This is an Environment, Health & Safety (ESH) Manual chapter from Lawrence Berkeley National Laboratory establishing comprehensive requirements for crane, hoist, and rigging safety operations. The document applies to all crane and hoist operations conducted at Laboratory-owned or -leased property, as well as Laboratory-managed field research, covering employees, affiliates, construction contractors, and non-construction contractors and vendors.

The policy mandates that all persons involved in crane or hoist operations must be aware of equipment hazards, know hazard control methods, and follow proper operating procedures. All operators must be formally trained, certified, and authorized by both line management and the specific Crane Manager for each crane. Crane, hoist, and rigging equipment must be procured through the Facilities Division or approved vendors and must be properly inspected, tested, and maintained. The document establishes detailed work processes covering general crane operation requirements, procurement and maintenance standards, operator authorization and qualifications, restricted operations including critical/high-consequence/high-value lifts, mobile crane operations, inspection procedures, and rigging equipment specifications. Critical lifts exceeding 75% of crane capacity, those involving simultaneous use of multiple hoists, or those with potential damages exceeding $500,000 require detailed Engineering Safety Notes with multi-party review and approval. Operators of overhead cranes must complete EHS0210 training for capacities up to two tons or EHS0206 for greater than two tons, with medical certification and practical examination requirements. The chapter references applicable OSHA standards (29 CFR 1910 Subparts N and 1926 Subpart CC) and includes appendices with typical pre-use inspection tags for daily crane inspections.

View the file

Other files for this federal contract opportunity

Other files attached to UPDATED ALS SHB pulsed RF HPA, newest first.
File Type Posted
RFP-SHB pulsed RF HPA Rev. 1.pdf PDF
Updated - SHB pulsed HPA ESD MARKUP Rev.1.pdf PDF
Rep Cert- SHB pulsed RF HPA Rev1.docx DOCX document
Price Proposal Schedule Attachment B.xlsx XLSX spreadsheet
RFP SHB pulsed RF HPA ESD Response sheet.xlsx XLSX spreadsheet
Updated SHB pulsed HPA SOW MARKUP Rev.1.pdf PDF
Sample Subcontract.pdf PDF
1 LBNL Electrical Equipment Build Standard V6.pdf PDF
1c Appendix C Ground Hook Safety.pdf PDF
4 LBNL ES_H Manual (PUB-3000) Chapter 08 Electrical Safety Program.pdf PDF
8 LBNL RPM on Cranes Hoists and Rigging Safety.pdf PDF
10 LBNL LBNL Facilities Master Specifications 260519.11_600 Volt Conductors and Cable.docx DOCX document
RFP-SHB pulsed RF HPA.pdf PDF
AL-1887-8783A SHB pulsed RF HPA SOW.pdf PDF
1b Appendix B Electrical Equipment Fabrication.pdf PDF
2 LBNL Electrical Safety Manual Revision 1.pdf PDF
6 LBNL RPM on Seismic Safety.pdf PDF
7 LBNL Lateral Force Design Criteria Resource Document (RD3.22) (version 18).pdf PDF
12 LBNL ES_H Manual (PUB-3000) Chapter 43 Non Ionizing Radiation.pdf PDF
13 LBNL PUB 3111 Quality Assurance Program Description.pdf PDF
Rep-Cert Form - SHB pulsed RF HPA.docx DOCX document
Past Performance Reference Information Form.docx DOCX document
RFP SHB pulsed RF HPA ESD Response sheet.xlsx XLSX spreadsheet
1a Appendix A Electrical Equipment Hazard Labeling.pdf PDF
3 LBNL RPM on Safe Electrical Installations Policy.pdf PDF
11 LBNL Facilities Master Specifications 260523_Low-Voltage Electrical Power Conductors and Cables.docx DOCX document
Price Proposal Schedule Attachment B.xlsx XLSX spreadsheet
AL-1887-8780A SHB pulsed RF HPA ESD.pdf PDF
1d Appendix D Rack Build Standard.pdf PDF
5 LBNL ES_H Manual (PUB-3000) Chapter 14 Electrical Equipment Safety Program.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

4/7/2020 CH27

https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 1/25

CH27

ESH Manual CH27

Chapter 27 Cranes, Hoists, and Rigging Safety

Contents

Approved by Michael Kincaid

Revised 12/18

27.1 Policy

27.2 Scope

27.3 Applicability

27.4 Roles and Responsibilities

27.5 Definitions

27.6 Required Work Processes

Work Process A. General Requirements for Crane Operation

Work Process B. Procurement and Maintenance of Cranes and Hoisting and Rigging Equipment

Work Process C. Authorization and Qualification to Use Cranes

Work Process D. Restricted Operations

Work Process E. Mobile Cranes

Work Process F. Crane Inspections

Work Process G. Rigging and Other Below-the-Hook Devices and Fixtures

27.7 Standards

27.8 Related ESH Manual Chapters

27.9 References

Appendix A. Typical Pre-use Inspection Tags

NOTE:

. . . .. Denotes a new section.

. . . . . .. . Denotes the beginning of changed text within a section.

. . . . . . . Denotes the end of changed text within a section.

27.1 Policy

Persons involved in crane or hoist operations at Lawrence Berkeley National Laboratory (Berkeley Lab) must:

https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 2/25

● Be aware of the hazards related to the equipment and the load

● Know the methods for controlling those hazards

● Follow the proper operating procedures applicable to the type of lift and equipment

The designated operator must be qualified and authorized to use specific equipment.

