Amendment_3_260573-OvercurentProtectiveDeviceCoordinationStudy.docx

DOCX document 35 KB Posted

Attached to
Construction of Cascade Lakes National Scenic Byway Welcome Station
Solicitation number
AG-04GG-S-14-0002
Issued by

About this file

Amendment 3 - Overcurrent protective device

View the file

Other files

File Type Posted
Amendment_5_Septic_Site_Eval_F-24008.pdf PDF
Amendment_5_narrative.docx DOCX document
Amendment_5_SF-30.doc DOC document
Amendment_4_Well_Location.pdf PDF
Amendment_4_DetailScheduleItems.xlsx XLSX spreadsheet
Amendment_4_SF-30.doc DOC document
Amendment_4_8-20.docx DOCX document
Amendment_3_260902-SubmersibleLevelTransmitter-20110512.doc DOC document
Amendment_3_Interior_Finishes_Schedule.pdf PDF
Amendment_3_specs_for_hydroseeding_and_soil_prep.docx DOCX document
Amendment_3_Addendum.docx DOCX document
Amendment_3_DeschutesDoubleGateLayout2014.pdf PDF
Amendment_3_260900-ControlsAnd_instrumentation-20140806.doc DOC document
Amendment_3_DetailScheduleItems.xlsx XLSX spreadsheet
Amendment_3_Bid_Bond_Form_SF_24.pdf PDF
Amendment_3_SF-30.doc DOC document
Amendment_2_DetailScheduleItems.xlsx XLSX spreadsheet
Amendment_2_EFS_1.pdf PDF
Amendment_2_7th_Mountain_Pit.pdf PDF
Amendment_2_USFS_CLWS_IFS-1.pdf PDF
Amendment_2_8-4.docx DOCX document
3.Welcome_St_All_Dwgs_in_Order.pdf PDF
5.Technical_Evaluation_Questionnaire.docx DOCX document
6.Fire_Clauses.pdf PDF
7.Welcome_Station_Wage_Rates_OR25_dvb.mht MHT file
4.Welcome_Station_Bidders_Packet2.docx DOCX document
2.WelcomeStAllSpecs0718.pdf PDF
1.Welcome_Station_RFP.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Forest Service Project Specifications

SECTION 26 05 73

OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

PART 1 - GENERAL

RELATED DOCUMENTS

Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

SUMMARY

This Section includes computer-based, fault-current and overcurrent protective device coordination studies. Protective devices shall be set based on results of the protective device coordination study.

ACTION SUBMITTALS

Product Data: For computer software program to be used for studies.

Other Action Submittals: The following submittals shall be made after the approval process for system protective devices has been completed. Submittals shall be in PDF digital form.

Coordination-study input data, including completed computer program input data sheets.

Study and Equipment Evaluation Reports.

Coordination-Study Report.

Setting report Arc flash report

INFORMATIONAL SUBMITTALS

Qualification Data: For coordination-study specialist.

Product Certificates: For coordination-study and fault-current-study computer software programs, certifying compliance with IEEE 399.

Informational submittals will not be approved until the coordination study is completed and the submittals indicate the study recommendations.

QUALITY ASSURANCE

Studies shall use computer programs that are distributed nationally and are in wide use. Software algorithms shall comply with requirements of standards and guides specified in this Section. Manual calculations are not acceptable.

Coordination-Study Specialist Qualifications: An entity experienced in the application of computer software used for studies, having performed successful studies of similar magnitude on electrical distribution systems using similar devices.

Professional engineer, licensed in the state where Project is located, shall be responsible for the study. All elements of the study shall be performed under the direct supervision and control of engineer.

Comply with IEEE 242 for short-circuit currents and coordination time intervals.

Comply with IEEE 1584-2002 for arc flash calculations.

Comply with IEEE 399 for general study procedures.

PART 2 - PRODUCTS

COMPUTER SOFTWARE DEVELOPERS

Computer Software Developers: Subject to compliance with requirements, provide products by one of the following:

EDSA Micro Corporation.

ESA Inc.

SKM Systems Analysis, Inc.

COMPUTER SOFTWARE PROGRAM REQUIREMENTS

Comply with IEEE 399 and IEEE 1584-2002.

Analytical features of fault-current-study computer software program shall include "mandatory," "very desirable," and "desirable" features as listed in IEEE 399.

Computer software program shall be capable of plotting and diagramming time-current- characteristic curves as part of its output. Computer software program shall report device settings and ratings of all overcurrent protective devices and shall demonstrate selective coordination by computer-generated, time-current coordination plots.

Optional Features:

Arcing faults.

Simultaneous faults.

Explicit negative sequence.

Mutual coupling in zero sequence.

Arc flash calculations: Software program shall be capable of calculating Arc Flash Incident Energy (AEIE) levels and flash protection boundary distances.

PART 3 - EXECUTION

EXAMINATION

Examine Project overcurrent protective device submittals for compliance with electrical distribution system coordination requirements and other conditions affecting performance. Devices to be coordinated are indicated on Drawings.

Proceed with coordination study only after relevant equipment submittals have been assembled. Overcurrent protective devices that have not been submitted and approved prior to coordination study may not be used in study.

Provide the study based on the actual electrical equipment supplied for the project.

POWER SYSTEM DATA

Gather and tabulate the following input data to support coordination study:

Product Data for overcurrent protective devices specified in other electrical Sections and involved in overcurrent protective device coordination studies. Use equipment designation tags that are consistent with electrical distribution system diagrams, overcurrent protective device submittals, input and output data, and recommended device settings.

Impedance of utility service entrance.

Electrical Distribution System Diagram: In hard-copy and electronic-copy formats, showing the following:

Circuit-breaker and fuse-current ratings and types.

Relays and associated power and current transformer ratings and ratios.

Transformer kilovolt amperes, primary and secondary voltages, connection type, impedance, and X/R ratios.

Generator kilovolt amperes, size, voltage, and source impedance.

Cables: Indicate conduit material, sizes of conductors, conductor material, insulation, and length.

Motor horsepower and code letter designation according to NEMA MG 1.

Data sheets to supplement electrical distribution system diagram, cross-referenced with tag numbers on diagram, showing the following:

Special load considerations, including starting inrush currents and frequent starting and stopping.

Transformer characteristics, including primary protective device, magnetic inrush current, and overload capability.

Motor full-load current, locked rotor current, service factor, starting time, type of start, and thermal-damage curve.

Generator thermal-damage curve.

Ratings, types, and settings of utility company's overcurrent protective devices.

Special overcurrent protective device settings or types stipulated by utility company.

Time-current-characteristic curves of devices indicated to be coordinated.

Manufacturer, frame size, interrupting rating in amperes rms symmetrical, ampere or current sensor rating, long-time adjustment range, short-time adjustment range, and instantaneous adjustment range for circuit breakers.

Manufacturer and type, ampere-tap adjustment range, time-delay adjustment range, instantaneous attachment adjustment range, and current transformer ratio for overcurrent relays.

Panelboards, switchboards, and interrupting rating in amperes rms symmetrical.

FAULT-CURRENT STUDY

Calculate the maximum available short-circuit current in amperes rms symmetrical at circuit- breaker positions of the electrical power distribution system. The calculation shall be for a current immediately after initiation and for a three-phase bolted short circuit at each of the following:

Switchboard bus.

Distribution panelboard.

Branch circuit panelboard.

Study electrical distribution system from normal and alternate power sources throughout electrical distribution system for Project. Include studies of system-switching configurations and alternate operations that could result in maximum fault conditions.

Calculate momentary and interrupting duties on the basis of maximum available fault current.

Calculations to verify interrupting ratings of overcurrent protective devices shall comply with IEEE 241 and IEEE 242.

Transformers:

ANSI C57.12.22.

IEEE C57.96.

Low-Voltage Circuit Breakers: IEEE 1015 and IEEE C37.20.1.

Low-Voltage Fuses: IEEE C37.46.

Study Report:

Show calculated X/R ratios and equipment interrupting rating (1/2-cycle) fault currents on electrical distribution system diagram.

Equipment Evaluation Report:

For 600-V overcurrent protective devices, ensure that interrupting ratings are equal to or higher than calculated 1/2-cycle symmetrical fault current.

For devices and equipment rated for asymmetrical fault current, apply multiplication factors listed in the standards to 1/2-cycle symmetrical fault current.

Verify adequacy of phase conductors at maximum three-phase bolted fault currents; verify adequacy of equipment grounding conductors and grounding electrode conductors at maximum ground-fault currents. Ensure that short-circuit withstand ratings are equal to or higher than calculated 1/2-cycle symmetrical fault current.

COORDINATION STUDY

Perform coordination study using approved computer software program. Prepare a written report using results of fault-current study. Comply with IEEE 399.

Calculate the maximum and minimum 1/2-cycle short-circuit currents.

Calculate the maximum and minimum ground-fault currents.

Comply with IEEE 241 and IEEE 242 recommendations for fault currents and time intervals.

Transformer Primary Overcurrent Protective Devices:

Device shall not operate in response to the following:

Inrush current when first energized.

Permissible transformer overloads according to IEEE C57.96 if required by unusual loading or emergency conditions.

Conductor Protection: Protect cables against damage from fault currents according to ICEA P- 32-382, ICEA P-45-482, and conductor melting curves in IEEE 242. Demonstrate that equipment withstands the maximum short-circuit current for a time equivalent to the tripping time of the primary relay protection or total clearing time of the fuse. To determine temperatures that damage insulation, use curves from cable manufacturers or from listed standards indicating conductor size and short-circuit current.

Coordination-Study Report: Prepare a written report indicating the following results of coordination study:

Tabular Format of Settings Selected for Overcurrent Protective Devices:

Device tag.

Relay-current transformer ratios; and tap, time-dial, and instantaneous-pickup values.

Circuit-breaker sensor rating; and long-time, short-time, and instantaneous settings.

Fuse-current rating and type.

Ground-fault relay-pickup and time-delay settings.

Coordination Curves: Prepared to determine settings of overcurrent protective devices to optimize selective coordination. Graphically illustrate that adequate time separation exists between devices installed in series, including power utility company's upstream devices. Prepare separate sets of curves for the switching schemes and for emergency periods where the power source is local generation. Show the following information:

Device tag.

Voltage and current ratio for curves.

Three-phase and single-phase damage points for each transformer.

No damage, melting, and clearing curves for fuses.

Cable damage curves.

Transformer inrush points.

Maximum fault-current cutoff point.

Completed data sheets for setting of overcurrent protective devices.

OVERCURRENT PROTECTIVE DEVICE SETTING

Manufacturer's Field Service: Engage a factory-authorized service representative, of electrical distribution equipment being set and adjusted, to set overcurrent protective devices within equipment.

Testing: Perform the following device setting and prepare reports:

After installing overcurrent protective devices and during energizing process of electrical distribution system, perform the following:

Verify that overcurrent protective devices meet parameters used in studies.

Adjust devices to values listed in study results.

Adjust devices according to recommendations in Chapter 7, "Inspection and Test Procedures," and Tables 10.7 and 10.8 in NETA ATS.

ARC FLASH STUDY

Study shall model worst-case arc flash conditions, and the final report shall describe, when applicable, how these conditions differ from worst case bolted fault conditions.

Provide study results in tabular form, and include:

Device or bus name Bolted fault and arcing fault currents levels Arc Flash Incident Energy Level (AFIE) at 18 inches expressed in cal/cm2 Flash protection boundary distances including Limited shock approach boundary Restricted shock approach boundary Prohibited shock approach boundary Personal-protective equipment class (PPE).

Provide engraved plastic nameplates with arc flash labels on all electrical distribution equipment that includes the information from subparagraph B above.

END OF SECTION 26 05 73