3 Questions and Answers TSFS 2023 DD.pdf

PDF 218 KB Posted

Attached to
TRAINING SHIP FREEDOM STAR (TSFS) FY23 REGULATORY DRY DOCKING
Solicitation number
6933A222Q000025
Issued by

About this file

This document contains questions and answers regarding a solicitation for the regulatory dry docking of the Training Ship Freedom Star. The solicitation is issued by the Maritime Administration within the Department of Transportation, and seeks industrial support services to dry dock the vessel in accordance with the provided Statement of Work. Questions from potential offerors involve clarification on the inclusion of technical references, preliminary inspection requirements for re-lamping work, estimated quantities for sewage disposal, and confirmation that the performance period is expected to be 38 days upon arrival of the vessel at the contractor's facility no later than March 16, 2023, with docking to occur within 72 hours of arrival.

View the file

Other files

File Type Posted
TSFS 2020 Anchor Chain Gauging.pdf PDF
Bow Thruster Maintenance - Final Service Report.pdf PDF
TSFS Tankages 2022.pdf PDF
Answers to questions submitted by various vendors.pdf PDF
Bow Thruster 1.pdf PDF
Bow Thruster Maintenance Report.pdf PDF
Bow Thruster 2.pdf PDF
Freedom Star 6-3-2020 Soundings.pdf PDF
Amdmt 0004 TSFS 6933A222Q000025.pdf PDF
2020 Rudder and Skeg Inspection and Pintle Clearances.pdf PDF
TSFS 6933A222Q000025 Amndmt 0003.pdf PDF
4 Questions and Answers TSFS 2023 DD.pdf PDF
Finding Detail Report - 229.2.pdf PDF
2020 Item 207 Ultrasonic Thickness Gauging - Final.pdf PDF
Rudder Anodes Pic 2.pdf PDF
Rudder Anodes Pic.pdf PDF
Windward 22 Gauging TS FREEDOM STAR.pdf PDF
2021 Corrosion Guaging Report.pdf PDF
Finding Detail Report - 230.2.pdf PDF
Freedom Star VALVE SURVEY FORM for Marad 9-8-22qt.xlsx XLSX spreadsheet
New WO Valves Quote.pdf PDF
MVFS Mooring Analysis.pdf PDF
2020 xx Zinc Anodes Locations.pdf PDF
1547 4420 Rev 3 Bow Thruster Arr.pdf PDF
Switchboard DWG 19159-1 19159-2 19159 3 19159 4 DWG 19157 1 19157 2 19157 3 19157 4.pdf PDF
TSFS 6933A222Q000025 Amdmt 00002.pdf PDF
Hurricane Preparedness and Heavy Weather Mooring Plan.pdf PDF
Item 201 DRY DOCK SHIP.pdf PDF
Stern Thruster 2768WG D 32HJP SECTIONAL ARRANGEMENET.pdf PDF
1547 4419 Rev 1 Stern Thruster Compt Machy Arr.pdf PDF
1427 802 Rev TV FREEDOM STAR General Arrangements and Profile.pdf PDF
KINGS POINTER Tank Tables 15 Oct 13.pdf PDF
1780 2550 Stern Thruster AD.pdf PDF
2 Questions and Answers TSFS 2023 DD.pdf PDF
Freedom Star NEW ITEM 205 SEA VALVES.pdf PDF
Tank Plan ST Locations.pdf PDF
1 Questions and Answers TSFS 2023 DD.pdf PDF
1547 2515 Rev 6 Transverse Bhds.pdf PDF
1547 2510 Rev 7 Long l Struct Sections.pdf PDF
Amdmt 0001 TSFS 6933A222Q000025.pdf PDF
TSFS FY22 DD combined synopsis solicitation.pdf PDF
Siemens-Allis Switchgear Parts Ordering Guide Type LA-600A.pdf PDF
August 2022 RRF Coatings Guidelines.xls XLS spreadsheet
1547-4705_Rudder Details.pdf PDF
Shell Expansion Drawing.pdf PDF
TSFS 2023 DD SOW Rev3.docx DOCX document
2018 Bow Thruster Maintenance - Final Service Report.pdf PDF
1547-1420 Docking Plan.pdf PDF
MA-57_Drydock_Report.pdf PDF
Gen Breakers Exterior.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

13. Work Item 106: Please provide references Mooring Analysis T/S FREEDOM STAR (As moored at Piney Point) dated September 28, 2015 and Hurricane Preparedness and Heavy Weather Mooring Plan as they were not included in the reference download. Files Attached

14. Work Item 111: The contractor has no way to determine the number of lighting fixtures in the specified areas that will require re-lamping. There is no preliminary inspection call out in the work item. The contractor recommends that a preliminary inspection of the lighting systems to identify lamps be completed and a CFR submitted for review to compensate the contractor for any lamp needing replacement in these areas. No re-lamping is required beyond lighting that fails during the contract. SOW states, “Contractor shall submit a Condition Report documenting any broken lamp globes, lenses, covers, etc. to the COR for review.” The lighting can also be observed at the site visit.

15. Work Item 127: This item supplies water for sanitary purposes and connects the vessel to the facility sewage connection or a container. The sewage disposal needs to be paid for by the customer. Please provide an estimated quantity of effluent to be disposed of during the contract period for bidding purposes. Item states, “Provide a hose from the ship's shore side sewage discharge connection to a shore side sewage line or container capable of handling all sewage produced from approximately 4 of the ship's crew each day.”

16. The solicitation, Technical submittal, paragraph 1 indicates that the performance period is estimated for 2 February 2023 through 22 March 2023. The Statement of work, paragraph “Availability and Performance Period” states that the performance period starts on or about 7 February 2023 thru 16 March 2023. These dates show a performance period of either 49 days or 38 days. What is the expected length of the performance period (regardless of when it starts)? SOW states, “The ship shall be available for work performance on or about 07 FEBRUARY 2023 (dependent upon location of CONTRACTOR) with a completion date sufficient to return the ship back to Piney Point, MD, no later than 16 MARCH 2023.”

(expected length is 38 days)

17. Work Item 201: The work item directs the contractor to “dry dock the ship immediately upon arrival in the repair yard.” This is not a feasible requirement as dock and blocking inspections, a Docking Conference and trimming of the vessel must be completed prior to docking. The contractor recommends that the vessel be docked within 72 hours of arrival at the contractors facility. See attached revision to item 201. The vessel will be docking in position 2, the shafts are not being pulled and we will allow up to 72 hours.

File details come from the government source that posted it. Updated .