Crane, hoist, and rigging equipment must be procured through the Facilities Division or from a Berkeley Lab approved vendor, as well as properly inspected, tested, and maintained.

27.2 Scope

Berkeley Lab’s Crane Safety Program is implemented through planning, authorization, qualification, and the appropriate use of properly inspected and rated hoisting equipment and rigging. Lifting and moving loads with forklifts is covered in ESH Manual, Chapter 28, Forklifts and Other Powered Industrial Trucks.

Construction operations involving cranes are covered in Chapter 10, Construction Safety.

27.3 Applicability

This policy establishes requirements for Berkeley Lab’s Crane, Hoisting, and Rigging Safety Program and applies to work with any crane or hoist operated at Laboratory-owned or -leased property, as well as

Laboratory-managed field research. This program applies to the following Berkeley Lab personnel:

1. Employees

2. Affiliates

3. Construction contractors

4. Non-construction contractors and vendors

27.4 Roles and Responsibilities

Role Responsibility

Supervisors and

Work Leads

● Ensure that personnel know how to safely operate cranes and hoists, and how to move objects safely

● Ensure that only formally trained and certified employees may operate a crane or hoist

● Enforce the use of safe lifting techniques

● Maintain lifting equipment in good mechanical and operating condition

Crane Manager

A Berkeley Lab employee must be

● Identify oneself, in writing, as the Crane Manager to the

Environment, Health & Safety (EHS) Division Crane Safety https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 3/25 identified as the

Crane Manager for each Berkeley Lab-owned crane or hoist, unless it is locked out.

Subject Matter Expert (SME) at cranesafety@lbl.gov or Mail

Stop 75B0101Q

● Maintains their individual authorization and training requirements for cranes via the Work Planning & Control (WPC) process/database

● Maintains control of any keys or other mechanisms for limiting crane use to qualified operators only

● Maintains any logbooks used in lieu of inspection tags

● Limits crane use to previously authorized operators o A qualified backup Crane Manager who has been identified to the Crane Safety SME may issue new crane authorizations in the absence of the Crane Manager

● Notifies the EHS Crane Safety SME (cranesafety@lbl.gov, Mail

Stop 75B0101Q) of any change

Employees

(Operators, Riggers, and

Helpers)

● Maintain training and medical qualification

● Safely operate cranes

● Maintain their individual authorization and training requirements for cranes via the WPC process/database

● Are certified by an independent certification agency as competent and qualified operators of mobile cranes with a greater-than-two-ton capacity

● Follows all established safety regulations related to safe lifting and handling techniques

Mechanical

Engineering

Designee

● Reviews and approves Engineering Safety Notes for lifting fixtures, critical/high-consequence/high-value lifts/moves using overhead cranes on behalf of the Engineering Division Director and for the Mechanical Engineering Subcommittee of the Safety

Advisory Committee

● Approves reasonable engineering alternatives not in conflict with Berkeley Lab’s Environment, Safety & Health Standards

Set

● Furnishes guidance to Berkeley Lab staff

Responsible

Designer

● Incorporates the requirements of the Cranes, Hoists, and

Rigging Safety program into the design of lifting fixtures and procedures

● Initiates the required proof testing

● Obtains design approval by means of an Engineering Safety

Note

Customer

Management

● Defines and requests any lift/move mailto:cranesafety@lbl.gov https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 4/25

● Determines which lifts are critical/high-consequence/high-value lifts/moves

● Writes lifting procedures where required

● Provides technical information on relevant characteristics of the apparatus, including special lifting fixtures when required

● Assigns someone to represent the customer during planning and coordination of all aspects of the job being performed

● Provides suggestions on rigging and moving

● Ensures that lifting devices and lifting fixtures are properly documented and inspected, and that they are used and maintained safely

● Requests the Facilities Division to prepare the Engineering

Safety Note, and to manage the move on the Work Request as needed

Facilities Division

Structural

Engineering Group

Designee

● Evaluates building floor loading, lifting fixtures, and lifting devices for structural adequacy

● Reviews and approves Engineering Safety Notes for critical/high-consequence/high-value lifts/moves using mobile cranes, forklifts, and jack and roll devices on behalf of the

Facilities Division and the Mechanical Engineering

Subcommittee of the Safety Advisory Committee

● Establishes design parameters for all cranes and hoists

● Provides guidance on wind loading for outdoor lifts/moves

● Provides Berkeley Lab staff with guidance on lift-related matters

Facilities Division

Rigging Supervisor

● Provides guidance and supervision for routine lifts when requested

● Participates in the development and review of critical/high-consequence/high-value lifts/moves

● Participates in pre-lift meetings

Facilities Division

Crane Maintenance

Vendor

● Arranges for all inspection, testing, and certification of cranes, hoists, and rigging

● Arranges for the testing and certification of lifting devices and lifting fixtures

Facilities Division

Maintenance

Manager

● Establishes the scope of work for the Facilities Division Crane

Maintenance Vendor

● Follows technical advice from the Facilities Division Crane

Maintenance Vendor to ensure that Laboratory purchases of crane, hoist, and rigging equipment, components, and devices https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 5/25 are traceable (through documentation) to a reputable U.S.

manufacturer

EHS Division Crane

Safety SME

● Manages the Cranes, Hoists, and Rigging Safety program

● Reviews Engineering Safety Notes for critical/high-consequence/high-value lifts/moves

● Conforms to Cranes, Hoists, and Rigging Safety program requirements

● Participates in pre-lift meetings for critical/high-consequence/high-value lifts/moves

● Notifies the Facilities Division Crane Maintenance Vendor to lock all cranes and hoists that do not have an official Crane

Manager

Designated Person

In Charge

The customer may be a manager, engineer, or other responsible person

(other than the operator).

