QA2_1-21-22.pdf
PDF 101 KB Posted
- Attached to
- WA PACIFIC 2015(2) Public Access Enhancement to Willapa National Wildlife Refuge Phase II
- Solicitation number
- 69056721B000010
About this file
This document contains answers to technical questions from contractors regarding Solicitation Number 69056721B000010 for public access enhancements to the Willapa National Wildlife Refuge Phase II project. The solicitation involves asphalt paving, utility and sewer line installation, concrete work including wheel stops, landscaping, and asphalt repair near the entrance to the Wildlife Refuge. Bidders should follow the plans for asphalt lifts, material testing, spoils placement, backhoe work hours, and base layer construction. Pricing does not include escalation clauses for potential material cost increases. The awarded contract start date is June 20, 2022, and the responsible agency is the Department of Transportation Federal Highway Administration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Tabulation of Bids Awarded.pdf | ||
| Bid Opening Sign-in sheet.pdf | ||
| BidSum.pdf | ||
| Amendment A002.pdf | ||
| Amendment A002.pdf | ||
| QA_1-25-22.pdf | ||
| QA_1-21-22.pdf | ||
| QA_1-20-22.pdf | ||
| QA_1-14-22.pdf | ||
| Amendment A001.pdf | ||
| QA_1-13-22.pdf | ||
| QA_1-12-22.pdf | ||
| Corridor Reports Approach 1.pdf | ||
| WA Pacific 2015 (2) IFB.pdf | ||
| wa-a2015025_va.pdf | ||
| wa-a2015025_Approach_Overflow_XS.pdf | ||
| wa-a2015025_ha.pdf | ||
| wa-a2015025_Approach1_XSReport.pdf | ||
| xml and dxf files.zip | ZIP file | |
| Geotech Report_PBS.pdf | ||
| Corridor Reports Overflow.pdf | ||
| GM 12 19 Final Geotechnical and Construction Recommendaitons.pdf | ||
| wa-a2015025_control_points.xlsx | XLSX spreadsheet | |
| final wa-a2015025_PlanSet.pdf | ||
| Qunatities by Named Boundaries.pdf | ||
| wa-a2015025_Overflow_XSReport.pdf |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WA pacific 2015(2) Public Access Enhancement to Willapa National Wildlife Refuge Phase II
# General Technical Question Answer Date
1 X Please advise where the 120 lineal feet of utility trench reference in bid item A0640 is shown on the plans. See Section F of the plan set. Bid accordingly 1/12/22
2 X
Thank you for the quick response, but this does not answer my question. I will try to clarify below.
I am familiar with Section F of the plan set. To be more specific:
‐ 2” waterline is shown on plan sheet F.2 and paid under bid item A0340 ‐ 4” sewer line is shown on plan sheet F.2 and paid under bid item A0360 ‐ Cleanout is shown on plan sheet F.2 and paid under bid item A0380 *** the utility trench bid item A0640 of 120lf is not shown on the plans and I am trying to figure out what exactly this is for and where it is on the plans.
Will be address under Amendment A001 1/13/22
3 X I have been getting questions from our concrete subcontractors needing clarification if Alkali‐silica reactivity (ASR) testing will be required for the concrete work and/or precast concrete wheel stops?
yes, please bid accordingly 1/14/22
4 X Is it possible to place spoils over the north bank behind the existing buildings show on Sheet F‐2? No. See FP‐14 Subsection 204.14. 1/20/22
5 X Please provide clarification on the 40 hours of backhoe work?
See Subsection 622.01 of the Special Contract Requirements.
1/20/22
6 X Can one 3 inch lift of asphalt concrete pavement be placed instead of two 1.5 inch lifts of asphalt concrete pavement? No. See Sheets C.1 & C.2 of the plans. 1/20/22
7 X The specs call for paving the 3” of asphalt concrete pavement in two equal lifts. Will we be allowed to pave in 1 ‐ 3" lift?
No. See Sheets C.1 & C.2 of the plans. 1/20/22
8 X Can the excavated gravel on the roadway be re‐used to build the base layer?
Construct the base layer according to the plans and Section 302.
1/21/22
9 X Any landscaping? See the plans and Section 625. 1/21/22
10 X Is there any asphalt repair near the entrance to the Wildlife Refuse?
See the solicitation documents for the prescribed work.
1/21/22
11 X Question about material pricing escalation – oil. Due to supply chain issues, with this project being 5‐ish months out from starting (6/20/22 start date from the bid documents), are there any escalation clauses in the event that pricing for materials increases? For asphalt paving, oil could potentially see a 5% increase.
This solicitation does not contain Adjustments for Price Fluctuations under Subsection 109.06A.
Please bid accordingly.
1/21/22