7-4. IFB 044-26-RM SPECIAL PROVISIONS.docx

DOCX document 18 KB Posted

Attached to
Pump Station 92 Replacement
Solicitation number
IFB-044-26-RM
Issued by
Leon County, Florida

About this file

This is a Special Provisions document for an Invitation for Bid (IFB 044-26-RM) issued by the City of Tallahassee, Florida, for the Pump Station 92 Replacement project located at 6636 Buck Lake Rd. The project involves constructing a new quadruplex submersible pump station with an above-ground valve array to replace the existing pump station while maintaining operational continuity. The scope encompasses deep foundations (micropiles), grading, clearing, stormwater retention area construction, driveway demolition and replacement, fencing modifications, landscaping, gravity and force main sanitary sewer piping with manholes, by-pass pumping, erosion control, electrical and water service installation, generator installation, electrical/motor control equipment array and shade structure, demolition and decommissioning of the existing station, sheeting and shoring, dewatering, and production of as-built and record drawings. A mandatory pre-bid meeting is scheduled for March 16, 2026, at 2:00 PM EST via Microsoft Teams.

The project is subject to multiple permits, including Leon County Environmental Management Permit (Appendix A, LEM25015), FDEP General Permit for Constructing a Domestic Wastewater Collection/Transmission System (Appendix B, 0464185-001-DWC/CG), and Leon County ROW Permit (Appendix C, pending). Bidders must examine all permit conditions and assume all associated costs with no claims for delays or unanticipated work. Contractors are solely responsible for securing and managing offsite staging areas, which require pre-approval from the City's Growth Management Department. Construction operations are limited to 8:30 AM to 7:00 PM Monday through Saturday, with no work permitted on Sundays or Saturdays if construction would disrupt water, sewer, gas, or electric services. The City reserves the right to further restrict work hours without providing additional compensation, though contractors may receive time extensions for City-imposed restrictions. Pre-construction photographs of deficient areas must be documented by the contractor to avoid bearing restoration costs.

View the file

Other files

File Type Posted
19-APPENDIX B - Pump Station 92 Replacement - FDEP Permit (0464185-001-DWC-CG).pdf PDF
6-3. IFB 044-26-RM SUPPLEMENTAL SPECIFICATIONS.pdf PDF
14-14. REQUIRED HUMAN TRAFFICKING AFFIDAVIT.pdf PDF
20-APPENDIX D - Pump Station 92 Supplemental Technical Specifications - 2026.02.11.pdf PDF
5-2. IFB 044-26-RM GENERAL PROVISIONSONS.pdf PDF
21-APPENDIX E - Pump Station 92 Report of Geotechnical Investigation (2026-02-10).pdf PDF
2-7. REQUIRED BID SCHEDULE.pdf PDF
12-12. REQUIRED IFB Representations Certifications.docx DOCX document
10-10. REQUIRED Vendor Conflict of Interest.docx DOCX document
18-APPENDIX A - Pump Station 92 Replacement - LC EMP (LEM25015).pdf PDF
8-5. IFB 044-26-RM SUPPLEMENTAL INFORMATION.docx DOCX document
13-13. DRAFT CONTRACT CONSTRUCTION (from IFB) 1.2024.doc DOC document
15-15 REQUIRED Responsible Vendor Review Form.docx DOCX document
11-11. REQUIRED Non Collusion Affidavit of Respondent.docx DOCX document
3-9. REQUIRED OEV FORMS ITB MWBE Forms Updated 10.06.22.docx DOCX document
1-1. REQUIRED IFB SECTIONS 123.docx DOCX document
17-18. BID SCHEDULRE EXELL .xlsx XLSX spreadsheet
22-APPENDIX F - Pump Station 92 SUE Test Hole Report (4-11-2025).pdf PDF
16-17. REQUIRED Certification of a Drug Free Workplace (1).pdf PDF
4-8. REQUIRED PERFORMANCE BOND BID BOND TRENCH SAFETY FORMS.docx DOCX document
9-6. IFB 044-26-RM PLANS - 2026.02.24 SS.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROVISIONS

I. PERMITS

The following permit(s) have been secured by the City (unless otherwise noted) and apply to this Contract.

1. NPDES Permit (Not Required, Not Provided by COT).

2. Leon County Environmental Management Permit (EMP), (Appendix A, LEM25015)

3. FDEP General Permit for Constructing a Domestic Wastewater Collection/Transmission System, (Appendix B, 0464185-001-DWC/CG)

4. Leon County ROW Permit, (Appendix C, Permit Pending)

Bidders shall examine the permits, review and understand all permit conditions, and abide by same during execution of the work, and anticipate all costs associated with doing so. No claims for project delays or unanticipated work associated with those tasks will be considered.

In addition to the permit conditions, bidders are advised that the Contractor will be solely responsible for determining what, if any, offsite staging areas will be used, and shall be responsible to the owner of such areas regarding leasing, restoration, traffic control, etc. All staging areas to be used must be pre-approved by the City’s Growth Management Department prior to their use.

The Contractor shall abide by these requirements before final payment will be released. Photographs of deficient areas existing prior to construction shall be produced by the Contractor to document such deficiencies. Otherwise, the Contractor may be required to correct such deficiencies as part of the restoration work at no extra cost to the City.

Appendices A-C on Bonfire

II. SUPPLEMENTAL TECHNICAL SPECIFICATIONS

The attached “Supplemental Technical Specifications for PS #92 Replacement” shall be used in conjunction with the City of Tallahassee Technical Specifications for Water and Sewer Construction (Latest Edition) and shall be considered the governing specifications for the work of this contract. For items of work not addressed by these specifications, the FDOT Stand Specifications or City of Tallahassee Supplemental Specifications shall govern, as noted in the Contract documents and as applicable.

1. Electrical Specifications for Pump Station 182 Redundant Power (Appendix D)

Appendix D on Bonfire

III. PROSECUTION AND PROGRESS

Subarticle 8-3.4 of the Standard Specifications is expanded by the following:

All construction operations shall be scheduled to begin no earlier than 8:30 am and to end no later than 7:00 pm Monday through Saturday. No construction operations are to be scheduled on Sundays. No construction operations are to be scheduled on Saturdays if construction would cause a disturbance to water, sewer, gas, or electric services.

The City reserves the right to limit the Contractor’s work and/or lane closure hours at any time during the project duration from those hours identified within these documents. The Contractor agrees to make no claim for additional compensation as a result of this decision by the City. However, the Contractor may be entitled to an extension of time for such acts by the City, only for the number of days which the City determines to be due to such acts.