This is a Lawrence Berkeley National Laboratory (Berkeley Lab) policy document establishing safety requirements and procedures for crane, hoist, and rigging operations.
The policy applies to all Berkeley Lab employees, visitors, affiliates, and subcontractors involved in crane or hoist operations. The document outlines mandatory safety protocols including hazard awareness, control methods, and proper operating procedures for equipment operators. All designated operators must be qualified and authorized to use specific equipment, and all crane, hoist, and rigging equipment must be procured through the Facilities Division or approved vendors and undergo proper inspection, testing, and maintenance. The policy excludes construction and demolition activities, which fall under the Berkeley Lab Construction Safety Program (29 CFR 1926 Subpart CC).
The document establishes eight procedural steps for crane operations: customer management evaluates lift necessity; supervisors confirm crane availability; operators verify authorization; customer management assesses lift type; supervisors and operators review mobile crane requirements if applicable; operators validate and perform inspections; operators and rigging personnel follow equipment requirements; and operators perform lifts with trained assistance. Specific roles and responsibilities are assigned to supervisors, crane managers, employees, mechanical engineering designees, responsible designers, customer management, facilities division personnel, EH&S division crane safety subject matter experts, procurement, and persons in charge. Key requirements include maintaining training and medical qualifications, possessing valid Berkeley Lab Crane Operator's Licenses, obtaining independent certification for mobile cranes exceeding two-ton capacity, and establishing engineering safety notes for high-consequence/high-value lifts exceeding $500,000 in potential damage. The policy was effective January 16, 2015, with revision history dating to 2012.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cranes, Hoists, and Rigging Safety - RPM-2 RPM-2 https://commons.lbl.gov/display/rpm2/Cranes%2C+Hoists%2C+and+Rigging+Safety[4/7/2020 5:28:48 PM]
RPM REQUIREMENTS AND
POLICIES MANUAL Search the RPM
Home View Browse
Home RPM Sections A-Z Index Glossary Contact
Home / RPM Sections / Section - Environment, Safety and Health / Policy Area - Industrial Hygiene and Safety
Cranes, Hoists, and Rigging Safety
Brief Document Information
Title: Cranes, Hoists, and Rigging Safety
Publication date: 1/16/2015
Effective date: 1/16/2015
POLICY
A. Purpose
Persons involved in crane or hoist operations at Lawrence Berkeley National Laboratory (Berkeley Lab) must:
Be aware of the hazards related to the equipment and the load
Know the methods for controlling those hazards
Follow the proper operating procedures applicable to the type of lift and equipment
The designated operator must be qualified and authorized to use specific equipment.Crane, hoist, and rigging equipment must be procured through the
Facilities Division or from a Berkeley Lab–approved vendor, as well as properly inspected, tested, and maintained.
B. Persons Affected
This policy applies to Berkeley Lab employees, casual and participating visitors, affiliates, and subcontractors who could be performing work that may include the use of cranes, hoists, and/or rigging.
C. Exceptions
Operation of cranes and rigging used in the course of construction or demolition is covered by the Berkeley Lab Construction Safety Program (Program 8.0) and is in accordance with the applicable requirements of 29 CFR 1926 Subpart CC.
D. Policy Statement
1. Customer Management evaluates the need for moving materials and determines whether a crane lift is the best option. Should a crane lift be required, review the Cranes, Hoisting, and Rigging Program, Work Process A, General Requirements for Crane Operation.
2. Supervisor determines if there is a crane available for the lift. Should a crane be needed that is not currently available, review the Cranes, Hoisting, and
Rigging Program, Work Process B, Procurement and Maintenance of Cranes and Hoisting and Rigging Equipment.
3. Operator verifies that he or she is authorized. Operators' supervisors and crane managers ensure crane operators are trained and qualified according to the Cranes, Hoisting, and Rigging Program, Work Process C, Authorization and Qualification to Use Cranes, prior to authorizing use.
