5. Construction Schedule - 19-035903.pdf

PDF 59 KB Posted

Attached to
VTD Upgrades
Solicitation number
6973GH-24-R-00121
Issued by

About this file

This document is a Construction Schedule for the VTD Upgrades federal contract opportunity. It outlines the key dates and activities for the project, which includes upgrading the HVAC systems, replacing the emergency generator, and updating the building controls and testing and balancing in the VTD facility at the Mike Monroney Aeronautical Center in Oklahoma City, OK.

The construction schedule shows key milestones such as the anticipated contract award and notice to proceed in August 2024, followed by submittals in September 2024, material ordering in October 2024, and the major construction work occurring from October 2024 through mid-January 2026. The work includes site preparation, installation, and commissioning, with various spaces throughout the building impacted at different times, including a full building shutdown. The solicitation number for this opportunity is 6973GH-24-R-00121, and it is being issued by the Department of Transportation Federal Aviation Administration Franchise Acquisition Services.

View the file

Other files

File Type Posted
18.MMAC VTP Storefront Substitution Request [17677]-SA_AAN.pdf PDF
17. Submittal24-33387-0-581343-SA_APP_LDG.pdf PDF
6973GH-24-R-00121-00005.pdf PDF
10. Past Performance Survey-7.12.24.docx DOCX document
15. Questions and Answers _7.12.24_6973GH-24-R-00121_VTD.pdf PDF
6973GH-24-R-00121-0004.pdf PDF
6973GH-24-R-00121-0003.pdf PDF
6-18-24 SIGN-IN SHEET - VTD SITE VISIT - ROOF.pdf PDF
6973GH-24-R-00121-0002.pdf PDF
LIST OF ATTENDEES _PRE-BID SITE VISIT 6-6-24 19-035903 VTD UPGRADEs.pdf PDF
6973GH-24-R-00121-0001.pdf PDF
10. Past Performance Survey-6.6.24.docx DOCX document
4. 19-035903_VTD Upgrades-100%Type B Specifications_240402_REV.pdf PDF
6973GH-24-R-00121.pdf PDF
14. Contractor Release.pdf PDF
9. Past Performance Experience Information Form.docx DOCX document
3. 19-035903_VTD Upgrades-100%Type B Drawings_240402_REV.pdf PDF
6. AMP400 OC Construction contractors combined.pdf PDF
12. SF 25 Performance Bond.pdf PDF
2. SOW 19-035903 VTD Upgrade 5-18-24.pdf PDF
10. Past Performance Survey.docx DOCX document
1. Section B - Supplies or Services-Prices.xlsx XLSX spreadsheet
11. Wage Determination OK20240049.pdf PDF
13. SF 25A Payment Bond.pdf PDF
7. Attachment F-4.pdf PDF
8. Client Authorization Letter.docx DOCX document
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Dates August 1, 2024

Submittals Sept. 2024

Order Materials Oct. 2024

Oct 2024 - Nov. 2025

Emergency Generator Site Prep + Installation Oct 2024 - Nov. 2025

Oct 2024 - Nov. 2025

Dec. 2024 - Mid Jan 2026

Various spaces throughout building for controls Jan - Feb 2026

Various spaces throughout building for TAB Jan - Feb 2026

Jan - Feb 2026

Legend

Work offsite, No impact to VTD

Night and Weekend Work

Whole Building Shut Down

VTD Upgrades WO 19-035903

Activity

Various spaces throughout building for Commissioning

Inside Work in Preparation to Whole Building Shutdown

Outside Drainage and Utility Work

Whole Building Shut Down

Anticipated Contract Award, NTP Issued