This document provides specifications for hazardous materials abatement as part of a solicitation from the Department of Veterans Affairs Technology Acquisition Center Austin. The solicitation seeks a contractor to perform infrastructure upgrades at the St. Cloud Veterans Affairs Health Care System, including electrical, HVAC, data center security, fiber infrastructure, and hazardous materials abatement. The abatement work involves removing asbestos-containing materials from the site in accordance with all applicable regulations and disposal requirements.
View the file
Other files for this federal contract opportunity
Show all 50
Y1AZ--EHRM Infrastructure Upgrades Construction - St. Cloud has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Anderson Engineering of Minnesota, LLC
13605 1st Avenue North Plymouth, MN 55441
Phone: 763-412-4000 Fax: 763-412-4090
Prepared in association with the following:
Specialized Engineering Solutions
10360 Ellison Circle Omaha, NE 68134
St. Cloud EHRM Infrastructure Upgrades
VA PROJECT NUMBER: 656-21-235
4801 VETERANS DRIVE
ST CLOUD, MN 56303
TECHNICAL SPECIFICATIONS
Volume 3: Appendix A – Asbestos Survey
ANDERSON ENGINEERING OF MN, LLC
Project Number: 16305
Issue for
100% CONSTRUCTION DOCUMENTS
Issued for Bidding
MARCH 30, 2022
ASBESTOS REINSPECTION REPORT
LOCATION:
ST. CLOUD VA MEDICAL CENTER
4801 VETERANS DRIVE
ST. CLOUD, MN 56303
VA PROJECT #: 656-C90115
SOLICITATION #: 36C26319Q0714
INSPECTION DATES:
NOVEMBER 4-6, 2019
JULY 13, 2020
PRIME CONTRACTOR:
CASTLE HILL ASSOCIATES, LLC
218-A MECHANIC ST.
WATERVILLE, OH 43566
567-952-0212
EMarkfort Text Box
APPENDIX A: VA PROJECT NUMBER 656‐21‐235 ST CLOUD EHRM INFRASTRUCTURE UPGRADES
ST. CLOUD VA MEDICAL CENTER – ST. CLOUD, MN
NOVEMBER 2019
TABLE OF CONTENTS
1.0 ASBESTOS INSPECTION REPORT
• Table 1 – List of Acronyms
• Table 2 - Removal Priority Protocols
2.0 APPENDICES
Appendix A – Asbestos Quantities, Assessments, & Remediation Cost Estimates
Appendix B – Photographs of Asbestos Materials
Appendix C - Inspector Certifications
Appendix D – Asbestos Sample & Material Location Drawings
Appendix E – Asbestos Bulk Sampling Data & Lab Reports
Appendix F – O&M Plan (Operations & Maintenance)
1.0 EXECUTIVE SUMMARY
On November 4-6, 2019, Castle Hill Associates, LLC was contracted by the US Department of Veterans Affairs (VA) to perform asbestos re-inspections of 47 buildings on the campus of the St.
Cloud VA Medical Center in St. Cloud, Minnesota. The survey was performed as part of the VA project number 656-C90115 under Solicitation Number 36C26319Q0714. The Performance Work Statement (PWS) issued by the VA defined the scope of work for the asbestos survey. The buildings that were surveyed as part of this project included:
Buildings 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 13, 14, 28, 29, 30, 32, 37, 48, 49, 50, 51, 54, 57, 59, 69, 87, 88, 91, 92, 93, 94, 95, 96, 97, 99, 100, 103, 104, 105, 106, 107, 108, 109, 110, Connecting Corridors, and Tunnels.
The inspection was conducted by Brett Brumbaugh who was assisted by Sam Ansara. The project manager was Mr. Brumbaugh who has been conducting asbestos surveys, sampling, and consulting work since 1987. He is a State of Minnesota certified Asbestos Inspector. Sam Ansara has been conducting asbestos surveys, sampling, and consulting work since 1989. There was a previous asbestos reinspection and sampling conducted at the facility most recently in 2017 and those reports were reviewed and utilized by Castle Hill prior to this inspection. There were no limitations or exceptions to the PWS for the surveys conducted.
All accessible functional areas in the facilities were surveyed. All previous asbestos survey information and sampling conducted at the facilities were evaluated and incorporated into this survey.
All confirmed asbestos-containing materials were verified. This report can be incorporated into the facility’s management plan for asbestos-containing materials.
2.0 STATE AND LOCAL REGULATIONS
The State of Minnesota asbestos inspection and licensing regulations are similar to the Federal regulations. State asbestos regulations include requirements for licensing and certification of personnel who will perform asbestos-related work activities. All personnel who engage in asbestos-related activities must comply with the state licensing/certification requirements as well as with all Federal requirements.
3.0 SUMMARY OF FINDINGS
3.1 Asbestos/Non-Asbestos Containing Buildings on Campus
The following table summarizes whether each building contains asbestos or has been determined to be “asbestos free” based on the previous testing and current inspection:
BUILDING
ASBESTOS
PRESENT
NO ASBESTOS
PRESENT
1 Y
2 Y
3 Y
4 Y
5 N 6 Y
7 Y
8 Y
9 Y
10 Y
11 Y
13 Y
14 Y
28 Y
29 Y
30 N 32 N 37 N 48 Y
49 Y
50 Y
51 Y
54 Y
57 N 59 Y
69 N 87 N 88 Y
91 Y
92 Y
93 Y
94 N 95 Y
96 Y
97 N 99 N
100 N 103 N 104 N 105 N 106 N 107 N 108 N 109 N 110 N
Corridors Y
Tunnels Y
3.2 Asbestos-Containing Materials, Locations and Quantities by Building The following is a summary of the asbestos containing materials, locations, quantities of materials in each inspected building for this project. Please refer to Appendix A & D (assessment database and drawings) for the exact locations in each building.
Building 1
Asbestos Containing Materials Locations (refer to drawings & database for exact locations)
Quantity
Pipe insulation – Mud fittings on fiberglass insulated lines
Basement, 1st floor, 2nd floor, and 3rd floor 235 ea.
Pipe insulation – Mag block Concealed behind plaster walls and ceilings on all floors
330 lf +
Contaminated soil in crawlspace Crawlspace off of X-Ray room 315 sf
9” & 12” vinyl floor tile and black mastic Basement, 1st floor, and 2nd floor 275 sf
Fire Doors Basement, 1st floor, 2nd floor, and 3rd floor 6 doors
Exterior caulking on brick wall joints Exterior brick 675 lf
Exterior tar on downspouts Exterior downspouts 9 ea.
Building 2
(refer to drawings & database for exact locations) Quantity
Pipe insulation – Mag block Concealed behind plaster walls and ceilings on all floors
420 lf +
Contaminated soil in crawlspace Crawlspaces under east and west wings 9,800 sf
Fire Doors Basement, 1st floor, 2nd floor, and 3rd floor 17 doors
Exterior window frame caulk Exterior brick 229 windows
Black wall waterproofing Basement 220 sf
Exterior tar on downspouts Exterior downspouts 21 ea.
Building 3
Quantity
12” vinyl floor tile and black mastic 1st floor and 2nd floor 3,494 sf
Fire Doors 1st floor and 2nd floor 4 doors
Exterior window caulking Basement, 1st and 2nd floors 78 windows
Black wall mastic 1st and 2nd floors 1,560 sf
Transite inside convectors under windows 1st and 2nd floors 2,808 sf
Black ebony lab table tops & upper shelves 1st floor dental lab 121 130 sf
Building 4
Quantity
Pipe insulation – Mag block Concealed behind plaster walls and ceilings on all floors; N. Penthouse; Mech. Room 300
120 lf +
Contaminated soil in crawlspaces Crawlspaces in basement 6,551 sf
12” vinyl floor tile and black mastic Basement, 1st floor, and 2nd floor 13,790 sf
Fire Doors Basement, 1st floor, 2nd floor, and 3rd floor 6 doors
Exterior window glazing & caulking Windows in basement, 1st, and 2nd floors 199 windows
Exterior tar on downspouts Exterior downspouts 3 ea.