● Oversees ordinary, critical/high-consequence/high-value lifts/moves, personnel or pre-engineered production lifts. to ensure lifts are completed safely and efficiently

● Confirms crane/hoist is within the current inspection interval and that charts, tables, or diagrams are appropriately posted or available to the operator

● Survey the lift site for hazardous/unsafe conditions and maintain hoisting routes to minimize exposure to personnel and equipment from overhead load(s)

● Confirms all applicable personnel understand the scope of the lift and that personnel (i.e. operator, signal person, rigger(s), are qualified/trained, and the signal person is identified to the operator

● Ensures all lifting equipment is properly selected, inspected, loads centered/configured/positioned properly and loads never exceed lifting device capacities

● Safely halt the lift if any potentially unsafe condition is recognized and obtain emergency assistance, as necessary, if an accident or injury occurs

Procurement ● Ensures that approved vendors who sell hoisting equipment ordered by divisions have provided manufacturer certification that equipment is authentic and has been load tested at 200% of rated capacity

27.5 Definitions

Term Definition

Crane A machine used for lifting and lowering a load vertically and moving it horizontally, and that has a hoisting mechanism https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 6/25

Engineering Note A detailed description of a (fixture) design, or a detailed description of a high-consequence/high-value lift/move, including protection of the load, rigging, and method(s) of transport

Ordinary Lifts Any non-critical/high consequence/high value or pre-engineered lift.

● Requires a designated individual with the knowledge and experience of the equipment and lifting operations be present through the entirety of the lift

● Designation may be written instructions, specific verbal instructions for the particular job or clearly stated defined responsibilities within the crew’s organization structure.

Pre-Engineered/Production lifts

A repetitive lift that is performed by production line personnel in the assembly or disassembly of components or systems where detailed lift planning, equipment selection, and lift-specific training may substitute for the qualifications.

Any engineered lifts shall be developed & approved via step by step procedures containing the following information:

● Identify the item(s) to be lifted

● Identify specific lifting components

● Identify hoist/equipment for use

● All equipment/components are current and pre-use inspections are complete

● Specific instructions/procedures for attaching fixture(s)/components(s) to load and lifting equipment/hoist

● Step by step procedure for moving the load

● Specific instructions for removing fixtures/component(s) from hoist/load

Procedure Verification:

● The proposed procedure(s) shall be reviewed by the facilities structural engineer, rigging supervisor, EHS https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 7/25 hoisting program manager and line authority representative for the division conducting the lift(s).

● These individuals shall conduct a formal verification and validation of procedures using a walk through or similar method(s) to ensure step by step methods are appropriate. Discrepancies shall be corrected and process repeated until the procedures are correct.

● A copy of the most current procedure shall be kept in the work area.

● Work shall be paused if any procedure deficiencies are identified.

● The process shall only be reinstated after a formal review using the verification process.

● Deviations from process shall only be permitted in an emergency situation dealing with life safety or property security. Personnel may return to a safe/stable condition without initiating a procedure change.

Procedure Training Specialized training shall be conducted for personnel involved in performance pre-engineered production lifts, with training oversight by responsible operating and oversight organizations. It shall cover at minimum:

● Thorough coverage of all aspects of the procedure and assigned responsibilities for the lift.

● A demonstration by the individual of operational competence in the performance of all assigned duties associated with the lift.

● Training shall be repeated periodically of when a modification to the procedure results in a significant change in the operations.

Critical Lift/High-

Consequence/High-Value

Lift/Move

● The customer’s designation for parts, components, assemblies, or lifting operations that could have the https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 8/25 following consequences in the event of falling from a crane or colliding with other objects:

o Damages in excess of $500,000 (This does not apply to routine movements of shielding blocks performed by members of the professional rigging crew.)

o Significant work delays or programmatic impacts o Undetectable damages resulting in future operational or safety problems o A significant release of radioactivity or another undesirable condition o A potentially unacceptable risk of personnel injury or property damage

● Any lift/move that requires the simultaneous use of both the main and auxiliary hoists of a given crane or the simultaneous use of two cranes

● Any lift that exceeds 75% of the crane configuration or set-up

Hoist A device that applies a force for lifting and lowering

Lifting Device A device, other than a sling, used below the hoisting hook for attaching loads to a hoist. There are four types of lifting devices:

● Structural and mechanical lifting devices (e.g., spreader bars, plate clamps, gripping devices, etc.)

● Vacuum lifting devices

● Close proximity lifting magnets

● Remotely operated lifting magnets

Lifting Fixture A fixture used below the hoisting hook designed and engineered for lifting a specific item

Mobile Crane A crane system fixed to a vehicle, typically a truck

Overhead Crane A crane system fixed to a structure, including but not limited to bridge cranes, monorail cranes, gantry cranes, and jib cranes https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 9/25

Rigging ● The hardware or equipment used to safely attach a load to a hook or lifting device

● The art or process of safely attaching a load to a hook by means of an adequately rated and properly applied sling and related hardware

27.6 Required Work Processes

Work Process A. General Requirements for Crane Operation

The work flowchart below provides a step-by-step overview of crane and hoist operations requirements (go here to download a PDF of the flowchart):

The following rules apply to all use of crane and hoist operations at Berkeley Lab.

