This is a solicitation for a cost-plus-fixed-fee completion contract to provide hardware, materials, facilities, services, labor, equipment, analyses and management activities for the preliminary design, final design, fabrication, integration and testing, delivery and post-delivery support of a Spin Eject Mechanism for NASA's Mars Sample Return Capture, Containment and Return System. The period of performance is 27 months from contract award with an anticipated award date of no later than March 2022. Offerors must submit proposals electronically by October 12, 2021 responding to the scope of work in Attachment A. The North American Industry Classification System code is 336414 and the small business size standard is 1,250 employees. The work will be performed offsite at the Contractor's facilities.
View the file
Other files for this federal contract opportunity
Show all 50
MARS SAMPLE RETURN (MSR) CAPTURE, CONTAINMENT AND RETURN SYSTEM (CCRS) EARTH ENTRY SYSTEM (EES) SPIN EJECT MECHANISM (SEM) Request for Proposals Amendment 5 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Effective Date: September 07, 202103/21/2022
Expiration Date: September 07, 202603/21/2027
Check https://ipdtdms.gsfc.nasa.gov to verify that this is the correct version prior to use
400-FORM-0002 (4/16/2014)
National Aeronautics and Space Administration
Goddard Space Flight Center Greenbelt, Maryland
MSR-CCRSMSRCCRS-ERM-SOW-0001, Revision -A
Mars Sample Return - Capture, Containment and
Return System (CCRS) Project
NASA/GSFC Code 435
Spin Eject Mechanism (SEM)
Statement of Work (SOW)
MSR-CCRS CMO (CRW)
September 07, 2021
RELEASED03/21/2022
Revision A https://ipdtdms.gsfc.nasa.gov/
MSR CCRS SEM SOW MSR-CCRSMSRCCRS-ERM-SOW-0001
Revision -A
Effective Date: 09/07/202103/21/2022 ii
Spin Eject Mechanism (SEM) Statement of Work
Signature/Approval Page Prepared by:
[signature on file]
Russell SteinCharlie Wang
CCRS Spin Eject Mechanism
RESEM
Code 544540
Reviewed by:
Chanel DuncanMatthew Magsamen
CCRS Chief Safety and Mission
Assurance Officer
Code 383
Brendan FeehanRobert
Montgomery signed 03/15/2022
CCRS Project Systems
EngineerDPM/R - Programmatics
Code 599159.9
Charles Bacon signed 03/17/2022
CCRS GSFC Flight Manager
Code 484435
Shan Butani signed
03/16/2022Russell Stein
CCRS Spin Eject Mechanism
PDLI&T
Code 540568
Approved by:
David LittmannKeith Walyus signed 03/16/2022
CCRS Deputy Project Manager
Code 435472 iii
*** Electronic signatures are available on-line at: https://ipdtdms.gsfc.nasa.gov*** iv
Preface
This document is a Mars Sample Return (MSR) Capture, Containment and Return System
(CCRS) Project configuration control board (CCB) controlled document. Changes to this document require prior approval of the CCB Chairperson or designee. Proposed changes shall be submitted in the Technical Data Management System (TDMS) via a configuration change request (CCR) along with supportive material justifying the proposed change. Changes to this document will be made by complete revision.
All of the requirements in this document assume the use of the word "shall" unless otherwise stated.
Questions or comments concerning this document should be addressed to:
CCRS Configuration Management Office
Mail Stop: 435
Goddard Space Flight Center
Greenbelt, Maryland 20771
GSFC-DL-CCRS-TDMSCM-Admin@mail.nasa.gov v
Change History Log
Revision Effective Date Description of Changes
(Reference the CCR & Approval Date)
Revision - 09/07/2021 Released per MSR-CCRSMSRCCRS-CCR-0050;
09/07/2021
Revision A 03/21/2022 Released per MSRCCRS-CCR-0081; 03/21/2022 vi
Table of TBDs/TBRs/TBSs
Action Item
No.