Transite wall sheets North Penthouse 348 sf
Black adhesive above windows Basement and 1st floor 23 windows
Building 5: No asbestos containing materials are present in this building.
Building 6
Quantity
Pipe insulation mud fittings on fiberglass insulated pipes
Rooms 101 and 102 (including inside univents) 20 fittings
Exterior window glazing & caulking All windows and doors
16 windows
4 doors Exterior tar roof overhang W. entry to Shop 104 6 lf Sink undercoating Shops 104 and 105 2 sinks
Building 7
Quantity
Pipe insulation Brine room 102 1 lf Tar/asphalt on drain pipe at floor Storage 105 20 lf Window caulking (exterior) All exterior metal windows on upper level 12 window units Sink undercoating Boiler room 100 1 sink
Building 8
Quantity
Pipe insulation – Mag block Elevator lobby 100 ceiling plenum 2 lf
9” & 12” vinyl floor tile and black mastic Basement and 1st floor 5,350 sf
Fire Doors 1st and 2nd floors 11 doors
Exterior window glazing & caulking Basement, 1st and 2nd floors 63 windows
Black adhesive on walls Basement and 1st floors above ceilings 60 sf
Building 9
Quantity
Pipe insulation – Mud fittings on fiberglass insulated lines
Basement and 1st floors above ceilings 18 ea.
12” vinyl floor tile and black mastic Basement, 1st floor, and 2nd floors 8,820 sf
Fire Doors Basement, 1st floor, 2nd floor 9 doors
Exterior window caulking Basement, 1st and 2nd floors 76 windows
Exterior tar on downspouts Exterior downspouts 7 ea.
Cove base adhesive/mastic Basement, 1st floor, 2nd floor 540 lf
Building 10
Quantity
12” vinyl floor tile and black mastic Basement Room 1 143 sf Door caulking (exterior) All exterior entry doors 8 doors Paper in light fixture Bathroom 202 1 fixture
Building 11
Quantity
Door caulking (exterior) All exterior entry doors 3 doors Window glazing West entry/stairs 28 windows
Building 13
Quantity
Pipe insulation Sub-floor pit in closet of Room 2 2 lf Exterior window glazing N. window of room 2 1 window
Building 14
Quantity
12” vinyl floor tile and black mastic S.E. entry hallway 244 sf
Window glazing West entry/stairs 2 windows
Building 28
Quantity
Pipe insulation – Mag. Block Basement, 1st, 2nd floor and attic 130 lf +
Contaminated soil in crawlspace Crawlspace in basement under corridor 20 sf
12” vinyl floor tile and black mastic Basement, 1st floor, and 2nd floors 12,760 sf
Fire Doors Basement, 1st floor, 2nd floors 8 doors
Transite inside convectors under windows 1st floor and 2nd floors 1,920 sf
Building 29
Quantity
Pipe insulation – Mag. Block Basement, 2nd floor, and attic 240 lf +
12” vinyl floor tile and black mastic Basement and 2nd floors 2,120 sf
Window frame caulk (exterior) Basement, 1st floor, 2nd floors 224 windows
Fire Doors Basement, 1st floor, 2nd floors 6 doors
Transite inside convectors under windows 1st floor and 2nd floor 1,050 sf
Cove base adhesive/mastic Storage Room 152 6 lf
Building 30: No asbestos containing materials are present in this building.
Building 32: No asbestos containing materials are present in this building.
Building 37: No asbestos containing materials are present in this building.
Building 48
Quantity
Pipe insulation – Mag block Concealed behind plaster walls and ceilings in Basement and 1st Floor
1,510 lf +
9” & 12” vinyl floor tile and black mastic Basement, 1st floor, and 2nd floor 2,260 sf
Fire Doors Basement, 1st floor, and 2nd floors 15 doors
Window glazing & caulking Windows in Basement, 1st, and 2nd floors 100 windows
Exterior vent caulking Exterior vents/grilles 11 vents
Exterior brick seam caulk Exterior brick seams 16 seams
Duct seam caulk Attic 1 duct
Building 49
Quantity
Pipe insulation – Mag block Concealed behind plaster walls and ceilings on all floors; N. Penthouse; Mech. Room 300
420 lf+
Contaminated soil in crawlspaces Crawlspace in sub-basement 16,625 sf
12” vinyl floor tile and black mastic Basement 4,510 sf
Fire Doors Basement 3 doors
Exterior door frame caulk 1st floor 1 door
2x4 lay-in ceiling tiles Basement – S.E. wing 1,436 sf
Vent caulk Basement S. entry 11 vents
Brown duct sealant/mastic 1st and 2nd floor above ceilings 20 lf
Black sink undercoating Basement Room 9 1 sink
Black tar wall waterproofing Basement Room 8, 9C, and 36A 460 sf
Building 50
Pipe insulation – Mag block Concealed behind plaster walls and ceilings on all floors; Attic
1,380 lf+
Contaminated soil in crawlspace South Crawlspace 9,210 sf
12” vinyl floor tile and black mastic Basement 460 sf
Fire Doors Basement, 1st, and 2nd floors 18 doors
Transite inside convectors under windows Basement, 1st, and 2nd floors 1,545 sf
Duct sealant/mastic 2nd floor above ceilings in N. wing 30 sf
Building 51
Pipe insulation – Mag block Concealed behind plaster walls and ceilings in basement and 1st floors
110 lf+
Contaminated soil in crawlspace Sub-Basement crawl space 16,625 sf
12” vinyl floor tile and black mastic Basement and 1st floor 708 sf
Fire Doors Basement, 1st, and 2nd floors 15 doors
Transite inside convectors under windows Basement, 1st, and 2nd floors 792 sf
Paper inside electrical switch box Basement hallway 1 sf
Glue pods for 12” ceiling tile 1st floor nurse station 32 sf
Caulking on exterior brick walls 1st and 2nd floors 48 lf
Building 54
Quantity
Pipe insulation – Mud fittings on fiberglass Metal shops 107 and 108 12 fittings 12” vinyl floor tile and black mastic Room 106, corridor 105, Office 102, and garage 103 602 sf
Black sink undercoating Break room 106 1 sink
Building 57: No asbestos containing materials are present in this building.
Building 59
Quantity
12” vinyl floor tile and black mastic Basement locker and bathrooms 1, 3, 8, and 9, 1st floor, and 2nd floor
2,260 sf
Fire Doors Basement and 1st floor stairwells 3 doors
Door frame caulk Basement & 1st floor entry doors 2 doors
Exterior vent caulking Exterior vents/grilles 11 vents
Exterior window glazing and caulking Basement & 1st floor windows 31 windows
Vibration dampening cloths on ducts 1st floor laundry room 101 4 each.
Building 69: No asbestos containing materials are present in this building.
Building 87: No asbestos containing materials are present in this building.
Building 88
Quantity
9” & 12” vinyl floor tile and black mastic Ground floor 3,634 sf
Fire Doors Ground floor corridor 3 doors
Exterior window glazing Ground floor windows 13 windows
Exterior expansion joint caulk Exterior brick expansion joints 32 lf
Building 91
Quantity
Fire door Entry door 1 door
Building 92
Quantity
Pipe penetration hole filler Northwest side of building exterior 1 sf Black sink undercoating Kitchen area 1 sink
Window frame caulk All windows 20 windows
Building 93
Black sink undercoating Kitchen area 1 sink
Building 94: No asbestos containing materials are present in this building.
Building 95
Brown duct seam sealant Above ceiling tiles on 1st floor ~220 lf
Building 96
Quantity
Black sink undercoating Kitchen 2 sinks Window frame caulk Windows 29 windows
Building 97: No asbestos containing materials are present in this building.