● Whoever needs to move a load must:

o First determine the value of the load and consequences of a failed move o Determine if the load needs to be moved by a crane o Determine who can operate the crane https://www.google.com/url?q=http://www2.lbl.gov/ehs/pub3000/CH27-CraneProcess.pdf&sa=D&ust=1586309138082000 https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 10/25

● Loads meeting the definition of Critical/High-Consequence/High-Value Lifts/Moves or other restricted operations (see Work Process D) require more detailed planning and may require the lift to be performed by the Facilities Division Riggers.

● Operators must be authorized by Line Management to use cranes.

● Operators must be authorized by the Crane Manager to use a specific crane.

● Operators must be qualified and authorized on the type of crane they intend to use.

● Operators must plan each lift, taking into account the path of travel to avoid contact with personnel and objects.

● Loads meeting the definition of Critical/High-Consequence/High-Value Lifts/Moves or other restricted operations (see Work Process B) require more detailed planning and may require the lift to be performed by the Facilities Division Riggers.

● Operators must inspect the crane and associated rigging prior to using the crane.

● Cranes and rigging found to be deficient must be taken out of service, and cannot be used unless repaired and recertified by the Facilities Division Crane Maintenance Vendor.

● Cranes and rigging must be rated to lift the intended load; no load (including rigging, devices, and lifting fixtures) may exceed the limits of the crane and rigging. If an employee is unsure of the weight of a load, or if the load weight exceeds 75% of the crane’s configured/set-up capacity

(whether on tires or outriggers), contact the Facilities Division Rigging Supervisor for assistance.

Crane testing by the Facilities Division Crane Service contractor is the only exception to this rule..

● Operators are responsible for ensuring that the load is properly rigged to avoid shifting during the lift. Test lifts of less than one foot from the ground to check for load shifting are permitted.

● For mobile telescopic and lattice boom cranes lifting operations must cease when the local weather forecast calls for thunder/lightning storms to be in the area.

● Refer to the manufacturer’s specifications for safe operations in windy conditions. If no specifications can be found and no licensed professional structural engineer is available to determine the safe working wind speed(s), then operations should cease if sustained gusts and/or winds of

25mph or greater occur. The nearest qualified weather reporting service should be referred to for wind speeds if the crane is not equipped with an anemometer. Contract the Facilities structural engineer if further assistance is needed.

● All personnel who are operating a crane or hoist, are participating in the lift, or are located within

15 feet of the vertical plane of the load — where the undercarriage of the bridge is more than 12 feet from the ground — must wear hard hats. Post or barricade the area as needed.

● Sturdy work gloves must be worn when handling wire rope or loads with rough or sharp edges or splinters.

Suspended Loads

These rules apply to operators of suspended loads:

https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 11/25

● Test brakes under load when load is 80% of the crane's rated load. Raise the load a few inches and apply the brakes.

● Ensure loads are never lowered below the point where less than two full wraps of rope remain on the hoisting drum.

● Do not allow hoisting chains or ropes to kink or twist, or to wrap around the load.

● Attach the load to the load block hook ONLY by means of slings or other approved devices; NEVER wrap the hoist rope around the load.

● Ensure loads are well secured and properly balanced in the sling or lifting device before it is lifted more than a few inches.

● Avoid suddenly accelerating or decelerating the moving load.

● Do not allow the load to contact obstructions.

● Do not allow loads moved with any material-handling equipment to pass over any personnel.

● Select the load path to eliminate the possibility of injury to employees should the material-handling equipment fail.

● Do not permit work on suspended loads. Rest the load on adequate cribbing if it needs to be worked on.

● Never leave a suspended load unattended nor leave the controls while the load is suspended.

Lower the load to the floor or the working surface or onto cribbing, and secure the material-handling equipment before leaving the load unattended.

Component Failure or Unintended Movement

If any component fails during a lift, or if there is any uncontrolled or unintended motion of the load during the lift, the lift must be terminated immediately in the safest manner possible. Immediately notify the

Crane Manager of the component failure. Contact EHS and the Facilities Division Rigging Supervisor.

Lifting may only resume after the failure or unintended motion has been investigated, and appropriate corrective steps have been implemented.

Securing Cranes

Any electric-powered crane, when not attended by a qualified operator during an entire shift and off-hours, must be secured by locked controls or equivalent means to prevent access to the crane, such as locking the doors or locking up radio controls. Only the Crane Manager or another qualified and authorized user of the secured crane may have control of the locking mechanism.

Work Process B. Procurement and Maintenance of Cranes and Hoisting and Rigging Equipment https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 12/25

Approval from the Facilities Division Structural Engineer must be obtained before purchasing hoists or cranes that will be attached to any LBNL building or structure. Free-standing lifting equipment or cranes as well as rigging such as shackles, clevises, wire rope or fabric slings, or spreader bars (strongbacks) must be purchased from an LBNL-approved hoisting and rigging vendor. Use of the pre-approved vendors ensures that the required standards and certification requirements are met. The Facilities Rigging Superintendent or the EHS Crane Safety SME can provide assistance in selecting cranes and rigging equipment to meet specific needs or circumstance.

If used equipment is procured, it must be inspected and certified to meet all applicable standards in force at the time of the acquisition prior to use at LBNL.

For Berkeley Lab—designed and/or fabricated lifting devices, see Work Process G.