Location Summary Individual/
Organization
Actionee vii
Table of Contents
1 INTRODUCTION ................................................................................................................. 1-1
1.1 Scope ................................................................................................................................ 1-1
1.2 MSR CCRS Overview ..................................................................................................... 1-1
1.3 Spin Eject Mechanism ..................................................................................................... 1-2
1.4 Basic Description ............................................................................................................. 1-4
1.5 Verb Application .............................................................................................................. 1-4
1.6 Changes ............................................................................................................................ 1-4
1.7 Related Documentation .................................................................................................... 1-5
1.7.1 Applicable Documents ............................................................................................. 1-5
1.7.2 Reference Documents ............................................................................................... 1-6
1.8 Work to be Performed ...................................................................................................... 1-6
2 MANAGEMENT, REPORTING, DOCUMENTATION, AND REVIEWS ........................ 2-1
2.1 Programmatic and Technical Communications Plan ....................................................... 2-1
2.2 Program Management ...................................................................................................... 2-1
2.3 Reviews and Meetings ..................................................................................................... 2-1
2.4 Weekly Status Teleconference ......................................................................................... 2-2
2.5 Written Monthly Reports ................................................................................................. 2-2
2.6 Kickoff Meeting (KOM) .................................................................................................. 2-2
2.7 Systems Requirements Review (SRR)............................................................................. 2-3
2.8 Preliminary Design Review (PDR) .................................................................................. 2-3
2.9 Critical Design Review (CDR) ........................................................................................ 2-4
2.10 Manufacturing Readiness Review (MRR) ....................................................................... 2-5
2.11 Pre-Environmental Review (PER) ................................................................................... 2-6
2.12 Test Readiness Review (TRR) ......................................................................................... 2-6
2.13 Pre-Ship Reviews (PSR) .................................................................................................. 2-7
3 HARDWARE DELIVERABLES .......................................................................................... 3-1
3.1 Hardware Definitions ....................................................................................................... 3-1
3.1.1 Flight Model (FM) .................................................................................................... 3-1
3.1.2 Flight Spare .............................................................................................................. 3-1
3.1.3 Engineering Test Unit (ETU) ................................................................................... 3-1
3.1.4 Engineering Development Unit (EDU) .................................................................... 3-1
3.1.5 Assembly Integration & Test Model (AM) .............................................................. 3-1
3.1.6 Prototype (PT) .......................................................................................................... 3-2
3.2 Spare Parts Kit ................................................................................................................. 3-2
3.3 Ground Support Equipment (GSE) Deliverables ............................................................. 3-2
4 SCHEDULE ........................................................................................................................... 4-1
4.1 Project Schedule............................................................................................................... 4-1
4.2 Deliverable Milestones .................................................................................................... 4-1
5 MANUFACTURING REQUIREMENTS ............................................................................ 5-1
5.1 Use of Work Instructions (Travelers) .............................................................................. 5-1
5.2 Employee Training........................................................................................................... 5-1
5.3 Manufacturing Risk Mitigation........................................................................................ 5-1 viii
5.4 EEE Wire Samples ........................................................................................................... 5-2
5.5 Fastener Torqueing .......................................................................................................... 5-2
5.6 Contamination Control..................................................................................................... 5-2
6 SAFETY AND MISSION ASSURANCE ............................................................................ 6-1
7 CONTRACT DATA REQUIREMENTS LIST (CDRL) ...................................................... 7-1
7.1 Technical Compliance Matrix .......................................................................................... 7-1
7.2 Mission Assurance Compliance Matrix ........................................................................... 7-2
7.3 Contamination Control Plan ............................................................................................ 7-2
7.4 Safety and Reliability Documentation ............................................................................. 7-2
7.5 Master EEE Parts List ...................................................................................................... 7-2
7.6 Materials Identification and Usage List ........................................................................... 7-3
7.7 Stress and Mechanisms Report ........................................................................................ 7-3
7.8 Dynamic Separation Analysis Report .............................................................................. 7-3
7.9 Interface Control Document (ICD) .................................................................................. 7-4
7.10 Computer Aided Design (CAD) Electronic Model ......................................................... 7-4
7.11 Project Schedule and Monthly Report ............................................................................. 7-5
7.12 End Item Data Package .................................................................................................... 7-5
7.12.1 Certificate of Conformance ...................................................................................... 7-5
7.12.2 As-Built vs. As-Designed Parts List......................................................................... 7-6
7.12.3 As-Built Assembly Travelers, Work Instructions, and Procedures .......................... 7-6
7.12.4 Engineering Drawings .............................................................................................. 7-6
7.12.5 Material Certifications .............................................................................................. 7-6
7.12.6 Test Reports .............................................................................................................. 7-7
7.12.7 Summary of Non-conformances .............................................................................. 7-7
8 SYSTEM INTEGRATION AND TESTING ........................................................................ 8-1
8.1 Acceptance Test Procedure (ATP) ................................................................................... 8-1
8.2 Comprehensive Performance Testing (CPT) ................................................................... 8-1
8.3 Random Vibration Test .................................................................................................... 8-2
8.4 Thermal Vacuum Test...................................................................................................... 8-2
9 HARDWARE HANDLING, CLEANING, PACKING & SHIPPING ................................. 9-1
9.1 Handling & Storage ......................................................................................................... 9-1
9.2 Cleaning ........................................................................................................................... 9-1
9.3 Packing ............................................................................................................................. 9-1
9.4 Shipping ........................................................................................................................... 9-1
10 POST-DELIVERY SUPPORT ............................................................................................ 10-1 Appendix A Abbreviations and Acronyms
1 INTRODUCTION ................................................................................................................. 1-1
1.1 Scope ................................................................................................................................ 1-1
1.2 MSR CCRS Overview ..................................................................................................... 1-1
1.3 Spin Eject Mechanism ..................................................................................................... 1-2
1.4 Basic Description ............................................................................................................. 1-4