Building 99: No asbestos containing materials are present in this building.
Building 100: No asbestos containing materials are present in this building.
Building 103: No asbestos containing materials are present in this building.
Building 104: No asbestos containing materials are present in this building.
Building 105: No asbestos containing materials are present in this building.
Building 106: No asbestos containing materials are present in this building.
Building 107: No asbestos containing materials are present in this building.
Building 108: No asbestos containing materials are present in this building.
Building 109: No asbestos containing materials are present in this building.
Building 110: No asbestos containing materials are present in this building.
Connecting Corridors
Quantity
Window glazing Windows 163 windows Window frame caulk Windows 163 windows Exterior brick expansion joint caulking Exterior of corridors 424 lf Black tar on gutter downspouts Exterior of corridors for 2-4 46 lf Mastic under floor tile 50-51 sunroom 558 sf Door frame caulk Corridor for 49-51 5 doors
Tunnels
Quantity
Pipe insulation mud fittings on fiberglass pipe Tunnel between boiler house and Building 4 13 fittings
Contaminated soil in crawlspace Crawl between 48-49; 29-48; 29-3; N. of 2 3,400 sf
4.0 Explanation of Assessment of Asbestos Containing Materials
Re-inspection protocol is based on the Asbestos Hazard Emergency Response Act (AHERA), Environmental Protection Act’s (EPA’s) revised Asbestos Model Accreditation Plan (MAP) mandated by the Asbestos School Hazard Abatement Reauthorization Act (ASHARA), and the Department of Veterans Affairs (VA) Directive 7700. The tabular listing included in this report contains Building Number, Floor, Room Number, Material Category (i.e., TSI, SM or MM), Material Type, quantity, a numerical priority ranking, condition, potential for damage, potential for human exposure, drawing number, hazard ranking, recommended response action and associated cost estimate for implementation of those response actions.
The material assessment categories of the ACM identified in the building is formatted in the following order for the summary tables enclosed in this report:
• Material Category - Surfacing Material (SUR); Thermal System Insulation (TSI); Miscellaneous (MM)
• Material Type - Friable (F); Non-Fable (NF)
• Condition of Material - Good; Fair; Poor
• Potential for Damage - Low; Medium; High
• Physical Assessment - Low; Medium; High
• Recommended Response Action - 1 through 7
Material category is the type of material such as surfacing material (SUR), thermal system insulation (TSI), and miscellaneous (MM)
• Surfacing Material (SUR) - Surfacing ACM means surfacing material that is ACM. Surfacing material means material in a school building that is sprayed-on, troweled-on, or otherwise applied to surfaces, such as acoustical plaster on ceilings and fireproofing materials on structural members, or other materials on surfaces for acoustical, fireproofing, or other purposes.
• Thermal System Insulation (TSI) - Thermal system insulation ACM means thermal system insulation that is ACM. Thermal system insulation means material in a school building applied to pipes, fittings, boilers, breeching, tanks, ducts, or other interior structural components to prevent heat loss or gain, or water condensation, or for other purposes.
• Miscellaneous (MM) - Miscellaneous ACM means miscellaneous material that is ACM Miscellaneous material means interior building material on structural components, structural members or fixtures, such as floor and ceiling tiles, and does not include surfacing material or thermal system insulation.
Material type refers to the hardness of a material to be crumbled, pulverized, or reduced to powder by hand pressure as friable (F), and includes previously non-friable (NF) material after such previously non-friable material becomes damaged to the extent that when dry it may be crumbled, pulverized, or reduced to powder by hand pressure.
• Condition of Material - Good; Fair; Poor
• Potential for Damage - Low; Medium; High
• Physical Assessment - Low; Medium; High
Seven Categories define in the AHERA regulation one of which must be assigned to each friable surfacing and miscellaneous ACBM and each asbestos-containing TSI during the inspection/re-inspection.
1. Damaged or significantly damaged TSI ACBM - Damaged or significantly damaged thermal system insulation ACM means thermal system insulation ACM on pipes, boilers, tanks, ducts, and other thermal
EMarkfort system insulation equipment where the insulation has lost its structural integrity, or its covering, in whole or in part, is crushed, water-stained, gouged, punctured, missing, or not intact such that it is not able to contain fibers. Damage may be further illustrated by occasional punctures, gouges or other signs of physical injury to ACM; occasional water damage on the protective coverings/jackets; or exposed ACM ends or joints. Asbestos debris originating from the ACBM in question may also indicate damage.
2. Damaged friable surfacing ACBM - Damaged friable surfacing ACM means friable surfacing ACM which has deteriorated or sustained physical injury such that the internal structure (cohesion) of the material is inadequate or which has delaminated such that its bond to the substrate (adhesion) is inadequate, or which, for any other reason, lacks fiber cohesion or adhesion qualities. Such damage or deterioration may be illustrated by the separation of ACM into layers; separation of ACM from the substrate; flaking, blistering, or crumbling of the ACM surface; water damage; significant or repeated water stains, scrapes, gouges, mars or other signs of physical injury on the ACM. Asbestos debris originating from the ACBM in question may also indicate damage.
3. Significantly damaged friable surfacing ACBM - Significantly damaged friable surfacing ACM means damaged friable surfacing ACM in a functional space where the damage is extensive and severe.
4. Damaged or significantly damaged friable miscellaneous ACBM - Damaged friable miscellaneous ACM means friable miscellaneous ACM which has deteriorated or sustained physical injury such that the internal structure (cohesion) of the material is inadequate or, if applicable, which has delaminated such that its bond to the substrate (adhesion) is inadequate or which for any other reason lacks fiber cohesion or adhesion qualities.
Such damage or deterioration may be illustrated by the separation of ACM into layers; separation of ACM from the substrate; flaking, blistering, or crumbling of the ACM surface; water damage; significant or repeated water stains, scrapes, gouges, mars or other signs of physical injury on the ACM. Asbestos debris originating from the ACBM in question may also indicate damage.
5. ACBM with Potential for Damage - Potential damage means circumstances in which:
(1) Friable ACBM is in an area regularly used by building occupants, including maintenance personnel, in the course of their normal activities.
(2) There are indications that there is a reasonable likelihood that the material or its covering will become damaged, deteriorated, or delaminated due to factors such as changes in building use, changes in operations and maintenance practices, changes in occupancy, or recurrent damage.
6. ACBM with potential for significant damaged - Potential significant damage means circumstances in which:
(1) Friable ACBM is in an area regularly used by building occupants, including maintenance personnel, in the course of their normal activities.
(2) There are indications that there is a reasonable likelihood that the material or its covering will become significantly damaged, deteriorated, or delaminated due to factors such as changes in building use, changes in operations and maintenance practices, changes in occupancy, or recurrent damage.
7. Any remaining friable ACBM or Friable Suspected ACBM
5.0 EXPLANATION OF REMEDIATION COST ESTIMATES
All remediation cost (removal and repair) estimates are based upon RS Means data. Since RS Means does not account for work in VA Medical Centers, all cost estimates are adjusted to reflect the VA specific requirements for abatement. In addition, the cost estimates reflect the quantity and location of the asbestos materials. For example, abatement work in crawl spaces is expected to be much costlier than work in more accessible areas of building. Also, the costs for each material in each building are intended to be for “stand alone” projects and the combination of areas for removal will reduce the costs due to an economy of scale.
