This document is an amendment to a federal solicitation issued by the Department of Transportation Federal Aviation Administration Franchise Acquisition Services for the VTD Upgrades project. The purpose of the amendment is to extend the proposal due date to July 5, 2024 at 1700 Oklahoma Time in order to allow time for questions to be answered.

The solicitation is for upgrades to the heating, ventilating, and air-conditioning (HVAC) systems in the VTD facility at the Mike Monroney Aeronautical Center in Oklahoma City, OK. The work includes replacing two 100-ton air-cooled chillers, two constant volume primary chilled water pumps, two variable flow secondary chilled water pumps, two variable air volume air handling units, two computer room air-conditioning units, and updating the existing energy management control system. The contractor shall provide all labor, materials, and equipment required for the work. Proposals must be submitted by the revised due date to the Contracting Officer, Elizabeth Fikes.

View the file

Other files for this federal contract opportunity

Other files attached to VTD Upgrades, newest first.
File Type Posted
6973GH-24-R-00121-00005.pdf PDF
10. Past Performance Survey-7.12.24.docx DOCX document
18.MMAC VTP Storefront Substitution Request [17677]-SA_AAN.pdf PDF
17. Submittal24-33387-0-581343-SA_APP_LDG.pdf PDF
15. Questions and Answers _7.12.24_6973GH-24-R-00121_VTD.pdf PDF
6973GH-24-R-00121-0004.pdf PDF
6-18-24 SIGN-IN SHEET - VTD SITE VISIT - ROOF.pdf PDF
6973GH-24-R-00121-0002.pdf PDF
LIST OF ATTENDEES _PRE-BID SITE VISIT 6-6-24 19-035903 VTD UPGRADEs.pdf PDF
10. Past Performance Survey-6.6.24.docx DOCX document
6973GH-24-R-00121-0001.pdf PDF
6973GH-24-R-00121.pdf PDF
1. Section B - Supplies or Services-Prices.xlsx XLSX spreadsheet
2. SOW 19-035903 VTD Upgrade 5-18-24.pdf PDF
9. Past Performance Experience Information Form.docx DOCX document
10. Past Performance Survey.docx DOCX document
14. Contractor Release.pdf PDF
4. 19-035903_VTD Upgrades-100%Type B Specifications_240402_REV.pdf PDF
3. 19-035903_VTD Upgrades-100%Type B Drawings_240402_REV.pdf PDF
5. Construction Schedule - 19-035903.pdf PDF
6. AMP400 OC Construction contractors combined.pdf PDF
12. SF 25 Performance Bond.pdf PDF
7. Attachment F-4.pdf PDF
8. Client Authorization Letter.docx DOCX document
11. Wage Determination OK20240049.pdf PDF
13. SF 25A Payment Bond.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LIST OF CHANGES:

The purpose of Amendment 0003 is to extend the proposal due date to allow questions submitted to be answered.

1. The proposal due date is extended to July 5, 2024 at 1700 Oklahoma Time.

END OF AMENDMENT 0003