About this file

This justification document supports a construction project at the St. Cloud VA Medical Center requiring certain brand name construction materials. The project scope includes electrical, HVAC, fire alarm, and data infrastructure upgrades. Brand name items specified include Best lock cores, Johnson Controls HVAC controls, and an Edwards fire alarm system to maintain compatibility with existing standardized systems. These components comprise an estimated portion of the overall project value between $10-20 million. While the components are identified as brand name, the construction procurement will be competed as a Service-Disabled Veteran-Owned Small-Business set-aside. This justification will be posted with solicitation number 36C77622B0035 for infrastructure upgrades at the St. Cloud Veterans Affairs Health Care System.

View the file

Other files for this federal contract opportunity

Other files attached to Y1AZ--EHRM Infrastructure Upgrades Construction - St. Cloud, newest first.
File Type Posted
Atch 41 - Construction Wage Rates - Stearns 7-29-22.pdf PDF
36C77622B0035 0003.pdf PDF
Atch 3 - Specifications Volume 3 - Asbestos addendum.pdf PDF
Atch 4 - General 1 of 2 addendum.pdf PDF
Atch 6 - BLDG 1 - 1 of 2 addendum.pdf PDF
Atch 8 - BLDG 2 addendum.pdf PDF
Atch 9 - BLDG 3 addendum.pdf PDF
Atch 12 - BLDG 6 addendum.pdf PDF
Atch 13 - BLDG 7 and 13 addendum.pdf PDF
Atch 27 - BLDG 96 addendum.pdf PDF
Atch 30 - BLDG 111 addendum.pdf PDF
Atch 31 - BLDG 112 addendum.pdf PDF
36C77622B0035 0002.pdf PDF
Technical Questions - FINAL - St. Cloud 7-28-22.pdf PDF
Atch 2 - Specifications Volume 2 addendum.pdf PDF
Atch 7 - BLDG 1 - 2 of 2 addendum.pdf PDF
Atch 16 - BLDG 10 addendum.pdf PDF
Atch 19 - BLDG 28 addendum.pdf PDF
Atch 23 - BLDG 50 addendum.pdf PDF
Atch 26 - BLDG 95 and 88 addendum.pdf PDF
Atch 29 - BLDG 109 and 57 addendum.pdf PDF
Atch 34 - BLDG 118 addendum.pdf PDF
Atch 35 - ADHC addendum.pdf PDF
Atch 36 - Parking Structure addendum.pdf PDF
36C77622B0035 - 6-9-22.pdf PDF
Atch 6 - BLDG 1 - 1 of 2.pdf PDF
Atch 16 - BLDG 10.pdf PDF
Atch 19 - BLDG 28.pdf PDF
Atch 22 - BLDG 49.pdf PDF
Atch 35 - ADHC.pdf PDF
Atch 2 - Specifications Volume 2.pdf PDF
Atch 3 - Specifications Volume 3 - Asbestos.pdf PDF
Atch 9 - BLDG 3.pdf PDF
Atch 11 - BLDG 5.pdf PDF
Atch 13 - BLDG 7 and 13.pdf PDF
Atch 14 - BLDG 8.pdf PDF
Atch 17 - BLDG 11.pdf PDF
Atch 29 - BLDG 109 and 57.pdf PDF
Atch 33 - BLDG 116.pdf PDF
Atch 38 - Contractor Core Work Hours.pdf PDF
Atch 39 - COVID-19 Safety Protocols 12-14-21.pdf PDF
Atch 41 - Construction Wage Rates - Stearns 4-1-22.pdf PDF
Atch 42 - Contractor Safety - Environmental Form.docx DOCX document
Atch 4 - General 1 of 2.pdf PDF
Atch 5 - General 2 of 2.pdf PDF
Atch 8 - BLDG 2.pdf PDF
Atch 23 - BLDG 50.pdf PDF
Atch 24 - BLDG 51.pdf PDF
Atch 27 - BLDG 96.pdf PDF
Atch 31 - BLDG 112.pdf PDF
Show all 50

Y1AZ--EHRM Infrastructure Upgrades Construction - St. Cloud has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF VETERANS AFFAIRS

Justification and Approval

For Other Than Full and Open Competition

1. Contracting Activity:

Veterans Health Administration (VHA), Program Contracting Activity Central (PCAC)

The proposed procurement, Invitation for Bid (IFB) 36C77622B0035 is for the EHRM Infrastructure Upgrades Construction project at the St. Cloud VA Medical Center (VAMC).

