This document provides details for a sealed bid solicitation for bridge preventative maintenance repairs on the Natchez Trace Parkway. The project consists of repairs to deteriorated expansion joints, asphalt pavement crack cleaning and sealing, concrete repairs, and other miscellaneous work, split into multiple schedules and contract options with a total expected cost between $500,000 and $1,000,000. Bids are due from certified Small Business Concerns by the date specified on the SF1442. Interested vendors must register and monitor the Federal Business Opportunities website for bid documents and updates. Annual Representations and Certifications must be completed in SAM, and the Vets-4212 form filled out online prior to award. Questions should be sent by email with the solicitation and project details to the provided email address.
Bid opening date is scheduled for November 21, 2019 at 2:00 p.m. EST.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Results of Bid Opening - NATR BMS FY19(1).pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document | |
| 5570-503P4583.pdf | ||
| 5570-135P2750.pdf | ||
| 5570-471P13750.pdf | ||
| 5570-499P1528.pdf | ||
| Plans_-_NP-NATR_BMS_FY19(1).pdf | ||
| 5570-484P3438.pdf | ||
| 5570-501P13750.pdf | ||
| 5570-474P3438.pdf | ||
| 5570-502P6875.pdf | ||
| 5570-473P4583.pdf | ||
| 5570-477P1964.pdf | ||
| 5570-500P28.pdf | ||
| FP14_Eng.pdf | ||
| 5570-479P1528.pdf | ||
| 5570-475P2750.pdf | ||
| 5570-498P1719.pdf | ||
| 5570-482P6875.pdf | ||
| VETS-4212_-_Form.pdf | ||
| NEPA_CE.pdf | ||
| 5570-472P6875.pdf | ||
| Synopsis_-_NATR_BMS_FY19(1).doc | DOC document |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
Page
Notice to Bidders 1 through 2
Checklist for Bid Submission 1 through 2
*SF-1442 Solicitation, Offer, and Award 1 through 4
Bid Schedule Instructions 1 through 3
*Bid Schedule B-1 through B-3
*SF-24 Bid Bond C-1 through C-2
FEDERAL ACQUISITION REGULATION & TRANSPORTATION ACQUISITION
REGULATION SOLICITATION PROVISIONS & CONTRACT CLAUSES
Index to Federal and Transportation Acquisition Regulations 1 through 7
Representations and Certifications (SAMs online) D-1 through D-2
Instructions to Bidders E-1
*Socioeconomic Program Requirements F-1 through F-4
Minimum Wage Schedule F-5 through F-16
*General Contract Requirements G-1 through G-7
Construction Contract Requirements H-1 through H-5
Special Contract Requirements J-1 through J-18
Section K K-1 through K-3
Permits Obtained for this Project 1 through 19
SPECIFICATIONS On CD
Plans 1 through 29
Bridge Inspection reports (16) See CD/FBO.gov
NEPA_CE 1 through 27
* Bidder’s Qualifications Form 1 through 7
* Federal Contractor Veterans’ Employment Report VETS-4212 1 through 5
*BOLD FACED ITEMS ARE TO BE INCLUDED WITH THE BID SUBMITTAL PACKAGE
NOTICE TO BIDDERS
CONTRACT FORMAT:
Bidders should note that the format of this contract is in accordance with Federal Acquisition Regulations (FAR), promulgated by the General Services Administration (GSA), effective April 1, 1984, including all applicable revisions. Applicable FAR provisions and clauses are incorporated in this contract by reference or full text as indicated in the INDEX before the D-page in this booklet.
FAR provisions and clauses incorporated by reference can be accessed on the Internet on the GSA website at www.arnet.gov/far/. Bidders are encouraged to review the documents thoroughly before bidding.
PROPOSAL BOOKLET AND OFFER SUBMITTAL:
It is the responsibility of the Bidder to verify that this proposal is complete as listed in the Table of Contents. The Bidder is responsible for submitting all required forms and documents with the offer.
Offerors should use the Checklist for Bid Submission included in this booklet to check that their bids are complete.
CONSTRUCTION CONTRACTS:
Additional guidance is given in FAR Subpart 35.005 where the majority of the project work is complex and specialized such as restoration work, bridge painting, and proprietary construction techniques (i.e. proprietary Cintec arch strengthening.) There are exceptions and they will be reviewed on a case-by-case basis.
HAZARDOUS MATERIALS IDENTIFICATION AND MATERIAL SAFETY DATA:
As required by FAR Clause 52.223-3, Hazardous Materials Identification and Safety Data, the apparent low Offeror must submit prior to award a Material Safety Data Sheet (MSDS's) for all hazardous materials that the Offeror identifies in paragraph (b) of this clause in the D-pages of this booklet. Failure to submit MSDS's may render the Offeror ineligible for award of contract. The apparent low Offeror should submit their MSDS's within two weeks after bid opening.
INTERNET BASED DATA BASES - REQUIRED INPUT:
According to the FAR Subpart 4.1102 contractors MUST be registered in System for Award Management (SAM) prior to contract award. Access the following web site to register:
www.sam.gov
According to the FAR Subpart 4.1201 contractors MUST complete their Online Annual Representations and Certifications Application prior to contract award online at http://sam.gov/.
