01C25R0038 Pre-Soliciation Questions_05072025.pdf
PDF 87 KB Posted
- Solicitation number
- 70B01C25R00000038
About this file
This document contains pre-solicitation questions and answers for Solicitation Number 70B01C25R00000038, a U.S. Customs and Border Protection opportunity for Tactical Infrastructure (TI) Maintenance. The Q&A clarifies that the solicitation is currently in draft form, and no proposals should be submitted at this time. Potential offerors are instructed to wait until the official Request for Proposal (RFP) is released before taking any action, including submitting Factor 1 - Experience or scheduling Phase 1 phone interviews. The solicitation covers maintenance requirements for tactical infrastructure along the international border in the Del Rio/Big Bend South, Laredo, and Rio Grande Valley Sectors, with an anticipated performance period of one base year and four potential one-year option periods.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
70B01C25R00000038 Pre- Solicitation Questions
1. Q: It is understood that the full RFP has not yet been released, but to clarify -should Factor 1 – Experience be submitted during the pre solicitation phase or should offerors wait until the RFP is officially issued?
A: No solicitation submittals are being accepted at this time. Offerors shall wait to submit any proposal until after the official RFP has been released.
2. Q: Is this solicitation still in draft form or is the solicitation final with all the applicable due dates in place? The document titled 01C25R0038 Pre-Solicitation Questions that was posted to SAM.gov states the full RFP has not been published yet.
A. The solicitation is still in draft form and the final RFP has not been published.
3. Q: When should offerors request to schedule a Phase 1 phone interview? Does this occur now during the pre-solicitation phase or when the final RFP is released?
A: Phone interviews will be scheduled after release of the final RFP.
File details come from the government source that posted it. Updated .