2. Nature and/or Description of the Action Being Processed:

This justification is to support the EHRM Infrastructure Upgrades Construction project at the St.

Cloud VAMC, that will be awarded as a firm-fixed price contract. This justification is for other than full and open competition for the procurement of certain construction materials. The use of a particular brand name for the items listed below accommodates standardization of these items throughout the facility.

a. Lock Cores

i. Best TE Series Interchangeable Core

b. HVAC Controls

i. Johnson Controls Direct-Digital Control

c. Fire Alarm

i. Edward EST Fire Alarm System

3. Description of Supplies/Services Required to Meet the Agency’s Needs:

This procurement is for the EHRM Infrastructure Upgrades Construction project at the St. Cloud VAMC. The scope includes everything necessary to complete the EHRM Infrastructure Upgrades Construction project that meets the requirements of the Department of Veterans Affairs. There are three (3) brand name items listed for which the VA is not able to accept equal or alternate items.

The value of these items is listed below and the VAAR Construction magnitude for the entire project is between $10,000,000 and $20,000,000.

a. Lock Cores

i. Best TE Series 7-pin

ii. Value:

iii. Description: interchangeable core keying system door locksets.

b. HVAC Controls

i. Johnson Controls Direct-Digital Control System

ii. Value:

iii. Description: HVAC control system for Heating, Ventilation, and Air Conditioning.

c. Fire Alarm System

i. Edward EST Fire Alarm System

ii. Value:

iii. Description: Installation of fire alarm equipment as specified in project specification.

4. Statutory Authority Permitting Other than Full and Open Competition:

(X) (1) Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements per FAR 6.302-1; 41 U.S.C. § 3304(a)(1)

( ) (2) Unusual and Compelling Urgency per FAR 6.302-2;

( ) (3) Industrial Mobilization, Engineering, Developmental or Research Capability or Expert Services per FAR 6.302-3;

( ) (4) International Agreement per FAR 6.302-4 ( ) (5) Authorized or Required by Statute FAR 6.302-5;

( ) (6) National Security per FAR 6.302-6;

( ) (7) Public Interest per FAR 6.302-7;

5. Demonstration that the Contractor’s Unique Qualifications or Nature of the Acquisition Requires the Use of the Authority Cited Above (applicability of authority):

These items have been standardized throughout the St. Cloud VAMC. Installing a different manufacturers’ system will create significant duplication in cost for the facility, and in most cases the equipment will not function properly. The specific impact for not using the brand name items is listed below:

a. Lock Cores

i. Best TE Series – 7 pin

ii. Impact: This product is the only key core used throughout the St. Cloud VA campus.

The medical center locksmith is trained to service these locksets and maintain them in working condition. It is necessary that all lockset hardware components added onto the existing system match the brand to facilitate proper interchangeability.

Supportability of the added lock cores will be accomplished with minimal additional investment in the existing system’s single standardized parts inventory.

b. HVAC Controls

i. Johnson Controls Direct-Digital Control System

ii. Impact: The patient occupied buildings, as well as the entire facility, employs the Johnson Controls system to regulate the buildings HVAC systems. The controls must be identical to the existing controls in every building to communicate with our centrally monitored Metasys System that our facility has in place. Expansion of the existing system to cover new construction will ensure compatibility and provide for seamless interface of the equipment while enhancing operability since personnel are already trained in maintenance and system operation. Supportability of the added system will be accomplished with minimal additional investment in the existing system’s single standardized parts inventory.

c. Fire Alarm System

i. Edwards EST Fire Alarm Systems

ii. Impacts: This partial requirement of this project is a minor extension of the existing system. At this time there are no competing vendors whose products are fully compatible with our existing Edwards EST; however, if equipment other than Edwards EST is found to have capability to provide interchangeable components and maintain a high level of fire alarm operations, then it will be considered. None to date is known or shown to be available.

6. Description of Efforts Made to ensure that offers are solicited from as many potential sources as deemed practicable:

In accordance with the Competition in Contracting Act (CICA), the components listed above are identified as brand name; however, the overall procurement will be competed as a Service-Disabled Veteran-Owned Small-Business (SDVOSB) Set-Aside. This Justification for Other Than Full and Open Competition will be posted to Contracting Opportunities with the solicitation.

Donald A. Marsh III Date Contracting Officer VHA Program Contracting Activity Central (PCAC)