When equipment is received, the recipient must contact the Facilities Division Crane Maintenance Vendor

(cranesafety@lbl.gov) to have the equipment inventoried for routine inspection and maintenance. Do not discard any certification papers received with the equipment. All hoisting and rigging equipment (except when impractical, e.g., shackles, swivel lifting rings, etc.) used at the Laboratory must have a Laboratory proof-load tag attached with a current inspection sticker. The user, supervisor, and operator are directly responsible for verifying the presence of current, proper tagging of hoisting and rigging equipment prior to use.

Work Process C. Authorization and Qualification to Use Cranes

All crane use must be authorized by an employee’s supervisor, through the Work Planning & Control (WPC) process, and by the Crane Manager for the particular crane(s) to be operated. The Crane Manager is a qualified crane operator who has been designated as the individual responsible for the safe operation of a specific crane. Before operating a crane in an area for the first time or in a new application, employees must discuss the proposed crane use with the Crane Manager and obtain approval. The Crane Manager will determine whether the operator is familiar with the controls for that particular crane and knows how to properly rig loads, and will verify that crane use will not conflict with other operations in the area.

Cranes may also be operated by qualified Crane Service personnel who have been authorized through the

WPC process or an SWJHA (for the on-site Facilities Division Crane Maintenance Vendor), and have been subcontracted to install, maintain, or repair cranes.

Qualifications, Training, Certification, and Approval Requirements for Overhead Crane and Hoist Operators

The operation of overhead cranes and hoists is restricted to trained personnel who have completed Berkeley

Lab—required training, and who have been certified in accordance with the requirements of this chapter.

mailto:cranesafety@lbl.gov https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 13/25

This includes the operation of cranes without a load for any reason. Requirements for operating mobile cranes can be found in Work Process F.

To become certified for operating cranes up to a two-ton capacity, the following requirements must be met:

● All prospective operators of cranes and hoists up to a two-ton capacity must meet the health requirements that would entitle them to operate a motor vehicle in the state of California.

Individuals who do not hold a valid driver’s license must be examined and approved by Health

Services at Berkeley Lab.

● The prospective operator must complete EHS0210, Crane/Hoist Operator — 2 Tons or Less. This course includes hands-on instruction. A record of training will be made with the EHS training department after the successful completion of the course.

Note that crane and hoist operators authorized for less than two-ton cranes may NOT operate cranes or hoists with a capacity of greater than two tons to lift loads of less than two tons or without any load.

To operate overhead cranes or hoists with a capacity of greater than two tons, the following is required:

● All prospective crane operators must complete an application and must pass a medical examination and/or review of medical information on file at Health Services prior to training. The application must identify a qualified crane operator who will provide hands-on instruction and close supervision during an initial training period. The supervisor and the operator who will provide the instruction must sign the application and agree to the initial training. If the prospective operator has prior experience operating cranes, he or she may be examined and authorized without an initial training period.

● The prospective operator must complete EHS0206 (Crane/Hoist Operator — Greater than 2 Tons).

Upon completion of this classroom training, the individual may only operate cranes and hoists they have been authorized to use per the crane manager under the direct supervision of the operator identified on the application, until such time the prospective operator is identified as qualified for the practical examination.

● When the prospective operator is ready, they may contact an overhead-crane practical-examination instructor to be examined on the operation of the specific crane to be operated most frequently. A list of qualified overhead-crane practical-examination instructors is maintained by the

EHS Division Training Group.

Crane operators must renew their training every three years, and must be medically recertified every three years.

Work Process D. Restricted Operations

Critical/High-Consequence/High-Value Lifts and Moves https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 14/25

The customer (i.e., the manager who requires the items to be moved) or a program organization designates parts, components, assemblies, or lifting operations as a critical/high-consequence/high-value lifts/moves, because the effect of those items falling from the crane, or colliding with other objects, could:

● Cause damage in excess of $500,000 o This requirement does not apply to routine movements of shielding blocks performed by members of the professional rigging crew.

● Cause significant work delay or programmatic impact

● Cause undetectable damage resulting in future operational or safety problems

● Result in significant release of radioactivity or other undesirable conditions

● Present a potentially unacceptable risk of personnel injury or property damage

● Any lift that exceeds 75% of the configured crane configuration/setup (for mobile, telescopic, and lattice boom cranes.

● In addition, any lift/move that requires the simultaneous use of both the main and auxiliary hoists of a given crane or the simultaneous use of two cranes must be considered a critical/high-consequence/high-value lift/move.

Critical/High-Consequence/High-Value Lift/Move Requirements

A detailed, step-by-step procedure in the form of an Engineering Note must be prepared for each critical/high-consequence/high-value lift/move. This requirement covers lifts and moves performed with forklifts or cranes. An Engineering Note template may be obtained from the Engineering Division through submitting a work request at https://workrequest.lbl.gov/jsp/workreq_add.jsp. While high-consequence/high-value lift procedures are customarily prepared for one-time use, general critical/high-consequence/high-value lift procedures may be employed to accomplish routine, recurrent high-consequence/high-value lift operations. For example, a general critical/high-consequence/high-value lift procedure may be applied to lift shielding blocks or a frequently lifted items. Examples can be found through the search page of the Berkeley Lab Engineering Note Repository at http://engineering.lbl.gov/employee-resources/. (Select "Document Control Center" - logging in using your

LDAP as necessary - then enter the keywords “high value” in the Category 4 Title 3 field).

The customer, i.e., the Laboratory manager who requires the item to be moved, is responsible for preparing the critical/high-consequence/high-value lift/move Safety Engineering Note. The customer can discharge this responsibility by indicating on the Facilities or Engineering Division Work Request that the scope of work should include preparation of the Engineering Safety Note and management of the move. It is the responsibility of the customer to notify all personnel whose review is required early in the process. See

Critical/High-Consequence/High-Value Move Lift/Move Approval below.