Policy https://commons.lbl.gov/display/rpm2/Home https://commons.lbl.gov/display/rpm2/Home http://search.lbl.gov/ http://jobs.lbl.gov/ http://www.lbl.gov/ds/ http://www.lbl.gov/lab-index/ http://www.lbl.gov/ mailto:requirementsmgmt@lbl.gov https://commons.lbl.gov/display/rpm2/Home https://commons.lbl.gov/display/rpm2/RPM+Sections?src=breadcrumbs https://commons.lbl.gov/display/rpm2/Section+-+Environment%2C+Safety+and+Health?src=breadcrumbs https://commons.lbl.gov/display/rpm2/Policy+Area+-+Industrial+Hygiene+and+Safety?src=breadcrumbs-parent http://www.lbl.gov/ehs/pub3000/CH27.html#27.6a http://www.lbl.gov/ehs/pub3000/CH27.html#27.6a http://www.lbl.gov/ehs/pub3000/CH27.html#27.6b http://www.lbl.gov/ehs/pub3000/CH27.html#27.6b http://www.lbl.gov/ehs/pub3000/CH27.html#27.6c
4. Customer Management assesses the type of lift using the Cranes, Hoisting, and Rigging Program, Work Process D, Restricted Operations.
5. If a mobile crane will be used, supervisors and operators review the Cranes, Hoisting, and Rigging Program, Work Process E, Mobile Cranes.
6. For all lifts, regardless of crane type, operators validate and perform inspections according to the Cranes, Hoisting, and Rigging Program, Work
Process F, Crane Inspections.
7. Once all equipment has passed inspection, operators and rigging personnel follow applicable requirements in the Cranes, Hoisting, and Rigging
Program, Work Process G, Rigging and Other Below-the-Hook Devices and Fixtures.
8. Operators perform the lift as trained, with assistance from other appropriately trained personnel.
E. Roles and Responsibilities
Managers, supervisors, and employees have the responsibility to adhere to the provisions of this policy.
Role Responsibility
Supervisors and Work Leads Ensure that personnel know how to safely operate cranes and hoists, and how to move objects safely
Ensure that only formally trained and certified employees may operate a crane or hoist
Enforce the use of safe lifting techniques
Maintain lifting equipment in good mechanical and operating condition
Crane Manager
A Berkeley Lab employee must be identified as the Crane Manager for each Berkeley Lab-owned crane or hoist, unless it is locked out.
Identifies oneself, in writing, as the Crane Manager to the Environment, Health & Safety (EH&S)
Division Crane Safety Subject Matter Expert (SME) at cranesafety@lbl.gov or Mail Stop
75B0101
Possesses a valid certificate for the operation of the crane in question
Controls the use of the crane, and limits use of the crane to qualified operators
Maintains control of any keys or other mechanisms for limiting crane use
Maintains any logbooks used in lieu of inspection tags
Limits crane use to previously authorized operators
A qualified backup Crane Manager who has been identified to the Crane Safety SME may issue new crane authorizations in the absence of the Crane Manager.
Notifies the EH&S Crane Safety SME (cranesafety@lbl.gov, Mail Stop 75B0101) of any change
Employees (Operators, Riggers, and Helpers) Maintain training and medical qualification
Safely operate cranes
Possess a valid Berkeley Lab Crane Operator's License
Are certified by an independent certification agency as competent and qualified operators of mobile cranes with a greater-than-two-ton capacity
Follows all established safety regulations related to safe lifting and handling techniques
Mechanical Engineering Designee Reviews and approves Engineering Safety Notes for lifting fixtures and high-consequence/high-value lifts/moves using overhead cranes on behalf of the Engineering Division Director and for the Mechanical Engineering Subcommittee of the Safety Advisory Committee
Approves reasonable engineering alternatives not in conflict with Berkeley Lab's Environment, Safety & Health Standards Set
Furnishes guidance to Berkeley Lab staff
Responsible Designer Incorporates the requirements of the Cranes, Hoists, and Rigging Safety program into the design of lifting fixtures and procedures
Initiates the required proof testing
Obtains design approval by means of an Engineering Safety Note http://www.lbl.gov/ehs/pub3000/CH27.html#27.6d http://www.lbl.gov/ehs/pub3000/CH27.html#27.6d http://www.lbl.gov/ehs/pub3000/CH27.html#27.6e http://www.lbl.gov/ehs/pub3000/CH27.html#27.6e http://www.lbl.gov/ehs/pub3000/CH27.html#27.6f http://www.lbl.gov/ehs/pub3000/CH27.html#27.6f http://www.lbl.gov/ehs/pub3000/CH27.html#27.6f http://www.lbl.gov/ehs/pub3000/CH27.html#27.6g http://www.lbl.gov/ehs/pub3000/CH27.html#27.6g mailto:cranesafety@lbl.gov mailto:cranesafety@lbl.gov
