This document is a pre-solicitation questions and answers file for Solicitation Number 70B01C25R00000038, related to Tactical Infrastructure (TI) Maintenance for U.S. Customs and Border Protection. The file clarifies key details about the upcoming Request for Proposal (RFP), specifically addressing four main points: (1) no solicitation submittals are currently being accepted, (2) the solicitation remains in draft form with the final RFP not yet published, (3) Phase 1 phone interviews will be scheduled after the final RFP release, and (4) no additional site visits will be conducted. The solicitation covers maintenance requirements for tactical infrastructure along the international border in the Del Rio/Big Bend South, Laredo, and Rio Grande Valley Sectors, with an anticipated performance period of one base year and four potential one-year option periods under a firm-fixed price contract.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
70B01C25R00000038 Pre- Solicitation Questions
1. Q: It is understood that the full RFP has not yet been released, but to clarify -should Factor 1 – Experience be submitted during the pre solicitation phase or should offerors wait until the RFP is officially issued?
A: No solicitation submittals are being accepted at this time. Offerors shall wait to submit any proposal until after the official RFP has been released.
2. Q: Is this solicitation still in draft form or is the solicitation final with all the applicable due dates in place? The document titled 01C25R0038 Pre-Solicitation Questions that was posted to SAM.gov states the full RFP has not been published yet.
A. The solicitation is still in draft form and the final RFP has not been published.
3. Q: When should offerors request to schedule a Phase 1 phone interview? Does this occur now during the pre-solicitation phase or when the final RFP is released?
A: Phone interviews will be scheduled after release of the final RFP
4. Q: Will another site visit be held?
A. No, another site visit will not be scheduled.
File details come from the government source that posted it. Updated .