This document is Addendum #2 issued by NOVA Engineering & Environmental LLC for the Valencia College East Campus Canopy #3 Covered Walkway project (NOVA Project #10109-0523129). The addendum modifies the original project scope by allocating 2,000 square feet for repairing metal structural components of the canopy, which extends beyond the initial work parameters. The contractor will be responsible for removing and reinstalling metal panels to ensure proper access for repairs and must provide a unit cost per square foot for any additional work required.

The addendum does not specify exact pricing details but indicates that the contractor must be prepared to quote additional work beyond the 2,000 square feet allocation. This modification suggests potential complexity in the repair process and allows flexibility for unexpected repair needs. The document is dated January 8, 2024, and is signed by the Business Unit Manager and Project Engineer, indicating formal approval of the scope change within the existing contract framework for the Valencia College project.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

650 NORTHLAKE BOULEVARD SUITE 430 ALTAMONTE SPRINGS FL 32701

407.902.2660 | USANOVA.COM

Addendum #2 Valencia College East Campus – Canopy #3

Covered Walkway – Canopy #3

NOVA Project #10109-0523129

To: Valencia College East Campus

From: NOVA Engineering & Environmental LLC.

Date: January 8, 2024.

The following change is hereby incorporated into the design and contract documents for the above-referenced project.

• An allocation of 2,000 square feet has been designated for the repair of the metal structural components of the canopy, which extends beyond the original scope of work. The contractor shall be responsible for the removal and reinstallation of the metal panels as required to ensure proper access for the necessary repairs. Additionally, the contractor is required to provide a unit cost per square foot for any additional work as needed.

Desiré Mahanna Stanley De Vargas

Business Unit Manager Project Engineer