1.5 Verb Application .............................................................................................................. 1-4
1.6 Changes ............................................................................................................................ 1-4 ix
1.7 Related Documentation .................................................................................................... 1-5
1.7.1 Applicable Documents ............................................................................................. 1-5
1.7.2 Reference Documents ............................................................................................... 1-6
1.8 Work to be Performed ...................................................................................................... 1-6
2 MANAGEMENT, REPORTING, DOCUMENTATION, AND REVIEWS ........................ 2-1
2.1 Programmatic and Technical Communications Plan ....................................................... 2-1
2.2 Program Management ...................................................................................................... 2-1
2.3 Reviews and Meetings ..................................................................................................... 2-1
2.4 Weekly Status Teleconference ......................................................................................... 2-2
2.5 Written Monthly Reports ................................................................................................. 2-2
2.6 Kickoff Meeting (KOM) .................................................................................................. 2-2
2.7 Systems Requirements Review (SRR)............................................................................. 2-3
2.8 Preliminary Design Review (PDR) .................................................................................. 2-3
2.9 Critical Design Review (CDR) ........................................................................................ 2-4
2.10 Manufacturing Readiness Review (MRR) ....................................................................... 2-5
2.11 Pre-Environmental Review (PER) ................................................................................... 2-6
2.12 Test Readiness Review (TRR) ......................................................................................... 2-6
2.13 Pre-Ship Reviews (PSR) .................................................................................................. 2-7
3 HARDWARE DELIVERABLES .......................................................................................... 3-1
3.1 Hardware Definitions ....................................................................................................... 3-1
3.1.1 Flight Model (FM) .................................................................................................... 3-1
3.1.2 DELETED ................................................................................................................ 3-1
3.1.3 Engineering Test Unit (ETU) ................................................................................... 3-1
3.1.4 Engineering Development Unit (EDU) .................................................................... 3-1
3.1.5 Assembly Integration & Test Model (AM) .............................................................. 3-1
3.1.6 Prototype (PT) .......................................................................................................... 3-2
3.2 Spare Parts Kit ................................................................................................................. 3-2
3.3 Ground Support Equipment (GSE) Deliverables ............................................................. 3-2
4 SCHEDULE ........................................................................................................................... 4-1
4.1 Project Schedule............................................................................................................... 4-1
4.2 Deliverable Milestones .................................................................................................... 4-1
5 MANUFACTURING REQUIREMENTS ............................................................................ 5-1
5.1 Use of Work Instructions (Travelers) .............................................................................. 5-1
5.2 Employee Training........................................................................................................... 5-1
5.3 Manufacturing Risk Mitigation........................................................................................ 5-1
5.4 EEE Wire Samples ........................................................................................................... 5-2
5.5 Fastener Torqueing .......................................................................................................... 5-2
5.6 Contamination Control..................................................................................................... 5-2
6 SAFETY AND MISSION ASSURANCE ............................................................................ 6-1
7 CONTRACT DATA REQUIREMENTS LIST (CDRL) ...................................................... 7-1
7.1 Technical Compliance Matrix .......................................................................................... 7-1
7.2 Mission Assurance Compliance Matrix ........................................................................... 7-2
7.3 Contamination Control Plan ............................................................................................ 7-2 x
7.4 Safety and Reliability Documentation ............................................................................. 7-2
7.5 Master EEE Parts List ...................................................................................................... 7-2
7.6 Materials Identification and Usage List ........................................................................... 7-3
7.7 Stress and Mechanisms Report ........................................................................................ 7-3
7.8 Dynamic Separation Analysis Report .............................................................................. 7-3
7.9 Interface Control Document (ICD) .................................................................................. 7-4
7.10 Computer Aided Design (CAD) Electronic Model ......................................................... 7-4
7.11 Project Schedule and Monthly Report ............................................................................. 7-5
7.12 End Item Data Package .................................................................................................... 7-5
7.12.1 Certificate of Conformance ...................................................................................... 7-5
7.12.2 As-Built vs. As-Designed Parts List......................................................................... 7-6
7.12.3 As-Built Assembly Travelers, Work Instructions, and Procedures .......................... 7-6
7.12.4 Engineering Drawings .............................................................................................. 7-6
7.12.5 Material Certifications .............................................................................................. 7-6
7.12.6 Test Reports .............................................................................................................. 7-7
7.12.7 Summary of Non-conformances .............................................................................. 7-7
7.13 Thermal Analysis Report ................................................................................................. 7-7
8 SYSTEM INTEGRATION AND TESTING ........................................................................ 8-1
8.1 Acceptance Test Procedure (ATP) ................................................................................... 8-1
8.2 Comprehensive Performance Testing (CPT) ................................................................... 8-1
8.3 Random Vibration Test .................................................................................................... 8-2
8.4 Thermal Vacuum Test...................................................................................................... 8-2
9 HARDWARE HANDLING, CLEANING, PACKING & SHIPPING ................................. 9-1
9.1 Handling & Storage ......................................................................................................... 9-1
9.2 Cleaning ........................................................................................................................... 9-1
9.3 Packing ............................................................................................................................. 9-1
9.4 Shipping ........................................................................................................................... 9-1
10 POST-DELIVERY SUPPORT ............................................................................................ 10-1
Appendix A Abbreviations and Acronyms xi
List of Figures
Figure 1-1: MSR Architectural Overview .................................................................................. 1-1
Figure 1-2: CCRS Functional Description (Reference Only) ..................................................... 1-2 Figure 1-3: CCRS Architecture (Reference Only) ....................................................................... 1-3 Figure 1-4: EES Assembly Description (Reference Only) .......................................................... 1-3 Figure 1-5: EES-SEM Interface (Reference Only) ...................................................................... 1-4
List of Tables
Table 1-1: Applicable Documents .............................................................................................. 1-5 Table 1-2: Reference Documents ................................................................................................ 1-6
1-1
1 INTRODUCTION
1.1 Scope
This Statement of Work (SOW) defines the effort to be contracted in support of the Goddard Space
Flight Center (GSFC) Mars Sample Return (MSR) Capture, Containment and Return System
(CCRS) for the design, fabrication, assembly, testing, and delivery of the Spin Eject Mechanism
(SEM).
1.2 MSR CCRS Overview
MSR is an effort to bring samples of Martian rocks and soil back to Earth, where they can be investigated in unprecedented detail, using all the capabilities of terrestrial laboratories. It is part of NASA's Mars Exploration Program, a long-term effort of robotic exploration of the Red Planet.
NASA is collaborating with its various centers and the European Space Agency (ESA) to develop the advanced technologies and hardware needed for the campaign.
The sample return mission architecture is designed to continue the work begun by NASA's Mars
2020 rover. The 2020 rover will collect samples on Mars and stash them on the planet’s surface for subsequent return to Earth. A follow-on campaign will include NASA-led Sample Retrieval
Lander (SRL) that would launch the retrieved samples into Mars orbit, and an ESA-led Earth
Return Orbiter (ERO) that would rendezvous with the samples in Mars orbit and bring them back to Earth (Figure 1-1).
Figure 1-1: MSR Architectural Overview
1-2
CCRS is the payload on the ERO, shown in Figure 1-2Error! Reference source not found..
The main functions of CCRS are:
• Capture, containing and orientating the Orbiting Sample (OS)
• Transferring contained OS to the CCRS clean zone
• Performing Earth Entry System (EES) in-flight assembly
• Protect EES from micro meteoroid damage
• Precision separation of EES from ERO
• Delivery of EES with contained OS to Utah Test and Training Range (UTTR)
Figure 1-2: CCRS Functional Description (Reference Only)
1.3 Spin Eject Mechanism
The Spin Eject Mechanism (SEM) is an integral part of the CCRS. It is responsible for restraining the EES during launch, cruise, and robotic operations while in Martian orbit. To facilitate robotic operations, the SEM requires a hollow inner diameter for robotic access to install the Contained
Orbiting Sample (C-OS) SCV Lid, and EES Lid onto the EES Aeroshell. Once all these components are assembled, shown in Figure 1-4. The SEM is then responsible for restraining the
EES during transport back to Earth, and finally ejecting the EES safely back to Earth.
Images detailing the CCRS architecture are shown in Error! Reference source not found. Figure
1-3 . The SEM is part of the primary load path into the EES for all mission stages.
1-3
Figure 1-3: CCRS Architecture (Reference Only)
Figure 1-4: EES Assembly Description (Reference Only)
1-4
1.4 Basic Description
In its most basic description, the SEM can be imagined as a hollow cylinder that provides a deployable structural load path between the CCRS Structure and EES. This interface needs to be strong enough to react launch loads while also remaining separable to provide precise and controlled ejection energy into the EES during the payload ejection event to return the payload to
Earth.
Figure 1-5: EES-SEM Interface (Reference Only)
The design envelope for these components will be controlled by Mechanical Interface Control documents outlined in MSR-CCRS-ERM-SPEC-0002.
Note: Images shown in Error! Reference source not found.Figure 1-2 through Figure 1-5 are notional design concepts for reference only. These do not represent a flight proven design.
1.5 Verb Application
Statements containing the verb “shall” are binding requirements regardless of location within this
Statement of Work. The verbs “should” and “may” are used for stating non-mandatory goals or denoting a statement of best practice. The verb “will” is used in a statement of fact, expected occurrence, or declaration of purpose.
1.6 Changes
All revisions, deletions and other changes to the Statement of Work and any referenced documents must be authorized in writing by the Buyer’s Contracting Officer.
1-5
1.7 Related Documentation
The latest revision of the applicable and reference documents at the time of contract execution shall be used unless otherwise specified. In the event of a conflict between the SOW and any applicable or reference document, the contents of the SOW shall take precedence.
The contractor shall notify the Contracting Officer of any inconsistency in this contract, including all attachments and applicable documents.
1.7.1 Applicable Documents
The following documents listed in Table 1-1 shall apply to the development of the SEM in the situations where they are specifically referenced in this document.
Table 1-1: Applicable Documents
Document Number Title
MSR-CCRS-ERM-SPEC-0002
Rev. -
Earth Entry System (EES) Spin Eject Mechanism (SEM) Technical
Specification
MSR-CCRS-ERM-CDRL-0002
Rev. -
Mars Sample Return (MSR) Capture, Containment and Return System
(CCRS) Spin Eject Mechanism (SEM) Deliverable Items List and
Schedule (DILS)
MSR-CCRS-SMA-REQ-0003 Rev. - Mars Sample Return (MSR) Capture, Containment and Return System
(CCRS) Mission Assurance Requirements (MAR)
MSR-CCRS-SYS-SPEC-0004 Rev.
CCRS Mechanical and Mechanism Design Specification
MSR-CCRS-SYS-REQ-0002 CCRS Environmental Requirement Document
MSR-CCRS-SYS-SPEC-0010 CCRS Thermal Model Exchange Guidelines
540-PG-8072.1.2C Mechanical Fastener Torque Guidelines
GSFC EEE-INST-002 Instructions for EEE Parts Selection, Screening, Qualification and
Derating
NASA-STD-8739.4
Workmanship Standard for Crimping, Interconnecting Cables, Harnesses, and Wiring
IPC-J-STD-001xS Requirements for Soldered Electrical and Electronic Assemblies Space
Addendum
IEST-STD-CC1246E
Product Cleanliness Levels –Applications, Requirements, and
Determination
GSFC-STD-1000G
Goddard Space Flight Center Rules for the Design, Development, Verification, and Operation of Flight Systems (GOLD Rules)
1-6
1.7.2 Reference Documents
The following documents listed in Table 1-2 may contain information pertinent to the performance of the Contract and should be referred to for clarification purposes only. The Applicable
Documents and other Government produced contract documentation shall take precedence over the reference documentation.
Table 1-2: Reference Documents
Document Number Title
NASA-STD-5017A Revalidated w-
Change 1 Design and Development Requirements for Mechanisms
GSFC-STD-7000B
Goddard Space Flight Center General Environmental Verification
Standard (GEVS) for GSFC Flight Programs and Projects
ASTM D2240 Standard Test Method for Rubber Property—Durometer Hardness
1.8 Work to be Performed
In accordance with the requirements of this document, the contract, all associated requirements documents, and other attachments and applicable documents to this contract, the Contractor shall provide the personnel, materials, services, equipment, and facilities necessary for the successful and on-time implementation of the design, analysis, development, development test, fabrication, assembly, verification, engineering data analysis, calibration, qualification, acceptance, delivery, and post-delivery support of the SEM.
The contractor's delivered hardware and other efforts shall meet all specifications of MSR-
CCRS-ERM-SPEC-0002 and other applicable documents, including the CCRS Program Mission
Assurance Requirements (MAR), MSR-CCRS-SMA-REQ-0003, the CCRS Mechanical and
Mechanism Design Specification, MSR-CCRS-SYS-SPEC-0004 and Goddard Open Learning
Design (GOLD) Rules, GSFC-STD-1000G. The contractor shall also generate deliverable documentation and data as required by the Contract Data Requirements List (CDRL) and
Deliverable Items List and Schedule (DILS) MSR-CCRS-ERM-CDRL-0002.
2-1
2 MANAGEMENT, REPORTING, DOCUMENTATION, AND
REVIEWS
2.1 Programmatic and Technical Communications Plan
The Contractor shall establish a plan for formal transfer of information between the contractor and NASA GSFC’s programmatic and technical teams. The plan shall be approved by NASA
GSFC.
2.2 Program Management
The Contractor shall plan, develop, integrate, and execute the program management activities necessary to successfully execute the requirements of this contract. The contractor shall provide the necessary skills and staffing levels to ensure successful performance on this contract. These activities shall include, but are not limited to, program planning; detailed technical planning;
conduct of technical and program reviews; financial and technical progress reporting; financial management; purchasing and procurement of required products, services and resources;
subcontract management; configuration management; safety management; security and property management; quality management; risk management; and performance assurance.
The Contractor shall develop and submit as part of Request for Proposal (RFP) package a time phased cost plan by element of cost.
The Contractor shall notify NASA GSFC if there are changes in key personnel or resources, (supplier or sub-tier supplier) critical to the procurement of the contract item within Five (5) workdays of the occurrence.
2.3 Reviews and Meetings
The Contractor shall provide labor, facilities, equipment, materials, and data (electronic copy) to support the meetings and reviews defined in this SOW. Reviews may be conducted at NASA
GSFC, at the Contractor, or remotely via teleconference or videoconference, unless otherwise specified. Remote access shall be provided for all the reviews.
The Contractor shall provide a review agenda no less than ten (10) workdays prior to the start of the review. Advanced (draft acceptable) review packages shall be provided no less than eight (8) workdays prior to the start of the review. Data Item Deliverables (DID) shall follow the due dates required in MSR-CCRS-SMA-REQ-0003, or different due dates approved by NASA
GSFC Safety and Mission Assurance (SMA).
A final version of the presentation package shall be delivered within five (5) workdays following the review and shall include, review meeting minutes, final agenda, all required deliverable data described in each review subsection, and responses to all recommendations and action items discussed during the review. Responses to actions not able to be closed within this post-review timeframe shall be accompanied by an action closure plan with associated closure schedule.
With NASA GSFC approval, reviews may be combined and / or omitted if sufficient documentation has been supplied to meet the specific goals of the review.
2-2
The Contractor shall support CCRS system level reviews, either virtually or in person at NASA
GSFC at the Contractor’s discretion.
2.4 Weekly Status Teleconference
The Contractor shall provide an informal weekly status teleconference. This approximately one
(1) hour long meeting shall provide updates on technical (30 minutes) and programmatic (30 minutes) progress, issues, and risks.
2.5 Written Monthly Reports
The Contractor shall provide a monthly status report via email. The first report shall be delivered twenty (20) workdays after authorization to proceed is received and no later than the 15th of each month thereafter. These reports shall provide data for the assessment of technical and programmatic (i.e. cost, schedule, etc.) progress. The monthly status reports shall include:
• Current project schedule and changes from previous version
• Changes to Estimate At Completion (EAC) and monthly cost variances
• Work accomplished for current reporting period
• Action item status
• Work planned for next reporting period
• Current programmatic and technical threats (risks) and opportunities, which may impact program schedule, cost, or technical performance and proposed mitigation and corrective action
• Other information that assists NASA GSFC in evaluating technical and schedule performance
The Contractor shall provide a monthly mass report update per Section 7.11 submitted with the monthly status report.
2.6 Kickoff Meeting (KOM)
Within five (5) workdays after contract award, the Contractor shall convene a Kickoff Meeting.
The Kickoff Meeting will provide an opportunity for meet and greet and high-level discussions of design concept and milestone schedules. It may be held virtually or at NASA GSFC at the
Contractor’s discretion.
KOM may be combined with Systems Requirements Review (SRR) with NASA GSFC’s approval.
The KOM package shall cover the following at minimum:
• Review of program organizational chart including key resources and points of contact
• Review of programmatic and technical communications plan
• Employee training certification
• Review of standard operating procedures
• Review of system requirements and any open questions
• Discussion of design concepts as provided in the bid package
• Discussion of milestone schedules
2-3
• Discussion of programmatic and technical threats, opportunities, and proposed mitigations
2.7 Systems Requirements Review (SRR)
Within twenty (20) workdays after contract award, the Contractor shall convene a Systems
Requirements Review (SRR). The SRR will provide a forum for the Contractor to present the preliminary technical specification compliance matrix and solicit additional clarifications from
NASA GSFC. SRR shall be conducted in person at the Contractor’s facility with capability for remote (virtual) access.
The SRR package shall cover the following at minimum:
• Review of updates to the Technical Compliance Matrix
• Review of preliminary Mission Assurance and Safety Control Plans
• Additional clarification of requirements
• Discussion of foreseeable planned exceptions
• Discussion of design concepts (with detailed architectural block diagrams for the different deliverable units), manufacturing plans (including Materials and Processes, manufacturing flow with inspection points), integration and test plans, cleanliness plans
• Discussion of Verification Matrix/Test Plan, Including Performance Test Description (if available).
• Discussion of Flight Heritage if applicable
• Identification of trade studies
• SRR deliverables required in the MAR, MSR-CCRS-SMA-REQ-0003.
• Review and additional identification of Mandatory Inspection Points (MIPs) not specifically outlined in Section 6.
• Scheduling of milestone review (PDR, CDR, PER, PSR, etc.)
The Contractor shall plan Technical Interchange Meetings (TIMs) to resolve any TBDs/TBRs in the requirements. The TIMs shall be held at the Contractor’s location with remote access provided.
2.8 Preliminary Design Review (PDR)
A PDR shall be held at a Government approved location to review the preliminary design of each deliverable and evaluate the design for compliance with the requirements of the applicable specification document. Contractor shall hold informal Table Top reviews no later than one (1) month ahead of PDR at the grass roots level and invite GSFC technical subject matter expertise as part of the review team.
The Contractor shall build and test minimum one (1) prototype (PT) as defined in Section 3.1.6 before PDR with sufficient lead time such that the results of the testing can be incorporated into the PDR package.
The PDR package shall contain the following at minimum:
• Programmatic presentation on schedule, resources, and risk
• Preliminary deliverable design and architecture
• Review of updates to Technical Compliance Matrix
2-4
• Estimated technical parameters and comparison to requirements
• Discussion of critical trade studies, as applicable
• Preliminary Safety and Reliability Analyses
• Preliminary Master EEE Parts List
• Preliminary Materials Identification and Usage List (MIUL)
• Preliminary Stress and Mechanisms Analysis
• Preliminary Dynamics and Separation Analysis
• Preliminary Thermal Analysis
• Preliminary Engineering calculations not listed above
• Preliminary Interface Control Drawing
• Preliminary Top Assembly and Sub-Assembly Drawings
• Preliminary CAD Model in both native and STEP model formats
• Fabrication, Assembly, Integration & Test plans, including:
o Integration plans o Verification and Validation plans o Provisions for meeting cleanliness requirements o Provisions for meeting delivery dates
• Mission Assurance and Safety Control Plans
• FMECA and Hazard Analyses
• All DIDs required for PDR in the MAR, MSR-CCRS-SMA-REQ-0003.
• Identification of long-lead and / or high-risk items, to include evaluation of supply chain ability to meet production needs
• Test and analysis results and media documentation of required prototype testing
• Risk mitigation plans including, but not limited to, contingency and sparing philosophy
2.9 Critical Design Review (CDR)
A CDR shall be held at a Government approved location to review the final design of each deliverable and evaluate the design’s readiness to proceed to manufacturing. Contractor shall hold informal Table Top reviews no later than one (1) month ahead of CDR at the grass roots level and invite GSFC technical subject matter expertise as part of the review team.
The CDR package shall contain the following at minimum:
• Programmatic presentation on schedule, resources, and risk
• Final deliverable design / architecture
• Review of updates to Technical Compliance Matrix
• Final technical parameters and comparison to requirements
• Changes of any nature from the PDR
• Responses to any outstanding PDR Requests For Action (RFA)
• Results of engineering unit testing, as applicable
• Delivery of Safety and Reliability Analyses
• Delivery of Master EEE Parts List
• Delivery of Materials Identification and Usage List (MIUL)
• Delivery of Stress and Mechanisms Analysis
2-5
• Delivery of Dynamics and Separation Analysis
• Delivery of Thermal Analysis
• Delivery of Engineering calculations not listed above
• Delivery of Interface Control Drawing
• Delivery of Top Assembly and Sub-Assembly Drawings
• Delivery of CAD Model in both native and STEP model formats
• Delivery of spare parts list
• Fabrication, Assembly, Integration & Test plans, including:
o Integration plans o Verification and Validation plans o Provisions for meeting cleanliness requirements o Provisions for meeting delivery dates
• Review of assembly procedures
• A drawing tree with Configuration Management status of all detailed drawings (goal is at least 80% of drawings released into Contractor’s CM system prior to start of manufacturing)
• Review of hardware performance test procedures
• Final Mission Assurance and Safety Control Plans
• Final FMECA and Hazard Analyses
• All DIDs required for CDR in the MAR, MSR-CCRS-SMA-REQ-0003.
• Review of any outstanding impediments to expedient delivery to include evaluation of supply chain ability to meet production needs
2.10 Manufacturing Readiness Review (MRR)
An MRR may be held in conjunction with the CDR or as a separate review. The MRR shall be held at the Contractor's facility with the goal of determining whether the Contractor is ready to receive parts and commence with assembly.
The following items shall be addressed at the MRR at minimum:
• Review of updates to Technical Compliance Matrix
• Verification that all inspection equipment is within calibration date
• Inspection/evaluation of cleaning apparatus
• Evaluation of contamination control plan / review of cleaning procedures
• Verification that cleanroom and / or flowbench certifications are current
• Review of lubrication procedures
• Review of released fabrication detail and assembly drawings
• Review of released assembly work instructions and procedures
• Review of Lot and Serial control plans and procedures
• Review of non-conformance, problem, and corrective action plans and procedures
• Review of communication plan
• Review of final spare parts list
• Inspection of assembly area
• Review of schedule
2-6
• Verification that employee certifications are current and that Contractor internal MRR per Section 5.2 has been completed
• Updates to any additional MIPs
2.11 Pre-Environmental Review (PER)
A PER shall be held at a Government approved location to review the status of the program prior to start of environmental testing.
PER may be combined with Test Readiness Review (TRR) with NASA GSFC’s approval.
The PER package shall contain the following:
• Review of updates to Technical Compliance Matrix
• Changes of any nature from the CDR
• Responses to any CDR Request for Action
• Review of executed Assembly Procedures for completed hardware
• Review of as-built inspection photos for completed hardware
• Review of executed Procedures
• Review of environmental test plans:
o Vibration o Thermal Vacuum o Shock
• Environmental testing schedule
• All DIDs required for PER in the MAR, MSR-CCRS-SMA-REQ-0003.
2.12 Test Readiness Review (TRR)
The Contractor shall hold a Test Readiness Review (TRR) prior to the commencement of each test. Government concurrence of a successful TRR is required prior to the Contractor proceeding with the test. Government participation in TRRs is expected remotely via teleconference but reserves the right to attend in person.
The TRR shall verify:
• Acceptability of released test procedures and associated artifacts to be obtained for requirement compliance for the specific test under consideration
• Test facilities are functionally able to receive the hardware
• Test equipment, MGSE and EGSE is certified and calibrated, available for test duration, configured, and properly checked prior to connection to the flight hardware
• All pre-test operations are complete
• Calibration of all environmental equipment is current
• Test specification/verification documents are under configuration control and available
• Test procedure documents (if different from specification/verification) are under configuration control and available
• Necessary test personnel are appropriately trained and certified and they are available to support the test
• All associated risks and / or non-conformances have been mitigated or resolved
2-7
• Any unresolved risks and / or non-conformances shall have NASA GSFC written concurrence to proceed at-risk
• Non-conformance, anomaly, problem, and corrective action plans and procedures
At the conclusion of the TRR, all parties must provide positive concurrence the subject hardware is ready for test. The Contractor shall be responsible for managing all resources, controlling schedules, managing all engineering, manufacturing and procurement activities, configuration management, Quality/Mission Assurance, Safety, documentation control, and distribution.
