About this file

This document outlines a federal contract opportunity for facility renovations, improvements, and repairs at the Baltimore National Cemetery. The solicitation number is 36C78622B0001 and is being issued by the Department of Veterans Affairs National Cemetery Administration. The contract involves renovations and repairs to existing facilities at the Baltimore National Cemetery, with a period of performance through 2023. Offerors are requested to submit pricing for construction and improvement services. The award date is not specified but responses are due by the listed solicitation closing date.

View the file

Other files

File Type Posted
Award Notice -Baltimore Nalt Cem- 36C78622C0019.pdf PDF
A0009 Baltimore Nalt Cem (36C78622B0001).pdf PDF
09 96 00 High Performance Epoxy Coatings (Baltimore Nalt Cem).pdf PDF
VITRUAL BID OPENING IFB (FY-22) BALTIMORE NALT CEM - PO 802CM3023 (05 Jan 2022).pdf PDF
PART 1-GENERAL (Baltimore Nalt Cem).pdf PDF
A0010 Baltimore Nalt Cem - 36C78622B0001.pdf PDF
092216 Non Structural Metal Framing (Baltimore Nalt Cem).pdf PDF
A0008 Baltimore Nalt Cem (36C78622B0001).pdf PDF
HAZMAT_Investigation_BNC_Final v2 -updated Appendix E.pdf PDF
Grille Ceilings.pdf PDF
RFI Question and Answers (Baltimore Nalt Cem) 14 Dec 2021.pdf PDF
Attachment 1 (52.228-1 Bid Guarantee).pdf PDF
A0007 Baltimore Nalt Cem - 36C78622B0001.pdf PDF
A0006 Baltimore Nalt Cem (36C78622B0001).pdf PDF
Amendment A0002 Baltimore Nalt Cem 36C78622B0001.pdf PDF
Amendment (A0005) Baltimore Nalt Cem (36C78622B0001).pdf PDF
A0004 Baltimore Nalt Cem (36C78622B0001) Vendor Portal Instructions.pdf PDF
Amendment (A0001) Baltimore Nalt Cem (36C78622B0001) 25 Oct 2021.pdf PDF
Amendment A0003 Baltimore Nalt Cem - 36C78622B0001 27 Oct 2021.pdf PDF
802CM3023 BNC Dwg BK05.pdf PDF
802CM3023 Baltimore SOW Construction.pdf PDF
COVID Safety Protocols for Federal Contractors FY-22.pdf PDF
802CM3023 BNC Dwg BK02.pdf PDF
802CM3023 BNC Dwg BK01.pdf PDF
802CM3023 BNC Specs BK02.pdf PDF
Sub-Contracting Limitation Attachment Certification.pdf PDF
802CM3023 BNC HAZARDOUS MATERIALS REPORT.pdf PDF
802CM3023 BNC Dwg BK04.pdf PDF
Sub-Contraction POLICY 819 Contractor Certification Doc.pdf PDF
Copy of IFB-Contractor Cost Estimate Worksheet Baltimore Nalt Cem.xlsx XLSX spreadsheet
DAVIS BACON WD BALTIMORE COUNTY MD.pdf PDF
802CM3023 BNC Dwg BK03.pdf PDF
802CM3023 BNC GEOTECHNICAL REPORT.pdf PDF
36C78622B0001.docx DOCX document
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Baltimore National Cemetery 5501 Frederick Avenue

Baltimore, Maryland 21228

“Facility Renovation, Improvements, and Repairs.”

VA Project Number: 802-CM3-023

Task 3 – Bid Set

July 2, 2021

U.S. Department of Veterans Affairs – North Atlantic Region

SHEET LEFT INTENTIONALLY BLANK

Baltimore National Cemetery Project 802CM3023 Facility Renovations, Improvements, Bid Set - July 2, 2021 and Repairs

SEALS PAGE 00 01 07 - 1

DOCUMENT 00 01 07 - SEALS PAGE

Lead Consultant/ Architect Architura Corporation

Sections covered by this seal include:

01 00 02, 01 32 17, 01 33 23, 01 42 19, 01 45 29, 01 57 19, 01 74 19, 02 41 10, 01 42 96, 02 82 13.13, 02 83 33.13, 03 30 53, 04 01 10, 04 05 13, 04 05 31, 04 20 00, 04 43 00, 05 10 70.63, 05 50 00, 05 51 00, 06 03 12, 06 10 00, 06 20 00, 07 13 00, 07 21 13, 07 21 23, 07 31 26, 07 60 00, 07 71 00, 07 72 00, 07 84 00, 07 92 00, 08 03 14, 08 03 52, 08 11 13, 08 14 00, 08 33 00, 08 52 00, 08 71 00, 08 80 00, 08 90 00, 09 29 00, 09 30 13, 09 65 13, 09 65 19, 09 68 00, 09 91 00, 10 14 05, 10 21 13, 10 28 00, 10 51 13, 11 17 17, 11 30 13, 12 36 00

Landscape Architect:

Pashek +MTR

Sections covered by this seal include:

10 14 00, 32 05 23, 32 12 16, 32 31 00, 32 31 13, 32 31 15, 32 33 00, 32 90 00

Civil Engineer:

KCI Technologies

Sections covered by this seal include:

02 30 00, 02 65 00, 31 20 11, and Repairs

SEALS PAGE 00 01 07 - 2

Plumbing/ Mechanical/ Electrical Engineer DAE Corporation

Sections covered by this seal include 22 05 11, 22 05 12, 22 05 19, 22 05 23, 22 11 00, 22 13 00, 22 34 00, 22 40 00, 23 05 11, 23 05 12, 23 05 41, 23 05 93, 23 07 11, 23 09 23, 23 11 23, 23 23 00, 23 31 00, 23 34 00, 23 37 00, 23 40 00, 23 55 23, 23 81 00, 23 82 16, 26 05 11, 26 05 19, 26 05 26, 26 05 33, 26 05 41, 26 24 16, 26 27 26, 26 29 11, 26 29 21, 26 51 00

ENDO OF DOCUMENT 00 01 07

and Repairs

TABLE OF CONTENTS 00 01 10 - 1

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS

00 01 07 Seals Page

00 01 10 Table of Contents

DIVISION 01 - GENERAL REQUIREMENTS

01 00 02 General Requirements (Minor NCA Projects)

01 32 17 Network Analysis Schedules (Microsoft Project Gantt

Chart)

01 33 23 Shop Drawings, Product Data, and Samples

01 42 19 Reference Standards

01 45 29 Testing Laboratory Services

01 57 19 Temporary Environmental Controls

01 74 19 Construction Waste Management

DIVISION 02 – EXISTING CONDITIONS

02 30 00 Geotechnical Report

02 41 10 Demolition and Site Clearing

02 42 96 Historic Removal and Dismantling

02 65 00 Storage Tank Removal

02 82 00 Hazardous Material Report

02 82 13.13 Glove Bag Asbestos Abatement

02 83 33.13 Lead-Based Paint Removal and Disposal

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete

DIVISION 04 – MASONRY

04 01 10 Masonry Cleaning

04 05 13 Masonry Mortaring

04 05 31 Masonry Tuck Pointing

04 20 00 Unit Masonry

04 43 00 Natural Stone Veneer

DIVISION 05 – METALS

05 10 70.63 Decorative Metal Finishing and Repairs

TABLE OF CONTENTS 00 01 10 - 2

05 50 00 Metal Fabrications

05 51 00 Metal Stairs

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

06 03 12 Historic Wood Repair

06 10 00 Rough Carpentry

06 20 00 Finish Carpentry

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 13 00 Bituminous Dampproofing

07 21 13 Thermal Insulation

07 21 23 Blown-In Insulation

07 31 26 Slate Shingles

07 60 00 Flashing and Sheet Metal

07 71 00 Roof Specialties

07 72 00 Roof Accessories

07 84 00 Firestopping

07 92 00 Joint Sealants

DIVISION 08 - OPENINGS

08 03 14 Historic Treatment of Wood Doors

08 03 52 Historic Treatment of Wood Windows

08 11 13 Hollow Metal Doors and Frames

08 14 00 Interior Wood Doors

08 33 00 Coiling Doors and Grilles

08 52 00 Wood Windows

08 71 00 Door Hardware

08 80 00 Glazing

08 90 00 Louvers and Vents

DIVISION 09 – FINISHES

09 29 00 Gypsum Board

09 30 13 Tiling

09 65 13 Resilient Base and Accessories

09 65 19 Resilient Tile Flooring

09 68 00 Carpeting

09 91 00 Painting

DIVISION 10 – SPECIALTIES

10 14 00 Exterior Signage (PMTR) and Repairs

TABLE OF CONTENTS 00 01 10 - 3

10 14 05 Interior Signage

10 21 13 Toilet Compartments

10 28 00 Toilet and Bath Accessories

10 51 13 Metal Lockers

DIVISION 11 – EQUIPMENT

11 17 17 Grave Locator Kiosk

11 30 13 Residential Appliances

DIVISION 12 – FURNISHINGS

12 36 00 Countertops

DIVISION 22 – PLUMBING (DAE)

22 05 11 Common Work Results for Plumbing

22 05 12 General Motor Requirements for Plumbing Equipment

22 05 19 Meters and Gages for Plumbing Piping

22 05 23 General-Duty Valves for Plumbing Piping

22 11 00 Facility Water Distribution

22 13 00 Facility Sanitary and Vent Piping

22 34 00 Fuel-Fired Domestic Water Heaters

22 40 00 Plumbing Fixtures

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC) (DAE)

23 05 11 Common Work Results for HVAC

23 05 12 General Motor Requirements for HVAC Equipment

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

23 05 93 Testing, Adjusting, and Balancing for HVAC

23 07 11 HVAC Insulation

23 09 23 Direct-Digital Control System for HVAC

23 11 23 Facility Natural-Gas Piping

23 23 00 Refrigerant Piping

23 31 00 HVAC Ducts and Casings

23 34 00 HVAC Fans

23 37 00 Air Outlets and Inlets

23 40 00 HVAC Air Cleaning Devices

23 55 23 Gas-Fired Radiant Heaters

23 81 00 Unitary HVAC Equipment

23 82 16 Air Coils

DIVISION 26 – ELECTRICAL (DAE)

26 05 11 Requirements for Electrical Installations

26 05 19 Low-Voltage Electrical Power Conductors and Cables and Repairs

TABLE OF CONTENTS 00 01 10 - 4

26 05 26 Grounding and Bonding for Electrical Systems

26 05 33 Raceway and Boxes for Electrical Systems

26 05 41 Underground Electrical Construction

26 24 16 Panelboards

26 27 26 Wiring Devices

26 29 11 Motor Controllers

26 29 21 Enclosed Switches and Circuit Breakers

26 51 00 Interior Lighting

DIVISION 31 – EARTHWORK (PMTR)

31 20 11 Earth Moving (Short Form)

DIVISION 32 – EXTERIOR IMPROVEMENTS (KCI/PMTR/AQUA)

32 05 23 Cement and Concrete for Exterior Improvements

32 12 16 Asphalt Paving

32 31 00 Ironwork Rehabilitation

32 31 13 Chain Link Fences and Gates

32 31 15 Wood Composite Fences and Gates

32 33 00 Site Furnishings

32 90 00 Planting

END OF DOCUMENT 00 01 10

i

SECTION 01 00 02

GENERAL REQUIREMENTS (MINOR NCA PROJECTS)

TABLE OF CONTENTS

1.1 GENERAL INTENTION

1.2 STATEMENT OF BID ITEM(S)

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.4 FIRE SAFETY

1.5 OPERATIONS AND STORAGE AREAS

1.6 ALTERATIONS

1.7 DISPOSAL AND RETENTION

1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

1.9 RESTORATION

1.10 PHYSICAL DATA

1.11 PROFESSIONAL SURVEYING SERVICES

1.12 LAYOUT OF WORK

1.13 AS-BUILT DRAWINGS

1.14 USE OF ROADWAYS

1.15 RE FIELD OFFICE

1.16 TEMPORARY TOILETS

1.17 AVAILABILITY AND USE OF UTILITY SERVICES

1.18 INSTRUCTIONS

1.19 GOVERNMENT-FURNISHED PROPERTY

1.20 CONSTRUCTION SIGN

1.21 SAFETY SIGN

1.22 CONSTRUCTION DIGITAL IMAGES

1.23 FINAL ELEVATION PHOTOGRAPHS

1.24 HISTORIC PRESERVATION

1.25 PROJECT HEALTH AND SAFETY PLAN

ii

This page intentionally blank and Repairs

GENERAL REQUIREMENTS 01 00 02 - 1

SECTION 01 00 02

GENERAL REQUIREMENTS (MINOR NCA PROJECTS)

1.1 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for

Facility Renovations, Improvements, and Repairs at Baltimore National

Cemetery as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the

Cemetery Director.

C. Offices of Architect – Engineers (A/E), may render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting

Officers Representative (COR) or his duly authorized representative.

D. All Testing Laboratory services will be retained and paid for by the

Contractor (see Spec Section 01 45 29, Testing Laboratory Services). However, the Department of Veterans Affairs may elect to retain its own Testing

Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans

Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with security requirements as established by the COR, be identified by name and employer. They shall be restricted from unauthorized access.

F. Prior to commencing work, general contractor shall provide proof that a

OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.

G. Training:

1. All employees of general contractor or subcontractors shall, at the minimum, have successfully completed the 10-hour OSHA certified

Construction Safety course and/or other relevant competency training, as approved by COR. The superintendent shall have completed the 30 hour certified Construction Safety Course and/or other relevant competency training.

and Repairs

GENERAL REQUIREMENTS 01 00 02 - 2

2. Submit OSHA training records of all employees for approval before the start of work.

1.2 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Installation of all work shown on the plans and described in the specifications including but not limited to:

All site work, temporary facilities, and building renovations as indicated in the Construction Documents

B. Bid Option No. 1: Ironwork fence rehabilitation indicated on drawings as “Bid Option 1”.

C. Bid Option No. 2: Cottage (Assistant Director’s Lodge) Repairs.

D. Bid Option No. 3: Pavement resurfacing, full depth paving, and curb replacement indicated on drawings as “Bid Option 3”.

E Bid Option No. 4: Director’s Lodge Repairs.

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. AFTER AWARD OF CONTRACT, drawings and specifications will be provided to the contractor in electronic (pdf) format.

1.4 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the site without following the procedures approved by the COR. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 3 days’ notice to the COR so that appropriate arrangements can be provided for the Cemetery employees.

This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the COR.

4. VA reserves the right to close or shut down the project site and order General Contractor’s employees off the premises in the event and Repairs

GENERAL REQUIREMENTS 01 00 02 - 3

of a national emergency. The General Contractor may return to the site only with the written approval of the COR.

C. Guards:

1. The General Contractor shall provide unarmed guards at the project site when theft or vandalism warrants.

D. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the RE/COR for the purpose of security inspections of every area of project including toolboxes and parked machines, and to take any necessary emergency action.

1.5 FIRE SAFETY

A. Applicable Publications: Publications listed below form part of this

Article to the extent referenced. Publications are referenced in text by basic designations only.

1. American Society for Testing and Materials (ASTM):

E84-2009a Surface Burning Characteristics of Building

Materials

2. National Fire Protection Association (NFPA):

10-2010 Standard for Portable Fire Extinguishers

30-2008 Flammable and Combustible Liquids Code

51B-2009 Standard for Fire Prevention During Welding, Cutting and Other Hot Work

70-2008 National Electrical Code

241-2009 Standard for Safeguarding Construction, Alteration, and Demolition Operations

3. Occupational Safety and Health Administration (OSHA):

29 CFR 1926 Safety and Health Regulations for Construction

B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to COR/Cemetery Director for review for compliance with contract requirements in accordance with

Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a safety briefing provided by the General

Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of and Repairs

GENERAL REQUIREMENTS 01 00 02 - 4

restrooms, use of NCA equipment, etc. Documentation shall be provided to the COR that individuals have undergone the

Contractor’s safety briefing.

C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police, and other emergency response forces in accordance with NFPA 241.

D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).

