Question Number
RFP
Reference
Page No. Paragraph Discussion/Comment/Issue Question Government Response
226 PWS 1.2.32 e 31 Would the Government consider finishing out the POs with LMCO rather than novating POs to new prime?
What happens if vendors do not agree to novations? Can the Government compel them to?
If the new prime is allowed to replace the existing PO with its own, what happens if vendors do not agree to new prime’s terms?
Can the Government confirm that the current prime will not inhibit novation or transfer of POs?
In the case of novation, how will the new prime be protected from risk of late delivery or non-delivery?
What if pricing on outstanding POs was not fair and reasonable?
Will the Government’s system indicate and the audit determine if pre-payments or progress payments were made to avoid double billing/double payments?
At what point does ownership of part transition from supplier to CBP? When it is loaded onto delivery vehicle at point of origin? When it is offloaded at CBP premises?
There will no longer be a requirement for novation. CBP is re working the PWS to identify the requirements for the successor contractor to continue repair, accept delivery of any purchases that will continue beyond the expiration date of the existing P3 contract. The PWS will be finalized in a subsequent amendment
227 General Material Management Is the contractor allowed use Canadian / International sub-contractors and suppliers? The contractor shall propose in accordance with the terms and conditions of the RFP
228 General Information Technology Can the document management system (CARMAC) be accessed outside of the US? The document management system (CARMAC) can be accessed outside of the US under the stipulation that this must only be conducted through a GFE and that inputting/processing/storing/outputting CBP information cannot be performed on non-GFE devices.
229 PWS C.1.2.16 Page 19 The Contractor shall provide maintenance, logistics and depot support to OGA’s and foreign government-owned aircraft at the direction of the Contracting Officer or the COR. Such activities entails ground handling and servicing, and will be performed with the existing workforce, and not-to-interfere with operational requirements.
US Government-owned aircraft can be supported using an ITAR exemption if the appropriate clause is included in the contract. Is the Contracting Officer willing to include an ITAR exemption export authorization clause in the contract to enable exports and imports of hardware to and from the US without a license? Are you able to identify the foreign governments so that we can evaluate which export authorizations may be required to support work on their aircraft?
No exemption clauses will be added to the RFP. The Contractor shall comply with all applicable laws and regulations regarding export-controlled items, including, but not limited to, the requirement for contractors to register with the Department of State in accordance with the ITAR.
Contractors are required to flow down this requirement to their subcontractors.
We are not able to identify foreign governments at this time
230 RFP Section L.4.3.2.e;
Q&A #7, #74, #100, #164
Q&A identifies 10 key positions. RFP Section L.4.3.2.e lists only 8 (missing Depot Manager and Depot Engineer).
Please clarify the list of key personnel for whom resumes are required. CBP has updated L.4.3.2e to add the missing Key Personnel (Depot Manager, Depot Engineer)
231 (1) RFP Section L.4.3.2.e;
(2) RFP Section L.4.3.2.f;
(3) PWS Section C.1.2.24(b)
Ref (1) has clarified the list of resumes of key personnel to be provided in the written volume, IAW the Q&A. Ref (2) refers to the key positions identified in Section C.1.2.24. The list of key personnel identified in Ref
(1) differs significantly from the list of key personnel identified in PWS Section C.1.2.24.
Please clarify. RFP Section L identifies the requirement for key personnel resumes only.
PWS C.1.2.24 identifies the full list of key personnel. The subsequent contractor will be required to comply with the PWS
232 Section L.15.4 Proposal Structure and L.15.4.3 Staffing Plan
Under proposal structure (page 62 of 84) instructions require resumes in the Transition Plan; in the Staffing Plan (page 71 of 84) resumes are required in the Staffing Plan.
Please clarify in which section resumes are required. Resumes are required in the Staffing Plan.
233 PWS C.1.2.9, PWS
C.1.2.9.1 and PWS C.1.2.11
The PWS numbering goes from C.1.2.9.1 to C.1.2.11. Please confirm there is no C.1.2.10, per Answers to Questions # 184. Ref Q&A Response number 184
234 PWS C.1.5.9; PWS
C.1.6.10
Page 54 The PWS numbering goes from C.1.5.9 to C.1.6.10 without other numbering in between.