According to the FAR Subpart 22.1302 (b) contractors and sub-contractors MUST complete the required Annual Vets-4212 Form in order to be eligible for a contract award. It can be completed on-line at http://www.dol.gov/vets/vets4212.htm. 2017 VETS-4212 Filing Cycle Effective August 1, 2017 and ends on September 30, 2018, Customers will no longer be able to electronically file a VETS-4212 Report. Customers may still file, but must first download the form from the VETS website http://www.dol.gov/vets/vets4212.htm, fill out the form and mail or email it to: VETS-4212 Service Center C/O Department of Labor National Contact Center (DOL-NCC), 7425 Boston Blvd, Springfield, VA (866) 237-0275 Or email to: VETS4212-customersupport@dol.gov.
PAYMENT:
Offerors are advised to review the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP), subsection 109.05, concerning direct and indirect payment included under a pay item in the bid schedule.
PROGRESS PAYMENTS:
ALL payments will be made via Electronic Funds Transfer (EFT) as such; the payment information in the CCR must be accurate in order for contractors' invoices to be considered proper invoices for the purpose of prompt payment under DOT contracts. Contractors must input and maintain (update as necessary) their EFT information in the CCR database. Offerors are advised that under FAR Clause 52.232-5, Payments Under Fixed Price Construction Contracts, upon request, progress payments will include premiums paid by the Contractor to obtain performance and payment bonds as required under
NOTICE TO BIDDERS
this contract. These payments shall not be made in addition to the contract price. As specified in the FP, “Section 151 - MOBILIZATION", payments for performance and payment bond premiums shall be included in mobilization.
WELFARE-TO-WORK INITIATIVE:
The President’s Welfare Reform Bill was initiated to assist welfare recipients and hopefully aid welfare recipients to find gainful employment. In support of this bill, Contractors are encouraged to hire welfare recipients whenever possible and to use welfare recipients in performance of duties on Government contracts.
INCREASING SEAT BELT USE IN THE UNITED STATES:
The President’s Executive Order 13043 dated April 16, 1997, was issued to increase the use of seat belts in the United States. In support of this Order, contractors and subcontractors are encouraged to adopt and enforce on-the-job seat belt policies for their employees when operating company-owned, rented, or personally owned vehicles.
OBTAINING BID DOCUMENTS:
Bid documents will not be mailed. All bid documents are available for direct download from the Federal Business Opportunities (FBO) website: http://www.fbo.gov/. Contractors are encouraged to register on the FBO website (for this specific project) in order to receive Email Notifications automatically when a document is added or updated for this specific project. All questions about this construction project must be emailed to the following address:
eflhd.contracts@dot.gov.
THE CONTRACTOR IS SOLELY RESPONSIBLE FOR MONITORING THE WEB PAGES
NOTED ABOVE FOR ALL CHANGES TO THE SOLICITATION AND ACTING ON SAID
CHANGES.
PLEASE NOTE: for security reasons, individuals requiring access to all government buildings must present a valid photo ID and be escorted to their destination by a Government employee. All visitors attending bid openings are urged to arrive at least 1 hour prior to schedule bid opening. All visitors must register with the receptionist in Room 100. A Government employee will collect all bids. Prior to bid opening, a Government employee will escort all bidders to the bid opening. Unescorted visitors will be denied entry and no exceptions will be made.
CHECKLIST FOR BID SUBMISSION
The following is a checklist of items included in the proposal/bid package that are required to be completed and returned (or filled in on-line) to the address in Block 7 of the Standard Form 1442, Solicitation, Offer, and Award (page 1). This checklist is for informational purposes only and is not required to be filled out by the bidder. Failure to submit a complete bid may be cause to reject your bid.
1. Bid Envelope:
a. Addressed as shown in Block 7 of SF-1442
b. In lower left corner, indicate the following: Solicitation No., Project Name & Number, mail to room
105, if proposals are hand delivered bring them to Reception Area Room 100 and a Contract Specialist will be notified.
2. Standard Form 1442: Solicitation, Offer and Award
a. Block 14: Name and Address of Bidder.
b. Block 15: Telephone Number of Bidder.
c. Block 16: Remittance Address if different from Block 14.
d. Block 19: All Amendments Acknowledged, with dates of Amendments.
e. Block 20: Bid is signed and dated.
3. Bid Schedule - (Pages B-1 through B-3)
a. Unit bid price and bid amount provided for each pay item in numbers.
b. Corrections initialed.
4. Standard Form 24, Bid Bond (Pages C-1 through C-2) (Required if bid guarantee is bid bond) a . Date executed b . Legal name and address of bidder.
c . Type of organization.
d . State of incorporation (if applicable).
e . Name and business address of Treasury approved surety.
f . Penal sum of bond (not less than 20% of bid total).
g . Bid identification.
h . Signature of Bidder i . Seal, if corporation j . Signature of Surety k . Seal, if corporation
BIDS RECEIVED WITHOUT A VALID BID BOND WILL BE REJECTED.
5. Power of Attorney.
a. Dated on or before execution date of bond
b. Power has original signature of surety, or is embossed with surety's seal in the certification section
BIDS RECEIVED WITHOUT A VALID POWER OF ATTORNEY WILL BE REJECTED.
CHECKLIST FOR BID SUBMISSION
6. Bidder's Qualifications form (provided separately as part of the Bid Documents Package).
Form completed, signed and submitted with bid
THE FOLLOWING THREE ITEMS IF NOT SUBMITTED WITH THE BID; MUST
BE COMPLETED ELECTRONICALLY PRIOR TO CONTRACT AWARD.