6.0 CONCLUSION/RECOMMENDATIONS
An operations and maintenance (O&M) program has been developed by the VAMC specifically for the positively identified ACBM in the facilities. Any renovation/demolition work which may impact these positive materials should be conducted in accordance with the O&M program and all applicable Federal, state, and local regulations by appropriately trained and VA-approved personnel and contractors. Since demolition was not performed as part of the inspection work at the facilities, certain areas such as pipe chases and areas above fixed permanent ceilings, fire-door interiors, and vault/safe wall and door linings were not inspected or tested. Prior to renovation and alteration work which could impact these areas, Castle Hill recommends that exploratory demolition be performed and a qualified inspector be utilized to examine the areas and collect samples as needed. Castle Hill recommends sampling of roofing materials and electrical components (not specifically examined as part of this survey) if renovation activities are planned which may disturb these materials.
Respectfully Submitted:
Brett L. Brumbaugh, REPA, CESCO State of Minnesota Asbestos Inspector License Number 3303004018
TABLE 1
LIST OF ACRONYMS
ACBM Asbestos Containing Building Material ACM Asbestos Containing Material AHERA Asbestos Hazard Emergency Response Act AIHA American Industrial Hygiene Association CAA Clean Air Act CFR Code of Federal Regulations EPA United States Environmental Protection Agency HazCom Hazard Communication HEPA High Efficiency Particulate Air Filter HVAC Heating, Ventilation, and Air Conditioning MISC Miscellaneous Asbestos Containing Material NESHAP National Emission Standards for Hazardous Air Pollutants NIOSH National Institute for Occupational Safety and Health NIST National Institute of Standards and Technology NOB Non-friable Organically Bound NVLAP National Voluntary Laboratory Accreditation Program OSHA Occupational Safety and Health Administration PAT AIHA Proficiency Analytical Testing Program PCM Phase Contrast Microscopy PEL Permissible Exposure Limit PLM Polarized Light Microscopy TEM Transmission Electron Microscopy TSCA Toxic Substances Control Act TSI Thermal Systems Insulation Castle Hill Castle Hill Associates, LLC VA United States Department of Veterans Affairs VAMC VA Medical Center XRD X-Ray Diffraction
TABLE 2
ASBESTOS REMOVAL PRIORITY PROTOCOLS
AHERA CATEGORY RESPONSE ACTION RECOMMENDATION
Significantly Damaged Evacuate or isolate the area. Remove or repair if feasible. O&M for all friable ACM.
Damaged with potential for significant damage
Evacuate or isolate the area. Remove, encapsulate, or repair if feasible. O&M for all friable ACM.
Damaged with potential for damage Remove, encapsulate, or repair. O&M for all friable
ACM.
Damaged Remove, encapsulate, or repair. O&M for all friable
ACM.
Potential for significant damage Take steps to reduce potential for damage. O&M for all friable ACM.
Potential for damage O&M for all friable ACM.
No problem O&M for all friable ACM.
APPENDIX A
Asbestos Quantities, Assessments, & Remediation Cost Estimates
BLDG No Asbestos
Floor Tile and
Mastic
Floor Tile
Mastic
Only
Convector
Insulation or
Transite
Fire Doors Window
Glazing
Window
Caulk
Door
Caulk
Pipe
Insulation Contam. Soil Sink Undercoating Wall Adhesive
Rain Leader
Tar
Ceiling Tile
Adh.
Base
Cove
Adh.
Duct
Seam
Caulk
Vib.
Damp.
Cloth
Ceiling
Panels
Wall
Water‐ proof
Elev.
Brakes Roof Tar Lab Counter
Light
Liner
Transite
Panels
Electrical
Box Paper
Misc.
Exterior
Caulks
1 X X X X X X X
2 X X X X X X
3 X X X X X X X X
4 X X X X X X X X X X X X
5 X
6 X X X X X X
7 X X X
8 X X X X X X X
9 X X X X X
10 X X X
11 X X
13 X X
14 X X
28 X X X X X X
29 X X X X X X
30 X
32 X
37 X
48 X X X X X X X
49 X X X X X X X X X X X
50 X X X X X X X
51 X X X X X X X
54 X X X X
57 X
59 X X X X X
69 X
87 X
88 X X X X X
91 X
92 X X X
93 X
94 X
95 X
96 X X
97 X
99 X
100 X
103 X
104 X
105 X
106 X
107 X
108 X
109 X
110 X
Corridors X X X X X X
Tunnels X X
ST. CLOUD VA MEDICAL CENTER
BUILDING BY BUILDING ASBESTOS SUMMARY
EMarkfort
FUNCTIONAL HOMOG. MATL. HEIGHT AHERA REMOVAL DATE
FLOOR SPACE/ROOM MATERIAL MATERIAL TYPE QUANTITY (FEET) CONDITION CATEGORY COST ABATED
Bsmt Room 5C 1 Fittings TSI 1 Fitting 10 Good 7 $60
Bsmt Room 12A 34, 35 Floor Tile Misc 66 SF 0 Good NF $330
Entry and Mastic
Bsmt Room 16 62 Fire Door Misc 1 Door 0-8 Good NF $100
Bsmt Room 25 66 Pipe Insulation TSI 1 LF 9 Good 7 $20
Inside Wall
Bsmt Room 25 1 Fittings TSI 4 Fittings 10 Good 7 $240
Bsmt Room 26 62 Fire Door Misc 1 Door 0-8 Good NF $100
Stairs
Bsmt Room 27 1 Fittings TSI 2 Fittings 10 Good 7 $120
Bsmt Room 34 1 Fittings TSI 3 Fittings 10 Good 7 $180
Bsmt Room 35 1 Fittings TSI 50 Fittings 0-11 Good 7 $3,000
Bsmt Corridor 1 Fittings TSI 16 Fittings 9-11 Good 7 $960
C0C-N
Bsmt Unexcavated 66 Contaminated TSI 315 SF 0 Poor 1 $15,750
Crawlspace Soil
Bsmt Unexcavated 1 Fittings TSI 2 Fittings 3 Good 7 $120
Crawlspace
1 Room 101 66 Pipe Insulation TSI 20 LF 0-10 Good 7 $400
Inside Wall
1 Room 114 70 Mastic Misc 36 SF 0 Good NF $180
Stairs
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 1
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 1
1 Room 121 70 Mastic Misc 50 SF 0 Good NF $250
Stairs
1 Room 123 66 Pipe Insulation TSI 20 LF 0-10 Good 7 $400
Inside Wall
1 Room 127 1 Fittings TSI 5 Fittings 11 Good 7 $300
1 Room 127 2,3 9" Floor Tile Misc 55 SF 0 Good NF $275
And Mastic
1 Room 121 70 Mastic Misc 50 SF 0 Good NF $250
Stairs
1 Room 123 66 Pipe Insulation TSI 20 LF 0-10 Good 7 $400
Inside Wall
1 Room 127 1 Fittings TSI 5 Fittings 11 Good 7 $300
1 Room 127 2,3 9" Floor Tile Misc 55 SF 0 Good NF $275
And Mastic
1 Room 123 66 Pipe Insulation TSI 20 LF 0-10 Good 7 $400
Inside Wall
1 Room 127 1 Fittings TSI 5 Fittings 11 Good 7 $300
