This document is a Questions and Answers file for NASA Ames Research Center's Ames Facilities Support Services II (AFSS II) Draft Request for Proposal. The solicitation seeks a contractor to provide operations, maintenance, and repair services for the Moffett Field site, which comprises approximately 1,960 acres and includes 5 million square feet of floor space with wind tunnels, laboratories, computing facilities, offices, and complex utility systems. Key changes to the procurement include removing the Mission Suitability evaluation factor, transitioning to a two-factor best value tradeoff between Past Performance and Cost/Price, and adding a second IDIQ CLIN for Firm Fixed Price Task Orders.

The document reveals ongoing updates and revisions to the draft solicitation, with NASA releasing multiple sets of questions and answers between June and July 2025. The procurement is targeted at 8(a) certified businesses and emphasizes lowering maintenance costs through predictive testing, inspection, and condition-based maintenance techniques. NASA encourages potential offerors to comment on all aspects of the draft solicitation, including requirements, schedules, proposal instructions, and evaluation approaches. The final Request for Proposal (RFP) is expected to be posted shortly, with contractors advised to monitor sam.gov for the upcoming posting.

View the file

Other files

File Type Posted
AFSS II Questions and Answers 7_22.pdf PDF
AFSS II Questions and Answers 7_3.pdf PDF
AFSS II Questions and Answers 6_26.pdf PDF
80ARC025R0001_Ames Facilities Support Services II_Updated V2.pdf PDF
J.1(b) Attachment 5 Quality Assurance Survillence Plan.pdf PDF
80ARC025R0001_Ames Facilities Support Services II_Updated.pdf PDF
80ARC025R0001_Ames Facilities Support Services II_Final Draft.pdf PDF
J.1(a) Attachment 1 Ames Facilities Support Services II PWS.pdf PDF
J.1(a) Attachment 2 Contract Data Requirements List (CDRLs).pdf PDF
J.1(a) Attachment 4 Award Fee Evaluation Plan.pdf PDF
J.1(a) Attachment 5 Service Contract Act Wage Determination 2015-5641 Rev. 26.pdf PDF
J.1(b) Attachment 7 Contract Facilities Capital Cost of Money.pdf PDF
J.1(b) Attachment 8 Sample Case Study Attachment #1.xlsx XLSX spreadsheet
J.1(b) Attachment 11 Sample Case Study Attachment #4.pdf PDF
J.1(a) Attachment 3 Performance Requirements Summary.pdf PDF
J.1(b) Attachment 4 Past Performance Relevancy Matrix.pdf PDF
J.1(b) Attachment 9 Sample Case Study Attachment #2.pdf PDF
J.1(b) Attachment 10 Sample Case Study Attachment #3.pdf PDF
J.1(b) Attachment 12 Sample Case Study Attachment #5.pdf PDF
J.1(b) Attachment 1 AFSS II Cost_Price Template Workbook.xlsx XLSX spreadsheet
Draft Request For Proposal (DRFP) Cover Letter.pdf PDF
J.1(b) Attachment 3 Past Performance Questionnaire.pdf PDF
J.1(b) Attachment 6 Facilities Capital Cost of Money Factors CASB-CMF.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question #

Question-Please note that questions such "Can you clarify section B, clause XX, paragraph XX, etc. will not be answered. All questions shall specifically state what is it that you don’t understand about a specific area.
Response
2
Is there a page count for Mission Suitability or Case Study?
Mission suitability is no longer an evaluation factor as part of the Final RFP
3
Will there be pricing associated with the case study?
Mission suitability is no longer an evaluation factor as part of the Final RFP
48
GovWin Opportunity ID#146109 depicts the spend associated with the current contract NNA15BB23C from 2019-2024 to be ~$130M in total and average $21.7M per year.

Question: Does the Government agree this contract spend is accurate for 2019-2024?

Please note that all forecasted dollar values are estimates only and are subject to change. Please also see acquisition forecast: https://www.hq.nasa.gov/office/procurement/forecast/

74
How important is innovation and improvements?
Mission suitability is no longer an evaluation factor as part of the Final RFP therefore there is no mechanism to evaluate proposed innovations. Any improvements or innovations can be discussed with the government during contract performance.
83
The Government RFI 80ARC024R0007 - AMES Facilities Support Services II (AFSS II) asked offerors to respond to any “Challenges or opportunities exist to partner with subcontractors that employ members of underserved communities as defined in Executive Order 13985?

Question: Does the Government believe there are changes to this reference to Executive Order 13985, based on the January 20, 2025, President Donald Trump Executive Order 14151, titled "Ending Radical and Wasteful Government DEI Programs and Preferencing.”

This question references the "Summary Performance Work statement" issued December 2023. This document has been superseded by the J.1(a) Attachment 1 Ames Facilities Support Services Performance Work Statement in the AFSS II Draft RFP posted April 2025. Since that time there have been changes to various regulations and guidance from the white house. The Draft RFP was posted to sam.gov on April 3rd, 2025, and is consistent with current regulations and guidance as of that date.

101
Enhancement Proposals. Will the Government evaluate and score the Contractor Proposed Enhancements (ARC 52.227-94) separately under Mission Suitability, or are they considered as part of the baseline technical approach?
Mission suitability is no longer an evaluation factor as part of the Final RFP
109
Will the Government provide evaluation criteria for the PM and other key leadership roles, particularly regarding experience at NASA or in managing CPAF contracts?
Mission suitability is no longer an evaluation factor as part of the Final RFP
110
Will the Government provide evaluation criteria for the three (3) Offeror-identified critical positions under MA-1 Organizational Structure, particularly regarding experience at NASA or in managing CPAF contracts.
Mission suitability is no longer an evaluation factor as part of the Final RFP
114
Are there any mission-critical areas that NASA considers higher risk under this contract that the management plan should address in detail?
Mission suitability is no longer an evaluation factor as part of the Final RFP
115
Should the contractor propose a formal risk register and mitigation strategy as part of the initial proposal, or is that expected post-award?
Mission suitability is no longer an evaluation factor as part of the Final RFP
116
What level of detail does NASA expect regarding subcontractor oversight, flow down of CPAF terms, and roles/responsibilities in the management plan?
Mission suitability is no longer an evaluation factor as part of the Final RFP
117
Will the contractor be evaluated on how they manage small business or 8(a) subcontractor participation, beyond compliance with subcontracting goals?
Mission suitability is no longer an evaluation factor as part of the Final RFP
122
Section L.3 L.3(a)(1)(iii) states: "The Offeror shall describe its proposed quality control approach to ensure the accuracy and timeliness of CMMS Maximo data entry requirements, per PWS Section 7.02.b.ii." are unable to find PWS Section 7.02.b.ii. Is this a clerical error? If not, will the Government provide this section?
Mission suitability is no longer an evaluation factor as part of the Final RFP
123
Will the Government allow the use of landscaped pages sized 11"x17". If so, will such pages be counted as 1 page or 2?
The Government requires all pages to be the standard letter size of 8.5" x 11". However, using a landscaped orientation for these pages is acceptable. Pages sized 11" x 17" are not permitted.
125
Section L states: "The Offeror shall submit the information required by the Data Requirements Description (DRD No. 004), Government Property Management Information Plan." DRD No. 004 requires the submission of a complete Property Management Plan that includes Property Management (roles and responsibilities); Property outcomes (acquisition, receiving, records, physical inventory, subcontractor control, reporting, relief of stewardship responsibilities, utilization, maintenance, property closeout); All required content stated in NFS provision 1852.245-80, Government Property Information." To respond effectively to this requirement will require a substantial technical response from Offerors. Will the Government consider either excluding MA-6 from the page limitations or expand the page limitations for the Management Approach Subfactor to accommodate?
Mission suitability is no longer an evaluation factor as part of the Final RFP
128
Will NASA include any technical case study, scenario-based response, or sample task order as part of the technical volume submission?
Mission suitability is no longer an evaluation factor as part of the Final RFP
135
How will the Task Order Management Factor rate identified in PWS section 10.02.a be evaluated?
The proposed dollar value associated with the proposed management factor will be included in the total evaluated price per Section M. Additionally, Per PWS 10.02.a.i, the maximum percentage allowable for the management is factor is 5%. If any Offeror elects to propose more than 5%, the government will not adjust the percentage, or associated dollar value, downward for purposes of the calculation of the total evaluated price. However, the contractor will only be able to propose a maximum of 5% on any future FFP task order, per PWS 10.02.a.i.
163
Will the Government provide additional detail or a rubric explaining how the Case Study responses will be scored across the 600 points?
Mission suitability is no longer an evaluation factor as part of the Final RFP
164
Are specific weightings applied to technical solution, innovation, risk management, or staffing within the Case Study score?
Mission suitability is no longer an evaluation factor as part of the Final RFP
165
Should offerors assume that Maximo data provided is comprehensive, or are there known gaps/missing information we should account for?
Mission suitability is no longer an evaluation factor as part of the Final RFP
166
Will the Government evaluate our ability to analyze and draw insights from the fictitious Maximo data, or focus more on our proposed actions and technical plan?
Mission suitability is no longer an evaluation factor as part of the Final RFP
167
Are there specific performance benchmarks or historical KPIs we should compare against when analyzing the provided data?
Mission suitability is no longer an evaluation factor as part of the Final RFP
168
Will NASA provide clarification or templates for the expected structure of the RCM program narrative (e.g., subheadings or DRD-style outline)?
Mission suitability is no longer an evaluation factor as part of the Final RFP
169
Will a template or example of a completed MAXIMO asset integration be provided to guide the HVAC replacement task order portion of the response?
Mission suitability is no longer an evaluation factor as part of the Final RFP
170
For the Room 219 research mitigation scenario, can NASA confirm whether utility shutoffs are allowable during certain hours, or must all systems be continuously online 24/7?
Mission suitability is no longer an evaluation factor as part of the Final RFP
171
Can the Government clarify the expectations around use of CBM in Building 455 (e.g., is it assumed all Tier 2 systems must be monitored with CBM tech or only selected systems)?
Mission suitability is no longer an evaluation factor as part of the Final RFP
173
Is there a scoring rubric for TA-1 that NASA can release to better understand the weight of each case study element in the Mission Suitability score?
Mission suitability is no longer an evaluation factor as part of the Final RFP
174
Is the Case Study a forum to introduce proposed technical or process enhancements, or should we only respond within the constraints of the provided scenario?
Mission suitability is no longer an evaluation factor as part of the Final RFP
175
How will proposed automation, energy savings initiatives, or predictive maintenance strategies be evaluated in the context of the Case Study?
Mission suitability is no longer an evaluation factor as part of the Final RFP
176
Should the Case Study response include a risk register, schedule, or phasing plan? If so, are templates or expectations provided?
Mission suitability is no longer an evaluation factor as part of the Final RFP
177
Is there a preferred format for describing contingency plans or operational continuity strategies in response to the scenario?
Mission suitability is no longer an evaluation factor as part of the Final RFP
178
Should offerors identify which team members or subcontractors would perform specific functions in the Case Study, or keep the response anonymous?
Mission suitability is no longer an evaluation factor as part of the Final RFP
179
Will the Government evaluate how well the Case Study allocates labor categories or integrates subcontractors?
Mission suitability is no longer an evaluation factor as part of the Final RFP
180
Does the Case Study require offerors to demonstrate familiarity with NASA safety, environmental, and property control policies (e.g., NPR 8831.2, NPR 4300.1)?
Mission suitability is no longer an evaluation factor as part of the Final RFP
191
Will the contractor be required to use a NASA-approved system (e.g., NEMS, SAP) for tracking divestitures, or can we use our own as long as it meets FAR 52.245-1 standards?
Offerors are required to use the front-end tool Equipment.nasa.gov for equipment assigned to contract individuals.
244
Will the Government provide any facilities and support during transition to be used for hiring and other administrative requirements, since the incumbent will still be using the government offices?
The government may provide limited facilities and support during the phase-in period.
246
Are the rates included in the Service Contract Act Wage Determination to be taken as reference or indexed against labor categories?
Offerors shall comply with current Service Contract Labor Standards (SCLS) labor and fringe rates for those Government Provided Labor Categories that are covered by SCLS, except when the labor category is covered by the CBAs provided in this RFP. As a reminder, the SCLS labor and fringe rates establish the minimum rates that shall be proposed for SCLS labor categories, except those covered by the CBAs provided in this RFP.
255
We estimate that the information needed to respond to NFS Provision 1852.245-80, Government Property Management Information will require most if not all of the 20 pages allocated by the Government for Volume II – Mission Suitability, Management Approach Subfactor. We respectfully request that the Government exclude MA-6: Government Property Management Information Plan from page count.
See answer to question 125.
256
Under Trouble calls item 1, please clarify "roof leak needs mitigated" given that we are not to specify repair of the roof.
Mission suitability is no longer an evaluation factor as part of the Final RFP
257
Under Trouble calls item 2, please provide the KVA rating of the transformer so that we can get a sense of the likely instrumentation and protection schemes.
Mission suitability is no longer an evaluation factor as part of the Final RFP
258
The reference to 6.a to 6.g appears to be a typo.
Mission suitability is no longer an evaluation factor as part of the Final RFP
329
Due to the limited page count for the Management Approach Subfactor, will the Government exclude the response to DRD 004 Government Property Management Plan from the 20-page limitation?
Mission suitability is no longer an evaluation factor as part of the Final RFP
330
Due to the limited page count for the Management Approach Subfactor, will the Government exclude the response to DRD 013 Representation of the Limited Rights and Restricted Computer Software from the 20-page limitation?
Mission suitability is no longer an evaluation factor as part of the Final RFP

AFSS II – Questions and Answers Original Posting 7_23 Page 1 of 20

File details come from the government source that posted it. Updated .