Customer Management Defines and requests any lift/move
Determines which lifts are high-consequence/high-value lifts/moves
Writes lifting procedures where required
Provides technical information on relevant characteristics of the apparatus, including special lifting fixtures when required
Assigns someone to represent the customer during planning and coordination of all aspects of the job being performed
Provides suggestions on rigging and moving
Ensures that lifting devices and lifting fixtures are properly documented and inspected, and that they are used and maintained safely
Requests the Facilities Division to prepare the Engineering Safety Note, and to manage the move on the Work Request as needed
Facilities Division Structural Engineering Group
Designee Evaluates building floor loading, lifting fixtures, and lifting devices for structural adequacy
Reviews and approves Engineering Safety Notes for high-consequence/high-value lifts/moves using mobile cranes, forklifts, and jack and roll devices on behalf of the Facilities Division and the
Mechanical Engineering Subcommittee of the Safety Advisory Committee
Establishes design parameters for all cranes and hoists
Provides guidance on wind loading for outdoor lifts/moves
Provides Berkeley Lab staff with guidance on lift-related matters
Facilities Division Rigging Supervisor Provides guidance and supervision for routine lifts when requested
Participates in the development and review of high-consequence/high-value lifts/moves
Participates in pre-lift meetings
Facilities Division Crane Maintenance Vendor Arranges for all inspection, testing, and certification of cranes, hoists, and rigging
Arranges for the testing and certification of lifting devices and lifting fixtures
Facilities Division Maintenance Manager Establishes the scope of work for the Facilities Division Crane Maintenance Vendor
Follows technical advice from the Facilities Division Crane Maintenance Vendor to ensure that
Laboratory purchases of crane, hoist, and rigging equipment, components, and devices are traceable (through documentation) to a reputable U.S. manufacturer
EH&S Division Crane Safety SME Manages the Cranes, Hoists, and Rigging Safety program
Reviews Engineering Safety Notes for high-consequence/high-value lifts/moves
Conforms to Cranes, Hoists, and Rigging Safety program requirements
Participates in pre-lift meetings for high-consequence/high-value lifts/moves
Notifies the Facilities Division Crane Maintenance Vendor to lock all cranes and hoists that do not have an official Crane Manager
Person In Charge
The customer may be a manager, engineer, or other responsible person (other than the operator).
Handles high-consequence/high-value lifts/moves in a safe manner
Procurement Ensures that approved vendors who sell hoisting equipment ordered by divisions have provided manufacturer certification that equipment is authentic and has been load tested at 200% of rated capacity
F. Definitions/Acronyms
Term Definition
Crane A machine used for lifting and lowering a load vertically and moving it horizontally; a hoisting mechanism is an integral part of this machine
Engineering Note A detailed description of a (fixture) design that can include a detailed description of protection of the load, rigging, and method(s) of transport for a high-consequence/high-value lift
High-
Consequence/High-
Value Lift/Move
Lifts that, if failed, could:
Cause damage in excess of $500,000
Routine movements of shielding blocks by members of the professional rigging crew are excepted from this requirement.
Cause significant work delay or programmatic impact
Cause undetectable damage resulting in future operational or safety problems
Result in significant release of radioactivity or other undesirable conditions
Present a potentially unacceptable risk of personnel injury or property damage In addition, any lift/move that requires the simultaneous use of both the main and auxiliary hoists of a given crane or the simultaneous use of two cranes shall be considered a high-consequence/high-value lift/move.
