This document is Solicitation Addendum #004 for the CMPS Structural Upgrades project (Solicitation S-10700-00013306), issued by the Department of Administrative Services (DAS) in Oregon. The addendum modifies the original bid document's schedule, specifically extending the deadline for solicitation protests, requests for clarification, and questions to April 30, 2025 at 2:00 PM, and setting the Bid Submittal Deadline for May 6, 2025 at 2:00 PM. The public opening will occur immediately after the bid opening, and any award protests must be submitted within 7 calendar days after the Notice of Intent to Award is issued.

The addendum does not constitute a material change to the bid and requires bidders to acknowledge its receipt by inserting the addendum number on the appropriate lines in Attachment A-1 of the bid document. All times referenced are in Pacific Standard Time (PST), and the dates listed are subject to change. The solicitation maintains the previously established mandatory pre-bid conference details, with specific reference to ITB Section A.10 for conference information. Bidders are advised that failure to acknowledge the addendum may result in bid rejection, and all requests for clarification or protests must be received by the specified deadline to be considered.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID

S-10700-00013306

SOLICITATION ADDENDUM #004

CMPS Structural Upgrades, S-10700-00013306 ADDENDUM # 4 Page 1 of 1

This Solicitation Addendum modifies the Bid Document(s) for Work only to the extent indicated herein. All other areas not specifically mentioned or affected by this Solicitation Addendum shall remain in full force. This Solicitation Addendum shall be added as a part of the Original Bidding Document.

This Solicitation Addendum must be acknowledged by providing the required signature prior to Bid Closing. Failure to do so may result in rejection of Bid.

Requests for clarification, requests for change, and protests of Solicitation Addendum provisions addressed in this Solicitation Addendum must be received by DAS by 2:00 P.M. (Pacific time) on April 29, 2025, or they will not be considered. DAS will not consider requests or protests of matters not added to or modified by this Solicitation Addendum.

New language is indicated by bold print and underline, deleted language is indicated by brackets [ ].

1 Revision

A.3 SOLICITATION SCHEDULE

All dates listed are subject to change. All times listed in this ITB and OregonBuys are Pacific Standard Time (“PST”).

ACTIVITY SCHEDULE/DEADLINE

Mandatory Pre-Bid Conference See ITB Section A.10.

Deadline for solicitation protests, request for change, requests for clarification, requests for approval of equivalents, and questions

[April 25, 2025] April 30, 2025 at 2:00 PM

Deadline for Bid Submittal (“Closing”) May 6, 2025 at 2:00 PM

Public Opening Immediately after Bid Opening Date and time. (See “Public Opening” below fro details on attending Public Opening)

Deadline for Award Protest 7 calendar days after issuance of the Notice of Intent to Award.

See Section D.4.

This Solicitation Addendum does not constitutes a material change to the bid. ITS RECEIPT MUST BE ACKNOWLEDGED BY INSERTING ITS NUMBER ON THE APPROPRIATE BLANK LINES IN ATTACHMENT A-1

OF THE BID DOCUMENT.