Item 201 DRY DOCK SHIP.pdf

PDF 130 KB Posted

Attached to
TRAINING SHIP FREEDOM STAR (TSFS) FY23 REGULATORY DRY DOCKING
Solicitation number
6933A222Q000025
Issued by

About this file

This document consists of a statement of work and related federal contract opportunity for the regulatory dry docking of the Training Ship Freedom Star.

The statement of work requires contractors to dry dock the ship within 72 hours of arrival and complete all required surveys, cleaning, painting and repairs below the waterline. Inspections must be performed of shell plate welding at and below the waterline for eroded or washed out welds, which shall be ultrasonically tested and repairs estimated at 4,000 shots. Contractors must furnish labor and materials to accomplish the dry docking to the satisfaction of the contracting officer's representative and all regulatory bodies, and submit the required MARAD Dry Docking Report.

The related federal contract opportunity is a solicitation by the Maritime Administration to provide industrial support for the regulatory dry docking of the Training Ship Freedom Star in accordance with the statement of work. The solicitation number is 6933A222Q000025 and it is seeking offers from contractors to perform the services described for the dry docking.

View the file

Other files

File Type Posted
TSFS 2020 Anchor Chain Gauging.pdf PDF
Bow Thruster Maintenance - Final Service Report.pdf PDF
TSFS Tankages 2022.pdf PDF
Answers to questions submitted by various vendors.pdf PDF
Bow Thruster 1.pdf PDF
Bow Thruster Maintenance Report.pdf PDF
Bow Thruster 2.pdf PDF
Freedom Star 6-3-2020 Soundings.pdf PDF
Amdmt 0004 TSFS 6933A222Q000025.pdf PDF
2020 Rudder and Skeg Inspection and Pintle Clearances.pdf PDF
TSFS 6933A222Q000025 Amndmt 0003.pdf PDF
4 Questions and Answers TSFS 2023 DD.pdf PDF
Finding Detail Report - 229.2.pdf PDF
2020 Item 207 Ultrasonic Thickness Gauging - Final.pdf PDF
Rudder Anodes Pic 2.pdf PDF
Rudder Anodes Pic.pdf PDF
Windward 22 Gauging TS FREEDOM STAR.pdf PDF
2021 Corrosion Guaging Report.pdf PDF
Finding Detail Report - 230.2.pdf PDF
Freedom Star VALVE SURVEY FORM for Marad 9-8-22qt.xlsx XLSX spreadsheet
New WO Valves Quote.pdf PDF
MVFS Mooring Analysis.pdf PDF
2020 xx Zinc Anodes Locations.pdf PDF
1547 4420 Rev 3 Bow Thruster Arr.pdf PDF
Switchboard DWG 19159-1 19159-2 19159 3 19159 4 DWG 19157 1 19157 2 19157 3 19157 4.pdf PDF
TSFS 6933A222Q000025 Amdmt 00002.pdf PDF
Hurricane Preparedness and Heavy Weather Mooring Plan.pdf PDF
Stern Thruster 2768WG D 32HJP SECTIONAL ARRANGEMENET.pdf PDF
1547 4419 Rev 1 Stern Thruster Compt Machy Arr.pdf PDF
1427 802 Rev TV FREEDOM STAR General Arrangements and Profile.pdf PDF
KINGS POINTER Tank Tables 15 Oct 13.pdf PDF
3 Questions and Answers TSFS 2023 DD.pdf PDF
1780 2550 Stern Thruster AD.pdf PDF
2 Questions and Answers TSFS 2023 DD.pdf PDF
Freedom Star NEW ITEM 205 SEA VALVES.pdf PDF
Tank Plan ST Locations.pdf PDF
1 Questions and Answers TSFS 2023 DD.pdf PDF
1547 2515 Rev 6 Transverse Bhds.pdf PDF
1547 2510 Rev 7 Long l Struct Sections.pdf PDF
Amdmt 0001 TSFS 6933A222Q000025.pdf PDF
TSFS FY22 DD combined synopsis solicitation.pdf PDF
Siemens-Allis Switchgear Parts Ordering Guide Type LA-600A.pdf PDF
August 2022 RRF Coatings Guidelines.xls XLS spreadsheet
1547-4705_Rudder Details.pdf PDF
Shell Expansion Drawing.pdf PDF
TSFS 2023 DD SOW Rev3.docx DOCX document
2018 Bow Thruster Maintenance - Final Service Report.pdf PDF
1547-1420 Docking Plan.pdf PDF
MA-57_Drydock_Report.pdf PDF
Gen Breakers Exterior.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item 201 DRY DOCK SHIP

ABSTRACT

It is the intent of this ITEM to dry dock the ship in a certified (NAVSEA, ABS or a recognized independent third party) drydock in order to perform the various inspections and repairs required by this SOW. Dock in position 2.

REFERENCES / ENCLOSURES

Dwg. 1547-1420 Docking Plan, sheet one of two; MARAD Dry-docking Report (MA-57) 1316-901 Kings Pointer Docking Plan, T/V KINGS POINTER DOCKING CALCULATIONS

LOCATION / DESCRIPTION

Contractor’s drydock

NOTES

See Item Number (ITEM) 201 in Section B that requires pricing from all vendors.

Special Blocking may be required for steel repairs to Flume Tank: - Bottom shell plating on Port and STBD sides of centerline within 3 feet of centerline between frames 35 – 41.

STATEMENT OF WORK

In accordance with all regulatory body requirements and to the satisfaction of the COR, the Contractor shall provide all labor, materials and services to accomplish the intent of this ITEM. In addition, and at a minimum, the Contractor shall:

Furnish the necessary labor and material to dry dock the ship within 72 hours of arrival in the repair yard. A copy of the docking plan is provided as a reference.

Provide docking blocks which are fabricated out of hard wood (Minimum 4 foot tall), in good condition and without excessive checking. Blocks shall be capped with soft caps in good condition.

Blocks shall be dogged or lagged together. Dock in position 2.

Meet with the COR prior to docking the ship to examine the blocks.

Set all blocks in a manner which allows the ship to be fleeted if necessary (fleeting is not anticipated). Blocks shall be arranged clear of all sea chests, transducers, fathometer wells, etc., and blocks shall be oriented such as to allow coating of the areas which were in way of blocks at the last dry-docking.

Complete the MARAD Dry-docking Report (MA-57) and deliver it to the COR prior to the final dock walk and before undocking the ship. This document is critical and is MARAD's permanent record of a ship's dry docking. In addition to data entries required on the actual form itself, any technical documentation describing the dry-dock work which took place must be attached. This will include reports from Contractors, sub-Contractors, Regulatory bodies and others. Failure to produce an accurate, timely MA-57 will result in a QDR and $20,000 deducted from the final invoice. There is no negotiation on this amount.

Complete all surveys, cleaning, painting and repairs in this SOW that are below the normal water line as soon as possible after the ship's arrival.

Within 24 hours of the ship being placed in dry-dock, provide necessary labor and material to visually inspect shell plate welding at and below the water line for any eroded or washed out welds.

Inspection to include all welds on plate butts and seams and any welds around sea chests, suctions, discharges, etc. All eroded or washed out welds shall be marked with waterproof marker for later inspection by COR, USCG Inspector and ABS Surveyor. A marked-up copy of the Shell Expansion drawing shall be used to indicate the location of all suspect areas. Weld repairs shall be the subject of a Delivery Order, based on unit pricing provided under "Supplemental Steel".

Provide the necessary labor and material to ultrasonically test all eroded or washed out welds found by the visual inspection. Using the marked-up shell expansion drawing, test and record the thickness of the suspect areas. Along with the report, submit a Condition Report identifying recommended repairs and associated costs. For quoting purposes, Contractor shall estimate 4000 UT shots.

PERFORMANCE CRITERIA / DELIVERABLES

MARAD Dry-docking Report (MA-57). Drydock certification.

File details come from the government source that posted it. Updated .