Hoist A device that applies a force for lifting and lowering
Lifting Device A device used below the hoisting hook, other than slings, for attaching loads to a hoist. Such devices are arranged into four categories:
Structural and Mechanical Lifting Devices (e.g., spreader bars, plate clamps, gripping devices, etc.)
Vacuum Lifting Devices
Close Proximity Lifting Magnets
Remotely Operated Lifting Magnets
Lifting Fixture A fixture used below the hoisting hook that is designed and engineered for lifting a specific item
Mobile Crane A crane system fixed to a vehicle (typically a truck)
Overhead Crane At Berkeley Lab, a crane system fixed to a structure, including but not limited to bridge cranes, monorail cranes, gantry cranes, and jib cranes
Rigging Both the hardware and equipment used to safely attach a load to a hook or lifting device, or the method or process of safely attaching a load to a hook by means of adequately rated and properly applied slings and related hardware
G. Recordkeeping Requirements LBNL Crane Inventory
Crane Inspections
Rigging Inspections
Crane Load Testing
Crane Maintenance
Training
Medical Evaluations
Program Effectiveness Review and Assurance
H. Implementing Documents
Document number PUB-3000 reference Title Type
07.07.008.001 Chapter 27 Cranes, Hoists, and Rigging Program
07.07.008.002 Ch. 27, Work Process A General Requirements for Crane Operation Work Process
07.07.008.003 Ch. 27, Work Process B Procurement and Maintenance of Cranes and Hoisting and Rigging Equipment Work Process
07.07.008.004 Ch. 27, Work Process C Authorization and Qualification to Use Cranes, Work Process http://www.lbl.gov/ehs/pub3000/CH27-quickstart.html http://www.lbl.gov/ehs/pub3000/CH27.html#27.6a http://www.lbl.gov/ehs/pub3000/CH27.html#27.6b
Like Be the first to like this
Commons contains user-contributed content and does not represent the position or endorsement of the Laboratory, DOE, or the University of California.
Your use of this site is subject to our security and privacy policies.
A U.S. Department of Energy National Laboratory Operated by the University of California
Questions & Comments Privacy & Security Notice
07.07.008.005 Ch. 27, Work Process D Restricted Operations. Work Process
07.07.008.006 Ch. 27, Work Process E Mobile Cranes Work Process
07.07.008.007 Ch. 27, Work Process F Crane Inspections Work Process
07.07.008.008 Ch. 27, Work Process G Rigging and Other Below-the-Hook Devices and Fixtures Work Process
07.07.025.001 Forklift and Other Powered Industrial Trucks Program Program
I. Contact Information
Crane Safety Subject Matter Expert
EH&S Division
J. Revision History
Date Revision By whom Revision Description Section(s) affected Change Type
1/16/2015 1.2 M.
Wisherop
Revised to be in sync with minor changes to ES&H Manual program
A and E Minor
9/10/2013 1.1 M.
Wisherop
Reviewed 8/28/13 Contact Info, ImpDocs, SRD, Next Review date
Minor
1/2/2012 1 M.
Wisherop
Re-write for wiki all Minor
Return to top Printed or exported copies of this LBNL policy are not official.
Users are responsible for working with the latest approved revision located in the online LBNL Requirements and Policies Manual.
No labels http://www.lbl.gov/Disclaimers.html http://www.universityofcalifornia.edu/ http://www.lbl.gov/websupport.html http://www.lbl.gov/Disclaimers.html http://www.lbl.gov/ehs/pub3000/CH27.html#27.6d http://www.lbl.gov/ehs/pub3000/CH27.html#27.6e http://www.lbl.gov/ehs/pub3000/CH27.html#27.6f http://www.lbl.gov/ehs/pub3000/CH27.html#27.6g http://www.lbl.gov/ehs/html/subject_matter.shtml
| lbl.gov |
| Cranes, Hoists, and Rigging Safety - RPM-2 RPM-2 |
| MrYW5kK1JpZ2dpbmcrU2FmZXR5AA==: |
| form1: |
| searchQuery.queryString: |
| input7: |
File details come from the government source that posted it. Updated .