1 Room 127 2,3 9" Floor Tile Misc 55 SF 0 Good NF $275
And Mastic
1 Room 128 1 Fittings TSI 7 Fittings 11 Good 7 $420
1 Room 134 70 Mastic Misc 36 SF 0 Good NF $180
Stairs Under 9"x9"
1 Room 165 62 Fire Door Misc 1 Door 0-8 Good NF $100
Stairs
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 1
2 Room 202 66 Pipe Insulation TSI 40 LF 0-10 Good 7 $800
Inside Wall
2 Room 218 70 Mastic Misc 44 SF 0 Good NF $220
Stairs
2 Room 218 75,76 12"x12" Floor Misc 50 SF 0 Good NF $250
Stairs Tile and Mastic
2 Room 225 70 Mastic Misc 50 Sf 0 Good NF $250
Stairs
2 Room 230C 66 Pipe Insulation TSI 20 LF 0-10 Good 7 $400
Inside Wall
2 Room 237 62 Fire Door Misc 1 Door 0-8 Good NF $100
Stairs
2 Room 237 70 Mastic Misc 60 SF 0 Good NF $300
Stairs
2 Room 243B 62 Fire Door Misc 1 Door 0-8 Good NF $100
Stairs
2 Corridor 1, 66 Pipe Insulation TSI 18 LF 0-9 Good 7 $360
C2N Fittings 4 Fittings
3 Room 307 1 Fittings TSI 3 Fittings 2 Good 7 $180
Stairs
2 Corridor 1, 66 Pipe Insulation TSI 18 LF 0-9 Good 7 $360
C2N Fittings 4 Fittings
3 Room 307 1 Fittings TSI 3 Fittings 2 Good 7 $180
Stairs
3 Corridor 62 Fire Door Misc 2 Doors 0-8 Good NF $200
C3W
3 Room 306 62 Fire Door Misc 1 Door 0-8 Good NF $100
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 1
Ext Exterior 60 Black Tar Misc 9 Each 0-3 Good NF $900 on Rainleader
Ext Exterior 81 Caulk on Brick Misc 675 LF 0-3 Good NF $450
East Side Wall
TOTAL COST $30,835.00
LF = linear feet
SF = square feet AHERA Category
NF = non-friable 1 = damaged or significantly damaged thermal system insulation ACM
MATL. TYPE 2 = damaged friable surfacing ACM
TSI = thermal system insulation 3 = significantly damaged friable surfacing ACM
SURF = surfacing material 4 = damaged or significantly damaged friable miscellaneous ACM
MISC = miscellaneous 5 = ACBM with potential for damage
6 = ACBM with potential for significant damage
7 = any remaining friable ACBM or friable suspected ACBM
EMarkfort
BSMT Room 1 50 Wall Adhesive MISC 20 LF 9-10 Good NF $200 Above Ceiling
BSMT Corridor Assumed Fire Door MISC 2 Doors 0-7 Good NF $200 C0W
1 Room 106 25 Pipe Insulation TSI 40 LF 0-10 Good 5 $800 Behind Plaster 4 Fittings
1 Room 121 50 Wall Adhesive MISC 12 LF 9-10 Good NF $120 Above Ceiling
1 Room 143 25 Pipe Insulation TSI 40 LF 0-10 Good 5 $800 Behind Plaster 4 Fittings
1 Room 146 50 Wall Adhesive MISC 1 LF 9-10 Good NF $10 Above Ceiling
1 Corridor Assumed Fire Door MISC 8 Doors 0-7 Good NF $800 C1C
1 Exterior 46 Black Tar MISC 21 0-3 Good NF $420 On Rain Leader Each
2 Corridor Assumed Fire Door MISC 7 Doors 0-7 Good NF $700
Ext Exterior 51 Window Caulk MISC 229 0-20 Good NF $57,250 (old caulk) Windows
BSMT Crawlspaces 25 Contaminated MISC 9,800 SF 0 Poor 1 $490,000 Soil
TOTAL COST $551,300.00
LF = linear feet SF = square feet AHERA Category NF = non-friable 1 = damaged or significantly damaged thermal system insulation ACM MATL. TYPE 2 = damaged friable surfacing ACM TSI = thermal system insulation 3 = significantly damaged friable surfacing ACM SURF = surfacing material 4 = damaged or significantly damaged friable miscellaneous ACM MISC = miscellaneous 5 = ACBM with potential for damage
6 = ACBM with potential for significant damage
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 2
EMarkfort
1 Room 101 Assumed Insulation Inside MISC 48 SF 0-3 Good NF $2,000
Convector 4 Each
1 Room 101 53 Black Wall MISC 32 LF 10 Good NF $800
Adhesive
1 Room 105 Assumed Insulation Inside MISC 36 SF 0-3 Good NF $1,500
Convector 3 Each
1 Room 105 53 Black Wall MISC 12 LF 10 Good NF $300
Adhesive
1 Room 106 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
1 Room 107 Assumed Insulation Inside MISC 24 SF 0-3 Good NF $1,000
Convector 2 Each
1 Room 107 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
1 Room 110 53 Black Wall MISC 12 LF 10 Good NF $300
Adhesive
1 Vestibule 111 Assumed Insulation Inside MISC 12 SF 0-3 Good NF $500
Convector 1 Each
1 Room 112 53 Black Wall MISC 12 LF 10 Good NF $300
Adhesive
1 Room 120 Assumed Insulation Inside MISC 12 SF 0-3 Good NF $500
Convector 1 Each
1 Room 120 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
1 Room 121 16 Countertop MISC 130 SF 3 Good NF $700
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 3
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 3
Black
1 Room 121 12,13 12"x12" Floor Tile MISC 360 SF 0 Good NF $1,800 and Mastic
1 Room 121 Assumed Insulation Inside MISC 36 SF 0-3 Good NF $1,500
Convector 3 Each
1 Room 121 53 Black Wall MISC 28 LF 10 Good NF $700
Adhesive
1 Room 121A 16 Countertop MISC 20 SF 3 Good NF $200
Black
1 Room 121A 12,13 12"x12" Floor Tile MISC 64 SF 0 Good NF $320 and Mastic
1 Room 122 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
1 Corridor C1F Assumed Insulation Inside MISC 12 SF 0-3 Good NF $500
Convector 1 Each
1 Corridor C1A Assumed Insulation Inside MISC 12 SF 0-3 Good NF $500
Convector 1 Each
1 Corridor C1A 53 Black Wall MISC 4 LF 10 Good NF $100
1 Corridor C1A Assumed Fire Doors MISC 1 Door 0-7 Good NF $100
1 Corridor C1C Assumed Fire Doors MISC 1 Door 0-7 Good NF $100
1 Corridor C1E 53 Black Wall MISC 12 LF 10 Good NF $300
Adhesive
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 3
2 Room 205 1,2
Floor Tile &
Mastic MISC 336 SF 0 Good NF $1,680
Under Carpet
2 Room 205 53 Black Wall MISC 8 LF 10 Good NF $200
Adhesive
2 Room 205A 1,2
Floor Tile &
Mastic MISC 144 SF 0 Good NF $720
Under Carpet
2 Room 205A 53 Black Wall MISC 16 LF 10 Good NF $800
Adhesive
2 Room 205B 1,2
Floor Tile &
Mastic MISC 184 SF 0 Good NF $920
Under Carpet
2 Room 205B 53 Black Wall MISC 8 LF 10 Good NF $200
Adhesive
2 Stair 206 Assumed Insulation Inside MISC 12 SF 0-3 Good NF $500
Convector 1 Each
2 Corridor 207 1,2
Floor Tile &
Mastic MISC 192 SF 0 Good NF $960
Under Carpet
2 Corridor 207 53 Black Wall MISC 4 LF 0-3 Good NF $100
Adhesive