Reviewers have special expertise and are available to provide guidance during the design of the lifting procedure. Please allow sufficient time for the review-and-approval process. There is no charge for the https://www.google.com/url?q=http://engineering.lbl.gov/employee-resources/&sa=D&ust=1586309138088000 https://www.google.com/url?q=http://engineering.lbl.gov/employee-resources/&sa=D&ust=1586309138089000 https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 15/25 review-and-approval process.

The procedure must contain the following:

● Identification of the item to be moved

● Identification of the Laboratory manager or engineer who is responsible for planning the lift

● Identification of the rigging supervisor or designated qualified rigger (other than the equipment operator) who will be the Person In Charge (PIC) of all aspects of the lift while the load is suspended

● Special precautions

● Weight of the item

● Total hook load (all component parts of the item plus tackle and load-measuring devices)

● Determination of the center of gravity

● A list of each piece of equipment and each accessory (e.g., slings, spreader bars, yokes) to be used in the lift

● Each accessory must be identified by type and rated capacity

● If a portable item to be used has no manufacturer’s serial number, a Berkeley Lab identification number must be assigned and affixed to the item

● Surveillance procedures, checkpoints, and estimated instrument readings (if used) must be listed to enable confirmation that the lift is proceeding as planned

● Calculation of stresses to be generated in the item during lifting and determination of the adequacy and proper labeling of the attachment points of the item to be lifted.

● A rigging sketch or sketches that include the following:

o Lifting points o Load vectors at all stages of the lift/move o Sling angles at all stages of the lift/move o Accessories used o Method(s) of attachment o Method of rotating about either horizontal axis, if applicable o Other factors affecting the capacity of the equipment or accessories o Identification of the capacity (or limit) of equipment and load o Identification of the expected load in each item of equipment and each accessory

● A load-path sketch of the load path with the expected height of the load at each point in the lift

● Where appropriate, floor loading diagrams are to be included to provide for setting the load down at any point in the path if that should be necessary.

● A travel sketch, either as a part of the load-path sketch or a separate sketch, indicating the planned travel path, and lifting and travel speeds

● Where clearances are an issue, a detailed drawing with verified dimensions that demonstrates the lift can be accomplished as planned

● An assessment of wind loading and weather concerns for all outdoor work

● Obtain assistance from the Facilities Division Structural Engineering Group for wind loading concerns.

https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 16/25

● A checklist detailing each step of the procedure, with each step initialed by the Laboratory manager or engineer responsible for the planning of the lift

● A sign-off sheet where all personnel involved in the lift verify that they are familiar with the contents of the procedure

● Load tests and practice lifts, if required

● Verification that all primary and secondary hoisting equipment is within the current inspection and test time requirements as specified in this chapter (for example, yearly periodic inspections and certification)

Critical/High-Consequence/High-Value Lift/Move Approval

The procedure must be reviewed by:

● Customer management

● The Engineering Division Mechanical Engineering Department Designee

● The assigned Facilities Division Structural Engineer

● The Facilities Division Rigging Supervisor

● The EHS Division Designee

The procedure must be approved by the appropriate engineer:

● For lifts/moves using overhead building cranes, the Engineering Division Mechanical Engineering

Department Designee is the approver.

● For lifts/moves using mobile cranes, forklifts, or jack and roll devices, the assigned Facilities

Division Structural Engineer is the approver.

All reviewers and approvers should be consulted early in the process to ensure their concerns are addressed, avoiding the need for later revisions to the procedure.

Unanticipated conditions may require on-the-spot changes of the lift procedure. Approvers of the lift procedure should be present during the lift or at least immediately available to approve changes. Changes must be recorded on the procedure and initialed by all available approvers before they are implemented.

Personnel Participating in Critical/High-Consequence/High-Value Lifts/Moves

Each person involved in a critical/high-consequence/high-value lift/move must be familiar with the procedure before beginning work. A pre-lift meeting with all participating personnel must be held before the lift. All participating personnel must initial the procedure sign-off sheet to verify that they are familiar with the procedure.

Cab-Operated Cranes https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 17/25

Operation of cranes from a cab is restricted to professional riggers. The following rules apply to cab-operated cranes:

● Do not store personal belongings (including necessary clothing) in a manner that interferes with operations.

● Store other necessary equipment (tools, oil cans, waste, extra fuses, etc.) in the toolbox. Do not store equipment loosely in or about the cab.

Heavy Lifts

Heavy lifts should be made by the professional rigging crew that performs such work routinely. Where there is a need for other personnel to lift loads over 10,000 lb., the proposed lift must be reviewed with and approved informally by the supervisor of the professional rigging crew or his or her designee.

Tilting Loads

Using a crane to tilt a load (standing up a load that is lying down or vice versa) carries a significant risk of shock-loading the crane or losing control of the load. When such operations involve loads that exceed 50% of the rated capacity of the crane, they must be reviewed by and may be performed only with the informal approval of the supervisor of the professional rigging crew or his or her designee. If two hooks are required to tilt the load, follow the critical/high-consequence/high-value lift procedures listed above.

Work Process E. Mobile Cranes

The operation of mobile cranes is restricted to those who have been certified as competent and qualified mobile crane operators by an independent certification agency. The Facilities Division Riggers have authorized and qualified mobile crane operators.