7. System for Award Management (SAM): The Contractor is currently registered in the Internet-Based SAM database at http://www.sam.gov. If contractor elects to not have SAM viewed by public they must submit a copy with Bidder’s Qualification Package.
8. Online Representations and Certifications Application: The Contractor's Representations and Certifications have been input online via the Internet-Based electronic database at http://sam.gov.
9. VETS – 4212 Reporting: The Contractor has completed the annual Internet-Based reporting requirement online at http://www.dol.gov/vets/vets4212.htm.
VETS 4212 Filing Cycle Effective August 1, 2017 and ends on September 30, 2018, Customers will no longer be able to electronically file a VETS 4212 Report. Customers may still file, but must first download the form from the VETS website http://www.dol.gov/vets/programs/fcp/vets-4212.pdf, fill out the form and mail or email it to: vets-4212 Service Center, In Care of: Department of Labor National Contact Center (DOL-NCC), 15000 Conference Center Drive, Suite B0132 Chantilly, VA 20151 (866) 237-0275 Or email to: VETS4212-customersupport@dol.gov.
NOTE: THE CONTRACTOR IS FULLY RESPONSIBLE TO VERIFY THAT ALL
DATA IN THE ABOVE DATABASES IS CORRECT EACH TIME A BID PACKAGE IS
SUBMITTED. FAILURE TO PROPERLY INPUT AND/OR UPDATE YOUR DATA
PRIOR TO CONTRACT AWARD MAY CAUSE THE BID TO BE REJECTED.
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Federal Highway Administration
Eastern Federal Lands Highway Div.
Acquisitions Office 21400 Ridgetop Circle
EFLHD-AC
Sterling VA 20166-6511
See Block 7
BRADLEY HIGLEY
See Block 10 x
10/22/2019
693C7320B000007
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
This Invitation for Bids is for the Natchez Trace Parkway, Project NATR BMS FY19(1), located in Hinds, and Madison Counties, Mississippi in strict accordance with the Solicitation/Contract instructions, notices, clauses, provisions, items listed below, and for the quantities of work actually performed at the unit prices as bid in the Bid Schedule, including all applicable Federal, State, and local taxes.
FP - Standard Specification for Construction of Roads & Bridges on Federal Highway Projects.
Bid Schedule, Section B - pages B-1 through B-3
Special Contract Requirements, Section J - pages J-1 through J-18
Plans, Sheets 1 through 29
MDOT Permit, pages 1 through 19
Bridge Inspection Reports (16), see CD/FBO.gov
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 115 calendar days and complete it within ________________ ________________ calendar days after receiving
Continuation Sheet Block 11
11/21/2019
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
EFLHD.Contracts@dot.gov
�����./�0::/303�#73//5�20�9/3:03;�2./�=03D�3/AB83/>�#2�2./�9384/5�59/48:8/>�$/60=�81�523842�#4403>#14/�=82.�2./�2/3;5�0:�2.85�5068482#2801?�8:�2.85�0::/3�85�#44/92/>
$@�2./��0E/31;/12�81�=382817�=82.81�--------------------�4#6/1>#3�>#@5�#:2/3�2./�>#2/�0::/35�#3/�>B/����������
| � | %(�� |
| �) | �� |
| �� | ����� |
| � | �� |
| ����� ���������� | ���� | ����� |
| � | �� |
�����./�0::/303�#73//5�20�:B3185.�#1@�3/AB83/>�9/3:03;#14/�#1>�9#@;/12�$01>5�
0��#������ ��2�
| ����� | ������ | � |
| H���� | �� |
������� �)4��
3�2���%����
| �����" | ��� � ����� | ��� |
| ����������� | �� |
| ��" ���� | ���������� | |
| �������� | ����� | "��� |
����������3 4��� '5 '6 �--����7��
3�2���%���
| �� | ������ | �� | ������ | ������ | � |
| H���� | �� |
������� )4������ �$���� �� �4������
����2�� #��0 ��2�����
�)��������� )�&4'��������������� ������������ &4'���������������
�"������&��*���G��'����, Block 26
Federal Highway Administration Eastern Federal Lands Highway Division ATTN: Construction Office 21400 Ridgetop Circle Sterling, VA 20166-6511
Federal Highway Administration Eastern Federal Lands Highway Division A/P Branch, AMZ-150 P.O. Box 25710 or E-MAIL
9-AMC-AMZ-EFLINVOICES@FAA.GOV
Oklahoma City, OK 73125
EFLHD-CO
CONTINUATION OF SF 1442
Block 2:
This project is RESTRICTED - Bids will be accepted from all eligible Small Business concerns.
This procurement falls under North American Industry Classification System (NAICS) code 237310 - Highway, Street, and Bridge Construction (see FAR Subpart 19.10)
Facsimile and electronic bids will not be accepted.
PHYSICAL DATA AVAILABLE FOR REVIEW
1. Manual on Uniform Traffic Control Devices for Streets and Highways, 2009 Edition, published by the Federal Highway Administration. http://mutcd.fhwa.dot.gov.
2. National Park Service Sign Manual, revised - January 1988, United States Department of the Interior. http://flh.fhwa.dot.gov/resources/design/library.
3. Categorical Exclusion (NEPA)
4. Bridge Inspection Reports (16)
5. Permit
Block 9:
In accordance with FAR Provision 52.236-27, Site Visit, a Government representative can be available to show the project to prospective bidders. All requests for site visits see Section E of the solicitation and e-mail all questions concerning this construction project to the following e-mail address eflhd.contracts@dot.gov. Interested parties must provide the Solicitation Number and the relevant project name with all requests and questions.
∗Block 11:
Construction activities at the project site cannot begin any earlier than February 2020.
If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 115 calendar days.
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 70 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 50 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
See Completion of Work section of the B-Pages – Bid Schedule Instructions for further information. The completion time for the contract is not to exceed the maximum time above.
Work restrictions can be found in SCR Sections 108 and 156.
CONTINUATION OF SF 1442
Notice to Proceed will be issued within 30 days following receipt of acceptable performance and payment bonds. (Actual Notice to Proceed date will be 10 days from issuance or the date specified in the Notice.)
Block 12A:
Furnish performance and payment bonds in accordance with FAR Clause 52.228-15.
Block 13:
A bid guarantee in the amount of not less than 20 percent of the bid price or $3 million, whichever is less, is required with this bid. If the bidder fails to provide the required bid guarantee, such failure may require rejection of the bid. Reference FAR Provision 52.228-1, Bid Guarantee.
Block 17:
Amounts should be completed as follows:
Schedule A - $ Schedule B (Government Option 1) - $
Other:
The estimated price is expected to fall within the price range of $500,000 to $1,000,000.
Responsibility of bidders shall be evaluated in accordance with the information provided on the Bidder's Qualification Form, which can be downloaded from FHWA web site. FP-14 versions can be downloaded at the FHWA web site. FHWA web site is http://flh.fhwa.dot.gov/resources/specs/ then click on “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects.”
BID SCHEDULE INSTRUCTIONS
PROJECT: NATR BMS FY19(1)
BIDDERS PLEASE NOTE: Before preparing the bid, carefully read the Instructions to
Bidders. While preparing the bid, comply with the following:
COMPLETING THE BID SCHEDULE
Complete the Bid Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places, for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit Bid Price and Amount Bid for the pay item. Determine the Bid Total for each specific individual Schedule of Work by adding the amounts of the listed items, and show in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.
To be eligible for award, bidders must submit prices for each pay item.
Review Subsection 109.05 of the FP (standard specifications book) regarding scope of payment for direct and indirect payment work.
Fill in the Bid Total(s) for each individual Schedule of Work as directed on the Bid Summary page. Fill in the Evaluation Total Price of Project in the space provided on the Bid Summary page.
The amount in Block 17 of the SF 1442 should be completed as follows:
Schedule A - $ .
Schedule B - $ .
SCHEDULES OF WORK
The Bid Schedule is comprised of the following separate schedules and options of work:
Schedule A (Base Contract) - Pages B-1
Schedule B (Government Option 1) - Pages B-2
The Government will award the project as a Base Contract (Schedule A) with the option to award Schedule B (Government Option 1); see FAR Clauses 52.217-4 and 52.217-5.
The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price, by proper utilization of programmed funds and upon receipt of any additional funds required to award the contract. If complete funding is in place at the time of award of Schedule A (Base Contract), the Government may award Schedule B (Government Option 1) at that time. If additional funding is required for the award of Schedule B (Government Option 1), and is received after the award of Schedule A (Base Contract), the Government has the right to exercise Schedule B (Government Option 1) at the unit prices bid no later than the contract completion date of Schedule A (Base Contract).
COMPLETION OF WORK
The Government has estimated the number of calendar days necessary to complete all contract work from the effective date of the Notice to Proceed to contract completion for the various contract award scenarios. The maximum number of calendar days allowed (i.e., the contact performance period) is shown in Block 11 of the SF-1442 and described below.
If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 115 calendar days.
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 70 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 50 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
In developing a construction schedule to determine the number of calendar days, the Government considered and included the work limitations shown in Sections 108 and 156 of the FP and Special Contract Requirements (SCR’s). Specific work limitations may be (but are not limited to): National legal holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items are (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc). The Government also considered time required for preparing material and drawing submittals, and the allowable Government review times for those submittals (Subsection 104.03 of the FP and SCR’s).
Bidders are to assume that the award of the contract and approval of the Contractor’s Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-15) may result in the start of construction activities to be no earlier than February 2020. See Subsection 108.01 of the SCR’s for additional details.
BASIS FOR AWARD
The contract will be awarded to the responsive, responsible bidder with the lowest Evaluation Total Price of Project, which is defined as:
Schedule A (Base Contract) Bid Total + Schedule B (Government Option 1) Bid Total.
B - 1
Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0040 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A0060 41401-2000 CRACKS, CLEANING AND SEALING
540 LNFT $____________ $____________
A0080 55220-0000 REPAIR CONCRETE
1 SQYD $____________ $____________
A0100 55225-0000 CLEAN AND RESEAL JOINTS (POURABLE JOINT)
1,540 LNFT $____________ $____________
A0120 55235-0000 EXPANSION JOINTS (STRIP SEAL)
420 LNFT $____________ $____________
A0140 55235-0000 EXPANSION JOINTS (PRECOMPRESSED HYBRID SEAL)
150 LNFT $____________ $____________
A0160 63501-0000 TEMPORARY TRAFFIC CONTROL
ALL LPSM $___LPSM_____ $____________
A0180 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
2 EACH $____________ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NATR BMS FY19(1) Project Name:NATR-Bridge Preventative Maintenance
B - 2
Item No. Pay Item No. Description Quantity Unit Unit Price Amount
B0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
B0040 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
B0060 41401-2000 CRACKS, CLEANING AND SEALING
380 LNFT $____________ $____________
B0080 55225-0000 CLEAN AND RESEAL JOINTS (POURABLE JOINT)
970 LNFT $____________ $____________
B0100 55235-0000 EXPANSION JOINTS (PRECOMPRESSED HYBRID SEAL)
325 LNFT $____________ $____________
B0120 55235-0000 EXPANSION JOINTS (ASPHALTIC PLUG)
185 LNFT $____________ $____________
B0140 55235-0000 EXPANSION JOINTS (STRIP SEAL)
75 LNFT $____________ $____________
B0160 56301-2000 PAINTING, STEEL STRUCTURE
ALL LPSM $___LPSM_____ $____________
B0180 63501-0000 TEMPORARY TRAFFIC CONTROL
ALL LPSM $___LPSM_____ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:B Schedule Type:Options
Project No:NATR BMS FY19(1) Project Name:NATR-Bridge Preventative Maintenance
B - 3
BID SUMMARY
Project NATR BMS FY19(1)
(1) Schedule A (Base Contract) Bid Total (from Page B-1) = (1) $____________________
(2) Schedule B (Government Option 1) Bid Total (from Page B-2) = (2) $____________________
Total Price of Project (for evaluation purposes only)
EVALUATION TOTAL PRICE OF PROJECT = (1) + (2) $____________________
Maximum Time Allowed for the Contract if Schedules A and B are Awarded at the Same Time
If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 115 calendar days.
Maximum Time Allowed for Each Schedule of Work if Awarded Separately
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 70 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 50 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
BID BOND
(See instructions on reverse)
OMB Control Number: 9000-0045 Expiration Date: 8/31/2022
PRINCIPAL (Legal name and business address) TYPE OF ORGANIZATION ("X" one)
STATE OF INCORPORATION
SURETY(IES) (Name and business address)
PERCENT
OF BID
PRICE
PENAL SUM OF BOND
AMOUNT NOT TO EXCEED
MILLION(S) THOUSAND(S) HUNDRED(S) CENTS
BID IDENTIFICATION
BID DATE INVITATION NUMBER
PRINCIPAL
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1. 2.
2.
3.
3.
(Seal) (Seal) (Seal) Corporate Seal
INDIVIDUAL SURETY(IES)
SIGNATURE(S)
NAME(S)
(Typed)
1.
1.
2.
2.
(Seal) (Seal)
CORPORATE SURETY(IES)
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1.
2.
2. Corporate Seal
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is NOT usable
STANDARD FORM 24 (REV. 8/2016)
Prescribed by GSA - FAR (48 CFR) 53.228(a)
FOR (Construction, Supplies or Services)
OBLIGATION:
We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.
CONDITIONS:
The Principal has submitted the bid identified above.
THEREFORE:
The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.
Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government.
Notice to the surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.
WITNESS:
The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.
DATE BOND EXECUTED (Must not be later than bid opening date)
Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0045. We estimate that it will take 1 hour to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.
JOINT VENTURE
OTHER (Specify)
PARTNERSHIPINDIVIDUAL
CORPORATION
INSTRUCTIONS
1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.
2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.
3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).
4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the LIABILITY LIMIT block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.
(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "CORPORATE SURETY(IES)." In the space designated "SURETY(IES)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.
(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond.
The Government may require the surety to furnish additional substantiating information concerning its financial capability.
5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals.
6. Type the name and title of each person signing this bond in the space provided.
7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and "offeror."
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1.
2.
2. Corporate Seal
Corporate Seal
LIABILITY LIMIT ($)STATE OF INCORPORATION
2.
2.
1.
1.NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
STANDARD FORM 24 (REV. 8/2016) BACK
CONTRACT CLAUSES INDEX
FEDERAL ACQUISITION REGULATION (FAR) TRANSPORTATION ACQUISITION REGULATION (TAR)
(Updated thru FAC 2019-06 on 10/10/2019)
FAR & TAR CLAUSES INCORPORATED BY REFERENCE
CLAUSE TITLE DATE REMARKS
52.202-1 DEFINITIONS Nov-13 52.203-3 GRATUITIES Apr-84 52.203-5 COVENANT AGAINST CONTINGENT FEES May-14 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT Sep-06 52.203-7 ANTI-KICKBACK PROCEDURES May-14 52.203-8 CANCEL & RECOVER OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY May-14 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY May-14
52.203-11
CERTIFICATION AND DISCLOSURE REGARDING PAYMENTS TO INFLUENCE CERTAIN FEDERAL
TRANSACTIONS Sep-07
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS Oct-10 52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT Oct-15 52.203-14 DISPLAY OF HOTLINE POSTER(S) Oct-15 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER May-11 52.204-7 SYSTEM FOR AWARD MANAGEMENT Oct-18 Contractor Mandatory Internet Data Input 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS Oct-18 Contractor Mandatory Internet Data Input 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE Oct-18 Contractor Mandatory Internet Data Input 52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS Oct-16 Contractor Mandatory Internet Data Input 52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING Jul-15 52.204-17 OWNERSHIP OR CONTROL OF OFFEROR Oct-16 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE Jul-16 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS Dec-14 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS Jun-16
52.209-6
PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS
DEBARRED, SUSPENDED OR PROPOSED FOR DEBARMENT Oct-15
52.209-11
REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A FELONY
CONVICTION UNDER ANY FEDERAL LAW Feb-16
52.214-5 SUBMISSION OF BIDS Mar-97 52.214-19 CONTRACT AWARD -- SEALED BIDDING-CONSTRUCTION Aug-96 52.214-26 ALT 1 AUDIT AND RECORDS -- SEALED BIDDING (ALT 1 - (MAR 09)) Oct-10 52.214-27 PRICE REDUCTION FOR DEFECTIVE COST OR PRICING DATA - MODIFICATIONS - SEALED BIDDING Aug-11 52.214-28 SUBCONTRACTOR COST OR PRICE DATA -- MODIFICATIONS--SEALED BIDDING Oct-10 52.214-29 ORDER OF PRECEDENCE - SEALED BIDDING Jan-86 52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE Apr-91 52.214-35 SUBMISSION OF OFFERS IN THE U.S. CURRENCY Apr-91 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE Nov-11
52.252-2 Clauses Incorporated By Reference (Feb 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. The full text of a clause may be accessed electronically at this address: www.arnet.gov/far/
(End of Clause)
(Updated thru FAC 2019-06 on 10/10/2019)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS Oct-18 52.219-14 LIMITATIONS ON SUBCONTRACTING Jan-17 52.219-16 LIQUIDATED DAMAGES - SUBCONTRACTING PLAN Jan-99 52.219-17 SECTION 8(a) AWARD Oct-19 8(a) Sole Source 52.219-27 NOTICE OF SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE Oct-19 SDVOSB Set-Aside
52.219-29 NOTICE OF SET-ASIDE FOR, OR SOLE SOURCE AWARD TO, ECONOMICALLY DISADVANTAGES WOMEN- OWNED SNALL BUSINESS CONCERNS Dec-15
52.219-30 NOTICE OF SET-ASIDE FOR, OR SOLE SOURCE AWARD TO, WOMEN-OWNED SMALL BUSINESS CONCERNS ELIGIBLE UNDER THE WOMEN-OWNED SMALL BUSINESS PROGRAM Dec-16
52.222-3 CONVICT LABOR Jun-03 52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS -- OVERTIME COMPENSATION May-18 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS - SECONDARY SITE OF THE WORK May-14 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS Aug-18 Contractor Mandatory Wage Rates Posting 52.222-7 WITHHOLDING OF FUNDS May-14 52.222-8 PAYROLLS AND BASIC RECORDS Aug-18 Contractor Weekly Payroll Submittals 52.222-9 APPRENTICES AND TRAINEES Jul-05 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS Feb-88 52.222-11 SUBCONTRACTS (LABOR STANDARDS) May-14 52.222-12 CONTRACT TERMINATION -- DEBARMENT May-14 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS May-14 52.222-14 DISPUTES CONCERNING LABOR STANDARDS Feb-88 52.222-15 CERTIFICATION OF ELIGIBILITY May-14 52.222-19 CHILD LABOR - COOPERATION WITH AUTHORITIES AND REMEDIES Jan-18 52.222-21 PROHIBITION OF SEGREGATED FACILITIES Feb-99 52.222-26 EQUAL OPPORTUNITY Sep-16 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION Apr-15 52.222-32 CONSTRUCTION WAGE RATE REQUIREMENTS - PRICE ADJUSTMENT (ACTUAL METHOD) Aug-18
52.222-35 EQUAL OPPORTUNITY FOR SPECIAL DISABLED VETERANS, VETERANS OF THE VIETNAM ERA, & OTHER ELIGIBLE VETERANS Oct-15
52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES Jul-14 52.222-37 EMPLOYMENT REPORTS ON VERTERANS Feb-16 52.222-38 COMPLIANCE WITH VETERANS' EMPLOYMENT REPORTING REQUIREMENTS Feb-16 Contractor Annual Mandatory Reporting Requirement 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT Mar-15 52.222-50 COMBATING TRAFFICKING IN PERSONS Jan-19 52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 Dec-15 52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 Jan-17 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACT Sep-13 http://www.biopreferred.gov 52.223-5 POLLUTION PREVENTION AND RIGHT TO KNOW INFORMATION May-11 52.223-6 DRUG-FREE WORKPLACE May-01 Contractor Annual Contractor Reporting Reqt 52.223-10 WASTE REDUCTION PROGRAM May-11 52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION CONTRACTS Aug-18 Mandatory 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING Aug-11 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES Jun-08 52.227-1 AUTHORIZATION AND CONSENT Dec-07 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT Dec-07 52.227-4 PATENT INDEMNITY-CONSTRUCTION CONTRACTS Dec-07 52.227-14 RIGHTS IN DATA - GENERAL May-14 52.227-17 RIGHTS IN DATA - SPECIAL WORKS Dec-07 52.228-1 BID GUARANTEE Sep-96 52.228-2 ADDITION BOND SECURITY Oct-97 Contractor Submittal Requirement
(Updated thru FAC 2019-06 on 10/10/2019)
52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION Jan-97 52.228-11 PLEDGES OF ASSETS Aug-18 52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS May-14 52.228-14 IRREVOCABLE LETTER OF CREDIT Nov-14 Contractor Submittal Requirement 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION Oct-10 52.229-2 NORTH CAROLINA STATE AND LOCAL SALES AND USE TAX Apr-84 52.229-3 FEDERAL, STATE, AND LOCAL TAXES Feb-13 52.230-2 COST ACCOUNTING STANDARDS Oct-15 52.230-3 DISCLOSURE AND CONSISTENCY OF COST ACCOUNTING PRACTICES Oct-15 52.230-6 ADMINISTRATION OF COST ACCOUNTING STANDARDS Jun-10 Contractor Submittal Requirement 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS May-14 52.232-13 NOTICE OF PROGRESS PAYMENTS Apr-84 52.232-16 PROGRESS PAYMENT Apr-12 52.232-17 INTEREST May-14 52.232-18 AVAILABILITY OF FUNDS Apr-84 52.232-23 ASSIGNMENT OF CLAIMS May-14 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS Jan-17 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD MANAGEMENT Oct-18 52.233-1 ALT 1 DISPUTES (ALT-1, DEC-91) May-14 52.233-3 PROTEST AFTER AWARD Aug-96 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM Oct-04 52.236-2 DIFFERING SITE CONDITIONS Apr-84 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK Apr-84 52.236-5 MATERIAL AND WORKMANSHIP Apr-84 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR Apr-84 52.236-7 PERMITS AND RESPONSIBILITIES Nov-91 52.236-8 OTHER CONTRACTS Apr-84 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES & IMPROVEMENTS Apr-84 52.236-10 OPERATIONS AND STORAGE AREAS Apr-84 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION Apr-84 52.236-12 CLEANING UP Apr-84 52.236-13 ACCIDENT PREVENTION Nov-91 Contractor Submittal Requirement 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS Apr-84 52.236-17 LAYOUT OF WORK Apr-84 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION Feb-97 52.236-26 PRECONSTRUCTION CONFERENCE Feb-95 52.242-5 PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS Jan-17 52.242-13 BANKRUPTCY Jul-95 52.242-14 SUSPENSION OF WORK Apr-84 52.243-4 CHANGES Jun-07 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS Jan-19 52.245-2 GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES Apr-12 52.246-12 INSPECTION OF CONSTRUCTION Aug-96 52.246-21 WARRANTY OF CONSTRUCTION Mar-94 52.248-3 ALT 1 VALUE ENGINEERING - CONSTRUCTION (ALT-1, APR-84) Oct-15 52.249-2 ALT 1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (ALT-I, Sep-96) Apr-12 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) Apr-84 52.253-1 COMPUTER GENERATED FORMS Jan-91
TAR CLAUSES INCORPORATED BY REFERENCE
1252.211-70 INDEX FOR SPECIFICATIONS Apr-05
(Updated thru FAC 2019-06 on 10/10/2019)
1252.242-73 CONTRACTING OFFICERS TECHNICAL REPRESENTATIVE Oct-94
FAR & TAR PROVISIONS INCORPORATED BY REFERENCE
52.217-4 EVALUATION OF OPTIONS EXERCISED AT TIME OF CONTRACT AWARD Jun-88 52.217-5 EVALUATION OF OPTIONS Jul-90 52-217-7 OPTION FOR INCREASED QUANTITY -- SEPARATELY PRICED LINE ITEM Mar-89
(Updated thru FAC 2019-06 on 10/10/2019)
FAR & TAR CLAUSES INCORPORATED BY FULL TEXT
CLAUSE TITLE DATE SECTION SECTION TYPE REMARKS
52.203-17
CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM
EMPLOYEES OF WHISTELBLOWER RIGHTS Apr-14 G GEN'L CONTRACT REQS.
52.203-18
PROHIBITION ON CONTRACTING WITH ENTITIES THAT REQUIRE CERTAIN INTERNAL
CONFIDENTIALITY AGREEMENTS OR STATEMENTS - REPRESENTATION Jan-17 G GEN'L CONTRACT REQS.
52.203-19
PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR
STATEMENTS Jan-17 G GEN'L CONTRACT REQS.
52.204-23
PROHIBITION ON CONTRACTING FOR HARDWARE, SOTFWARE, AND SERVICES DEVELOPED OR
PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES Jul-18 G GEN'L CONTRACT REQS.
52.204-25
PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMINICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT Aug-19 G GEN'L CONTRACT REQS.
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS Oct-18 G GEN'L CONTRACT REQS.
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK Apr-84 H CONSTR. CONTRACTS REQS Government Fill In 52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION Sep-00 H CONSTR. CONTRACTS REQS Government Fill In 52.211-18 VARIATION IN ESTIMATED QUANTITY Apr-84 H CONSTR. CONTRACTS REQS
52.222-23
NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT
OPPORTUNITY FOR CONSTRUCTION Feb-99 F SOCIOECON PROG REQS Contractor Reporting Reqs
52.223-3 ALT I HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (ALT-I, JUL-95) Jan-97 G GEN'L CONTRACT REQS. Contractor Submittal Reqs 52.223-4 RECOVERED MATERIAL CERTIFICATION May-08 G GEN'L CONTRACT REQS. Contractor Submittal Reqs 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA DESIGN ITEMS May-08 G GEN'L CONTRACT REQS. Contractor Reporting Reqs 52.225-9 BUY AMERICAN - CONSTRUCTION MATERIALS May-14 F SOCIOECON PROG REQS Govt & Contractor Fill In 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION Oct-10 G GEN'L CONTRACT REQS. Contractor Submittal Reqs 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR Apr-84 H CONSTR. CONTRACTS REQS Government Fill In 52.236-4 PHYSICAL DATA Apr-84 H CONSTR. CONTRACTS REQS Government Fill In 52.248-3 Alt 1 VALUE ENGINEERING - CONSTRUCTION (ALT -I APR-84) Oct-15 G GEN'L CONTRACT REQS. Contractor Submittal Reqs
TAR CLAUSES INCORPORATED BY FULL TEXT
FAR PT 22.9 NONDISCRIMINATION BECAUSE OF AGE POLICY Feb-64 F SOCIOECON PROG REQS Executive Order 11141-Not A Clause
(Updated thru FAC 2019-06 on 10/10/2019)
FAR & TAR PROVISIONS INCORPORATED BY REFERENCE
CLAUSE TITLE DATE REMARKS
52.204-20 PREDECESSOR OF OFFEROR Jul-16 52.204-22 ALTERNATIVE LINE ITEM PROPOSAL Jan-17 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS-CERTIFICATION Jun-18 52.211-6 BRAND NAME OR EQUAL Aug-99 52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS Dec-89 52.214-4 FALSE STATEMENTS IN BIDS Apr-84 52.214-5 SUBMISSION OF BIDS Mar-97 52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS Apr-84 52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS Nov-99 52.214-18 PREPARATION OF BIDS -- CONSTRUCTION Apr-84 52.214-19 CONTRACT AWARD -- SEALED BIDDING -- CONSTRUCTION Aug-96 52.223-1 BIOBASED PRODUCT CERTIFICATION May-12 52.225-25 PROHIBITION ON CONTRACTING WITH ENTITIES ENGAGING IN CERTAIN ACTIVITIES OR TRANSACTIONS RELATIN Aug-18
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by the paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision my be accessed electronically at this address: www.arnet.gov/far/ (End of Clause)
52.252-1 Solicitation Provisions Incorporated By Reference (Feb 1998)
(Updated thru FAC 2019-06 on 10/10/2019)
FAR PROVISIONS INCORPORATED BY FULL TEXT
PROVISION TITLE DATE SECTION SECTION TYPE REMARKS
52.203-11
CERTIFICATION AND DISCLOSURE REGARDING PAYMENTS TO INFLUENCE
CERTAIN FEDERAL TRANSACTIONS Sep-07 F
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS Oct-18 D REPS & CERTIFICATIONS Mandatory Contractor On-Line Input
52.204-24
REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT Aug-19 G GEN'L CONTRACT REQS.
52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS Oct-15 K 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS Oct-18 K
52.211-4 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS NOT LISTED IN GSA INDEX
OF FEDERAL SPECIFICATION, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS
Jun-88 E INSTRUCTIONS TO BIDDERS Government Fill In
52.216-1 TYPE OF CONTRACT Apr-84 E INSTRUCTIONS TO BIDDERS Government Fill In 52.222-38 COMPLIANCE WITH VETERANS' EMPLOYMENT REPORTING REQUIREMENTS Sep-10 K
52.223-22
PUBLIC DISCLOSURE OF GREENHOUSE GSA EMISSIONS AND REDUCTION GOALS -
REPRESENTATION Dec-16 F
52.225-10 ALT
NOTICE OF BUY AMERICAN REQUIREMENT - CONSTRUCTION MATERIAL (ALT 1
MAY-14) May-14 F SOCIOECON PROG REQS
52.225-20
PROHIBITION ON CONDUCTING RESTRICTED BUSINESS OPERATIONS IN SUDAN -
CERTIFICATION
Aug-09 K
52.228-1 BID GUARANTEE Sep-96 E INSTRUCTIONS TO BIDDERS Contractor Submittal Reqs 52.230-7 PROPOSAL DISCLOSURE - COST ACCOUNTING PRACTICE CHANGES Apr-05 K 52.233-2 SERVICE OF PROTEST Sep-06 E INSTRUCTIONS TO BIDDERS Government Fill In 52.236-27 SITE VISIT (CONSTRUCTION) Feb-95 E CONSTR. CONTRACT REQS. Government Fill In
OTHER PROVISIONS INCORPORATED BY FULL TEXT
D-1
FEDERAL ACQUISITION REGULATION AND TRANSPORTATION
ACQUISITION PROVISIONS
(Updated through FAC 2019-06)
REPRESENTATIONS AND CERTIFICATIONS
Annual Representations and Certifications. Prospective contractors shall complete electronic annual representations and certifications on-line at this web address:
http://www.sam.gov (See Far 4.1201) the System for Award Management (SAM) database (see FAR 4.1102).
Vets4212 Form must also be filled-in online at http://www.dol.gov/vets/vets4212.htm in accordance with FAR Clause 52.222-37.
CONTRACTORS ARE NOT ELIGIBLE FOR AWARD
WITHOUT COMPLETING THESE REQUIREMENTS.
52.204-8 -- Annual Representations and Certifications (Oct 2018)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237310.
(2) The small business size standard is 39.5.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .