Att 5-504-23-053 EHRM PCRA.pdf

PDF 475 KB Posted

Attached to
Z2DA--EHRM Construction Amarillo-Project 504-21-700 Federal contract opportunity
Solicitation number
36C77624R0084
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This is a Pre-Construction Risk Assessment (PCRA) template and completed permit form for an Electronic Health Record Modernization (EHRM) Infrastructure Upgrades project at the Thomas E. Creek VA Medical Center in Amarillo (Project 504-21-700). The document provides a standardized framework for assessing construction, renovation, and maintenance work risks and determining required control measures.

The completed permit shows this is classified as a "Large Scale" activity requiring comprehensive control measures including dust control, pollution prevention, crane operations, fall protection, and confined entry plans. The project has received signatures from key stakeholders including Infection Prevention and Control, the Project Manager (Logan Dunn), Safety Officer (Lance Dewitt), and Construction Safety Committee in December 2023. The PCRA template details three levels of activity types (Inspection/Upkeep, Small-scale, and Large-scale) with increasingly stringent control requirements and must be used in conjunction with an Infection Control Risk Assessment (ICRA) when required. The document emphasizes the importance of coordination with adjacent areas and communication plans to minimize disruption to facility operations.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--EHRM Construction Amarillo-Project 504-21-700, newest first.
File Type Posted
36C77624R0084 0014.docx DOCX document
36C77624R0084 0013.docx DOCX document
PPQ - Amarillo.docx DOCX document
Att 28 - 504-21-700.EHRM.Amarillo.Add4.20250401.pdf PDF
Att 22 - 00 41 13.10 - Construction Estimate Breakdown Template.xlsx XLSX spreadsheet
RFP 36C77624R0084 3-28-2025.docx DOCX document
Att 1 Construction SOW Revised 504-21-700 - 3-27-25.pdf PDF
Limitations on Subcontracting - Construction.docx DOCX document
36C77624R0084 0006 SF 30.docx DOCX document
36C77624R0084 0012.docx DOCX document
0011 - DBA Wage Rates - Potter County - 3-14-25.pdf PDF
36C77624R0084 0011.pdf PDF
36C77624R0084 0010.docx DOCX document
Att 27- 504-21-700 EHRM Amarillo Add3 20250306.pdf PDF
36C77624R0084 0009.docx DOCX document
36C77624R0084 0008.docx DOCX document
Att 26-504-21-700 EHRM Amarillo.ADD 2-13-25.pdf PDF
36C77624R0084 0007.docx DOCX document
Att 20-Updated Wage Determ 1-3-25 Potter County TX.pdf PDF
Att 23-S05-Vendor Questions and RFIs Rspns Final.xlsx XLSX spreadsheet
Att 25- Amendment 0006-updated RFP 36C77624R0084.docx DOCX document
Att 24-504-21-700 EHRM Amarillo.ADD-1.20250128.pdf PDF
Prebid Site Visit Sign-in 1-6-25 n 1-17-25 combined.pdf PDF
36C77624R0084 0005.docx DOCX document
36C77624R0084 0004.docx DOCX document
36C77624R0084 0003.docx DOCX document
36C77624R0084 0002.docx DOCX document
36C77624R0084 0001.docx DOCX document
36C77624R0084_1 tradeoffs Final.pdf PDF
Att 10-EHRM Ama IFC Bld8.zip ZIP file
Att 11-EHRM Ama IFC Bld7 Bld9.zip ZIP file
Att 13-EHRM Ama IFC Bld26 Bld28 Bld29.zip ZIP file
Att 20-WD-Amarillo verified 12-17-24.pdf PDF
Att 1 Construction SOW Prj 504-21-700 11.13.24.pdf PDF
Att 3-ICRA DRAFT EHRM 12 14 2023 LEVEL 4.pdf PDF
Att 6- OIT-InfrastrucStdTelecomSpaces-AppxA B07.pdf PDF
Att 9-EHRM Ama IFC Bld1 Bld4.zip ZIP file
Att 19-Asbestos Insp Rpt.zip ZIP file
Att 22-Division Cost Breakdown.xlsx XLSX spreadsheet
Att 2-Limitations on Subcont - Constr.pdf PDF
Att 4-EHRM Prj Stnd Compl Memo.pdf PDF
Att 7-Amarillo_EHRM.SPEC.part 1.zip ZIP file
Att 14-EHRM Ama IFC Bld33 Bld34 Bld35 Bld36.zip ZIP file
Att 17-EHRM Ama IFC Bld54.zip ZIP file
Att 8-Amarillo_EHRM.SPEC.part 2.zip ZIP file
Att 12-EHRM Ama IFC Bld10 Bld11 Bld12 Bld14.zip ZIP file
Att 15-EHRM Ama IFC Bld44 Bld45 Bld46.zip ZIP file
Att 16-EHRM Ama IFC Bld48 Bld49 Bld53.zip ZIP file
Att 18-EHRM Ama IFC SITE.20241022.zip ZIP file
Att 21-PPQ.docx DOCX document
Show all 50

Z2DA--EHRM Construction Amarillo-Project 504-21-700 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHA Pre-Construction Risk Assessment (PCRA)

VHA-PCRA-2023-1.0 Page 1 of 5

PCRA Introductory Information and Instructions

Use this template as a baseline for performing facility Pre-Construction Risk Assessments (PCRA) for Construction, Renovation, and Maintenance work (referred to as the “activity” in this document). The template provides minimum requirements for categorizing activity type(s) and safety risk to determine the level of precautions needed to prevent impact related to Construction, Renovation and Maintenance on patients, employees, and contractors.

Ensure that the activity statement of work and any drawings available are used for the PCRA assessment and included in the project file with the completed PCRA.

Communication and coordination of all types of activity with affected areas are to be included among the control measures. The development of communication and coordination plans must begin during the activity planning phase.

Facilities may customize this template to incorporate site-specific information and requirements.

NOTE: This VHA PCRA template pertains specifically to non-infection-related safety for Construction, Renovation, and Maintenance activities. It must be used in conjunction with the VHA Infection Control Risk Assessment (ICRA) for the activity, if required, which specifically addresses infection risks outside the scope of this PCRA.

PERMIT: See the last page of this document for a fillable permit form to be used for posting at the activity site.

Activity Location:

Activity Name, Number, and/or Brief Description:

Table 1 - Construction, Renovation, and/or Maintenance Activity Type and Control Measures

NOTE: If any of the bulleted criteria in a higher activity type pertains to the work that will be done (even if the other criteria are in a lower type), use the higher activity type for the VHA PCRA.

Controls defined in Table 1 for the activity must be in place before the activity begins and maintained until work is completed and the area is activated. Control measures for each activity must also include the control measures in the preceding row(s).

As the activity progresses, a full re-evaluation of remaining activity type and risk is required prior to changing the level of control measures.

Activity Type determined from Table 1:

Activity Type and Description Control Measures Inspection/upkeep generally defined as follows:

• Work can be completed in a single shift, not to exceed 10 hours.

• Patients, employees and/or visitors may be in the area depending on the activity.

• Work that does not create dust or debris.

• Work that does not create vapors or fumes.

• Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety systems and are limited to 1 tile per 50 square feet with limited

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team.

Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the

VHA-PCRA-2023-1.0 Page 2 of 5 exposure time (not to exceed an hour for each tile) within the shift.

• Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.

• Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.

shop involved must work with Safety to ensure proper precautions are in place.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact to patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small scale Construction, Renovation and general maintenance/repair work, generally defined as follows:

• Prolonged work that may take longer than a single shift but not exceeding six months.

• Patients and employees are not to be in the area until activity is completed.

• Work that creates some noise and vibration due to power tool use.

• Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may o disturb asbestos, lead or silica o create the potential for falling objects o create vibration and/or noise in excess of 80 dB(A) in surrounding areas.

o cause penetrations in fire or smoke barrier

• Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:

o LOTO o The use of compressed gas cylinders

• Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.

• Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:

o Work on ladders o Rigging, hoisting or lifting of equipment or materials overhead

• Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.

• Architectural, structural, or any other work that may cause vapors or fumes such as:

o Roofing work o Flooring work o Painting or other large-scale use of such substances.

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. Where construction, Renovation and maintenance are done in an accredited facility, and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS.01.02.01 and the local facility policy including Fire watch if necessary. Staff is trained and the ILSM is verified regularly

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.

Large-scale construction, renovation, or maintenance generally defined as follows:

• Work exceeding 6 months in duration.

• Patients and employees are not to be in the area until activity is completed.

All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☐

VHA-PCRA-2023-1.0 Page 3 of 5

• Excavation or heavy equipment use taking place o Dig safe required utility location o Trench safety o Dust control plan o Equipment exhaust, Noise, Vibration

• Confined space entry required (permit required or not)

• Requires crane work o General crane work o Lift over buildings

• Includes elevated work o Roof work, fall protection o Window work, scaffolding and fall protection o Odor control

• Welding, cutting or use of torches requiring burn permits

• Demolition of building components and infrastructure including removal of multiple doors, walls, framing, ceilings, flooring, piping, electrical and HVAC that may o require asbestos, lead or silica abatement o create the potential for falling objects o create vibration and/or noise in excess of 90 dB(A) in surrounding areas.

o cause breaches to fire or smoke barrier

• The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators

• Plumbing work requiring LOTO and system shutdown and startup such as the installation of:

o new medical gas systems, o steam/heating hot water, condensate systems, o Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.

• Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. requiring LOTO and system isolation.

• Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors

• Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, terminal units and controls requiring lifting and support of equipment and systems.

3. Pollution prevention plan in place ☐

4. Dig safe paper work in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

Table 2. Affected Adjacent Area Assessment

In addition to the minimum precautions noted above for the Activity Type, it is critical that the activity be coordinated with the areas adjacent to the activity to ensure operations in those areas are not disrupted or impacted. List the adjacent areas in Table 2 below and develop activity-specific coordination plans and associated communication plans with each area to address activity work that could impact or disrupt the operation of the areas, in general as follows:

• If adjacent area is vacant (e.g., work outside, construction of new building, etc.):

o Coordination is typically not necessary other than potentially traffic flow and pedestrian access.

VHA-PCRA-2023-1.0 Page 4 of 5

• If adjacent area is non-continuously occupied (e.g., areas where outpatient care is provided, employee health, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., conduct work after hours).

• If adjacent area is occupied continuously (e.g., areas where inpatient care is provided, residential areas such as Community Living Centers, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., move affected party temporarily).

Area Service(s)/Type(s) of Area(s)

(e.g., OR, Unit/Ward, Sterile Processing, Administrative, etc)*

Point of Contact

(POC)

POC Contact Information

Construction plan communicated to POC?

Activity Area**

Area Above

Area Below

Adjacent Area 1

Adjacent Area 2

Adjacent Area 3

Adjacent Area 4

* There may be more than one Service/type of area for each row. List all. The information entered on this table must be used in the ICRA if required.

** List the area(s) in which the construction/renovation/maintenance activity will occur.

Infection Control Risk Assessment (ICRA)

Consult with Infection Prevention and Control regarding the assessment of potential infection risks associated with the activity and the need for control measures. See VHA Directive 7715 and the VHA ICRA Template for more information.

Is an ICRA required for the Activity? Yes ☐ No ☐

VHA-PCRA-2023-1.0

Pre-Construction Risk Assessment (PCRA) Permit This page must be posted at the entrance to the project area, or other designated area

Unique permit number:

Location and brief description of construction/renovation/maintenance Project manager Project start date Contact phone number Completion date Contractor or lead shop Permit expiration date

Activity Type Inspection/Upkeep, Small-scale, or Large-scale)

Activity Type Control measures to be in place for the duration of the activity (Check the box for the Activity Type to indicate the Control Measures)

Inspection/Upkeep

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small-scale

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. ILSMs in place and staff trained on situation

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor and documented on their daily log.

Large-scale

All control measures in both rows above and the following Activity Hazard Analyses and Control Plans as applicable (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☐

3. Pollution prevention plan in place ☐

4. Dig safe paperwork in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

*The location of all Activity Hazard Analyses and Control Plans (excavation, dust, pollution, etc.) as applicable shall be identified on this permit and shall be made available to all workers on the job.

Additional requirements:

Is an Infection Control Risk Assessment (ICRA) required for the Activity? Yes ☐ No ☐ Infection Prevention and Control signature:

Date:

Project Manager signature Date

Safety Officer signature Date

Chair, Construction Safety Committee signature

Date

PERMIT See the last page of this document for a fillable permit form to be used for posting at the activity site: Thomas E. Creek VA Medical Center
andor Brief Description: 504-21-700 Electronic Health Record Modernization (EHRM) Infrastructure Upgrades Amarillo
As the activity progresses a full reevaluation of remaining activity type and risk is required prior to changing: Large Scale
Excavation safety plan in place: On
Dust control plan in place: On
Dig safe paper work in place: On
Crane lift plan in place: On
Fall protection plan in place and staff trained: On
undefined: On
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcActivity Area: Buildings 1, 4, 7, 6/8, 9, 10, 11, 12, 13, 14, 26, 28, 29, 33, 34, 35, 36, 44, 45, 46, 48, 49, 53, 54 and the site
Point of Contact POCActivity Area:
POC Contact InformationActivity Area:
Construction plan communicated to POCActivity Area:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Above:
Point of Contact POCArea Above:
POC Contact InformationArea Above:
Construction plan communicated to POCArea Above:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Below:
Point of Contact POCArea Below:
POC Contact InformationArea Below:
Construction plan communicated to POCArea Below:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 1:
Point of Contact POCAdjacent Area 1:
POC Contact InformationAdjacent Area 1:
Construction plan communicated to POCAdjacent Area 1:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 2:
Point of Contact POCAdjacent Area 2:
POC Contact InformationAdjacent Area 2:
Construction plan communicated to POCAdjacent Area 2:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 3:
Point of Contact POCAdjacent Area 3:
POC Contact InformationAdjacent Area 3:
Construction plan communicated to POCAdjacent Area 3:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 4:
Point of Contact POCAdjacent Area 4:
POC Contact InformationAdjacent Area 4:
Construction plan communicated to POCAdjacent Area 4:
Is an ICRA required for the Activity: Yes
Activity Type InspectionUpkeep Smallscale or Largescale: Large Scale
1 Excavation safety plan in place: On
2 Dust control plan in place: On
3 Pollution prevention plan in place: On
4 Dig safe paperwork in place: On
5 Crane lift plan in place: On
6 Fall protection plan in place and staff trained: On
7 Confined entry plan in place and staff trained: On
Additional requirements:
Is an Infection Control Risk Assessment ICRA required for the Activity: Yes_2
Pollution prevention plan in place: On
Unique permit number: 504-23-053
Project manager: Logan Dunn, Serven Bebanco
Contact phone number: 806-355-9703 x4516, 806-355-9703 x7951
Project Start Date_af_date:
Completion Date_af_date:
Permit Expiration Date_af_date:
Contractor or lead shop: TBD
Location and brief description of Construction/Renovation/Maintenance: 504-21-700 Electronic Health Record Modernization (EHRM) Infrastructure Upgrades Amarillo
Check Box6: Off
Check Box7: Off
Check Box8: Yes
Date10_af_date: 12/14/2023
2023-12-15T09:37:38-0600
LOGAN DUNN
2023-12-15T09:41:35-0600
LANCE DEWITT
Project Manager Date Signed_af_date: 12/15/2023
Safety Officer Date Signed_af_date: 12/15/2023
2023-12-15T09:41:12-0600
LANCE DEWITT
CCS Date Signed_af_date: 12/15/2023
2023-12-14T12:50:56-0600
ALLISON J. HENRY 1658882

File details come from the government source that posted it. Updated .