Mobile crane operations for construction have additional requirements, which are found in Chapter 10

Construction Safety. For the purpose of the Berkeley Lab Cranes, Hoisting, and Rigging Program, small truck-mounted jib cranes with capacities of less than 2 tons are not considered mobile cranes. Mobile crane operations are conducted in accordance with all applicable Occupational Safety and Health Administration

(OSHA) (and Cal/OSHA for construction) requirements.

Any mobile crane, when not attended by a qualified operator during an entire shift or during off-hours, must be secured by locked controls or equivalent means to prevent access to the crane, such as locking the doors or locking up radio controls. Only the Crane Manager or another qualified and authorized user of the secured crane may have control of the locking mechanism.

https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 18/25

Work Process F. Crane Inspections

Each crane or hoist must be inspected by a qualified crane operator before use, during any given work shift.

The inspection can be documented either on a tag attached to the crane controls or in a log that is kept with the key to the crane controls. If the crane is not used during any shift, it does not need to be inspected. Cranes used infrequently (idle for one to six months) may be inspected by a qualified operator as a before-use inspection. However, if a crane has been idle for more than six months, the Facilities

Division Crane and Hoist Services Contractor must perform a periodic inspection before it may be used. Where applicable, crane inspection logs will be reviewed by the Crane and Hoist Services Contractor.

Typical crane inspection checklists are shown in Appendix A of this ES&H Manual chapter.

All other required equipment inspections (including periodic crane and hoist inspections) and tests are performed by the Facilities Division Crane and Hoist Services Contractor. Equipment and the frequency of equipment inspections and tests are listed in a Facilities Division database as required by applicable regulations and/or standards. Facilities Division Crane and Hoist Services Contractor work orders are automatically generated monthly and are based on information in the database.

Work Process G. Rigging and Other Below-the-Hook Devices and Fixtures

The crane operator is responsible for verifying that the load is properly rigged. The crane operator must also take the following precautions when performing work:

● Thoroughly inspect rigging before use (document the inspection on the Daily Crane Inspection

Tag).

● Remove defective rigging from service. DO NOT USE and DO NOT REPAIR defective rigging.

● All other required rigging inspections and tests are performed by the Facilities Division Crane and

Hoist Services Contractor. The frequency of these various inspections and tests are detailed in

Facilities Division work orders.

● Only use slings in accordance with the manufacturer’s recommendations.

● All manufactured pick/hoisting points should be inspected prior to hoisting to confirm they are free from damage that could have occurred prior to being received at LBNL.

● Additional sling protectors (a.k.a. softeners) must be used in all situations where slings may, can, or do come into contact with non-rounded or sharp edges.

● Use engineered attachment points and standard hardware (swivel lift rings, shackles, and nylon slings) wherever possible.

● Verify that all slings and hardware are rated for more than the expected load and are appropriate for the intended type of load and configuration.

● Verify that all slings and special lifting hardware have current Berkeley Lab inspection tags.

● Never shorten slings with knots, bolts, or other makeshift devices.

● Never load rigging in excess of its rated capacities.

https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 19/25

● Use padding to protect natural fiber or synthetic slings from damage (e.g., contact with sharp edges). Make sure all slings are properly secured to prevent shifting during lifts.

● Verify loads are balanced to prevent slippage (e.g., when using a basket hitch).

● Remove slings from a load when the load is not resting on the sling.

● Contact the EHS Crane and Hoist Subject Matter Expert (cranesafety@lbl.gov) or the Facilities

Division Crane Maintenance Vendor (ext. 7667) before rigging is used in any manner or environment

(e.g., used in close proximity with corrosives or degrading chemicals, operated in temperature extremes of –20°F or +180°F, etc.) that may compromise its construction or strength.

Inspection and Testing of Lifting Devices

Each division is responsible for the safety and pre-use inspection of its lifting devices (such as screw pin shackles, hoist rings, commercial equipment, etc.) and for its lifting fixtures (such as spreader bars, special slings, equipment designed at Berkeley Lab, etc.). Berkeley Lab proof-load tags and inspection stickers must be current, where applicable. Special-purpose lifting fixtures must be marked with a

Laboratory equipment number and labeled to identify applicable Engineering Safety Notes for fixture design and/or critical/high-consequence/high-value lifts/moves.

All lifting fixtures designed at the Laboratory must be proof-tested to twice their maximum rated loads before being placed in service. A Non-Destructive Examination (NDE) is required after the proof test. The exact type of NDE must be specified in the Engineering Safety Note for the lifting fixture. The rated capacity must be marked on the lifting fixture so that it is clearly visible to the equipment operator.

Order commercially available lifting fixtures through the pre-approved hoist and rigging vendor or the

Facilities Division Maintenance Manager or Designee to assure they are ordered with a certificate of proof load testing. For commercial lifting fixtures without certified load ratings, an Engineering Safety Note must be written to determine the safe load capacity and furnish guidance for load testing.

Where the lifting fixture cannot be proof-tested because it is an integral part or component of the experimental device, equivalent alternative safety precautions acceptable to the Mechanical Engineering designee must be described in the Engineering Safety Note, which delineates the lift procedure.

All lifting device pins of 5 cm (2 in.) in diameter or larger must have a magnetic-particle inspection before they are placed in service. These pins are always part of a lifting device or fixture. Make arrangements with the Facilities Division Crane Maintenance Vendor or the Work Request Center, ext. 6274, to have lifting fixtures inspected.