Please confirm that C.1.6.10 should read 1.5.10. The PWS has been updated to change C.1.6.10 to C.1.6
235 Ref: Questions 16, 44, 87, and 186
The responses to these questions mention updates to appendices that were included in the file named J-7_Appendices__CDRLs_FINAL in the initial release. However, the amendment posting does not include an update to this file.
Will the Government provide the updated appendices? Updated Appendix was inadvertently omitted. Now included
236 Answers to questions #173 and PWS C.1.1.2
What is the process for entering the country when subject to the Chief of Mission Authority (COM)?
This information will not be publicly released
237 Answers to questions #173 and PWS C.1.1.2
What is the process for entering the country when subject to the Memorandum of Agreements (MOA)?
This information will not be publicly released
238 Answers to questions #173 and PWS C.1.1.2
Can the customer provide a copy of the MOA(s)? No
239 Answers to questions #173 and PWS C.1.1.2
Which locations are subject to the COM? And which locations are subject to the MOA(s)? This information will not be publicly released
Q&A 69, 99, 125
In the PDF question and answer document posted by the Government, these question numbers (69, 99, 125) were missing.
Please provide the questions and answers or confirm that the numbers were omitted. The numbers were omitted
L.4.0
Page 62 Our slide deck is 50MB in PowerPoint MS Office 2010 format.
Will the Government's email account accept files of that size? If not, will the Government allow us to submit slides in PDF format, at approximately 1/10 the size?
CBP email will not accept 50MB attachment. The Power Point requirement remains. Please zip the file to under 20MB. You are allowed to submit multiple emails if necessary. If you submit multiple emails please label each email 1 of X, 2 of X, etc
L.4.1 Page 63
Under Proposal Timeline, the Amendment 1 RFP instructions state, "Offerors’ Notification of Intent to participate in oral presentations due > 5 business days after CBP’s response to offerors’ questions are posted on FBO."
Given the inconsistencies remaining between Amendment 1 and the PWS (such as the Key Personnel requirement changed in RFP Section L but not the PWS), we ask the Government to resolve those inconsistencies in Amendment 2, and make the determination that the 5-day period begins at the time the Government posts answers to Questions 225-229 and to clarifying questions as Amendment 2.
There will be no change to the deadline for notification of participating in oral presentations
E.1; C.1.2.7
RFP 23; PWS 12 81, 158
The RFP Amendment 1 (E.1 52-252-2) states QA will comply with at a minimum AS9100C, while the Amendment 1 PWS (C.1.2.7) says, "The Contractor’s Quality Management System shall be certified AS9100 Rev D". Answers to questions 81 and 158 also appear to conflict.
Which certification is required? AS9100D is required. Clause E.6 52.246-11 has been updated.
PWS C.1.1.4, Q&A #80
8 In the answer to Question 80, the Government states, "Depot personnel are required to have repairman certificate in their area of expertise."
This conflicts with the FAA directive as follows: 14 CFR Part 145 certificated processes and procedures to deliver safe, quality aircraft maintenance depot services allows for a combination of FAA Licensed, Repairman Certificated and experienced maintenance personnel. FAA mandated oversight of all work and process ensures that all relevant quality and continued airworthiness requirements are met.
Will the Government please revise the requirement to cite compliance with the FAA directive.
The response to the Questions was related to a FAA Repair station. CBP does not require a Repairman certification at the Depot.
245 PWS In the answer to Question 225, the Government states, "The PWS has been revised to remove "COMPETITION SENSITIVE FOUO" from the footer.", however; the PWS still reflects COMPETITION SENSITIVE FOUO in the footer.
Will the Governemnt revise the PWS in another amendment? PWS was updated. Reposted with Amendment A0002
246 RFP H.3
PWS 1.2.28
MD 11055 is cited in both the RFP and PWS and establishes security procedures for the program, however, it is not available on the dhs.gov website. A copy of MD 11055 is requested.
Upon further review MD 11055 is no longer valid and has been removed from the Security Procedures clause and the PWS. H.3 SECURITY PROCEDURES (OCT 2009) is hereby replaced with H.3 SECURITY PROCEDURES (APR 2019). The PWS has been revised in accordance with H.3 dated Apr 2019