2 Room 207A 2 Mastic under MISC 120 SF 0 Good NF $600
Carpet
2 Room 207A 53 Black Wall MISC 44 LF 10 Good NF $1,800
Adhesive
2 Room 207B 2 Mastic under MISC 168 SF 0 Good NF $840
Carpet
2 Room 207B 53 Black Wall MISC 4 LF 10 Good NF $100
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 3
Adhesive
2 Room 207C 53 Black Wall MISC 36 LF 10 Good NF $1,500
Adhesive
2 Room 208 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
2 Room 209 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
2 Room 210 2 Mastic under MISC 130 SF 0 Good NF $650
Carpet
2 Room 210 53 Black Wall MISC 20 LF 10 Good NF $300
Adhesive
2 Room 211 2 Mastic under MISC 228 SF 0 Good NF $1,140
Carpet
2 Room 211 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
2 Room 211A 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
2 Room 212 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
2 Room 213 1,2
Floor Tile &
Mastic MISC 88 SF 0 Good NF $440
Under Carpet
2 Room 213 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
2 Room 213A 1,2
Floor Tile &
Mastic MISC 400 SF 0 Good NF $2,000
Under Carpet
2 Room 213A 53 Black Wall MISC 36 LF 10 Good NF $1,500
Adhesive
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 3
2 Room 213B 1,2
Floor Tile &
Mastic MISC 100 SF 0 Good NF $500
Under Carpet
2 Room 213B 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
2 Room 213C 1,2
Floor Tile &
Mastic MISC 100 SF 0 Good NF $500
Under Carpet
2 Room 213C 42 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
2 Alcove 214 Assumed Insulation Inside MISC 12 SF 0-3 Good NF $500
Convector 1 Each
2 Room 215 53 Black Wall MISC 8 LF 10 Good NF $200
Adhesive
2 Room 215A 53 Black Wall MISC 4 LF 10 Good NF $100
Adhesive
2 Room 215B 53 Black Wall MISC 8 LF 10 Good NF $200
Adhesive
2 Corridor C2C 1,2
Floor Tile &
Mastic MISC 710 SF 0 Good NF $3,550
Under Carpet
2 Corridor C2C Assumed Fire Door MISC 2 Doors 0-7 Good NF $200
Exterior Exterior 50 Window Caulk MISC 78 0-25 Good NF $19,500
Windows Window
TOTAL COST $57,420.00
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 3
LF = linear feet
SF = square feet AHERA Category
NF = non-friable 1 = damaged or significantly damaged thermal system insulation ACM
MATL. TYPE 2 = damaged friable surfacing ACM
TSI = thermal system insulation 3 = significantly damaged friable surfacing ACM
SURF = surfacing material 4 = damaged or significantly damaged friable miscellaneous ACM
MISC = miscellaneous 5 = ACBM with potential for damage
6 = ACBM with potential for significant damage
7 = any remaining friable ACBM or friable suspected ACBM
EMarkfort
BSMT Room 8 3,4 Floor Tile MISC 340 SF 0 Good NF $1,700 and Mastic
BSMT Room 9 3,4 Floor Tile MISC 160 SF 0 Good NF $800 and Mastic
BSMT Room 10 3,4 Floor Tile MISC 185 SF 0 Good NF $925 and Mastic
BSMT Room 11 3,4 Floor Tile MISC 27 SF 0 Good NF $135 and Mastic
BSMT Room 12 3,4 Floor Tile MISC 440 SF 0 Good NF $2,200 and Mastic
BSMT Room 12A 3,4 Floor Tile MISC 115 SF 0 Good NF $575 and Mastic
BSMT Room 13 3,4 Floor Tile MISC 300 SF 0 Good NF $1,500 and Mastic
BSMT Room 14 3,4 Floor Tile MISC 48 SF 0 Good NF $240 and Mastic
BSMT Room 15 61 Fire Door MISC 1 Door 0-7 Good NF $100
Stairs
BSMT Room 16 3,4 Floor Tile MISC 192 SF 0 Good NF $960 and Mastic
BSMT Room 21 5,6 Floor Tile MISC 150 SF 0 Good NF $750 and Mastic
BSMT Room 21A 1,2 Floor Tile MISC 452 SF 0 Good NF $2,260 and Mastic
BSMT Room 21C 5,6 Floor Tile MISC 95 SF 0 Good NF $475 and Mastic
BSMT Room 22 61 Fire Door MISC 1 Door 0-7 Good NF $100
Stairs
BSMT Corridor C0N 1,2 Floor Tile MISC 940 SF 0 Good NF $4,700 and Mastic
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 4
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 4
1 Room 102 17,18 Floor Tile MISC 150 SF 0 Good NF $750 and Mastic
1 Room 106 17,18 Floor Tile MISC 112 SF 0 Good NF $560 and Mastic
1 Room 109 17,18 Floor Tile MISC 50 SF 0 Good NF $250 and Mastic
1 Room 112A 1,2 Floor Tile MISC 18 SF 0 Good NF $90 and Mastic
1 Room 112B 1,2 Floor Tile MISC 28 SF 0 Good NF $140 and Mastic
1 Room 114B 6 Mastic MISC 710 SF 0 Good NF $3,550
Under Carpet
1 Room 114B 45 Mastic MISC 660 SF 11-May Good NF $3,300
On Walls
1 Room 114B 48 Pipe Insulation TSI 20 LF 0-10 Good 5 $400
Behind Plaster
1 Room 115 64 Mastic MISC 72 SF 0 Good NF $360
Under 12" Tile
1 Room 116 48 Pipe Insulation TSI 30 LF 0-10 Good 5 $600
(behind plaster) Assumed
1 Room 116 48 Pipe Insulation TSI 13 LF 0 Good 5 $260
(horizontal runs) 2 Ftgs
1 Room 120A 3,4 Floor Tile MISC 134 SF 0 Good NF $670 and Mastic
1 Room 120C 3,4 Floor Tile MISC 130 SF 0 Good NF $650 and Mastic
1 Room 120D 3,4 Floor Tile MISC 130 SF 0 Good NF $650 and Mastic
1 Room 120E 3,4 Floor Tile MISC 130 SF 0 Good NF $650 and Mastic
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 4
1 Room 120F 3,4 Floor Tile MISC 130 SF 0 Good NF $650 and Mastic
1 Room 120G 3,4 Floor Tile MISC 130 SF 0 Good NF $650 and Mastic
1 Room 120H 3,4 Floor Tile MISC 67 SF 0 Good NF $335 and Mastic
1 Room 120I 5,6 Floor Tile MISC 460 SF 0 Good NF $2,300 and Mastic
1 Room 120J 5,6 Floor Tile MISC 130 SF 0 Good NF $650 and Mastic
1 Room 120K 5,6 Floor Tile MISC 130 SF 0 Good NF $650 and Mastic
1 Room 120L 5,6 Floor Tile MISC 130 SF 0 Good NF $650 and Mastic
1 Room 120M 5,6 Floor Tile MISC 23 SF 0 Good NF $115 and Mastic
1 Room 121A 48 Pipe Insulation TSI 10 LF 0-10 Good 5 $200
(behind plaster) Assumed
1 Room 123A 61 Fire Door MISC 1 Door 0-7 Good NF $100
1 Room 124 11,12 Floor Tile MISC 375 SF 0 Good NF $1,875 and Mastic
1 Room 124 48 Pipe Insulation TSI 10 LF 0-10 Good 5 $200
(behind plaster) Assumed
1 Room 124A 11,12 Floor Tile MISC 18 SF 0 Good NF $90 and Mastic
1 Room 125 11,12 Floor Tile MISC 46 SF 0 Good NF $230 and Mastic
1 Room 126 48 Pipe Insulation TSI 10 LF 0-10 Good 5 $200
(behind plaster)
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 4