Active lifting devices and fixtures must be examined by an NDE at least once every four years (or upon request), using magnetic-particle detection or other appropriate methods. Make arrangements to have lifting fixtures inspected with the Facilities Division Crane Maintenance Vendor or contact the Work Request

Center, ext. 6274. Records must be maintained by the Facilities Division and NDE organizations. Inactive mailto:cranesafety@lbl.gov https://www.google.com/url?q=http://fac.lbl.gov/Facilities/&sa=D&ust=1586309138096000 https://www.google.com/url?q=http://fac.lbl.gov/Facilities/&sa=D&ust=1586309138096000 https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 20/25 lifting devices and fixtures must be clearly marked “STOP: DO NOT USE,” and must be load tested and certified prior to renewed use.

The Responsible User must ensure that:

● Proof-testing is performed by the Facilities Division on all lifting fixtures designed at the

Laboratory, before they are placed in service

● Adequate test records are kept

● Lifting devices and fixtures are used and maintained correctly

The Responsible Designer must obtain design approval by means of an Engineering Safety Note, as described below. For equipment designed at the Laboratory, the Responsible Designer must provide the user with the information required to operate the lifting device or fixture safely. The Facilities Division will provide a test report to the user upon request.

Design of Lifting Fixtures

A qualified engineer must be designated to be responsible for the design, fabrication, and testing of lifting fixtures not purchased commercially. The actual physical testing usually will be performed by the Facilities

Division in accordance with the written test procedure specified by the Project Engineer.

All lifting fixtures not procured through the Facilities Division, a Berkeley Lab approved vendor, or provided by the equipment (to be hoisted) manufacturer with proper engineering documentation must be covered by an Engineering Safety Note. The Engineering Safety Note must include the calculation of lifting fixture stresses and deflections, and must be reviewed by:

● The Responsible Designer

● Customer Management

● The Engineering Division Mechanical Engineering Department designee

● The Facilities Division Plant Operations Department Rigging Supervisor

● The EHS Division designee

The Engineering Safety Note must be approved by:

● The Engineering Division Mechanical Engineering Department designee.

The design stress for lifting fixtures or lifting attachment points must not exceed one-fifth the ultimate strength of the material at its operating temperature. If welded fabrication is used, the design stress must take into consideration any weakening effects of welding, such as those that occur in aluminum alloys.

If practical, avoid welding in the fabrication of lifting fixtures. If welding must be used, design and fabrication in conformance with the latest standards of the American Welding Society (AWS) are required.

https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 21/25

Careful, thoughtful design and follow-up are required.

Follow these rules for all lifting fixtures:

● All welds in lifting fixtures must be certified welds, performed by certified welders, and inspected and certified by certified weld inspectors.

● If at all possible, do not allow welds to be subjected to tearing loads. Stresses in welds must be substantially uniform.

● Where possible, design lifting fixtures so that the main loads are carried only by structural members, plates, or shear pins rather than by welds. Examine this possibility carefully.

● Proof-test lifting fixtures to twice the maximum rated load. Follow by a nondestructive examination. X-ray primary load-carrying welds and welds in tension, or perform other suitable subsurface crack-detection examinations.

● The screw-thread engagement required for conservative development of the full strength of a screw fastener depends upon the screw-fastener material and the material of the threaded member.

o If the fastener is made of the same material as the female threaded member — e.g., a low-carbon steel bolt and a hole threaded into low-carbon steel — an engagement of at least 1½ diameters is required.

o A hardened steel screw (Allen screw) in mild steel requires at least 2 diameters of engagement.

o A low-carbon screw fastener, threaded into a tapped hole in aluminum alloy, copper, or cast iron must have a threaded engagement of 1½ diameters.

o Other material combinations must be approved by the Mechanical Engineering Department designee.

● Safety hoist rings may be used to make lifts up to their rated load when screwed 2 hoist-ring bolt diameters into materials such as aluminum alloy, copper, or cast iron.

● When special high-strength bolts are required, test any bolt used as part of Laboratory-designed lifting fixtures or pickup devices to two times its rated load. A crack-detection inspection must be performed after the load test to ensure integrity. Try to maintain a supply of tested bolts in the event that one is lost, or better yet, to have the bolt on a permanent lanyard. Once a lifting device or fixture has been delivered to the user, the user is responsible for ensuring that the proper bolt is inserted to the proper depth and correctly torqued.

● When the lifting fixture also serves as a shipping container or frame holding the experimental device during transport, specify tie-down requirements and other special shipping requirements to ensure the integrity of the experimental device, e.g., anticipate flexing of the truck bed, acceleration due to bumps and potholes, and/or vibration.

● Label lifting attachment points adequately to ensure proper and safe use of the fixture.

Any deviation from these rules requires equivalent alternative safety measures that have been explicitly approved by the Mechanical Engineering Department designee.

https://docs.google.com/document/u/1/d/e/2PACX-1vRWPTlfXeDq36uLYwMxWsjfCeErqdfjqpd4Ay3yBDBJuUYlHZqreaKBP-0wpgdUzWPIeeCgcf… 22/25

Single-Bolt Pickup Devices

When equipment is designed to be crane-lifted at a single point with a single-bolt pickup device, the vertical lifting load through the screw thread of the bolt must be in line with the axis of the bolt so the load will remain level when it is lifted. With this bolt alignment, the lift will be through the center of gravity and will be safer, since the load will not tilt or kick out when it is lifted. A single-bolt pickup device must be used, such as a safety hoist ring or an equivalent in-house device that is carefully designed and maintained. The threaded engagement must comply with the requirements in the Design of Lifting Fixtures section, above.

When a load…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .