Updated Price Proposal Form.pdf
PDF 202 KB Posted
- Attached to
- REHABILITATE WATERFRONT MSU USCG CLEVELAND HARBOR, CLEVELAND OH (NMACC III POOL 2 PHASE 2)
- Solicitation number
- 70Z04724RPCNI0001
About this file
This document contains a price proposal form and details of a federal contract opportunity to rehabilitate a waterfront at the US Coast Guard in Cleveland, Ohio. The price proposal form requests pricing for base and option items to design and construct new waterfront infrastructure including a bulkhead, fender system, concrete cap, utility shore ties for telecom, electrical, water and sewer, and repairs to an existing floating pier and fuel distribution system. The base item also includes site work such as pavement patching and utility work. The option item adds new pavement, signage, bollards and parking stops, and demolition of existing pavement. Offerors must hold a valid NMACC III Pool 2 Phase 1 contract and the project is available only to those contractors. The total proposed price should cover completion of the work per plans and specifications. Proposals are valid for 120 calendar days from receipt by the government.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE PROPOSAL FORM
PROJECT 5092184
TASK ORDER ANNOUNCEMENT #70Z04724RPCNI0001:
Base Item 0001: Provide all services and materials necessary to design and construct in accordance with RFP specifications and drawings to complete the design and build the project. The scope includes new waterfront infrastructure, site work, utility work, temporary facilities, demolition, etc. Work includes a new bulkhead, tieback/anchors, fender system, concrete cap, cutter utility shore ties (telecom, electrical, water, & sewer), etc. Repair the float pier and marine fuel distribution system and bilge water tank. Install news sanitary sewer lines to prevent freezing and sloped for positive flow. Site work includes pavement patching, utility work, lighting, striping, etc.
Design $ Construction $ Total $
Option Item 0001: Provide all services and materials necessary to design and construct in accordance with RFP specifications and drawings to complete the design and build project. The scope includes installing new Portland concrete pavement, striping, signage, bollards, and new concrete parking stop blocks. Demolish the existing pavement. The contractor shall perform the work in accordance with this specification and as shown on the enclosed drawing sheets.
Design $ Construction $ Total $
TOTAL PRICE
(Base Line Item 0001 + Option Item 0001): $
The TOTAL BASE AND OPTION ITEMS shall be deemed to include all costs required for the specified work to be completed in accordance with the plans and specifications.
Proposal Acceptance Period: The contractor’s proposal must indicate that it is valid for 120 calendar days from the Government’s receipt of offer.