD
See note 2
TBD
See note 1 $242,900
One (1) Type 292T-50 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
54,050
TBD
See note 2
TBD
$206,850
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
Four (4) Type 292X-60 (DE) with 25.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
23,300 ea.
TBD
See note 2
TBD
See note 1 $96,550 ea.
One (1) Type 292X-60 (DE) with 31-FT embedment dulled-galvanized steel pole structure with maintenance provisions
24,200
TBD
See note 2
TBD
See note 1 $100,250
Three (3) Type 292X-65 (DE) with 27.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
26,500 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$104,300 ea.
Three (3) Type 292X-65 (DE) with 27.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
26,500 ea.
TBD
See note 2
TBD
See note 1 $104,300 ea.
One (1) Type 292X-65 (DE) with 29.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
26,900 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$105,750 ea.
One (1) Type 292X-65 (DE) with 29.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
26,900 ea.
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$105,750 ea.
Four (4) Type 292X-65 (DE) with 29.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
26,900 ea.
TBD
See note 2
TBD
See note 1 $105,750 ea.
One (1) Type 292X-65 (DE) with 31.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
27,300
TBD
See note 2
TBD
See note 1 $107,250
Four (4) Type 292X-70 (DE) with 26.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
26,950 ea.
TBD
See note 2
TBD
See note 1 $106,150 ea.
Three (3) Type 292X-70 (DE) with 30- FT embedment dulled-galvanized steel pole structures with maintenance provisions
27,650 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$108,750 ea.
Eight (8) Type 292X-70 (DE) with 34- FT embedment dulled-galvanized steel pole structures with maintenance provisions
28,850 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$113,200 ea.
Two (2) Type 292X-70 (DE) with 36-FT embedment dulled-galvanized steel pole structures with maintenance provisions
29,250 ea.
TBD
See note 2
TBD
See note 1 $114,700 ea.
Two (2) Type 292X-75 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
27,550 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley
$114,050 ea.
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
Five (5) Type 292X-75 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
27,550 ea.
TBD
See note 2
TBD
See note 1 $114,050 ea.
Three (3) Type 292X-75 (DE) with 26- FT embedment dulled-galvanized steel pole structures with maintenance provisions
27,900 ea.
TBD
See note 2
TBD
See note 1 $110,050 ea.
Five (5) Type 292X-75 (DE) with 30-FT embedment dulled-galvanized steel pole structures with maintenance provisions
28,700 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$113,050 ea.
Two (2) Type 292X-75 (DE) with 30-FT embedment dulled-galvanized steel pole structures with maintenance provisions
28,700 ea.
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$113,050 ea.
Three (3) Type 292X-75 (DE) with 30- FT embedment dulled-galvanized steel pole structures with maintenance provisions
28,700 ea.
TBD
See note 2
TBD
See note 1 $113,050 ea.
One (1) Type 292X-75 (DE) with 34.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
30,000
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$117,850
One (1) Type 292X-75 (DE) with 41-FT embedment dulled-galvanized steel pole structure with maintenance provisions
31,300
TBD
See note 2
TBD
See note 1 $122,700
Four (4) Type 292X-80 (BP) dulled-galvanized steel pole structures with maintenance provisions and anchor bolt cages
28,200 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$111,750 ea.
One (1) Type 292X-80 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
28,200 ea.
TBD
See note 2
TBD
See note 1 $111,750 ea.
Three (3) Type 292X-80 (DE) with 27- FT embedment dulled-galvanized steel pole structures with maintenance provisions
29,150 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$114,900 ea.
Three (3) Type 292X-80 (DE) with 27- FT embedment dulled-galvanized steel pole structures with maintenance provisions
29,150 ea.
TBD
See note 2
TBD
See note 1 $114,900 ea.
Thirteen (13) Type 292X-80 (DE) with 29.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
29,700 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$116,950 ea.
Two (2) Type 292X-80 (DE) with 30.5-ft embedment dulled-galvanized steel pole structures with maintenance provisions
29,900 ea.
TBD
See note 2
TBD
$117,700 ea.
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
Two (2) Type 292X-80 (DE) with 33-FT embedment dulled-galvanized steel pole structures with maintenance provisions
30,400 ea.
TBD
See note 2
TBD
See note 1 $119,550 ea.
Three (3) Type 292X-80 (DE) with 38.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
31,950 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$125,300 ea.
One (1) Type 292X-80 (DE) with 38.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
31,950 ea.
TBD
See note 2
TBD
See note 1 $125,300 ea.
Two (2) Type 292X-80 (DE) with 45-FT embedment dulled-galvanized steel pole structures with maintenance provisions
33,300 ea.
TBD
See note 2
TBD
See note 1 $130,350 ea.
One (1) Type 292X-85 (BP) dulled-galvanized steel pole structure with maintenance provisions and anchor bolt cage
29,250
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$116,050
Five (5) Type 292X-85 (DE) with 27-FT embedment dulled-galvanized steel pole structures with maintenance provisions
30,250 ea.
TBD
See note 2
TBD
See note 1 $119,350 ea.
Two (2) Type 292X-85 (DE) with 30.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
30,950 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$121,950 ea.
Three (3) Type 292X-85 (DE) with 30.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
30,950 ea.
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$121,950 ea.
Two (2) Type 292X-85 (DE) with 41.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
33,700 ea.
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$132,200 ea.
One (1) Type 292X-85 (DE) with 41.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
33,700 ea.
TBD
See note 2
TBD
See note 1 $132,200 ea.
One (1) Type 292X-90 (DE) with 27-FT embedment dulled-galvanized steel pole structure with maintenance provisions
31,350
TBD
See note 2
TBD
See note 1 $123,650
One (1) Type 292X-90 (DE) with 30.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
32,100 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$126,450 ea.
Two (2) Type 292X-90 (DE) with 30.5- FT embedment dulled-galvanized steel pole structures with maintenance provisions
32,100 ea.
TBD
See note 2
TBD
$126,450 ea.
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
One (1) Type 292X-90 (DE) with 41.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
35,400
TBD
See note 2
TBD
See note 1 $138,700
One (1) Type 292X-95 (DE) with 30.5- FT embedment dulled-galvanized steel pole structure with maintenance provisions
33,700
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$132,750
One (1) Type 292X-100 (DE) with 27.5-FT embedment dulled-galvanized steel pole structure with maintenance provisions
34,700
TBD
See note 2
TBD
See note 1 $136,700
One (1) Type 292X-100 (DE) with 42.5-FT embedment dulled-galvanized steel pole structure with maintenance provisions
38,600
TBD
See note 2
TBD
See note 1 $151,200
Two (2) Type 292X-105 (DE) with 30.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
36,550 ea.
NST 12/16/24
NLT 2/28/25
Avra Valley Appendix B
$143,950 ea.
Two (2) Type 292X-105 (DE) with 34- FT embedment dulled-galvanized steel pole structures with maintenance provisions
37,350 ea.
TBD
See note 2
TBD
See note 1 $146,900 ea.
One (1) Type 292X-110 (DE) with 43- FT embedment dulled-galvanized steel pole structure with maintenance provisions
43,850
TBD
See note 2
TBD
See note 1 $171,300
One (1) Type 292X-115 (DE) with 34.5-FT embedment dulled-galvanized steel pole structure with maintenance provisions
42,550
TBD
See note 2
TBD
See note 1 $166,650
One (1) Type 292X-120 (DE) with 28- FT embedment dulled-galvanized steel pole structure with maintenance provisions
43,400
TBD
See note 2
TBD
See note 1 $170,150
Two (2) Type 292X-120 (DE) with 37- FT embedment dulled-galvanized steel pole structures with maintenance provisions
46,350 ea.
TBD
See note 2
TBD
See note 1 $181,150 ea.
One (1) Type 292X-125 (DE) with 28- FT embedment dulled-galvanized steel pole structure with maintenance provisions
44,900
TBD
See note 2
TBD
See note 1 $175,950
Two (2) Type 292X-140 (DE) with 33.5-FT embedment dulled-galvanized steel pole structures with maintenance provisions
51,600 ea.
NST 2/1/25
NLT 7/15/25
Avra Valley Appendix B
$201,800 ea.
One (1) Type 292X-140 (DE) with 33.5-FT embedment dulled-galvanized steel pole structure with maintenance provisions
51,600 ea.
TBD
See note 2
TBD
$201,800 ea.
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
DELIVERY
LOCATION
ESTIMATED
COST
10,934 Left Anchor Plates dulled-galvanized – Mark 1FP-5L
1.3 ea.
TBD
See note 2
TBD
See note 1 $17.00 ea.
10,934 Right Anchor Plates dulled-galvanized – Mark 1FP-5R
1.3 ea.
TBD
See note 2
TBD
$17.00 ea.
NST – No sooner than.
NLT – No later than.
1. POINTS-OF-DELIVERY: Material furnished by WAPA will be delivered to the locations identified in the table, except for materials listed as delivery location TBD. The Contractor shall select the delivery locations for the materials listed as TBD. The Contractor shall load, transport and unload the material to the jobsite. The Contractor shall inspect the equipment and report any damages to the COR.
a. Materials delivered to the Phoenix Warehouse are located at the following address:
615 S 43rd Avenue Phoenix, AZ 85009
2. DELIVERY DATES: Delivery dates that are known are shown in the table. WAPA will notify the
Contractor at a later date for material delivery dates marked “TBD”.
G. RIGHTS-OF-WAY:
1. GENERAL: WAPA’s transmission line right-of-way is 100-feet-wide in most areas but is subject to variability. WAPA does not represent that the Contractor can gain access to every structure site or travel continuously along the transmission line.
Orient construction methods and equipment to utilize Government-Furnished rights-of-way or obtain additional temporary access without additional cost to WAPA.