2.13 Pre-Ship Reviews (PSR)
The Contractor shall hold a Pre-Ship Review (PSR) prior to delivering any hardware to NASA
GSFC. Hardware deliverables are detailed in MSR-CCRS-ERM-CDRL-0002 Table 1. The populated compliance matrix is to be presented at this review for flight deliverables. Evidence for verification of each item in the compliance matrix for which the Contractor is responsible shall be provided.
The PSR shall take place at the completion of requirement verification tests and prior to shipment of the hardware to NASA GSFC.
The Pre-Ship Review (PSR) package shall contain the following at minimum:
• Final review and approval of Technical Compliance Matrix
• Detailed review of executed environmental test procedures and associated artifacts demonstrating requirement compliance
• Witness of final pre-ship functional test execution to verify hardware functionality prior to shipment.
• A visual inspection for cosmetic defects and workmanship, and for proper marking and serialization
• Documentation of any liens, nonconformance reports, NASA GSFC Material Review
Board (MRB’s), requests for deviation, open/unresolved issues and GSFC approved plans to close/resolve the issues
• Detailed Review of the End Item Data Package (EIDP)
• All DIDs required for PSR in the MAR, MSR-CCRS-SMA-REQ-0003.
3-1
3 HARDWARE DELIVERABLES
3.1 Hardware Definitions
3.1.1 Flight Model (FM)
A Flight Model (FM) is the actual developmental end item that is intended for deployment and operations in a space environment. It is subjected to formal functional and environmental acceptance testing as described in Section 8.
3.1.2 Flight Spare
3.1.2 A Flight Spare is a fully qualified spare end item. It is subjected to the same formal functional and environmental acceptance testing as the FM.DELETED
3.1.3 Engineering Test Unit (ETU)
An Engineering Test Unit (ETU) is a full-scale, high-fidelity unit that demonstrates critical aspects of the engineering processes involved in the development of the operational FM as outlined below:
• Intended to closely resemble the FM to the maximum extent possible
• Demonstrates function, form, fit or any combination thereof at a scale that is deemed to be representative of the operation in its operational environment
• Built and tested to a full test program to establish confidence that the FM will function in the expected environments, as described in Section 8.
• Provide validation of test facilities and Ground Support Equipment (GSE) and the related procedures prior to testing the FM
• Used for functional qualification, failure survival demonstration, life testing, and parameter drift checking
• Undergo critical environmental testing to verify system performance and buy down risk for FM builds
• Used to correlate dynamic model to tested values via rigorous ground and environmental testing
3.1.4 Engineering Development Unit (EDU)
An Engineering Development Unit (EDU) is a full-scale, high-fidelity unit that demonstrates critical aspects of the engineering processes involved in the development of the operational FM similar to an ETU but does not need to undergo or survive environmental testing as is required for an ETU units, as described in Section 8.
3.1.5 Assembly Integration & Test Model (AM)
An Assembly Integration & Test Model (AM) is a full-scale simplified Structural Thermal
Model (STM). It must possess flight-like mass and thermal properties but is not required to be mechanically functional or contain any mechanized components.
3-2
3.1.6 Prototype (PT)
Prototypes (PT) are early “Proof of Concept” units intended to buy down risk for subsequent builds. Prototypes could be a scaled mockup or full-size versions of critical assemblies or sub-assemblies. Prototypes may be fabricated out of rapid prototyped parts (3D printing, plastic, or metal) and inexpensive Commercial Off-the-Shelf (COTS) components. The intent of these types of PT units are to verify and provide confidence that the overall mechanism kinematics and mechanism design is sound and robust.
3.2 Spare Parts Kit
The Contractor shall design, fabricate, test and deliver spares parts for any components that are limited life, require refurbishment by an OEM supplier, or would otherwise cause an unacceptable schedule delay if needed during the spacecraft I&T program. Examples include Hold-Down
Release Mechanism (HDRM) restraint bolts and HDRMs that require factory refurbishment or replacement.
The spare parts kit shall include enough spare parts to allow a minimum of ten (10) test deployments during the spacecraft I&T program.
A proposed spare parts list shall be provided as part of the Design Review package. NASA review and approval of this list shall be obtained prior to proceeding with manufacture as part of
MRR.
3.3 Ground Support Equipment (GSE) Deliverables
The Contractor shall identify, design, fabricate, test, and deliver Mechanical Ground Support
Equipment (MGSE) and Electrical Ground Support Equipment (EGSE) required to move/lift, transport or operate the SEM.
4-1
4 SCHEDULE
4.1 Project Schedule
The Contractor shall develop a top-level project schedule, which illustrates the…