E. Temporary Construction Partitions:

1. Install and maintain temporary construction partitions to provide smoke-tight separations between construction areas and adjoining areas. Construct partitions of gypsum board or treated plywood

(flame spread rating of 25 or less in accordance with ASTM E84) on both sides of fire retardant treated wood or metal steel studs.

Extend the partitions through suspended ceilings to floor slab deck or roof. Seal joints and penetrations. At door openings, install

Class C, 3/4-hour fire/smoke rated doors with self-closing devices.

2. Install temporary construction partitions as shown on drawings to maintain integrity of existing exit passageways, fire-rated enclosures of hazardous areas, horizontal exits, smoke barriers, and opening enclosures.

3. Close openings in smoke barriers and fire-rated construction to maintain fire ratings. Seal penetrations with listed through-penetration firestop materials in accordance with Section 07 84 00, FIRESTOPPING.

F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.

G. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with

COR/Cemetery Director.

H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to COR.

I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA 241 and NFPA 10.

and Repairs

GENERAL REQUIREMENTS 01 00 02 - 5

J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.

K. Existing Fire Protection: Do not impair smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Request interruptions in accordance with

Article, OPERATIONS AND STORAGE AREAS, and coordinate with COR. All existing or temporary fire protection systems (fire alarms) located in construction areas shall be tested as coordinated with the Cemetery. Parameters for the testing and results of any tests performed shall be recorded by the Cemetery and copies provided to the COR.

L. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with COR.

M. Hot Work: Perform and safeguard hot work operations in accordance with

NFPA 241 and NFPA 51B. Coordinate with COR. Designate Contractor's responsible project-site fire prevention program manager to permit hot work.

Coordinate with COR.

N. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to COR.

O. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.

P. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily and site weekly.

Q. Perform other construction, alteration, and demolition operations in accordance with 29 CFR 1926.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the

RE/COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the

Contractor's performance.

B. Temporary buildings (e.g., storage trailers, office trailers) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities and Repairs

GENERAL REQUIREMENTS 01 00 02 - 6

shall remain the property of the Contractor and shall be removed by the

Contractor at its expense upon completion of the work.

C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any

Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as shown on the drawings and as determined by the COR with agreement of the

Cemetery. Contractor parking will be only in areas and on roadways designated and agreed to by the COR in agreement of the Cemetery.

E. Workmen are subject to rules of the Cemetery applicable to their conduct.

F. Execute work to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the Cemetery in quantities sufficient for not more than two workdays. Provide unobstructed access to the Cemetery areas required to remain in operation.

3. Where access by Cemetery personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Phasing: To ensure such executions, the Contractor shall furnish the

COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, the Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure and Repairs

GENERAL REQUIREMENTS 01 00 02 - 7

accomplishment of this work in successive phases mutually agreeable to the

Cemetery Director, COR, and Contractor, as shown and noted on the

Construction Staging and Sequencing Plan.

H. The Director’s Lodge will be occupied during performance of work; but immediate areas of alterations will be vacated.

1. The Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Cemetery’s operations will not be hindered. The Contractor shall permit access to Cemetery personnel through other construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by Cemetery Staff so that Cemetery operations will continue during the construction period.

2. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

I. Construction Fence: Before construction operations begin, the

Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.

Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm

(15 inches). Bottom of fences shall extend to 25mm (one inch) above grade.

The temporary fencing shall encompass the construction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site.

Remove the fence when directed by COR.

J. When a building is turned over to Contractor, Contractor shall accept entire responsibility, therefore.

1. The Contractor shall always maintain a minimum temperature of 4 degrees C (40 degrees F), except as otherwise specified.

2. The Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, the Contractor shall decide for pre-inspection of the site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from the Contractor's employee.

and Repairs

GENERAL REQUIREMENTS 01 00 02 - 8

K. Utilities Services: always Maintain existing utility services for the

Cemetery. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, sewer or air pipes, or conduits, wires, cables, etc.

of utility services or of fire protection systems and communications systems

(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the Utility Company involved.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the COR, and Cemetery Director’s prior knowledge and written approval.

2. The Contractor shall submit a request to interrupt any such services to both COR and the Cemetery Director in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. The Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Cemetery. Interruption time approved by the Cemetery and COR may occur at other than

Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but not required to be entirely removed, shall be sealed, capped, or plugged. The lines shall not be caped in finished areas, but shall be removed and sealed, capped or plugged-in ceilings, within furred spaces, in unfinished areas, or within walls and Repairs

GENERAL REQUIREMENTS 01 00 02 - 9

or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of

Cemetery traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be always open to traffic.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

O. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery

Director, through the COR, in arranging construction schedule to cause the least possible interference with Cemetery activities in actual burial areas.

Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.

1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

2. Cleaning up shall include the removal of all equipment, tools, materials, and debris and leaving the areas in a clean, neat condition.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas in which alterations occur and areas which are anticipated routes of access, and furnish a signed report, to the

Contracting Officer. This report shall list by rooms and spaces:

and Repairs

GENERAL REQUIREMENTS 01 00 02 - 10

1. Existing condition and types of resilient flooring, doors, windows, walls, and other surfaces not required to be altered throughout affected areas.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by the Contractor with new items in accordance with specifications which will be furnished by the Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE

CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report.

1. Re-survey report shall also list any damage caused by the Contractor to such flooring and other surfaces, despite protection measures;

and will form the basis for determining extent of repair work required of the Contractor to restore damage caused by the

Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

and Repairs

GENERAL REQUIREMENTS 01 00 02 - 11

3. Always protect the interior of existing structures, from damage, dust and weather inclemency. Wherever work is performed any indicated surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 ENVIRONMENTAL CONTROLS

A. In general, following preventive measures shall be adopted during construction to keep down dust and prevent mold.

1. Dampen debris to keep down dust and provide temporary construction partitions in existing structures where directed by COR. Block off ducts and diffusers to prevent circulation of dust into occupied areas during construction.

B. Vacuum and wet mop all transition areas from construction to the occupied Cemetery buildings at the end of each workday.

C. Final Cleanup:

1. Upon completion of the project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.

2. All new air ducts shall be cleaned prior to final inspection.

1.9 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Cemetery.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to and Repairs

GENERAL REQUIREMENTS 01 00 02 - 12

be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not indicated to be removed. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall employ a qualified Arborist to trim those limbs or branches with a clean cut.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the

Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the RE/COR may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils, and the environment.

Refer to Articles, "Alterations", "Restoration", and "Operations and Storage

Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Areas to be cleaned in this Project include:

1. Remove any oil residue from all walls and floor of the old oil tank room in the Administration Building. Residue collected is to be disposed in an approved manner according to the Owner.

2. Clean existing slate roof of the Cottage of any mold and debris.

Method is to be verified with Owner.

1.11 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, and Repairs

GENERAL REQUIREMENTS 01 00 02 - 13

plumbing, steam, gas, water/irrigation or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed.

Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, landscape stone, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At the Contractor's own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services, fire protection systems, communications systems (including telephone), irrigation system control, and power which are indicated on drawings and which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and

VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.12 PHYSICAL DATA

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the

Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by KCI

Technologies, Inc.

(FAR 52.236-4)

B. Subsurface conditions have been developed by core borings and test pits.

Logs of subsurface exploration conducted by John D. Haynes & Associates are shown diagrammatically on drawings.

C. A copy of the geotechnical investigation report is provided in the Project

Manual for reference only.

and Repairs

GENERAL REQUIREMENTS 01 00 02 - 14

D. The Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine the site of work and logs of borings and, after investigation, decide for themselves the character of materials and make their bids accordingly. Upon proper application to the Department of

Veterans Affairs, including approved scheduling bidders will be permitted to make subsurface explorations of their own at site.

B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration conducted by ________________ are shown diagrammatically on drawings.

C. A copy of the geotechnical investigation report is provided in the

Project Manual for reference only.

D. The Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine the site of work and logs of borings and, after investigation, decide for themselves the character of materials and make their bids accordingly. Upon proper application to the Department of Veterans

Affairs, including approved scheduling bidders will be permitted to make subsurface explorations of their own at site.

1.13 PROFESSIONAL SURVEYING SERVICES

A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.14 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and benchmarks indicated on the drawings and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at the Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The

Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the COR. The Contractor shall and Repairs

GENERAL REQUIREMENTS 01 00 02 - 15

also be responsible for maintaining and preserving all stakes and other marks established by the RE/COR until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark center lines for each building and/or addition to each existing building, lines for each gravesite control monument, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, gravesite control monuments, are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish, and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. The Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities, and other major controlling features) is placed.

D. During progress of work, the Contractor shall have lines, grades, locations and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.

E. Upon completion of the work, the Contractor shall furnish the RE/COR with reproducible drawings, in AutoCAD form, at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.

F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of

Article "Professional Surveying Services".

and Repairs

GENERAL REQUIREMENTS 01 00 02 - 16

1.15 AS-BUILT DRAWINGS

A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, which will include all contract changes, modifications, and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR's review, as often as requested.

C. The Contractor shall deliver two approved completed sets of as-built drawings to the COR within 15 calendar days after acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.16 USE OF ROADWAYS

A. For hauling, use only established public roads and designated, permanent roads on Cemetery property and, when authorized by the COR, such

Contractor constructed, temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the

Contractor at the Contractor's expense, following approved plans that include: construction, operation, maintenance and restoration. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at the time set for completion of such buildings or parts thereof.

1.17 TEMPORARY CEMETERY OFFICE TRAILER

A. The Contractor shall, within fifteen (15) days after receipt of Notice to Proceed, provide where shown on the drawings a temporary office trailer, associated steel or aluminum ADA compliant ramps and a landing where shown on drawings, and two inch deep gravel surfaced area for use of the Cemetery

Staff displaced from the existing administration building.

B. The field office shall provide not less than 136 square meters (1440 gross square feet) of floor area in one unit. Installation of the office shall meet all local codes.

C. Provide office with two, 900 mm (three foot) wide exterior doors, including hardware and OSHA approved platform and stairs leading to grade.

and Repairs

GENERAL REQUIREMENTS 01 00 02 - 17

D. Enclose the entire perimeter of the office from the floor to the ground and finish to match exterior. Provide R7 insulation and seal tight to the ground with a painted 19 mm (3/4 inch) exterior grade plywood skirt.

E. Exterior finishes shall be manufacturer's standards.

F. Provide floor, wall, and roof with not less than R5 insulation.

G. Interior finishes shall consist of resilient flooring, plywood paneling or painted wallboard on walls, and acoustical tile ceilings. Interior doors may be either painted or stained.

H. Interior shall be subdivided with full height partitions as shown on drawings. Provide each space with 900 mm (three foot) wide doors with master keyed locks.

I. Provide 750 mm (2-1/2 feet) wide by 900 mm (3 feet) high operable windows; two in each office. Provide only one 600 mm (2 foot) high window in toilet room(s). Window openings shall be fitted with security bars to prevent any forced entry. The doors of temporary office trailer shall have a hasp and padlock and also deadbolts keyed from both sides.

J. Provide sufficient fluorescent lighting in each room to deliver 325 lux

(35 foot-candles) of light at desk top height without the aid of daylight.

Provide one light switch in each room.

K. Provide one duplex receptacle in each wall of each room. If a wall is

3.0 m (10 feet) long or more, provide two receptacles for each 3.0 m (10 feet), or portion thereof, of wall.

L. The Contractor shall provide the following:

1. Electricity (200 amp, 208 volt, 1 phase), 100 gallon non-potable holding tank/shed and 200 gallon waste holding tank, and necessary utility services (except telephone).

2. All necessary piping, power circuits, network cabling, patch panels, equipment racks, cat 6e or better cabling for phones and computers, electrical fixtures, lighting, and other items necessary to provide a habitable structure for the purpose intended. Provide minimum of

12 network receptacles and 24 electrical receptacles located as approved by COR upon review of the Contractor’s submitted plan.

3. Thermostatically controlled, centralized heating and air conditioning system designed to maintain the temperature between 21 and 27 degrees C (70 and 80 degrees F) with 50 percent relative humidity maintained during the air conditioning season. Thermostats and Repairs

GENERAL REQUIREMENTS 01 00 02 - 18

shall be energy saving programmable type with a minimum of three temperature settings for each day of the week.

4. One ADA accessible water closet, lavatory, mirror, toilet paper dispenser, paper towel dispenser, soap dispenser, and two-prong coat hooks for toilet room. Provide a 6-gallon electric hot water heater connected to sinks. Provide holding tank for sanitary sewer, including periodic pumping as required

5. One (1) wall mounted first aid kit that meets or exceeds current

OSHA and AMSI Z.803-1 requirements.

6. One (1) wall mounted key safe with push-button combination lock sized for 48 keys.

7. Two (2) wall mounted 10 pound Tri-Class (ABC) dry chemical fire extinguishers.

8. The Contractor shall install a suitable security system for the temporary office trailer and provide alarm monitoring services for the duration of the Cemetery Staff’s occupancy.

M. The Contractor shall, for the duration of the Cemetery Staff's occupancy, provide the following:

1. Satisfactory conditions in and around the temporary office.

2. Maintenance of stone dust path, in an acceptable condition for foot traffic at all times.

3. Maintenance of utility services.

4. Non-Potable water, fuel and electric power for normal office uses, including lights, heating, and air conditioning.

5.Internet, Data and Voice Equipment/Connection and Communications.

Provide and install the following service to the temporary office trailer from the new tele/data room in the administration building.

a. 2 Voice lines (one dedicated phone line for FAX and internet machine and one dedicated phone line for communications)

b. 10 voice line numbers must have local area code.

c. Seven (7) desk telephones, with speaker, answering machine, and long telephone cord.

d. One (1) conference room telephone set with conference speaker(s) and extra-long telephone cord.

e. Indoor equipment: Must provide separate RJ45 connections for data communications (Cat 6 cabling) and RJ11 connections for analog voice communications in quantities specified in General and Repairs

GENERAL REQUIREMENTS 01 00 02 - 19

Requirements paragraph 1.17.L.2 above. Provide central location for termination of the Cat 6 cabling.

f. Data Connection: Provide T-1 connection lines. Methods and material shall be per ANSI/EIA/TIA-568-1991 Standard. For each office, install (2) four pair Category Cat 6 cable unshielded twisted pair (total of 8 conductors) (UTP) Category Cat 6 IEEE

802.3 100BaseT UTP Level Cat 6, 24 AWG cables. Contractor shall supply 100BaseT, Category 6 certified rack-mounted modular RJ45 punch down block/panel as required (24/48 ports) for jacks meeting the ANSI/EIA/TIA-568-A-5 category Cat 6 standards.

g. 24/7 live phone-base technical support.

h. Next business day on-site support, maintenance, and service.

N. Furnishings and equipment shall be furnished by the Cemetery and installed by Contractor. The Contractor will move the following furnishings and equipment from existing administration building.

The Contractor shall move the following items from the existing

Administration building to temporary office trailer, and back to

Administration building at the conclusion of construction. All file cabinets containing confidential material shall be shrink wrapped and moved under supervision of Cemetery staff.

2 Large filing cabinets: 2.5 feet, by 8.5 feet by 5.5 feet each.

2 Grave locator kiosks.

1 stand.

8 Filing Cabinets, 4 drawer.

9 Office Chairs.

1 Two-piece workstation with two-drawer below-mounted file cabinets.

2 – two drawer rolling file cabinets.

2 desks.

2 – 2-piece desks.

2 – three-part desks.

5 bookshelves.

1 storage cabinet.

1 small cabinet.

1 small table.

O. At the completion of all work, including the punch list, the temporary administration office trailer shall become the property of the Contractor and the Contractor shall remove same, including utility connections, from the and Repairs

GENERAL REQUIREMENTS 01 00 02 - 20

Cemetery. Furniture relocation is to be coordinated with Owner. The site shall be restored to original condition and finished in accordance with contract requirements.

P. The Contractor shall furnish floor plan including ramps and landings and sample of finishes for approval by the COR.

R. Trailer shall be anchored to resist high winds and must meet applicable

State of Maryland standards for anchoring mobile trailers.

1.18 TEMPORARY STAFF RESTROOM TRAILER (ATTACHED TO END OF ADMINSTRATION

TRAILER)

A. The Contractor shall, within fifteen (15) days after receipt of Notice to Proceed, provide…

This is the start of the file's text. The full file is on GovTribe.