This is an amendment summary to a Request for Proposals (RFP) for a Design-Build construction IDIQ contract issued by the Department of Homeland Security's U.S. Customs and Border Protection (CBP). Amendment A005, issued January 28, 2026, clarifies six key requirements: (1) Small Business Subcontracting plans and goals should be based on the $2B IDIQ Level with vendors responsible for submitting their own socioeconomic category goals without a mandated template; (2) offerors may use overall industry experience to satisfy the ten-year experience requirement rather than detailed, role-specific project experience; (3) only new vertical construction projects are acceptable, with renovation projects excluded; (4) offerors may submit design-bid-build projects provided they also include at least two design-build projects to meet minimum requirements; and (5) there are only six evaluation factors. The Phase 1B response deadline of January 30, 2026 at 1:00 PM ET remains firm, with all other provisions, terms, and conditions unchanged.
The underlying RFP seeks to establish multiple Indefinite Delivery/Indefinite Quantity (IDIQ) contracts for a five-year term to design and construct CBP facilities including checkpoints, sector headquarters, border patrol stations, and air facilities throughout the United States. The procurement uses a Design-Build selection process and is structured in multiple phases, with Phase 1A responses due January 19, 2026 at 5:00 PM ET and Phase 1B responses due January 30, 2026 at 1:00 PM ET. Technical inquiries should be directed to Sai.P.Velaga@cbp.dhs.gov or Gary.R.Robertson@cbp.dhs.gov, with no phone calls accepted.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CBP RFP 70B01C26R0000000007 - Amendment A008.pdf | ||
| CBP RFP 70B01C26R0000000007 - Amendment A007.pdf | ||
| Attachment B - D-B Construction Recommendations SOW 2.20.26.pdf | ||
| CBP RFP 70B01C26R00000007 - Amendment A006.pdf | ||
| CBP RFP 70B01C26R00000007 Amendment A004.pdf | ||
| RFP 70B01C26R00000007 A004 Summary.docx | DOCX document | |
| RFP 70B01C26R00000007 A003 Amendment.pdf | ||
| CBP RFP 70B01C26R00000007 Amendment A0002.pdf | ||
| Solicitation 70B01C26R00000007 Amendment 0002 Summarized.docx | DOCX document | |
| Solicitation 70B01C26R00000007 Amendment 0001 Summarized.docx | DOCX document | |
| CBP RFP 70B01C26R00000007 _ Amendment A0001.pdf | ||
| Attachment A Statement of Work Construction IDIQ.pdf | ||
| CBP RPF 70B01C26R00000007 Design Build Construction IDIQ.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
70B01C26R00000007, Amendment A005
Solicitation Number: 70B01C26R00000007 Date: January 28, 2026 Amendment Number: A005
Summary:
This Amendment A005 is issued to clarify the following:
1. The Small Business Subcontracting plan and goals should be based off IDIQ Level valued at $2B and there is no template for how the Small Business Subcontracting Plan should be presented.
2. Vendors are responsible for submitting their own subcontracting goals per socioeconomic category.
3. Offerors may use overall industry experience to meet the ten-year requirement; detailed, role-specific project experience is not required.
4. Only new vertical construction projects will be accepted; renovation projects are not included.
5. Offerors may submit design-bid-build projects as long as they also provide at least two design-build projects for the minimum requirement.
6. There are only 6 evaluation factors.
January 30, 2026 due date for Phase 1B responses remains firm and All other provisions, terms and conditions remain unchanged.