1 Room 126A 11,12 Floor Tile MISC 124 SF 0 Good NF $620 and Mastic
1 Room 126A 48 Pipe Insulation TSI 20 LF 0-10 Good 5 $400
(behind plaster) Assumed
1 Room 129 48 Pipe Insulation TSI 140 LF 0-10 Good 5 $2,800
(behind plaster) Assumed
1 Corridor 120 5,6 Floor Tile MISC 445 SF 0 Good NF $2,225 and Mastic
1 Corridor C1E 1,2 Floor Tile MISC 210 SF 0 Good NF $1,050 and Mastic
1 Cooridor C1E 61 Fire Door MISC 1 Door 0-7 Good NF $100
2 Room 200 61 Fire Door MISC 1 Door 0-7 Good NF $100
Stairs
2 Room 201 22 Mastic MISC 190 SF 0 Good NF $950
Under Carpet
2 Room 202 22 Mastic MISC 190 SF 0 Good NF $950
Under Carpet
2 Room 203 22 Mastic MISC 160 SF 0 Good NF $800
Under Carpet
2 Room 203 21,22 Floor Tile MISC 28 SF 0 Good NF $140
Closets and Mastic
2 Room 204 22 Mastic MISC 165 SF 0 Good NF $825
Under Carpet
2 Room 204 21,22 Floor Tile MISC 14 SF 0 Good NF $70
Closet and Mastic
2 Room 205 22 Mastic MISC 350 SF 0 Good NF $1,750
Under Carpet
2 Room 205 21,22 Floor Tile MISC 28 SF 0 Good NF $140
Closet and Mastic
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 4
2 Room 206 22 Mastic MISC 190 SF 0 Good NF $950
Under Carpet
2 Room 208 22 Mastic MISC 190 SF 0 Good NF $950
Under Carpet
2 Room 209 22 Mastic MISC 160 SF 0 Good NF $800
Under Carpet
2 Room 209 21,22 Floor Tile MISC 28 SF 0 Good NF $140
Closet and Mastic
2 Room 210 22 Mastic MISC 175 SF 0 Good NF $875
Under Carpet
2 Room 210 21,22 Floor Tile MISC 28 SF 0 Good NF $140
Closet and Mastic
2 Room 212 22 Mastic MISC 160 SF 0 Good NF $800
Under Carpet
2 Room 212 21,22 Floor Tile MISC 28 SF 0 Good NF $140
Closet and Mastic
2 Room 212A 26 Mastic MISC 13 SF 0 Good NF $65 under 12" Tile
2 Room 214 21,22 Floor Tile MISC 190 SF 0 Good NF $950 and Mastic
2 Room 215 22 Mastic MISC 175 SF 0 Good NF $800
Under Carpet
2 Room 215 21,22 Floor Tile MISC 14 SF 0 Good NF $140
Closet and Mastic
2 Room 216 22 Mastic MISC 175 SF 0 Good NF $800
Under Carpet
2 Room 217 22 Mastic MISC 180 SF 0 Good NF $900
Under Carpet
2 Room 218 21,22 Floor Tile MISC 165 SF 0 Good NF $825 and Mastic
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 4
2 Room 218 21,22 Floor Tile MISC 14 SF 0 Good NF $70
Closet and Mastic
2 Room 219 22 Mastic MISC 190 SF 0 Good NF $950
Under Carpet
2 Room 220 21,22 Floor Tile MISC 290 SF 0 Good NF $1,450 and Mastic
2 Room 221 22 Mastic MISC 190 SF 0 Good NF $950
Under Carpet
2 Room 222 21,22 Floor Tile MISC 348 SF 0 Good NF $1,740
West Half and Mastic
2 Room 222 22 Mastic MISC 256 SF 0 Good NF $1,280
East Half Under Carpet
2 Room 222 21,22 Floor Tile MISC 16 SF 0 Good NF $80
Closet and Mastic
2 Room 223 22 Mastic MISC 170 SF 0 Good NF $850
Under 12" Tile
2 Room 223A 26 Mastic MISC 32 SF 0 Good NF $160
Under 12" Tile
2 Room 223B 22 Mastic MISC 295 SF 0 Good NF $1,475
Under Carpet
2 Room 225 22 Mastic MISC 410 SF 0 Good NF $2,050
Under Carpet
2 Room 228 26 Mastic MISC 32 SF 0 Good NF $160
Under 12" Tile
2 Room 229 22 Mastic MISC 190 SF 0 Good NF $950
Under Carpet
2 Room 230 22 Mastic MISC 190 SF 0 Good NF $950
Under Carpet
2 Room 231 22 Mastic MISC 175 SF 0 Good NF $875
Under Carpet
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 4
2 Room 231 21,22 Floor Tile MISC 14 SF 0 Good NF $70
Closet and Mastic
2 Room 232 22 Mastic MISC 175 SF 0 Good NF $875
Under Carpet
2 Room 232 21,22 Floor Tile MISC 14 SF 0 Good NF $70
Closet and Mastic
2 Room 233 22 Mastic MISC 170 SF 0 Good NF $850
Under Carpet
2 Room 233 21,22 Floor Tile MISC 14 SF 0 Good NF $70
Closet and Mastic
2 Room 234 22 Mastic MISC 210 SF 0 Good NF $1,050
Under 12" Tile
2 Room 234 21,22 Floor Tile MISC 5 SF 0 Good NF $25
Closet and Mastic
2 Room 251 61 Fire Door MISC 1 Door 0-7 Good NF $100
Stairs
2 Corridor 22 Mastic MISC 1,735 SF 0 Good NF $8,675
C2C Under Carpet
EXT Exterior 57 Black Tar MISC 3 Each 0 Good NF $300
On Rain Leader
EXT Exterior 58 Window MISC 199 4 Good NF $49,750
Caulk Windows
EXT Exterior 71,74,76 Window MISC 203 4 Good NF $20,300
Glazing Windows
EXT Exterior 57 Black Tar MISC 3 Each 0 Good NF $300
On Rain Leader
EXT Exterior 58 Window MISC 205 4 Good NF $51,250
Caulk Windows
EXT Exterior 71,74,76 Window MISC 205 4 Good NF $20,500
Glazing Windows
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 4
BSMT Crawlspaces 48 Contaminated TSI 6,551 SF 0 Good NF $327,000
Soil
BSMT Basement 72 Black Adhesive MISC 6 7-8 Good NF $1,200
North Side Above Windows Windows
1 First Floor 72 Black Adhesive MISC 17 7-8 Good NF $3,400
Select Areas Above Windows Windows
TOTAL COST $561,165
LF = linear feet
SF = square feet AHERA Category
NF = non-friable 1 = damaged or significantly damaged thermal system insulation ACM
MATL. TYPE 2 = damaged friable surfacing ACM
TSI = thermal system insulation 3 = significantly damaged friable surfacing ACM
SURF = surfacing material 4 = damaged or significantly damaged friable miscellaneous ACM
MISC = miscellaneous 5 = ACBM with potential for damage
6 = ACBM with potential for significant damage
7 = any remaining friable ACBM or friable suspected ACBM
EMarkfort
1 Exterior 8 Window Caulk MISC 16 0-8 Good NF $4,800
Windows
1 Exterior 8 Door caulk MISC 1 door 0-6 Good NF $300
1 Room 101 14 LPS Pipe TSI 4 8 Poor 1 $400
Fittings
1 Room 102 14 LPS Pipe TSI 16 8 Good 5 $1,500
Fittings
1 Electrical 105 17 Sink MISC 1 Sink 3 Poor NF $200
Undercoating
1 Carpetner 104 18 Sink MISC 1 Sink 3 Good NF $200
Undercoating
1 Exterior 24 Window Glazing MISC 2 0-8 Poor NF $500
East Side Windows
1 Exterior 25 Roof Overhang MISC 6 Feet 8 Good NF $120
West Side Tar
TOTAL COST $8,020
SF = square feet
NF = non-friable
AHERA Category
MATL. TYPE 1 = damaged or significantly damaged thermal system insulation ACM
TSI = thermal system insulation 2 = damaged friable surfacing ACM
SURF = surfacing material 3 = significantly damaged friable surfacing ACM
MISC = miscellaneous 4 = damaged or significantly damaged friable miscellaneous ACM
5 = ACBM with potential for damage
6 = ACBM with potential for significant damage
7 = any remaining friable ACBM or friable suspected ACBM Page 1 of 1
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 6
EMarkfort
1 Room 100 37 Sink MISC 1 sink 3 Good NF $100
Undercoating
1 Room 102 12 Pipe TSI 4 LF 8 Good 5 $200
Insulation
1 Room 105 12 Pipe Insulation TSI 2 SF 0-8 Good 1 $250
Debris West Side
1 Room 105 34 Pipe TSI 30 LF 0 Good 5 $1,500
Insulation/Tar
1 Room 109 40 Pipe Insulation TSI 20 LF 0 Good 5 $2,000
1 Exterior 11 Window Glazing MISC 12 0-20 Good NF $3,000 windows
TOTAL COST $7,050
LF = linear feet
SF = square feet AHERA Category
NF = non-friable 1 = damaged or significantly damaged thermal system insulation ACM
MATL. TYPE 2 = damaged friable surfacing ACM
TSI = thermal system insulation 3 = significantly damaged friable surfacing ACM
SURF = surfacing material 4 = damaged or significantly damaged friable miscellaneous ACM
MISC = miscellaneous 5 = ACBM with potential for damage
6 = ACBM with potential for significant damage
7 = any remaining friable ACBM or friable suspected ACBM
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 7
EMarkfort
BSMT Room 2 11 9"x9" Floor Tile MISC 360 SF 0 Good NF $1,800 and Mastic
BSMT Room 2 Assumed Fire Door MISC 1 door 0-6 Good NF $100
BSMT Corridor 3 Assumed Fire Door MISC 2 doors 0-6 Good NF $200
BSMT Room 12 4 Floor Tile Mastic MISC 2,465 SF 0 Good NF $12,325
BSMT Room 12A 4 Floor Tile Mastic MISC 15 SF 0 Good NF $75
BSMT Room 14 Assumed Fire Door MISC 1 door 0-6 Good NF $100
1 Corridor 100 32 Pipe Insulation TSI 2 LF 10 Good 5 $100
Aircell
1 Corridor 100 Assumed Fire Door MISC 1 door 0-6 Good NF $100
Lobby
1 Corridor 102 4 Floor Tile Mastic MISC 605 SF 0 Good NF $3,025
1 Corridor 102 Assumed Fire Door MISC 5 doors 0-6 Good NF $500
1 Corridor 105 4 Mastic Under MISC 130 SF 0 Good NF $650
Carpet
1 Room 106 4 Mastic Under MISC 177 SF 0 Good NF $885
Carpet
1 Room 106 42 Black Wall MISC 10 SF 10 Good NF $200
Adhesive
1 Room 107 4 Mastic Under MISC 110 SF 0 Good NF $550
Carpet
1 Room 107 42 Black Wall MISC 5 SF 10 Good NF $100
Adhesive
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 8
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 8
1 Room 108 4 Mastic Under MISC 300 SF 0 Good NF $1,500
Carpet
1 Room 108 42 Black Wall MISC 15 SF 10 Good NF $300
Adhesive
1 Room 108A 4 Mastic Under MISC 100 SF 0 Good NF $500
Carpet
1 Room 108A 42 Black Wall MISC 10 SF 10 Good NF $200
Adhesive
1 Room 109 4 Mastic Under MISC 430 SF 0 Good NF $2,150
Carpet
1 Room 109 42 Black Wall MISC 20 SF 10 Good NF $400
Adhesive
1 Room 112 16 12"x12" Floor Tile MISC 1,810 SF 0 Good NF $5,430 and Mastic
1 Room 112 Assumed Fire Door MISC 2 doors 0-6 Good NF $200
1 Room 115 11 9"x9" Floor Tile MISC 182 SF 0 Good NF $910 and Mastic
1 Room 116 4 Floor Tile Mastic MISC 96 SF 0 Good NF $480
EXT Exterior 39,67 Window Caulk MISC 40 0-40 Good NF $12,000 wiindows
EXT Exterior 58,66 Window Glazing MISC 63 0-6 Good NF $6,300 windows
TOTAL COST $51,080
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 8
LF = linear feet
SF = square feet AHERA Category
NF = non-friable 1 = damaged or significantly damaged thermal system insulation ACM
MATL. TYPE 2 = damaged friable surfacing ACM
TSI = thermal system insulation 3 = significantly damaged friable surfacing ACM
SURF = surfacing material 4 = damaged or significantly damaged friable miscellaneous ACM
MISC = miscellaneous 5 = ACBM with potential for damage
6 = ACBM with potential for significant damage
7 = any remaining friable ACBM or friable suspected ACBM
EMarkfort
BSMT ROOM 4 4 MASTIC MISC 140 SF 0 Good NF $700
OFFICE
BSMT ROOM 6 4 MASTIC MISC 140 SF 0 Good NF $700
CLEAN LINEN
BSMT ROOM 8 4 MASTIC MISC 140 SF 0 Good NF $700
BSMT ROOM 8 18 ADHESIVE MISC 3 LF 0 Good NF $30
BSMT ROOM 9 4 MASTIC MISC 140 SF 0 Good NF $700
BSMT ROOM 9 18 ADHESIVE MISC 3 LF 0 Good NF $30
BSMT ROOM 10 4 MASTIC MISC 140 SF 0 Good NF $700
BSMT ROOM 11 4 MASTIC MISC 140 SF 0 Good NF $700
BSMT ROOM 11 18 ADHESIVE MISC 3 LF 0 Good NF $30
BSMT ROOM 13 4 MASTIC MISC 280 SF 0 Good NF $1,400
BSMT ROOM 13 18 ADHESIVE MISC 25 LF 0 Good NF $250
BSMT ROOM 13A 4 MASTIC MISC 112 SF 0 Good NF $560
BSMT ROOM 13A 18 ADHESIVE MISC 44 LF 0 Good NF $440
BSMT ROOM 13B 4 MASTIC MISC 140 SF 0 Good NF $700
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 9
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 9
BSMT ROOM 13C 4 MASTIC MISC 140 SF 0 Good NF $700
BSMT ROOM 15 34 MUDDED TSI 6 EACH 8 3-Good, 7 $570
FITTINGS 1-Fair, 1-Poor 1,1
BSMT CORRIDOR C0C 4 MASTIC MISC 684 SF 0 Good NF $3,420
BSMT CORRIDOR C0C 32 FIREDOOR MISC 1 DOOR 0-7 Good NF $100
CORE
BSMT CORRIDOR C0C 18 ADHESIVE MISC 140 LF 0 Good NF $1,400
1 ROOM 100 4 MASTIC MISC 300 SF 0 Good NF $1,500
LOBBY
1 ROOM 100 18 ADHESIVE MISC 55 LF 0 Good NF $550
LOBBY
1 ROOM 100A 4 MASTIC MISC 62 SF 0 Good NF $310
1 ROOM 101 18 ADHESIVE MISC 3 LF 0 Good NF $30
LOUNGE
1 ROOM 100B 4 MASTIC MISC 15 SF 0 Not Checked NF $75
CLOSET
1 ROOM 104 4 MASTIC MISC 140 SF 0 Not Checked NF $700
1 ROOM 104 18 ADHESIVE MISC 3 LF 0 Not Checked NF $30
1 ROOM 105 34 MUDDED TSI 3 EACH 10 2-Good 7, 1 $285
FITTINGS 1-Fair
1 ROOM 105 4 MASTIC MISC 140 SF 0 Good NF $700
EMarkfort
ASBESTOS MATERIALS RE-ASSESSMENT 2019
BUILDING 9
1 ROOM 105 18 ADHESIVE MISC 3 LF 0 Good NF $30
1 ROOM 106 4 MASTIC MISC 140 SF 0 Good NF $700
1 ROOM 106 18 ADHESIVE MISC 3 LF 0 Good NF $30
1 ROOM 106 34 MUDDED TSI 3 EACH 10 Good 7 $285
FITTINGS
1 ROOM 109 4 MASTIC MISC 140 SF 0 Good NF $700
1 ROOM 109 18 ADHESIVE MISC 3 LF 0 Good NF $30
1 ROOM 110 4 MASTIC MISC 140 SF 0 Good NF $700
UNDER STAIRS
1 ROOM 111 4 MASTIC MISC 140 SF 0 Good NF $700
1 ROOM 111 18 ADHESIVE MISC 3 LF 0 Good NF $30
1 ROOM…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .