OR DOT CRGNSA 100(6)_Earthwork Volumes_V and M Line.pdf
PDF 454 KB Posted
- Solicitation number
- 69056721B000016
About this file
This document includes an earthwork volume report and calculations for the OR DOT CRGNSA 100(6), Historic Columbia River Highway State Trail project. The report provides excavation and embankment quantities in cubic yards for the "V" Line, "M" Line, and campground and maintenance facility site grading components of the project. Total excavation is estimated at 1,694 cubic yards with total embankment including conserved topsoil at 1,719 cubic yards. The related federal contract opportunity is solicitation number 69056721B000016 for the OR DOT CRGNSA 100(6), Historic Columbia River Highway State Trail project, issued by the Department of Transportation Federal Highway Administration as an Invitation for Bid. No further details are provided on products or services required, pricing terms, response dates, or other salient information.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
I D
HIGHWAY STATE TRAIL,
HISTORIC COLUMBIA RIVER
OR DOT CRGNSA 100(6)
VIENTO TO MITCHELL POINT CROSSING
100% FINAL EARTHWORK
VOLUME REPORT/CALCS
"V" Line, "M" Line, & Campground/Maintenance
Facility Site Grading
Date:
Volumes obtained from Openroads Component Quantities & End Area Volume Reports (See following Pages)
Roadway
Trail & BPA Accesses CY Trail & BPA Accesses CY
Viento Campground 1505 CY Viento Campground 1459 CY
OPRD Maintenance Facility 189 CY OPRD Maintenance Facility 259 CY
I-84 CY I-84 CY
Conserved Topsoil 1 CY Total Embankment Including
Conserved Topsoil CY
Total Excavation 1694 CY
TOTAL:
1694 CY 1694 1719 CY
ALLOWANCE: 6 CY 25 CY
75 CY
Corridor Name
Viento Campground 559 CY 981 CY
CG Restroom North Daylight 0 CY 95 CY
PP1 Parking Pad 10 CY 0 CY
PP2 Parking Pad 14 CY 0 CY
PP3 Parking Pad 18 CY 0 CY
PP4 Parking Pad 6 CY 1 CY
PP5 ADA Parking Pad 0 CY 162 CY
PP5 ADA Daylight Grading 0 CY 184 CY
PP6 ADA Parking Pad 263 CY 0 CY
PP6 ADA Gravel Cut Slope 8 CY 1 CY
PP7 Host Site 431 CY 1 CY
Cut Slope_Host ADA Site 175 CY 0 CY
HB_Trail 21 CY 34 CY
CAMPGROUND TOTAL 1505 CY 1459 CY
CL_Maint Facility_Accesses 134 CY 202 CY
"M" NW Shoulder 0 CY 0 CY
"M" SE Shoulder 7 CY 57 CY
Maint Facility_South Shoulder 48 CY 0 CY
MAINT FACILITY TOTAL 189 CY 259 CY
20401-0000 Roadway Excavation (CY) Roadway 20420-0000 Embankment in Place (CY)
EARTHWORK SUMMATION_HCRH Campground & Maintenance Facility
4/15/2021
EARTHWORK
TOTAL (Including Conserved Topsoil):
TOTAL UNCLASSIFIED BORROW:
ALLOWANCE:
Campground & Maint Facility Summation from Component Quantities 20401-0000 Roadway Excavation (CY) 20420-0000 Embankment in Place (CY)
MISC CORRIDOR VOLUMES"HB" "M" "V" & "PP_" CORRIDORS
"HB" "M" "V" & "PP_" CORRIDORS MISC CORRIDOR VOLUMES
File details come from the government source that posted it. Updated .